Change to Chloramines
Teresa RogersTexas Commission on Environmental QualityWater Supply Division - Utilities & Districts Section
Change to Chloramines
Using Chloramines Requires Getting TCEQ Approval
Before You Begin
Change to Chloramines
Give us the RIGHT STUFF!
Change to Chloramines
How to Get Projects Approved?
• Give the Right Stuff• Include Time for Review• Learn from Goat MUD
Change to ChloraminesHow to Get Projects Approved
The Right Stuff• Cover Letter
• Plan Review Submittal Form
• Engineering Report
• Plans & Specs
Change to ChloraminesHow to Get Projects Approved
The Right Stuff
•Cover Letter
• Plan Review Submittal Form
• Engineering Report
• Plans & Specs
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Sealed Cover Letter
•Written Request for Exception
•Project Description
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Sealed Cover Letter
• Written Request for ExceptionThe [District] intends to change its disinfectant from chlorine to chloramines and requests approval of an exception per 30 TAC § 290.39(l)and § 290.42(e)(3)(G) to change its disinfectant from chlorine to chloramines.
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Sealed Cover Letter
•Project DescriptionThe [District] intends to add additional chlorination lines … including two (2) 200 ppd each gas chlorinators …. LAS injection system ….including two (2) 2.0 gph each chemical metering pumps and one (1) 250 gallon HDPE double walled…
Change to ChloraminesHow to Get Projects Approved
The Right Stuff• Cover Letter
• Plan Review Submittal Form
• Engineering Report
• Plans & Specs
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Plan Review Submittal Form
Complete and Seal
X Exception
X Other - Explain
Change to ChloraminesHow to Get Projects Approved
The Right Stuff• Cover Letter
• Plan Review Submittal Form
•Engineering Report
• Plans & Specs
Change to ChloraminesHow to Get Projects Approved
The Right Stuff
Engineering Report
• Existing Facilities• Proposed Facilities• Calculations
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Engineering Report
• Existing Facilities• Size• Capacity• Site Plan
• Proposed Facilities• Calculations
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Engineering Report
• Existing Facilities• Proposed Facilities
• Size• Capacity• Site Plan
• Calculations
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Engineering Report
• Existing Facilities• Proposed Facilities• Calculations
• Chemical Dosing• Feed Pump Sizing• Chemical Tank Sizing
Change to ChloraminesHow to Get Projects Approved
The Right Stuff• Cover Letter
• Plan Review Submittal Form
• Engineering Report
•Plans & Specs
Change to Chloramines
How to Get Projects ApprovedThe Right StuffPlans & Specs
Bound Cover SEALED
Each Sheet SEALED
Change to Chloramines
How to Get Projects ApprovedThe Right Stuff
Plans & Specifications
• Site plan with yard piping and location of all existing & proposed facilities
• Chemical injection & monitoring point locations
Change to ChloraminesHow to Get Projects Approved?
Give TCEQ The Right Stuff!(1) Cover Letter
(2) Submittal Form
(3) Engineering Report
(4) Plans & Specs
Change to Chloramines
How to Get Projects Approved?
• The Right Stuff• Include Time for Review• Goat MUD Go Through
Change to ChloraminesInclude Time for Review
Since 2004 ~600 conversions188 in Harris County2 in Fort Bend County
~50%Harris County MUDsConverted to Chloramines
Change to ChloraminesInclude Time for Review
45 - 60Days from
Receipt
TCEQ Review Time
Change to ChloraminesInclude Time for Review
150 - 200 Plan Sets Per Month
TCEQ Review Process
Change to ChloraminesInclude Time for Review
How to Get Projects Approved?
Avoid the Rush!
Schedule time for TCEQ review
Change to Chloramines
How to Get Projects Approved?
•Give the Right Stuff• Include Time for Review•Learn from Goat MUD
Goat MUDWhat happened?
Goat MUDWhat happened?
Change to Chloramines: Goat MUD
First Go Through
• NO Cover Letter• NO TCEQ Plan Submittal Form• NO Engineering Report• NO Plans & Specs
Oh no!
Change to Chloramines Goat MUD
WHAT TO DO NOW?
Hire an Engineer!
Change to Chloramines: Goat MUD
Submit the complete package!
