Disaster Recovery Plan for Office of Information Technologies

2010 – Draft 3

OIT Disaster Recovery Plan, 2010 Page 2 of 59 6/14/2010

TABLE of CONTENTS

1.1 Mission Statement .................................................................................................4

1.2 Disaster Recovery Planning ..................................................................................4

1.3 Recovery Objectives ..............................................................................................5

1.4 Assumptions of the Plan........................................................................................6

1.5 Overview of the Disaster Recovery Plan ...............................................................6

2.0 DISASTER RISKS AND PREVENTION ...........................................................8

2.1 Earthquake ...........................................................................................................8

2.2 Fire ......................................................................................................................9

2.3 Smoke ..................................................................................................................9

2.4 Flood or Water Damage ....................................................................................10

2.5 Power Outage ....................................................................................................10

2.6 Terrorist Activity or Sabotage ..........................................................................10

2.7 Sudden Loss of key personnel ...........................................................................11

3.0 DISASTER PREPARATION .............................................................................11

3.1 Disaster Recovery Planning............................................................................12

3.2 Warm Sites for the Fourth Avenue Building Data Center ................................12

3.3 Replacement Equipment ...................................................................................13

3.4 General Backup Information ............................................................................13

3.5 Backup Procedures ...........................................................................................14

3.6 Offsite Storage Agreement ................................................................................14

3.7 Documentation of Current Systems ..................................................................14

3.8 Storage of DRP..................................................................................................14

4.0 DISASTER DETECTION AND INITIATION.................................................15

4.1 Red Cross Information......................................................................................15

4.2 Disaster Recovery Teams ..................................................................................16

4.3 Disaster Detection and Determination ..............................................................17

4.4 Disaster Notification..........................................................................................17

4.5 When to Activate the Plan.................................................................................18

4.6 What to Do When a Crisis Erupts.....................................................................18

OIT Disaster Recovery Plan, 2010 Page 3 of 59 6/14/2010

5.0 ACTIVATING THE PLAN ..............................................................................19

6.0 DISASTER RECOVERY STRATEGY ............................................................20

6.1 Recovery Procedures.........................................................................................20

6.2 Team Plans Defined ..........................................................................................20

6.3 Team Plans by Service ......................................................................................21

6.5 Central Services Recovery Plan .......................................................................28

7.0 PLAN MAINTENANCE AND TESTING ........................................................29

8.0 Appendix A: EMERGENCY CONTACT LIST ...............................................31

9.0 Appendix B: VENDOR LIST............................................................................35

10.0 Appendix C: NETWORK DIAGRAMS..........................................................37

..................................................................................................................................38

11.0 Appendix D: WARM SITE AGREEMENT....................................................39

..................................................................................................................................44

12.0 Appendix E: AGREEMENT WITH IRON MOUNTAIN OFFSITE STORAGE ................................................................................................................45

13.0 Appendix F: WARM SITE EQUIPMENT AND CONFIG...............................46Hardware...................................................................................................................................................................... 46Network & Cabling .................................................................................................................................................. 46Storage .......................................................................................................................................................................... 47

14.0 Appendix G: DATA CENTER STARTUP/SHUTDOWN PROCEDURES .....49

15.0 Appendix F: OIT CONTINUITY OF OPERATIONS PLAN – 2009 ...............51

OIT Disaster Recovery Plan, 2010 Page 4 of 59 6/14/2010

1.0 INTRODUCTION Portland State University depends heavily upon information and the ability to process and analyze this information. The university increasingly depends on computer-supported information processing and services. Technology and automated systems are often used to process and analyze information and their disruption for even a few hours could cause severely affect the overall performance of the institution. This dependency on IT services will only continue to grow.

1.1 Mission Statement The Office of Information Technologies (OIT) is a support organization dedicated to providing state-of-the-art information technology and communications to students, faculty, researchers, and staff for instruction, general research, administration, and public service in support of the University's plan for excellence. Towards that end, OIT provides a myriad of computing and communication services to the University and some other educational entities. The continuing goals of OIT are to meet the changing and expanding computing and communications needs of the University and to provide outstanding service to all University constituents.

1.2 Disaster Recovery Planning A disaster is an adverse incident that in some way causes the loss of the ability to perform a specific or group of business functions or activities. This incident could be the result of a natural event, a human mistake or willful damage. A disaster recovery plan for Technology Infrastructure Services (TIS) must respond to each of these events. The Technology Infrastructure Services Disaster Recovery Plan is a comprehensive statement of actions to be taken before, during and after a disaster. This plan is designed to reduce the risk to an acceptable level by ensuring the restoration of critical functions and services within a short time frame, and all essential production within a longer, but permissible, time frame. This plan identifies the critical functions and services for the university and the resources required to support them. Guidelines and recommendations are provided for ensuring that needed personnel and resources are available for disaster preparation, assessment and response to permit the timely restoration of services.

OIT Disaster Recovery Plan, 2010 Page 5 of 59 6/14/2010

1.3 Recovery Objectives The reason for having a disaster recovery plan is to minimize business interruption. The risk and size of the impact on university services is also minimized and subsequently, the cost implications of an interruption in these services to students, faculty and staff is minimized as well. This Disaster Recovery Plan protects the university in the event that all or part of its information technology operations is rendered unusable. The objectives of this document are: • present a course of action for restoring critical systems to Portland State University

within a minimum number of days of initiation of the plan • minimize the disruption of IT operations and services • describe an organizational structure for carrying out the plan • identify the equipment, procedures and other items necessary for recovery • ensure an orderly recovery after a disaster occurs • minimize risk of lost production or services • provide a standard for testing the plan • minimize decision-making during a disaster This recovery plan and the associated documents provide a measure of security for the services, information and other non-computer assets of Technology Infrastructure Services. The activities associated with the preparation of this plan include: • Identification of the risks to the Fourth Avenue Building which may affect the critical

functions • Identification of the likely impacts should a disaster occur, and the likelihood of their

occurrence • After identification, determination of a reasonable level of expenditure on the

business recovery planning process, and prevention and recovery • Determination of suitable prevention and protection processes • Demonstration of the validity of the plan by testing

OIT Disaster Recovery Plan, 2010 Page 6 of 59 6/14/2010

1.4 Assumptions of the Plan This document plans for the major/worst case disaster. However, if an outage of services occurs to a lesser degree, this plan will cover the incident. NOTE: This plan does not guarantee zero data loss! Recovery efforts in this plan are targeted at getting the critical systems functional using the last available off-site backup tapes or other sources. Considerable effort will be required after critical systems are restored to restore data integrity to the point of the disaster and to synchronize that data with any new data produced from the point of the disaster forward. In addition, this recovery plan is predicated on the following three assumptions: • The situation that caused the disaster is localized to the Fourth Avenue Building. • It is not a general disaster affecting a major portion of the greater Portland

metropolitan area. It should be noted, that this Plan will still be functional and effective even in an area-wide disaster. Even though the basic priorities for restoration of essential services to the community will normally take precedence over the recovery of Portland State University’s IT services, this plan will still outline ways in which the services can be brought back online quickly.

• The Plan is based on the availability of a warm site. The accessibility of this site is a

significant requirement. This plan is also based on the concept that the technical teams tasked with Data Center management and Networking will provide the baseline infrastructure needs in the event of an emergency. These teams will ensure a warm site is activated or another location on campus will be made available to house sensitive equipment. The Data Center/Network Teams will ensure that Fourth Avenue Building or any other site will have proper electrical, networking and security for housing systems that will process sensitive University information. The teams and their plans are detailed later in this document.

1.5 Overview of the Disaster Recovery Plan This plan will address the following areas in the event of a disaster that destroys or severely cripples the main computing center for Portland State University: • data center recovery planning • warm site recovery planning

OIT Disaster Recovery Plan, 2010 Page 7 of 59 6/14/2010

• network recovery planning • central services recovery planning • recovery of Banner processes Personnel Immediately following a disaster, a planned sequence of events begins. Key TIS personnel are notified and recovery teams are grouped to implement the plan. Personnel currently employed are listed in the plan. However, the plan has been designed to be effective if some or all of the personnel are unavailable. Portland State University must take special pains to ensure that the recovery workers are provided with resources to meet their physical and emotional needs. If the disaster is one that affects the greater metropolitan area, many local support agencies such as the Police and Fire Departments and the Red Cross will be involved. PSU will make efforts to work with any or all of these outside agencies to protect life and property and to ensure security. Salvage Operations at Disaster Site Early efforts are targeted at protecting and preserving computer equipment. In particular, any storage media (hard drives and backup tapes) are identified and either protected from the elements or removed to a clean, dry environment away from the disaster site. Designation and Activation of a Warm Site A survey of the disaster scene is done by the appropriate personnel to determine which warm site will be activated. If the disaster is contained to strictly Fourth Avenue Building, TIS will move critical systems/functions to the alternate locations on campus. If the disaster is campus wide, the Disaster Recovery Manager will determine if it is needed to activate the warm site agreement with Western Washington University. If it is determined to do so, the Associate CIO for Technology Infrastructure Services will contact WWU to alert them to PSU's status. Key personnel will begin to restore and activate our critical systems that are physically located at WWU. This may require that one or more employees leave and restore on site at Western Washington University. During this emergency restoration of critical systems, a survey of the disaster scene is done by appropriate personnel to estimate the amount of time required to relocate all OIT operations of FAB to a location some distance away from the scene of the disaster where computing and networking capabilities can be temporarily restored until the primary site is ready. Work begins almost immediately at repairing or rebuilding the primary site. This may take months, the details of which are beyond the scope of this document.

