Line Protection ConceptsREx670
Parameswaran.S, Sr. Engineer, Application , PG-GAS , ABB India Ltd 13.04.2016
-
7/26/2019 Distance 130416
2/61
Overview
Transmission Lines and Classifications
Protection Scheme
Distance Protection
Differential Protection
Power Swing Block
Back Up Protection
Directional Over Current
Over Voltage
Supplementary Functions Auto Reclose (1ph and 3 ph)
Synchro-check.
Month DD, Year | Sl ide 2
ABB Group
-
7/26/2019 Distance 130416
3/61
Line Protection DistanceOverview
Month DD, Year | Sl ide 3
ABB Group
X X
79
21
85
68
67/67N
51/51N
50STB
DR
59/27
60
25
BUS
BPT BPT
BUS
52 52CT CT
LPT LPT
-
7/26/2019 Distance 130416
4/61
Line Protection DifferentialOverview
Month DD, Year | Sl ide 4
ABB Group
X X
79
DR
59/27
60
25
BUS
BPT BPT
BUS
52 52CT CT
LPT LPT
87
67 / 67N
51 / 51N
DR
-
7/26/2019 Distance 130416
5/61
Line Classification
Classification depends on
Source to Line Impedance Ratio (SIR)
Nominal Voltage
IEEE C37.113 119
Source Impedance Ratio
Month DD, Year | Sl ide 5
ABB Group
Line Type SIR
Short Line > 4
Medium Line 0.5 to 4
Long Line < 0.5
-
7/26/2019 Distance 130416
6/61
Line Protection
Short Line
Differential Protection
Distance Protection with Permissive Over Reach or Blockingscheme.
Medium Line
Distance Protection with Permissive Under Reach or Permissive Over Reach
Back up Over current protection (Directional or Non Directional)
Optional over-voltage and differential protection
Application
Month DD, Year | Sl ide 6
ABB Group
-
7/26/2019 Distance 130416
7/61
Line Protection
Long Line
Distance Protection with Permissive Under Reach optionalPermissive Over Reach
Back up Over current protection (Directional or Non
Directional) Over-voltage
Optional differential protection
Application
Month DD, Year | Sl ide 7
ABB Group
-
7/26/2019 Distance 130416
8/61
DistanceMeasuring Principle
Month DD, Year | Sl ide 8
ABB Group
X X
BUS BUS
Z and the measuredzero sequence current is below the set value 3I0
-
7/26/2019 Distance 130416
51/61
Fuse FailConfiguration and Settings
Month DD, Year | Sl ide 51 ABB Group
Settings shown areinformative only, notto be used for sitecommissioningdirectly without priorvalidationby ABB
Configuration shownare informative onlyand not to be adoptedfor commission
without prior validationby ABB
-
7/26/2019 Distance 130416
52/61
Scheme CommunicationConfiguration and Settings
Month DD, Year | Sl ide 52 ABB Group
Settings shown areinformative only, notto be used for sitecommissioningdirectly without priorvalidationby ABB
Configuration shownare informative onlyand not to be adoptedfor commission
without prior validationby ABB
-
7/26/2019 Distance 130416
53/61
Application ConfigurationDifferential Protection RED670
Month DD, Year | Sl ide 53 ABB Group
Configuration shownare informative onlyand not to be adoptedfor commissionwithout priorvalidation by ABB
-
7/26/2019 Distance 130416
54/61
Parameter SettingDifferential Protection
Month DD, Year | Sl ide 54 ABB Group
Settings shown areinformative only, notto be used for sitecommissioningdirectly withoutvalidating.
-
7/26/2019 Distance 130416
55/61
Case Study 1Normal Operation AR, Fault
Month DD, Year | Sl ide 55 ABB Group
Fault in line, and main CB not ready for AR, but Tie CBs AR issuccessful.
-
7/26/2019 Distance 130416
56/61
Case Study 1Impedance Locus during first fault
Month DD, Year | Sl ide 56 ABB Group
Impedance Locus enters zone 1 and trips CB instantaneously
-
7/26/2019 Distance 130416
57/61
Case Study 1Fault during reclaim time
Month DD, Year | Sl ide 57 ABB Group
Fault during reclaim time, all the three phases of Tie CB is opened
-
7/26/2019 Distance 130416
58/61
Case Study 1Impedance Locus during second fault
Month DD, Year | Sl ide 58 ABB Group
Impedance Locus enters zone 1 and trips CB instantaneously
-
7/26/2019 Distance 130416
59/61
Power Swing Block
Power swing may occur when
Heavily loaded line gets disconnected
A big generator trips
Wrong Synchronizing
Month DD, Year | Sl ide 59 ABB Group
-
7/26/2019 Distance 130416
60/61
Power SwingImpedance Locus Movement
Month DD, Year | Sl ide 60 ABB Group
-