Engineers’ Tasks:• Draft Cover Letter• Complete Submittal Form• Write Engineering Report• Develop Plans & Specs
Change to Chloramines: Goat MUDSecond Go Through
• Missing calculations• Missing details in drawings • Missing specs on tanks & pumps• Missing BFP on makeup water lines• Missing NSF certification chemicals
Change to Chloramines: Goat MUDThird time’s a charm!
What Goat MUD did right!• Cover Letter
• Plan Review Submittal Form
• Engineering Report (Example)
• Plans & Specs (Example)
Change to Chloramines: Goat MUD
The Engineering Report
• Existing Facilities• 650 GPM well & 650 GPM SW• 2000 GPM service pumps• One chlorinator
• Proposed Facilities• Calculations
Change to Chloramines: Goat MUD
The Engineering Report• Existing Facilities• Proposed Facilities
• 38% 1.2 SG NSF certified LAS• Two feed pumps GW / SW• One 200 gal bulk storage tank
w/containment• Calculations
Change to Chloramines: Goat MUD
Engineering Report• Existing Facilities
• Proposed Facilities
• Calculations• Chemical Dosing• Feed Pump Sizing• Chemical Tank Sizing
Change to Chloramines: Goat MUD
Engineering Report Calculations
• Chemical Dosing• Feed Pump Sizing• Chemical Tank Sizing
Change to Chloramines: Goat MUD
Engineering Report Calculations
• Chemical Dosing• Stoichiometry• Target residual 2.0 mg/L Cl2• Assume 0.0 mg/L Cl2 SW
• Feed Pump Sizing
• Chemical Tank Sizing
Engineering Report Calculations• Chemical Dosing• Feed Pump Sizing (2 pumps)
• LAS dose• Design flow rate GW / SW• LAS feed rate
• Chemical Tank Sizing
Change to Chloramines: Goat MUD
Change to Chloramines: Goat MUDEngineering Report Calculations
• Chemical Dosing
• Feed Pump Sizing
• Chemical Tank Sizing • 15 day supply• Design flow the smaller of
(GW + SW) or SP• Containment
Change to Chloramines: Goat MUDCalculations
Chemical Dosing – StoichiometryFORMULA MW RATIO RATIO
Cl2 / (NH4)2SO4 CL2/AS-N
MW Cl2 = (35.5)(2) = 71.00 5.07
MW NH3-N = 14.00 1.08MW Ammonium
Sulfate-(NH4)2SO4 = 132.0 4.71MW Ammonium
Sulfate-N = (14)(2) = 28.00
Change to Chloramines: Goat MUD
Engineering Report Calculations• Chemical Dosing
• Stoichiometry • Target residual 2.0 mg/L Cl2• Assume 0.0 mg/L Cl2 SW
Calculate LAS dose (mg/L)
2.0 mg/L Cl2*(1 mg/L AS-N/1.08 mg/L Cl2) / 0.38 = 4.87 mg/L (or ppm) LAS Soln
Change to Chloramines: Goat MUD
Engineering Report Calculations
• Chemical Dosing• Feed Pump Sizing• Chemical Tank Sizing
Choose Appropriate Flow Rate
Change to Chloramines: Goat MUD
Engineering Report Calculations
Choose Appropriate Flow Rate✮ Feed Pump Sizing (2 pumps)
• Ground Water (GW) / Surface Water (SW)
✮ Tank Sizing - smaller of • Total source capacity (GW + SW) or• Total service pump capacity (SP)
Goat MUD Capacity (GPM)GW 650 / SW 650 / SP 2000
1300 GPM < 2000 GPM
Change to Chloramines: Goat MUD
Engineering Report Calculations• Chemical Dosing• Feed Pump Sizing• Chemical Tank Sizing
Convert Flow to MGD(1300 GPM) * (1440 min/day/106) = 1.87 MGD
Change to Chloramines: Goat MUD
Engineering Report Calculations
• Feed Pump Sizing (2 pumps)• LAS dose• LAS feed rate
Calculate LAS feed rate lb/day
[4.87 ppm LAS *1.87 MGD* 8.34 lb/gal] = 76.0 lb/day LAS Soln
Change to Chloramines: Goat MUD
Engineer Report Calculations
• Feed Pump Sizing (2 pumps)• LAS dose• Design flow rate GW + SW• LAS feed rate ( x 1.5 )
Calculate LAS feed rate gal/day
[ 76.0 lb/day LAS] / [1.2 SG*8.34 lb/gal ] =7.6 gal/day x 1.5 = 11.4 gal/day LAS feed
Change to Chloramines: Goat MUD
Engineer Report Calculations
• Chemical Tank Sizing• 15 day supply• Design flow rate (GW + SW) or SP
whichever is smaller• Containment
Calculate tank storage11.4 gal/day LAS soln x 15 Days
= 170 gal LAS soln