OIT Disaster Recovery Plan, 2010 Page 8 of 59 6/14/2010

Purchase New Equipment The recovery process relies heavily upon vendors to quickly provide replacements for the resources that cannot be salvaged. The University will need to provide expedited procurement procedures (approved by the University's purchasing office and the Office of State Purchasing) to quickly place orders for equipment, supplies, software, and any other needs. Begin Reassembly at Recovery Site Salvaged and new components are reassembled at the recovery site according to the instructions contained in this plan. If vendors cannot provide a certain piece of equipment on a timely basis, it may be necessary for the recovery personnel to make last-minute substitutions. After the equipment reassembly phase is complete, the work turns to concentrate on the data recovery procedures. Restore Data from Backups Data recovery relies entirely upon the use of backups stored in locations off-site from FAB. Early data recovery efforts focus on restoring application and university data (financial, student information, etc.) from the backup tapes or other sources. Some applications and/or data may be available only to a limited few key personnel. Specific departmental information will be restored as appropriate and may require involvement with outside administrators to ensure that data is restored properly. Move Back to Restored Permanent Facility If the recovery process has taken place at the warm site, physical restoration of the Fourth Avenue Building Data Center (or an alternate facility) will have begun. When that facility is ready for occupancy, the systems assembled at the warm site are to be moved back to their permanent home. This plan does not attempt to address the logistics of this move, which should be vastly less complicated than the work done to do the recovery at a warm site.

2.0 DISASTER RISKS AND PREVENTION As important as having a disaster recovery plan is, taking measures to prevent a disaster or to mitigate its effects beforehand is even more important. This portion of the plan reviews the various threats that can lead to a disaster, where our vulnerabilities are, and steps we should take to minimize our risk. There are many forms of catastrophic loss that can occur. This section lists some of the events and situations that are considered when determining what to include in the plan.

2.1 Earthquake Earthquakes could result in partial or total loss of data for an extended period. Recovery could be slow or impossible. The probability of an earthquake in the greater Portland area is low but the severity of loss and damage in the event of an earthquake is high.

OIT Disaster Recovery Plan, 2010 Page 9 of 59 6/14/2010

Preventive Measures Building construction makes all the difference in whether the facility will survive or not. Even if the building survives, earthquakes can interrupt power and other utilities for an extended period of time. The Fourth Avenue Building, where the Data Center is located, is served by redundant power feeds. PGE serves the building from the North and South from separate substations. In the event of a failure of both feeds, the building is serviced by a turbine that can run the complex for several days before requiring refueling. The cooling systems are run by well water drawn from sources internal to the building, a benefit in the event the external water supply to the buildings is compromised.

2.2 Fire Fire can also result in partial or total loss of data for an extended period. The probability of fire within the Fourth Avenue Building Data Center is high based on the high power consumption requirements of the equipment and heat generation in the room. Preventive Measures The Fourth Avenue Building is equipped with a sophisticated fire alarm system, with ceiling-mounted smoke detectors scattered widely throughout the building. Hand-held fire extinguishers are available. The Data Center is equipped with a air-sampling VESDA system to detect the early onset of smoke particles. Temperature sensors are also available to trigger on heat thresholds. These alert systems trigger the building alarm panels and notify campus facilities. IT systems also monitor the alarms and notify OIT personnel. If the fire is not dealt with in time, overhead sprinkler systems are deployed. Building management personnel perform periodic maintenance checks of the fire alarm systems.

2.3 Smoke Smoke particles on magnetic media can render it useless. The damage from smoke occurs much faster than damage from the actual fire or water. A relatively small amount of smoke can cause a huge degree of loss in terms of data. It is imperative that smoke be contained to the smallest possible area. Preventative Measures The preventative measures for smoke detection are the same as for fire detection. The Fourth Avenue Building is equipped with a sophisticated fire alarm system, with ceiling-mounted smoke detectors scattered widely throughout the building. Hand-held fire extinguishers are available. The Data Center is equipped with an air-sampling VESDA system to detect the early onset of smoke particles. Temperature sensors are also available to trigger on heat thresholds. These alert systems trigger the building alarm panels and notify campus facilities. IT systems also monitor the alarms and notify OIT

OIT Disaster Recovery Plan, 2010 Page 10 of 59 6/14/2010

personnel. If the fire is not dealt with in time, overhead sprinkler systems are deployed. Building management personnel perform periodic maintenance checks of the fire alarm systems

2.4 Flood or Water Damage The possibility of floods from natural causes is small for the Fourth Avenue Building. However, there is the risk of broken water and sewer lines causing major water or flood damage. Being able to detect flooding and the presence of water in the data center could help curtail serious damage to some costly pieces of equipment. Preventative Measures: Humidity levels in the Data Center are monitored by the CRAC units and reported to facilities. Water sensors are embedded under the raised floor and monitored by a NetBot which alerts IT personnel. Cramer Hall has water sensor contacts installed in the central campus router room in order to have quick detection of flooding.

2.5 Power Outage The likelihood of a power outage in the downtown Portland area is high. A three unit UPS system provides clean power to the rooms and protects against any power surges. Preventative Measures: The Fourth Avenue Building, where the Data Center is located, is served by redundant power feeds. PGE serves the building from the North and South from separate substations. In the event of a failure of both feeds, the building is serviced by a turbine that can run the complex for several days before requiring refueling. The UPS system dedicated to the Data Center can keep things running for up to an hour while the turbine spins up. In the event of a turbine system failure during an emergency, the one hour of UPS time allows IT personnel an opportunity to shut systems down in an orderly fashion.

2.6 Terrorist Activity or Sabotage It is a reality that irrational things can be done that would adversely affect Technology Infrastructure Services ability to provide IT services to the campus community. Physical damage to the Fourth Avenue Building Data Center data or facilities by disgruntled employee(s) (or students, or hackers) can pose a serious threat to data integrity. To minimize these risks, an effective guideline for the handling of human relations issues and labor disputes, in conjunction with good data protection procedures, will minimize the exposure to these risks.

OIT Disaster Recovery Plan, 2010 Page 11 of 59 6/14/2010

Preventative Measures Portland State University uses an HID proximity card-based access system for secure areas. Every employee of OIT requiring access to the Data Center is issued a proximity card with a number that is unique to that person. The Fourth Avenue Building Data Center is protected by having these card readers on all doors into the facility. Every entry to any door that is used with these cards is logged to a database. Card access reports are looked over once a month for any odd activity and to ensure that only key personnel have access to the data center. There are also two cameras within the data center and perimeter that monitor the center at all times. The images are kept for a period of 30 days before they are deleted. The Banner system that houses all student information and financial information for the university has been placed behind a tightly controlled firewall. Most systems in the Data Center are also firewalled to some extent. All systems and services are consistently monitored through Nagios. Any unusual activity or high bandwidth traffic pages system administrators in order for someone to investigate the activity.

2.7 Sudden Loss of key personnel The loss of key personnel through death, unexpected departure or job termination is a valid and serious exposure in Technology Infrastructure Services. This type of loss can be minimized by cross training in each team and through the documentation of the services and processes TIS provides to the university. Preventative Measures If needed, consulting can be acquired from the major vendors for the university, i.e. SungardHE Banner, Microsoft, etc. Recommendations Documentation of critical systems and services should be kept in an offsite location. All critical system passwords should be documented and taken to the offsite storage location. These passwords should be updated in the document on a regular basis. Cross training in each team in TIS should be a high priority for the staff.

3.0 DISASTER PREPARATION In order to facilitate recovery from a disaster that destroys all or part of the data center in Fourth Avenue Building, certain preparations have been made in advance. This document describes what has been done to lay the way for a quick and orderly restoration of the facilities that TIS operates.

OIT Disaster Recovery Plan, 2010 Page 12 of 59 6/14/2010

3.1 Disaster Recovery Planning The first thing to do is to have a plan. This document is part of an overall plan that Portland State University will use in response to a disaster. The extent to which a business continuity plan can be effective, however, depends on disaster recovery plans by other departments and units within the University. Every other business unit within the university should develop a plan on how they will conduct business, both in the event of a disaster in their own building or a disaster in OIT that removes their access to data for a period of time. Those business units need means to function while the computers and networks are down, plus they need a plan to synchronize the data that is restored on the central computers with the current state of affairs.

3.2 Warm Sites for the Fourth Avenue Building Data Center If Fourth Avenue Bulding is either totally or partially destroyed in a disaster, repair or rebuilding of the building and data center may take an extended period of time. In the interim it will be necessary to restore computer and network services at an alternate site. The university has a number of options for alternate sites. Each option has a cost associated with it. Western Washington University There is a warm site agreement between Portland State University and Western Washington University. This agreement stipulates that Banner related equipment is held in the other's facility. In the event of a major catastrophe that affects the entire Portland State campus, the financial data for Portland State will be recovered at the Western Washington site. The formal agreement between Portland State and Western Washington has been renewed. The details of the agreement can be found in Appendix D. A new set of equipment has been placed in this remote location (see Appendix F), a snapshot of the Oracle and Banner software trees are periodically transferred to the remote systems and an incremental data backup is performed nightly. Cramer Hall Development of this on-site warmsite has resumed. This local warmsite will be built with a focus on dealing with a localized disaster in the Fourth Avenue Building that leaves the rest of the campus intact. This planned local warmsite is located in the Urban Center Building.. The expansion to this area will provide two racks worth of capacity, with related power and linkage to the data center network infrastructure. Some infrastructure components for this site have been purchased. The Urban Center warm site is designed to be a temporary measure until the main data center is brought back on line. There isn’t enough space in this location to re-build the entire data center capacity.

OIT Disaster Recovery Plan, 2010 Page 13 of 59 6/14/2010

Disaster Partnerships One of the most critical issues involved in the recovery process is the availability of qualified personnel to oversee and carry out the recovery. This is often where disaster partnerships can have their greatest benefit. Through cooperative agreement, if one partner loses key personnel in the disaster, the other partner can provide skilled workers to carry out recovery and restoration tasks until the disabled partner can hire replacements for its staff. There is an informal agreement with the University of Oregon (UO) to host DNS services for Portland State University in the event of an emergency. UO currently hosts one of PSU’s secondary DNS servers. When possible, formal agreements should be made between the departments in OIT to outside partners.

3.3 Replacement Equipment This plan contains a complete inventory of the components of each of the servers and network systems that must be restored after a disaster. Where possible, agreements have been made with vendors to supply replacements on an emergency basis. To avoid problems and delays in the recovery, every attempt should be made to replicate the current system configuration. However, there will likely be cases where components are not available or the delivery timeframe is unacceptably long. Although some changes may be required to the procedures documented in the plan, using different models of equipment or equipment from a different vendor may be suitable to expediting the recovery process.

3.4 General Backup Information New hardware can be purchased. New buildings can be built. New employees can be hired. However, the data that was stored on the old equipment cannot be bought at any price. It must be restored from a copy that was not affected by the disaster. There are a number of options available to help ensure that such a copy of OIT’s critical data, currently residing the Data Center, survives a disaster at the primary facility. Design of the Current Backup Systems OIT backs up all servers hosted in the data center to two Sun StorageTek towers. Each tape backup library tower can hold 84 LTO-3 tapes. Each tape can approximately hold 400-800 gigabytes of data depending on the types of files to be saved. Currently, backup compression occurs on the backup host. Windows Server Backups Windows servers are backed up using CommVault backup software. Most servers have an incremental backup each night and a full backup every two weeks. The current retention is at least 45 days for all servers. To speed up recovery in a disaster situation, CommVault runs a disaster recovery backup each night at 5 PM. This information is sent

OIT Disaster Recovery Plan, 2010 Page 14 of 59 6/14/2010

to the WWU site and contains a copy of the CommVault database and associated settings for faster restore in a disaster situation. UNIX/Linux Server Backups Unix/Linux server backups, which include all Portland State University’s financial and other data from Banner, are backed up using Legato. There are nightly incremental backups and a full backup every two weeks. A copy of the Legato configuration is also periodically included in the backup tapes that are sent off site. The current retention is 2 to 3 months.

3.5 Backup Procedures Well documented backup procedures help to ensure that recovery time is kept to a minimum. The different teams in TIS have documented procedures for backing up the critical data sets for OIT and Portland State University.

3.6 Offsite Storage Agreement OIT has contracted with Iron Mountain to store the backup tapes offsite in a secure location in a different area of Portland. The current frequency of the offsite rotation is to have full backup tape sets for all servers sent offsite every week. This will allow for the oldest data set to be 7 days or less in the event that restores need to occur.

3.7 Documentation of Current Systems Maintaining current documentation of the file and directory systems will also ease the process of recovery. In the event that key personnel are lost or injured, alternates or replacements will be able to understand the configuration of the systems. Each team in TIS maintains documentation on the structure of the services provided to the campus. The IS Team maintains their own documentation about the structure and recovery procedures for Oracle and SungardHE Banner.

3.8 Storage of DRP An up-to-date paper copy of the Disaster Recovery Plan will be stored at the offsite Iron Mountain location. A copy of this entire document, burned onto CD’s, will be given to each member of the Disaster Recovery Management team as well as to the Western Washington University IT Director.

OIT Disaster Recovery Plan, 2010 Page 15 of 59 6/14/2010

4.0 DISASTER DETECTION AND INITIATION In almost any disaster, hazards and dangers can abound. While survival of the disaster itself can be a harrowing experience, further injury or death following the disaster stemming from carelessness or negligence is senseless. Safety of personnel will be the top priority of TIS. This section will discuss the possible hazards to be aware of during an emergency.

4.1 Red Cross Information As disaster workers seek to meet the needs of victims and communities following any type of disaster, they are surrounded by and exposed to disorganization, confusion, scenes of destruction, and the tears and the pain of victims. Disaster workers have the potential to become "secondary victims," as they work long, hard hours under poor conditions. In some cases, physical dangers exist for responders. Worker accommodations may be poor when they are near or within the affected area, or may require an hour or more of travel when located outside the affected area. Personal support systems are left at home, and new supports must be formed while on the operation and while time is scarce. Supervisory styles are different from person to person; administrative organization and regulation often must change with little warning, adding additional stressors as workers try to satisfy the needs of the clients and of the organization. Most disaster workers are dedicated individuals who also tend to be perfectionists. Because of this, they are at risk of pushing themselves too hard and of not being satisfied with what they have accomplished. With so much yet to do, they often fail to take credit for the amount of work completed and the effort contributed to the operation. Frustration is common, and our usual sense of humor is often stretched beyond limits. Workers become exhausted, and anger comes easily to the surface. The anger of others -- workers, victims, and media -- becomes difficult to deal with, and may be seen as a personal attack on the worker rather than as a normal response to exhaustion. Survivor guilt may emerge as workers see the losses of others when they have suffered none themselves. COPING: Remember that you are giving those victimized by the disaster a gift of yourself -- your time and your caring -- a gift you could not give if you were also a victim. This may be your first experience with scenes of great destruction or high levels of injury and death. These are realities we don't often face, and methods of coping with these are not developed overnight. In each of us, there is an unconscious fear that a victim could be you or a loved one. You need to understand and appreciate the intensity of your emotions, and talk about your feelings to others.

OIT Disaster Recovery Plan, 2010 Page 16 of 59 6/14/2010

Although we may function in superhuman ways during a disaster operation, the stress associated with our jobs takes its toll. We get tired . . . and confused . . . and hurt . . . and scared. It is critical both for ourselves and those we try to help that we understand the effects of stress and make every effort to deal with it. Stress-relieving activities are not as difficult or time consuming as we may think. A 15-minute walk during a lunch or coffee break; talking to a co-worker, supervisor, or mental health worker; going out to dinner or a movie; or just learning and using deep breathing exercises can significantly reduce stress. During the operation, it's important to eat nutritional foods, avoid drinking large amounts of caffeine and alcohol, get some exercise whenever possible, and get as much sleep as you can. That way you'll be better able to continue meeting the challenges of your job. Your supervisors will be attempting to juggle schedules so that you can have some time off to yourself to sleep, read, or just sit in the sunshine. If you feel that you need this time off before you're scheduled for it, just ask. If you need a change of assignment or setting, just ask. And, hard as it may be to turn over your duties to someone else, when it is time for your shift to be over, leave and take time to recharge.

4.2 Disaster Recovery Teams To function in an efficient manner and to allow independent tasks to proceed simultaneously, the recovery process will be handled by teams. This plan calls for teams that work together, but for which specific portions of the recovery are assigned. Disaster Recovery Management Team The Disaster Recovery Management Team oversees the whole recovery process. The members of this team should be comprised of personnel who are extremely familiar with the structure, systems, and services that Technology Infrastructure Services provides to Portland State University. The DR Manager leads the DR Management Team. In the case of TIS, the DR Manager will be the current Associate CIO for Technology Infrastructure Services. The DR Manager has the final authority on technical decisions that must be made during the recovery but works closely with the Incident Commander dedicated to OIT, typically the CIO, to ensure organizational goals are being met while dealing with the disaster. The DR Manager is responsible for appointing the other members of the Recovery Management Team. If appropriate, the DR Manager will ask additional university staff from Facilities or other areas to participate on the team. If the University Disaster Response Team has been mobilized, the DR Manager will take direction from the Incident Command center. Damage Assessment Team

OIT Disaster Recovery Plan, 2010 Page 17 of 59 6/14/2010

The Damage Assessment Team will be comprised of personnel who are knowledgeable about the hardware and equipment located in the Fourth Avenue Building Data Center. Likely choices for this team would be a member(s) from Physical Plant, NTS, CIS teams and the IS team. The primary thrust for this team is to do two things: Provide information for the Recovery Management Team to be able to make the choice of the recovery site and provide an assessment of the recoverability of major hardware components. This team will also be the main group involved with salvaging any equipment in the data center. Based on this assessment the DR Management Team can begin the process of acquiring replacement equipment for the recovery. Facility Recovery Team The Facility Recovery Team should be led by a member in Facilities but will also need to include members from TIS. This team will be responsible for the details of preparing the recovery site to accommodate the hardware, supplies, and personnel necessary for recovery. They will be responsible for the oversight of the activities for the repair and/or rebuilding of Fourth Avenue Building or a secondary site. It is anticipated that the major responsibility for this will lie within Facilities and contractors. However, this team must oversee these operations to ensure that any facility is repaired to properly support data center operations. All infrastructure recovery (networking, power, AC, UPS, generator, security, etc.) will be the responsibility of Facilities and relevant TIS Teams. The recovery of specific services and data will be the responsibility of the individual teams in OIT (NTS, CIS and IS). Each team has separate recovery plans for restoring services quickly. Overall Data Center restart strategy can be found in Appendix G.

4.3 Disaster Detection and Determination The detection of an event which could result in a disaster affecting production or information processing systems at Portland State University is the responsibility of the Associate CIO for Technology Infrastructure Services, CIS, NTS or whoever first discovers or receives information about an emergency situation developing in one of the functional areas of Technology Infrastructure Services.