Change to Chloramines: Goat MUD
Engineer Report Calculations• Chemical Tank Sizing
• 15 day supply• Design flow rate (GW + SW) or SP
• Containment
Calculate Goat MUD Tank Containment200 gal LAS tank x 1.10 =
220 gal containment
Change to Chloramines: Goat MUDEngineer Report Calculations
Consider Double Walled Tanks• Screened openings & connects
through domed inner roof
• One drain close to bottom outer shell
• Inner tank level indicator & method for leak detection
• Anti-siphon device on piping
Change to Chloramines: Goat MUDEngineer Report Calculations
Double Walled Containment
LAS
Change to Chloramines: Goat MUD
What Goat MUD did right!• Cover Letter
• Plan Review Submittal Form
• Engineering Report
•Plans & Specifications
Change to Chloramines: Goat MUD
Plans & Specifications
• Locate injection & monitoring
• Site plan & yard piping for existing & proposed facilities
• Technical Specifications
Change to Chloramines: Goat MUDPlans & Specifications
• Locate injection & monitoring
• Site plan & yard piping for existing & proposed facilities
• Technical Specifications
Change to Chloramines: Goat MUDPlans & Specifications
Location GW line
• Inject LAS at least two (2) pipe diameters or 4 - 6 feet downstreamof chlorine injection point
Chlorine > Ammonia
• with stingers at the same depth
Change to Chloramines: Goat MUDPlans & Specifications
Location SW line(Booster Chloramination)
• Inject LAS upstream of chlorine as close as possible
Ammonia > Chlorine• with stingers at the same depth
Change to Chloramines: Goat MUDPlans & Specifications
Monitoring InstrumentsMust have ability to monitor for
these parameters:
• free ammonia • monochloramine • total chlorine• free chlorine
Change to Chloramines: Goat MUD
Plans & Specifications• Locate injection & monitoring
points• Site plan with yard piping for
existing & proposed facilities• Technical Specifications
Change to Chloramines: Goat MUDSite Plan
WellCl2
Surface Water
LAS
LAS
DAuthority
Meter
GST
HSPumps
Ground Water
Cl2
TCl2 Mono FAA
TCl2FAANO2NO3
TCl2 Mono FAA
TCl2MonoFAA
Change to Chloramines: Goat MUD
Plans & Specifications• Locate injection & monitoring
points• Site plan with yard piping for
existing & proposed facilities• Technical Specifications
Change to Chloramines: Goat MUDPlans & Specifications
Technical Specifications• All proposed equipment
• Ammonia• Lab equipment • Pump model, feed rate range• ANSI/NSF certified chemical
• Chemical tank• ASTM standard• Compatible/UV resistant material
Change to Chloramines
Recap:How to Get Projects Approved?
• Give the Right Stuff• Include Time for Review• Learn from Goat MUD
Change to Chloramines: Goat MUDThird time’s a charm!
Conditional Approval !
Change to Chloramines: Goat MUDConditional Approval
Conditions:✮ Provide TCEQ with monitoring plan
• Record weekly• Before/after changes in source
water or dosing
Change to Chloramines: Goat MUDConditional Approval
✮ Provide TCEQ Certification of Delivery with copy of notice
PWS
PWS
PWS PWS
PWS
PWS
Notifies
Notifies
Notifies
N
N
N
N
Change to Chloramines: Goat MUDWhat Goat MUD did right!
Verify compliance w/TCEQ design requirements Adequately describe the systemCalculate dosing and feed ratesSize pumps and tanksConsider containmentSelect ammoniaDesign booster chloramination systemLocate injection & monitoring pointsRemember TCEQ monitoring & reporting requirements
How to Get Projects ApprovedSummary
•Give the Right Stuff
• Include Time for Review
•Learn from Goat MUD
Change to Chloramines: Goat MUD
APPROVED!
Change to Chloramines
Teresa RogersTexas Commission on Environmental QualityWater Supply Division – Plan & Groundwater [email protected]