4.4 Disaster Notification Whoever detects the disaster should notify the Associate CIO for Technology Infrastructure Services or the Associate Director for Computing Infrastructure Services (CIS) who is responsible for the Data Center. In addition to providing some fault tolerance in initial response, this role sharing enables effective use of shifts during the

OIT Disaster Recovery Plan, 2010 Page 18 of 59 6/14/2010

disaster recover process. The Associate CIO for TIS or Associate Director for CIS will monitor the evolving situation and, if appropriate, will then notify the Disaster Recovery Teams in TIS. The complete emergency contact list for the university is included in Appendix A.

4.5 When to Activate the Plan The plan should be activated if any of the following circumstances occur: Any damage to the Fourth Avenue building for any reason, which includes but is not limited to fire, water, acts of terrorism and/or sabotage. Furthermore, this Disaster Recovery Plan could be activated whenever an action occurs that hampers Technology Infrastructure Services ability to provide service to the campus community for a period greater than 48 hours.

4.6 What to Do When a Crisis Erupts As soon as a potential crisis situation develops, the first person to be alerted should be the Associate CIO for Technology Infrastructure Services who will also be the DR Manager. If it is determined that a crisis situation has occurred, that person will alert TIS personnel in order to help activate the Disaster Recovery Plan. The first phase begins with the initial response to a disaster and activation of the plan. During this phase, the existing emergency plans and procedures of Portland State’s Campus Public Safety Office direct efforts to protect life and property, the primary goal of initial response. Security over the area is established as local support services such as the Police and Fire Departments are enlisted through existing mechanisms. Once access to the facility is permitted, an assessment of the damage is made to determine the estimated length of the outage. If access to the facility is precluded, then the estimate includes the time until the effect of the disaster on the facility can be evaluated. If the estimated outage is less than 48 hours, recovery will be initiated under normal operational recovery procedures. Use of facilities in the Urban Center or Cramer Hall should be investigated to see if systems can be brought online in that location. If the service outage is longer than 48 hours, the DR Manager will decide upon the appropriate warm site for recovery (on-site at another location, Western Washington or elsewhere).

OIT Disaster Recovery Plan, 2010 Page 19 of 59 6/14/2010

5.0 ACTIVATING THE PLAN The DR Recovery Manager sets the plan into motion. Early steps to take are as follows: The Recovery Manager should retrieve the Disaster Recovery Plan. Copies of the plan should be made and handed out at the first meeting of the DR Recovery Management Team if possible. Determine Personnel Status One of the Recovery Manager's important early duties is to determine the status of personnel working at the time of the disaster. Safety personnel on site after the disaster will affect any rescues or first aid necessary to people caught in the disaster. However, the Recovery Manager should produce a list of the able-bodied people who will be available to aid in the recovery process. Taking care of people is a very important task and should receive the highest priority immediately following the disaster. While we will have a huge technical task of restoring computer and network operations ahead of us, we can't lose sight of the human interests at stake. Equipment Protection and Salvage A primary goal of the recovery process is to restore all computer operations without the loss of any data. The Damage Assessment Team can immediately set about the task of assessing the damage to the data center, and protecting and salvaging any equipment or hardware, especially those on which data may be stored. This document contains information on procedures to be used immediately following an incident to preserve and protect resources in the area damaged. It is important that any equipment or hardware in the Fourth Avenue Building be protected from the elements to avoid any further damage. Some hardware may be salvageable or repairable and save time in restoring operations. The Damage Assessment team should cover all computer equipment to avoid water damage. Ask the police to post security guards at the primary site to prevent further damage. All salvageable equipment will need to be moved to a secure location or the warm site. As soon as practical a complete inventory of all recovered equipment must be taken, along with estimates about when the equipment will be ready for use (in the case that repairs or refurbishment is required). This inventory list should be given to the DR Manager who will use it to determine which items from the disaster recovery hardware and supplies lists must be purchased to begin building the recovery systems. Establish the Recovery Control Center The Recovery Control Center is the location from which the disaster recovery process is coordinated. The Recovery Manager should designate where the Recovery Control Center is to be established. Depending on the extent of damage, the center may be located off of the campus. Initial Steps of the Disaster Recovery Management Team

OIT Disaster Recovery Plan, 2010 Page 20 of 59 6/14/2010

The DR Manager is to call a meeting of the Recovery Management Team at the Recovery Control Center or a designated alternate site. Each member of the team is to review the status of their respective areas of responsibility. The DR Manager briefly reviews the plan with the team. Any adjustments to the Disaster Recovery Plan to accommodate special circumstances are to be discussed and decided upon. Each member of the team is charged with fulfilling his/her respective role in the recovery and to begin work as scheduled in the DR Plan. Each member of the team is to review the makeup of their respective recovery teams. If key personnel on any recovery team are unavailable, the DR Manager is to assist in locating others who have the skills and experience necessary, including locating outside help from other OUS institutions or vendors. The next meeting of the Recovery Management Team is scheduled. The DR Management team should meet at least once each day for the first week of the recovery process. An assessment can be made at the end of the first week to decide the frequency of additional meetings. The DR Management Team members are to immediately start the process of calling teams together to begin the recovery process. Cell phones and two-way radios will be important during the early phases of the recovery process. Some departments in OIT have two-way radio units that may be available if damage is not severe to the Fourth Avenue Building.

6.0 DISASTER RECOVERY STRATEGY The disaster recovery strategy pertains specifically to a disaster disabling the main computing facility in the Fourth Avenue Building. This functional area provides the infrastructure and major server support to Portland State’s administrative applications.

6.1 Recovery Procedures The time required for recovery of the functional area and the eventual restoration of normal processing depends on the damage caused by the disaster. The time frame for recovery can vary from several days to several months. In either case, the recovery process begins immediately after the disaster and takes place in parallel with back-up operations at the designated warm site. The primary goal is to restore critical operations as soon as possible.

6.2 Team Plans Defined

OIT Disaster Recovery Plan, 2010 Page 21 of 59 6/14/2010

Each team under the TIS umbrella and IS have documented the configuration and installation details for the different services and applications provided to the campus. This enables them to work on recovery and restore procedures as needed for various scenarios. Each team documents the list of services they provide, additional hazards specific to the particular services and applications, the equipment necessary for recovery, assuming that all infrastructure will be provided either at the Fourth Avenue facility or rebuilt at another facility and the restore procedures for recouping data. This also includes activating the limited warm site at WWU. These plans also define the various levels of criticality for the services and applications OIT provides to the university. These levels of criticality will be used to define the order in which TIS and IS services will be brought back online in the event of an emergency. Each team plan uses these definitions when assigning importance to the recovery of the services and applications provided to the campus. The levels are: Critical (Category 1) – the University can not run without these applications and/or information and/or services and these things cannot be run without identical capabilities being setup in another location (Western Washington University or other). Vital (Category 2) – this information and/or applications and/or services have a higher tolerance of interruptions but for only very brief amounts of time. Sensitive (Category 3) – this information and/or applications and/or services can be run by manual means or not at all for a longer period of time with the knowledge that once restored there will be significant amounts of “catch-up” to be done. Noncritical (Category 4) – this information and/or application and/or service can be interrupted for a significant amount of time without loss to business. There is no “catch-up” to be done once the application has been restored.

6.3 Team Plans by Service The plan is presented in 4 parts: I. Services provided by the TIS Teams II. Levels of Severity III. Disaster Conditions IV. Disaster Recovery Strategies I. Services provided by the TIS Teams

A. Network Connectivity within the Data Center

OIT Disaster Recovery Plan, 2010 Page 22 of 59 6/14/2010

This encompasses Fast Ethernet or higher connectivity for OIT servers, such as the central UNIX/Linux and Windows servers and systems that comprise Banner. This service focuses only on connectivity between these servers, and not necessarily to the rest of the PSU campus or to the Internet. This service must be available all the times that it is necessary for Banner to be functional.

B. Network Connectivity on PSU Campus This service is Gigabit or Fast Ethernet connectivity between PSU buildings and sites on campus. It includes connectivity between Data Center and the rest of the PSU campus. This service should be available almost all the time; however, it is slightly less critical than service A.

C. Internet Connectivity This service provides a connection to the Internet for the PSU Campus. Any connectivity to sites not on the PSU campus falls into this service. This service should be available nearly all the time. It is slightly less critical than service B.

D. VPN (and dialup) Provides remote access to the PSU campus network. This service should be available as often as possible; however, business is not interrupted without this service.

E. Tape Backup/Restore and Offsite Storage Provides tape backup of all systems and regular rotation of tapes to an offsite storage location. Also provides the ability to restore from previous backups. While important, this service will likely begin to operate mostly in a Restore mode after a disaster. If systems are damaged or destroyed, recovery may be necessary from tapes on the PSU campus or located at the offsite storage facility. Operation of this service in a restore mode may be vital to restoring the business functions of PSU.

F. Authentication Services LDAP and Active Directory are provided as authentication mechanisms for users. E-mail, desktop logins, wifi authentication and access to storage are some services that use one of these authentication services.

OIT Disaster Recovery Plan, 2010 Page 23 of 59 6/14/2010

This is a critical service to maintain while users are being served. The services are delivered in a redundant manner to enhance uptime. In the event of a disaster where recovery of core systems takes precedence, bringing up authentication services for all users may be of secondary importance.

G. Domain Name Services Web sites within the University, e-mail addresses and logins to various systems require DNS to be functioning. This is a critical service, even during a disaster, as external connections such as e-mail would still need to resolve to PSU domain names, even though the sites may not be available. This is a critical service and to that end, the service is delivered with some redundancy (including external DNS servers).

H. File Services File services provide individual and shared access to data storage to users on various platforms using various access methods. Access to user files on these servers must be at least 95% available at all times during normal operations. Storage for file services is delivered using redundantly configured equipment whenever possible. In the event of a disaster, recovering file services may be prioritized based on business needs that dictate which services are brought on line first.

I. Print Services Print Services include components such as print servers, print queues, print devices and printing configuration in a network environment. Print services are provided either by Windows or UNIX servers. Access to print services must be at least 95% available during normal operations. During a disaster, they may have a reduced priority.

J. Electronic Messaging services Electronic Messaging services refer to the comprehensive enterprise messaging system that provides electronic mail, scheduling and other groupware components. This service must be available 95% during normal operation. During a disaster, bringing up e-mail services is critical but may be constrained by the time taken to restore the data before bringing the service online.

K. Banner Systems The Banner ERP system is delivered by a series of servers. During normal operation, this service must be available 95% and during a disaster scenario, it is one of the first large

OIT Disaster Recovery Plan, 2010 Page 24 of 59 6/14/2010

systems that must be brought back online. This will require personnel from CIS who deal with bringing up the servers and personnel from IS who deal with the configuration of the Banner software.

L. Web services PSU provides a University level web presence in addition to those for other academic and administrative departments. During normal operation, this service needs to be delivered with a high degree of reliability. During disaster conditions, bringing up a makeshift University level web presence on the warm site as a means of communicating with constituents is vital. Due to the complex nature of the existing technologies used for the websites, it may not be possible to deliver the existing websites in their entirety on the warm site. As PSU continues to develop the new system for campus-wide website delivery, it may be possible to mirror this system offsite. II. Disaster Conditions • Major Disaster (Earthquakes, Fires, Floods) • • Power Outage • • Cooling Unit failure • • KVM switch or console access failure • • Server hardware component failure • • Server operating system errors • • Server enterprise application\program errors • • Data Corruption • • Denial of Service • • Unauthorized access of network resources III. Disaster Recovery Strategies A. Major Disaster (Earthquakes, Fires, Floods) Warm sites for recovery (Western Washington, local warmsite – if available, etc)

OIT Disaster Recovery Plan, 2010 Page 25 of 59 6/14/2010

In the event of such a major disaster, priority will be given to restoring service A (connectivity between servers for critical services). Once Banner and its supporting services have been restored, attention can be given to assessing damage and the possibility of reconnecting PSU campus sites/buildings to the campus network. Network hardware, whether previously in production or not, from other PSU sites/buildings may be used in order to restore service A if necessary. Restoration from Backups either at a warm site or at the offsite storage facility may be necessary in the event of a major disaster. Thus, it is vital that tape drives be available in order to restore data. A tape drive and other necessary hardware and software should be located at our warm site or some other off-site location. A tape subsystem has not yet been procured for the WWU warmsite pending the results of a backup system redesign that is ongoing at PSU. B.1 Power Outage – External The Fourth Avenue Building is driven from two redundant power feeds originating from separate substations. In the event of the loss of one feed, the building switches to the remaining feed in a matter of seconds. If the building loses both power feeds, the Data Center UPS system picks up the load until the building turbine spins up and starts delivering power to the facility. The UPS system for the Data Center is able to keep systems running for about one hour. This provides a comfortable margin for the turbine to spin up. The turbine is able to drive the building for up to three days before requiring refueling. The redundant systems ensure the Data Center is well protected from external power outages. B.2 Power Outage – Internal The Fourth Avenue Building could experience an internal power event that cuts off power to the Data Center. This could be the result of a failure of the redundant internal power systems or a manual activation of the Emergency Power Off (EPO) controls. When power is lost to the Data Center in this manner, all inbound power must de-activated (typically at the PDUs) so that a restoration of power does not cause unsynchronized reboots of systems. After the power event has been examined and power restored to the Data Center, the systems need to be powered back up according to the Data Center startup/shutdown sequence. (See Appendix G.) C. Cooling Unit failure Failure of air conditioning units in the Fourth Avenue Building Data Center or the CH switchroom could cause extensive shutdowns and/or equipment damage if not dealt with. The FAB Data Center has four separate CRAC units and can continue to sustain acceptable temperatures with the loss of one unit. If more than one unit fails, load shedding would be instituted by shutting down non-essential systems to lower the heat output into the room, and to increase ventilation and air exchange as much as possible.

OIT Disaster Recovery Plan, 2010 Page 26 of 59 6/14/2010

Problems with the CRAC units are handled by PSU Facilities. D. KVM switch failure KVM failure would be especially crippling when coupled with another outage such as a network outage, rendering systems completely inaccessible. A number of legacy KVM switches have been kept by OIT, along with their cabling components, in the case of failure of the entire CAT5-based KVM switching system. Also, overflow space exists on the head-end KVM switch in case of failure of any single switch. Critical or necessary systems would be attached to an alternate KVM switch if such was necessary in order to regain control of the system or administer it. With the increased support for network based remote console access in newer server purchases (like Dell’s DRAC and SUN’s ALOM for example), console access can be achieved directly from a management station on the network. E. Network hardware component failure Hardware failure affecting network equipment, such as switches or routers, would likely bring down a portion of the campus network, but no single failure could bring down all network services. The Data Center network is engineered with redundant network switches and dual connects to many critical systems. Spares exist for most types of Cisco switching modules, and critical Cisco equipment is also covered under 24x7x4 service contracts. If spares of the failed component did not exist and 4-hour response was to be delayed or insufficient, other equipment could be repurposed, potentially altering the network topology near the failure, in order to bring systems back up to some level of connectivity. F. Server hardware component failure Examples of server hardware components that could fail are the following: • Hardware components in Servers and Storage Area Network systems such as power

supplies, hard drives, hard drive controllers, RAID arrays, processors, network cards, memory modules and SAN switches;

• Tape libraries; • External hard drive arrays; • Backup tape drives or towers; Server and storage system failures are dealt with by placing critical (and unique) equipment under a maintenance plan with a quick delivery of spares and/or diagnostic services. In the case of server models that are in widespread use in the data center, a failure would be dealt with by pulling a less critical unit into service to replace the failed unit. As the purchases of new servers moves increasingly into the Blade Server area, a higher level of built-in redundancy provides systems that are able to recovery more easily from component failures.

OIT Disaster Recovery Plan, 2010 Page 27 of 59 6/14/2010

G. Networking system errors Major software error/failure on a network component is almost always resolved by rebooting the affected device, causing minimal downtime. If a reboot did not solve the problem, it is likely that an active attack is occurring, or some hardware component has failed or become unreliable. In this case, advanced troubleshooting/diagnosis will be required to resolve the issue. H. Server operating system errors Errors may appear due to operating system bugs, configuration issues or in interactions with software or the network. Diagnostic procedures are platform dependent. The system administrators need to ensure patches are being applied in a timely fashion. I. Data Corruption Data corruption would be especially disastrous if it occurred on the backup tapes and backups were necessary due to another disaster. It is therefore vital to test restoration from backup tapes regularly to ensure PSU can restore from backups. J. Denial of Service This type of attack is common and can almost be expected to occur at some time on a major scale at PSU. By observing traffic patterns on the network, using a network sniffer, and other troubleshooting steps, the source of the attack can usually be identified and either filtered or disconnected from the network. If the attack is distributed, with many clients both internal and external to PSU and network filtering is unable to block the attack, systematic disconnection of affected systems is the only method to ensure restoration of critical services. This may take time, and thus if the attack is severe and distributed enough, it may be necessary to disconnect the majority of the network and only reconnect small sections at a time as critical services are needed. K. Unauthorized access of network resources This should only be classified as a disaster if the unauthorized access cannot easily be stopped, or vital data to the ongoing security of PSU systems or Enterprise data has been compromised. If unauthorized access is ongoing and the data are critical, the machine should be unplugged from the network or even from power to stop the access. If it becomes known that vital Enterprise data such as student records, financial information, etc. has been compromised, law enforcement must be involved in the investigation, and OIT resources should be dedicated to discovering the extent of the access and compromised data, ascertaining how the data was accessed, and ensuring the data will be secure in the future.

OIT Disaster Recovery Plan, 2010 Page 28 of 59 6/14/2010

6.5 Central Services Recovery Plan Urban Center (construction of this localized warmsite has now resumed): We plan to construct a limited warm site in this building, collocated with the network infrastructure in place in the building entry terminal. Two racks with power and network connectivity will be provided. This location will serve as the localized warm site, containing a mixture of directory services, a basic University web presence and a functional version of Banner that can be used by administrators in the event of a disaster. Western Washington University PSU has an Inter-Governmental Agreement with WWU, giving each institution access to two racks worth of data center capacity on a reciprocal basis. We have installed a complement of equipment that is capable of running a limited instance of Banner. In the event of a catastrophic failure at PSU that disables the FAB Data center, the WWU warm site will be brought online. NOTE: if Banner is in use at WWU, we cannot access or use Banner here at PSU as there is only one master mode. Once Banner is brought back up at PSU, we will need to ensure that all transaction logs are copied back to local systems here at PSU before going live with Banner locally. Currently, the Banner warm site is implemented by two Sun servers, one for running the database and the other for running the Banner applications servers (Banweb and inb). Oracle db data updates are copied from PSU to WWU nightly. Periodically, a copy of the Oracle and Banner application trees are also copied over to WWU. This process allows us to keep a current copy of Banner at an offsite location without having to use backup tapes to recover from in the event of an emergency. In the event of warm site activation, IS personnel will access the systems remotely through a VPN (located at WWU), configure and load the database and then bring up the application servers. The activation process could take up to 48 hours. In the future, we intend to speed up the ability to activate the warm site by using Oracle DataGuard to sync up the Banner . General Information: System Administration procedures related to Disaster Recovery The CIS UNIX and Windows teams document and maintain system administration procedures related to backup and restores, service setup and recovery and other processes that may be used during disaster recovery. Since this information changes frequently, it

OIT Disaster Recovery Plan, 2010 Page 29 of 59 6/14/2010

will not be copied into this document. Instead, a monthly copy of system administration procedures will be placed along with the offsite copy of the Disaster Recovery plan. A copy is also placed at the warm site.

7.0 PLAN MAINTENANCE AND TESTING Having a disaster recovery plan is critical. But the plan will rapidly become obsolete if a workable procedure for maintaining the plan is not also developed and implemented. This document provides information about the maintenance procedures necessary to keep it up to date. Basic Maintenance The plan will be annually evaluated and updated. All portions of the plan will be reviewed by the Associate CIO for Technology and the Associate Director for CIS. If it is deemed that portions need to change or be rewritten or reviewed by other TIS Teams, the Associate CIO for Technology will assign that task to the appropriate team. In addition the plan will be tested on a regular basis and any faults will be corrected. The Data Center Management Group, comprised of the Associate Director of CIS along with select members of the team, has the responsibility of overseeing the individual components and files and ensuring that they meet standards consistent with the rest of the plan. Change-Driven Maintenance It is inevitable in the changing environment of the computer industry that this disaster recovery plan will become outdated if not evaluated annually. Changes that will likely affect the plan fall into several categories: • Hardware changes • Software or Application changes • Facility changes • Procedural changes • Personnel changes As changes occur in any of the areas mentioned above, TIS management will determine if changes to the plan are necessary. This decision will require that the managers be familiar with the plan in some detail. A document referencing common changes that will require plan maintenance will be made available and updated when required. Changes Requiring Plan Maintenance The following lists some of the types of changes that may require revisions to the disaster recovery plan. Any change that can potentially affect whether the plan can be used to successfully restore the operations in OIT systems should be reflected in the plan. Hardware

Additions, deletions, or upgrades to hardware platforms. Software or Application

OIT Disaster Recovery Plan, 2010 Page 30 of 59 6/14/2010

Additions, deletions, or upgrades to system software. Changes to system configuration. Changes to applications software affected by the plan.

Facilities

Changes that affect the availability/usability of any warm sites. Personnel

Changes to personnel identified in the plan. Changes to organizational structure of the department.

Procedural

Changes to off-site backup procedures, locations, etc. Changes to application backups. Changes to vendor lists maintained for acquisition and support purposes.

Testing This plan will be tested on an annual basis to ensure that the procedures will work in the event of a disaster. A report will be submitted to the TIS management staff after the completion of the test that will detail the success and/or failure of the test. A discussion surrounding any improvements to the plan will happen. Any revisions to the document based upon the results of the test and the discussion in management will be integrated into the document. The current warm site configuration, with new hardware and software configurations, is awaiting its first test.

OIT Disaster Recovery Plan, 2010 Page 31 of 59 6/14/2010

8.0 Appendix A: EMERGENCY CONTACT LIST Current OIT Contact List:

NAME E-MAIL OFFICE HOME # CELLULAR PAGER ARC - Academic Research Consultants [email protected] 5.9112 Arnold, Rick [email protected] 5.9145 503.557.3990 971.222.8247 Atalig, David [email protected] 5.9115 503.482.5800 *503.853.4341 Avery, Terell [email protected] 5.9523 503.560.1497 Bass, Ryan (Director) [email protected] 5.4759 *503.577.8958 Beall, Scott [email protected] 5.3268 503.287.5141 503.789.5275 Bechdoldt, Inna [email protected] 5.3267 503.707.5930 Birch-Wheeles, Tamarack [email protected] 5.3201 971.255.0479 *503.317.6499 Blanton, Sharon (CIO) [email protected] 5.9144 503.206.8728 *503.320.3787 Booth, Jeremy [email protected] 5.5907 Bowen, Rick [email protected] 5.3399 503.654.4617 *503.204.2713 Bowen, Sandy [email protected] 5.3278 503.654.4617 Broderick, Kirby [email protected] 5.4367 503.317.4769 Buono, Nick [email protected] 5.9160 503.784.6484 Burt, Jason [email protected] 5.3270 805.776.3709 CAMPUS OPERATOR 5.6411 Charbonneau, Michelle [email protected] 5.6202 503.481.6119 *503.481.6119 Chen, Christopher [email protected] 5.8424 415.710.6139 CIS - SERVER OPERATIONS

[email protected] 5.9151

Cookus, Rocky [email protected] 5.4369 503.789.3077 Cooley, Will [email protected] 5.8479 503.788.4688 971.235.5105 Cox, Bryan [email protected] 5.8490 Daffron, Clayton [email protected] 5.6201 971.409.6582 Ehlert, Michael [email protected] 5.3498 Evanoff, Anni [email protected] 5.3294 *503.327.3542 Everall, Brian [email protected] 5.9182 971.404.8264 Fetter, David [email protected] 5.9154 971.238.0793 503.202.1814 Foster, Brad [email protected] 5.9119 206.235.3408 Freeman, Mark [email protected] 5.8493 503.531.3489 *503.720.5006

OIT Disaster Recovery Plan, 2010 Page 32 of 59 6/14/2010

Frey, Gordon [email protected] 5.3480 503.283.5610 503.309.8552 Garrick, Will [email protected] 5.3235 503.236.3915 *503.539.6669 Gilbert, Dennis [email protected] 5.3250 503.384.0289 *503.348.3143 Giles, Shem [email protected] 5.3255 503.294.9999 *503.572.9893 Gostomski, Michael [email protected] 5.9153 503.475.5314 Guyette, David [email protected] 5.4366 734.904.0040 Harris, Ann (Director) [email protected] 5.3448 503.786.7935 *503.348.2601 Hartig, Ben [email protected] 5.9112 503.957.5257 Harvey, Morgan [email protected] 5.9112 503.953.3976 Henderson, Beverly [email protected] 5.3141 503.231.9132 503.804.9686 Henry, Nate [email protected] 5.3488 503.282.4732

Hison, Tudor [email protected] 5.3284

*503.740.7503 Hoover, Lance [email protected] 5.5894 503.257.8492 *503.319.2065 IS - BANNER TECHNICAL HOTLINE 5.9560 IS/CIS/ARC ADMIN OFFICE 5.4441 ITS - CLASSROOM AUDIO VISUAL SUPPORT [email protected] 5.9100 ITS - DLC OPERATIONS 5.9146 ITS - VIDEO PRODUCTION SERVICES 5.2630 Jayawardena, Janaka (ACIO) [email protected] 5.5410 503.336.3750 *503.941.0374 503.921.1385 Johnston, Tim (Director) [email protected] 5.2776 503.588.0955 *971.645.2216 King, Todd [email protected] 5.5430 360.896.8587 Kutch, Brenna [email protected] 5.8522 *503.929.0485 La Tourrette, Tyson [email protected] 5.9166 Lee, Carolyn [email protected] 5.4358 503.547.8408 *503.381.6828 Linton, Thom [email protected] 5.9100 919.302.1103 McCartney, Doug (Director) [email protected] 5.9110 503.262.8102 *503.890.8751 McElroy, Kenny [email protected] 5.3368 503.267.6150 Miller, Leslie [email protected] 5.6420 *503.481.6326 Miranda, [email protected] 5.3289 503.284.0150 *971.285.5004

OIT Disaster Recovery Plan, 2010 Page 33 of 59 6/14/2010

Adrian Mitarnowski, Matthew [email protected] 5.6204 503.929.3368 Moore, James [email protected] 5.8467 503.473.6260 Morillas, Monica [email protected] 5.9104 503.740.5257 Moskal, Mary Kay [email protected] 5.5544 360.885.0510 360.989.0792 Myers, Brian [email protected] 5.9143 *503.756.6625 Naanee, Lisa [email protected] 5.4067 503.866.0414 Nimura, Alison [email protected] 5.9868 503.515.8691 NTS - NETWORK OPERATIONS CENTER [email protected] 5.3280 NTS - TELEPHONE REPAIR AFTER HOURS 5.6400 Oreste, Joe [email protected] 5.4359 503.888.9481 Owens, Thomas [email protected] 5.9529 503.560.4193 Oxman, Max [email protected] 5.8580 503.880.7535 Parmer, Max [email protected] 5.9157 503.380.7455 Powell, Shari [email protected] 5.3394 *971.544.1984 Richeson, Rod [email protected] 5.6203 503.267.1320 Robbins, Ward [email protected] 5.4218 503.632.2336 *971.998.7950 Schiller, Craig [email protected] 5.9107 *503.330.3162 Schmierbach, James [email protected] 5.9158 503.381.8256 Shapiro, David [email protected] 5.3370 503.238.4580 503.599.7749 Stapleton, Jim [email protected] 5.8492 503.774.0880 *503.753.3782 Sukhun, Jahed (Director) [email protected] 5.3323 503.848.5921 *971.998.4162 Thomas, Erica [email protected] 5.9147 *859.327.7711 Thomas, Jerrod [email protected] 5.8558 971.285.6044 Tuggle, Jim [email protected] 5.4466 360.636.2754 USS - HELP DESK [email protected] 5.4357 USS - LABS AND CLASSROOMS [email protected] 5.8725 Vo, Jacquelyn Tran [email protected] 5.3588 503.775.1371 503.860.1935 Waisanen, Ben [email protected] 5.8461 503.238.5217 503.921.1364 Walker, Mark [email protected] 5.8280 503.570.7941 Walsh, Dan [email protected] 5.3310 503.654.7890 *503.704.8393 503.599.2979

OIT Disaster Recovery Plan, 2010 Page 34 of 59 6/14/2010

Weeks, Ellen [email protected] 5.2345 *503.231.1838 Weltin, Markus [email protected] 5.9112 971.207.8632 Williams, Matt [email protected] 5.8344 *971.544.0842 503.921.1583 Wortman, Inge [email protected] 5.5483 *503.740.2727 Wrate, Timothy [email protected] 5.4201 Wright, Jeffery [email protected] 5.9108 503.803.8986 Zaw-Tun, Naing [email protected] 5.5893 503.980.3422 503.329.6581 FAB 83 (Large IS) Conference Room 5.9179 FAB 83-09 (Small IS) Conference Room 5.5720 FAB 84 (Telecom) Conference Room 5.8075 FAB 87-01 Conference Room 5.9014 FAB 90-01 Conference Room 5.2968 SMSU 18N Conference Room 5.9130 Help Desk (SMSU 18) Fax 5.3360 FAB 83 Fax 5.6487 SMSU 18P Fax 5.3476

OIT Disaster Recovery Plan, 2010 Page 35 of 59 6/14/2010

9.0 Appendix B: VENDOR LIST Below is the contact information for the vendors of all components in this recovery plan. This list will be updated for all vendors used by TIS and IS as it relates to disaster recovery efforts. Vendor Product Support Number Support ID CommVault Backup

Software (877) 780-3077 F4B30

HP (Comark)

Servers 1-800-633-3600

Dell Servers 1-800-234-1490 Sun Servers and

Software 800-USA-4SUN

Microsoft Software 800-936-4900 Sungard Banner 800-825-2518 Cisco Network

Switches, Routers

1 800 553 2447 1 408 526 7209

Avaya Campus Phone System

OUS INOC (1-541-713-3331) Avaya (1-800-242-2121)

Customer ID #0003033700

Oracle Database 800-223-1711 Qwest Local PBX

Trunks, QMOE link to Pittock

1-800-214-8043; 503-425-5214; QMOE:

1-800-227-2218

Juniper Network Switch/Router

1-888-314-JTAC (1-888-314-5822)

Iron Mountain

Offsite Backup Storage

888-365-4766 102932

Black Box Network Services (BBNS) /AVST

Campus Voice Mail System

Normal Bus. Hrs.: 1-888-565-2400 (press “2); Emergency After Hrs.: 1-800-895-2400 (press “1”); If Req’d., Escalation: 1-800-895-2400, ext. 255

Integra Telecom

Link to CapCenter, Link to PBA,

OIT Disaster Recovery Plan, 2010 Page 36 of 59 6/14/2010

Modem Pool Lines

USA Mobility Wireless Inc.

Pagers 503-477-4541

AT&T Mobility

Cell Phones

425-580-5565;

Cellular: 425-495-9118

City of Portland IRNE

Main campus link to Pittock

503-823-1000

OIT Disaster Recovery Plan, 2010 Page 37 of 59 6/14/2010

10.0 Appendix C: NETWORK DIAGRAMS PSU Network Connectivity (internal and external)

OIT Disaster Recovery Plan, 2010 Page 38 of 59 6/14/2010

WWU Warm site connectivity with PSU

OIT Disaster Recovery Plan, 2010 Page 39 of 59 6/14/2010

11.0 Appendix D: WARM SITE AGREEMENT

OIT Disaster Recovery Plan, 2010 Page 40 of 59 6/14/2010

OIT Disaster Recovery Plan, 2010 Page 41 of 59 6/14/2010

OIT Disaster Recovery Plan, 2010 Page 42 of 59 6/14/2010

OIT Disaster Recovery Plan, 2010 Page 43 of 59 6/14/2010

OIT Disaster Recovery Plan, 2010 Page 44 of 59 6/14/2010

OIT Disaster Recovery Plan, 2010 Page 45 of 59 6/14/2010

12.0 Appendix E: AGREEMENT WITH IRON MOUNTAIN OFFSITE STORAGE Offsite Storage for Critical Data Processing Records Description of Services: Iron Mountain agrees to provide offsite storage and security of data processing records for Portland State University. This service is to include storage, handling, pick-up and delivery of media at the customer’s location. Each Iron Mountain facility is designed and constructed specifically for the storage of magnetic media (no bulk paper) and conforms to ANSI and NFPA requirements. The entire facility is constructed with building features designed to minimize risk of fire and unauthorized entry. Protective measures include: • Halon-protected, climate-controlled vaults • Building is seismically upgraded • Building located outside of the 100 year flood plain • Concrete vaults are built independent of exterior structure, a building within a

building • Building alarmed with Sonitrol alarm systems. Each is monitored by both fire and

police departments • Iron Mountain employees only interact with authorized Customer personnel • Vehicles are: independently climate-controlled and halon-protected, locked and

alarmed at all times, with cellular phones for communications

OIT Disaster Recovery Plan, 2010 Page 46 of 59 6/14/2010

13.0 Appendix F: WARM SITE EQUIPMENT AND CONFIG

HARDWARE The following equipment is located at the Western Washington University Warm Site (333 32nd St, Bellingham, WA 98225) – Contact Number 360-650-3000:

• Firewall: Cisco ASA 5550 w/VPN Premium License • Switch: Cisco WS-C3750G-24TS • Server: Sun Netra T2000, 4 core, 16 thread 1.2Ghz Niagara T1, 32GB RAM

(laga.oit.pdx.edu – Banner DB) • Server: Sun Netra T2000, 8 core, 32 thread 1.2Ghz Niagara T1, 32GB RAM

(nott.oit.pdx.edu – Banner App) • Storage Array: Sun StorageTek 2500 Array • Server: HP DL380 G3 (aah.psu.ds.pdx.edu) • Cyclades terminal server • Misc: Netbotz

NETWORK & CABLING

Cyclades Port Addressing

• Port 3: Laga or Nott • Port 4: Laga or Nott • Port 5: Warmsite_SAN Controller A

Network Addressing

All subnets are /24, with a gateway at .1.

DNS: 131.252.120.128, 131.252.120.129.

• laga.oit.pdx.edu o e1000g0: 10.140.20.45 (prod VLAN) o e1000g3: 10.140.0.47 (mgmt VLAN) o LOM: 10.140.0.45 (mgmt VLAN)

• nott.oit.pdx.edu o e1000g0: 10.140.20.46 o e1000g3: 10.140.0.48 o LOM: 10.140.0.46

OIT Disaster Recovery Plan, 2010 Page 47 of 59 6/14/2010

• Sun StorageTek 2500 Array (Warmsite_SAN) o Controller A: 10.140.0.49 o Controller B: 10.140.0.50

Fiber Channel Cabling

• Laga HBA port 1 to Warmsite_SAN Controller A port 1 • Laba HBA port 2 to Warmsite_SAN Controller B port 1 • Nott HBA port 1 to Warmsite_SAN Controller A port 2 • Nott HBA port 2 to Warmsite_SAN Controller B port 2

External Network Connectivity via Firewall when Warm Site is Activated

All external access requires VPN (ipsec with local account auth) except as otherwise stated. Ports 22, 80 and 443 for nott.oit.pdx.edu (80/443 must be open to the world) Ports 22 and 1526 for laga.oit.pdx.edu Port 3389 for aah.psu.ds.pdx.edu

STORAGE Of the 12 drives in the enclosure, 9 are allocated to laga, and 3 are allocated to nott.

OIT Disaster Recovery Plan, 2010 Page 48 of 59 6/14/2010

OIT Disaster Recovery Plan, 2010 Page 49 of 59 6/14/2010

14.0 Appendix G: DATA CENTER STARTUP/SHUTDOWN PROCEDURES Due to dependencies caused by the interconnected nature of the systems in the Data Center, care must be exercised in startup up and shutting down systems. Bringing up a system providing a service before various dependent services are already online can adversely affect the service and at worst corrupt data. The following tables list the order in which broad categories of services are brought online and taken offline. Specific details of configuration management can be found in the technical documentation of the respective teams. Startup Sequence:

Order System Estimated Time (Minutes) Notes

1 Lenel Card Access 20 1 DNS 20 1 SAN 45 1 LDAP 30 1 Active Directory 20

TOTAL TIME for part 1, assuming one administrator per task 45

2 Banner 45 2 Luminis 45 2 OAM 30 2 pdx.edu Drupal 45 2 Email 60 2 File Servers 30 2 ESX 45

TOTAL TIME for part 2, assuming one administrator per task 60

3 Co-Lo Customers 90 4 Backups 60

GRAND TOTAL TIME 255

OIT Disaster Recovery Plan, 2010 Page 50 of 59 6/14/2010

Shutdown Sequence:

Order System Estimated Time (Minutes) Notes

1 Backups 20 2 Co-Lo Customers 30 3 ESX 30 3 File Servers 10 3 Email 20 3 Banner 30 3 Luminis 20 3 OAM 20 3 pdx.edu Drupal 30 3 Misc Servers 30

TOTAL TIME for part 3, assuming one administrator per task 30

4 Active Directory 15 4 LDAP 30 4 SAN 20 4 DNS 15

TOTAL TIME for part 2, assuming one administrator per task 60

5 Lenel Card Access 15

GRAND TOTAL TIME 155

OIT Disaster Recovery Plan, 2010 Page 51 of 59 6/14/2010

15.0 Appendix F: OIT CONTINUITY OF OPERATIONS PLAN – 2009

Continuity of Operations Plan (COOP) Portland State University

Instructions: As part of PSU emergency response preparations, all PSU departments and units are required to complete this form to document their Continuity of Operations Plan (COOP)—to describe how your department will operate during a natural disaster, pandemic, or other emergency situation and to recover afterwards to be fully operational. This is your Plan; feel free to augment this template to meet your needs. For more information, call Campus Public Safety Director Mike Soto at (503)725-4782, or PSU Emergency Management Coordinator Bryant Haley at (503)725-2220 or Don Johansen, Risk Manager at (503)725-5340.

Department/Unit OIT

Developer Date Plan Finalized Sharon Blanton 9/23/09

Name Phone Number Alt Phone Number Head of Operations Sharon Blanton 5-9144 503-320-3787

Email address [email protected]

A: Your Department’s Objectives Considering your department’s unique mission, describe your teaching, research and service objectives: What We Do PSU-OIT serves campus customers by:

• Providing leadership and direction for the optimal integration of information technology in all University endeavors

• Designing and deploying an efficient and effective campus technology infrastructure including networks, telecommunications, servers and data storage, e-mail and web services, lab and classroom technologies, etc.

• Leading the campus in the development and use of enabling information technologies that support instruction, research and public service

• Developing, implementing and supporting quality information systems for administrative and academic uses

• Supporting the campus community of technology users through assistance, training, and troubleshooting

OIT Disaster Recovery Plan, 2010 Page 52 of 59 6/14/2010

OIT Disaster Recovery Plan, 2010 Page 53 of 59 6/14/2010

B: Emergency Communication Systems All PSU employees are responsible for keeping informed of emergencies by monitoring news media reports, the PSU’s website home page and/or Campus Alert phone messages. To rapidly communicate with employees in an emergency, we encourage all departments to prepare and maintain a call tree. Note below the system(s) you will use to contact your employees in an emergency. Departments should identify multiple communication systems that can be used for backup, after hours, when not on campus, or for other contingencies. Phone Email Text messaging Call tree Departmental web site Pager Instant messaging Other (describe): __all__________________

C: Emergency Access to Information and Systems If access to your department’s information and systems is essential in an emergency, describe your emergency access plan below. This may include remote access (or authorization to allow remote access), contacting IT support, Blackboard, off-site data backup, backup files on flash drives, hard copies, Blackberry/Treo or use of PSU’s webmail email system. All OIT staff use VPN to securely access PSU systems. We have a private IRC channel for emergency communications. We also make extensive use of the OIT wiki that is housed off site. We will file telecommuting forms for all staff. We have also contracted with an external provider for 24x7 helpdesk support.

D: Your Department’s Essential Functions List below your department’s functions that are essential to operational continuity and/or recovery, and who is responsible to perform them. Also indicate if this function can be performed off-site. Make sure that alternates are sufficiently cross-trained to assume responsibilities.

Essential Function: User Support Services

Primary Alternate Second Alternate People Responsible Jahed Sukhun Heather Gregg Max Oxman

Phone Numbers 5-3323; 971-998-4162 5-3466; 503-860-7039 5-8580; 503-880-7535

Remote Capabilities? Y Y Y

Essential Function: Network and Telecomm

Primary Alternate Second Alternate People Responsible Tim Johnston Clayton Daffron Dan Walsh

Phone Numbers 5-2776; 971-645-2216 5-6201; 971-409-6582 5-3310; 503-704-8393

OIT Disaster Recovery Plan, 2010 Page 54 of 59 6/14/2010

Remote Capabilities? Y Y Y

Essential Function: Enterprise Information Systems

Primary Alternate Second Alternate People Responsible Ann Harris Joe Oreste Scott Beall

Phone Numbers 5-3448; 503-348-2601 5-4359; 503-888-9481 5-3268; 503-789-5275

Remote Capabilities? Y Y Y

Essential Function: Enterprise Infrastructure Services

Primary Alternate Second Alternate

People Responsible Ryan Bass Wil Cooley Error! Contact not defined.

Phone Numbers 5-4759; 503-577-8958 5-8479; 971-235-5105 5-5410; 503-476-5541

Remote Capabilities? Y Y Y

Essential Function: Instructional Technology Services

Primary Alternate Second Alternate People Responsible Doug McCartney Mark Walker Rick Arnold

Phone Numbers 5-9110; 503-890-8751 5-8280; 503-449-9733 5-9145; 971-222-8247

Remote Capabilities? Y Y Y

Essential Function: CIO Administrative Operations

Primary Alternate Second Alternate People Responsible Sharon Blanton David Atalig Jackie Vo

Phone Numbers 5-9144; 503-320-3787 5-9115; 503-853-4341 5-3588; 503-860-1935

Remote Capabilities? Y Y N

Review your department’s key personnel, leaders, heads and those responsible for the above essential functions to identify your department’s Emergency Operations Personnel (EOP). Your department’s Human Resources contact can help you identify EOP. For more information on EOP, see Section M below. We strongly encourage all employees to update their contact information in the PSU Emergency Notification System through Employee Link at http://www.pdx.edu/cpso/psu-alert-notification-system, which is kept as private information by default. This contact information may be important in an emergency.

E: Your Department’s Leadership Succession List the people who can make operational decisions if the head of your department or unit is absent.

Name Phone Number Alt Phone Number Head of Operations

Sharon Blanton 5-9144 503-320-3787 (cell)

OIT Disaster Recovery Plan, 2010 Page 55 of 59 6/14/2010

First Successor Janaka Jayawardena 5-5410 503-476-5541 (cell)

Second Successor

Mark Gregory 5-3281 503-348-2672 (cell)

Third Successor Jahed Sukhun 5-3323 971-998-4162 (cell)

F: Key Internal (Within PSU) Dependencies All PSU departments rely on Office of Information Technology, Payroll, Purchasing, Finance, Business Affairs, CPSO, Human Resources, Risk Management, and Facilities Management. List below the other products and services upon which your department depends and the internal (PSU) departments or units that provide them.

Dependency (product or service) : Contracts

Provider (PSU department): Karen Preston

Dependency (product or service) : Legal

Provider (PSU department): David Reece

Dependency (product or service) :

Provider (PSU department):

Dependency (product or service) :

Provider (PSU department):

Dependency (product or service) :

Provider (PSU department):

Dependency (product or service) :

Provider (PSU department):

Dependency (product or service) :

Provider (PSU department):

Dependency (product or service) :

Provider (PSU department):

G: Key External Dependencies List below the products, services, suppliers and providers upon which your department depends. We recommend that you encourage them to prepare continuity of operations plans. Dependency (product or service) :

Disaster recovery site

Primary Alternate

Supplier/Provider Western Washington University

OIT Disaster Recovery Plan, 2010 Page 56 of 59 6/14/2010

Phone Numbers 360-650-3000

Dependency (product or service) :

Data storage

Alternate

Supplier/Provider Iron Mountain

Phone Numbers 800-899-4766

Dependency (product or service) :

Primary Alternate Supplier/Provider

Phone Numbers

Dependency (product or service) :

Primary Alternate Supplier/Provider

Phone Numbers

Dependency (product or service) :

Primary Alternate Supplier/Provider

Phone Numbers

Dependency (product or service) :

Primary Alternate Supplier/Provider

Phone Numbers

Dependency (product or service) :

Primary Alternate Supplier/Provider

Phone Numbers

H: Mitigation Strategies Considering your objectives, dependencies and essential functions, describe below the steps you can take now to minimize the emergency’s impact on your operations. For example, you may wish to stock up on your critical supplies and develop contingency work-at-home procedures. This may be the most important step of your emergency planning process. Formulation of your mitigation strategies may require reevaluation of your objectives and functions. OIT implemented Elluminate, which provides an outsourced capability to hold

OIT Disaster Recovery Plan, 2010 Page 57 of 59 6/14/2010

meetings online.

OIT is in the process of significantly expanding the VPN capability.

OIT is reviewing and renewing telecommuting authorizations.

OIT also has a disaster recovery plan.

I: Exercising Your Plan & Informing Your Staff Share your completed Plan with your staff. Hold exercises to test the Plan and maintain awareness. Note below the type of exercises you will use and their scheduled dates. For assistance in exercising your Plan, contact PSU Emergency Management Coordinator Bryant Haley at (503)725-2220. Staff orientation meeting Emergency communication

test Exercise Dates

Call tree drill Off site information access test

Tabletop exercise Unscheduled work at home day Staff Distribution Date

Interdepartmental exercise

Emergency assembly drill

Other drill (describe): ___________________________________

J: Resumption of Operations Describe your Plan to fully resume operations as soon as possible after the emergency event has passed. Identify and address resumption/scheduling of normal activities and services, work backlog, resupply of inventories, continued absenteeism, the use of earned time off, and emotional needs. See attached DR plan.

OIT Disaster Recovery Plan, 2010 Page 58 of 59 6/14/2010

K: Special Considerations for Your Department Describe here any additional or unique considerations that your department may face in the case of forced closure. Even if we have to shut down operations, we still have to maintain services for the rest of campus. If we have to activate our DR site at Western Washington University, then travel and lodging will be needed.

OIT Disaster Recovery Plan, 2010 Page 59 of 59 6/14/2010

L: Additional Resources and Policy Summaries Emergency Employee Selection Guidelines Departments should identify as Emergency Operations Personnel (EOP) those who are responsible for performing functions that are absolutely essential to the continuation of core university operations (e.g., protection of property or safety, support of campus health services, payroll, etc.) during a multi-week public health or other type of emergency when classes and most other university activities are suspended. Emergency Operations Personnel must satisfactorily perform their responsibilities in any type of emergency. Visit the Emergency Management Unit website for more information on training: http://www.pdx.edu/cpso/emergency-management-unit-emu.

M: More Information Regarding Your Department Please note below information for your department’s contact.

Name Phone Number Campus PO Box COOP Contact David Atalig 5-9115 751 OIT

Email address [email protected]

Dept. locations SMSU, FAB, Cramer, Neuberger, Urban

Please indicate below the principle nature of your department’s operations (check all that apply): Instruction Student life support Laboratory research Research support Other research Facilities support Administration Other (describe):