Dinmore station accessibility upgrade Project update – June 2016 Project progress The following construction activities were recently completed: installation of new light pole footings excavation and concrete pours for new footbridge and lift foundations trenching and conduit works. Upcoming works In the coming weeks, the following activities are planned: scaffolding installation construction of temporary access ramps between the platforms and carparks relocation of go card touch on/touch off pedestals to align with temporary ramps foundation works for new light poles commence construction of lift shaft walls and footbridge support columns. Temporary changes – Mason Street bus zone To enable construction works at the Ipswich end of platform 2, temporary changes to the road conditions at the Mason Street bus zone will occur. The bus zone will continue to operate and Mason Street will remain open to traffic. Customers, pedestrians and motorists are advised to follow all directional signage while these change traffic conditions are in place. Construction impacts Excavation works have begun at Dinmore station to allow for the new footbridge and lift foundations. This upgrade is being undertaken as part

Upload: buinguyet

Post on 22-Mar-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Dinmore Project Update (June 2016) Word vsn · Web viewProject update – June 2016 Excavation works have begun at Dinmore station to allow for the new footbridge and lift foundations

Dinmore station accessibility upgradeProject update – June 2016

Project progressThe following construction activities were recently completed:

installation of new light pole footings excavation and concrete pours for new

footbridge and lift foundations trenching and conduit works.

Upcoming worksIn the coming weeks, the following activities are planned:

scaffolding installation construction of temporary access ramps

between the platforms and carparks relocation of go card touch on/touch off

pedestals to align with temporary ramps foundation works for new light poles commence construction of lift shaft walls and

footbridge support columns.

Temporary changes – Mason Street bus zoneTo enable construction works at the Ipswich end of platform 2, temporary changes to the road conditions at the Mason Street bus zone will occur.

The bus zone will continue to operate and Mason Street will remain open to traffic.

Customers, pedestrians and motorists are advised to follow all directional signage while these change traffic conditions are in place.

Excavation works have begun at Dinmore station to allow for the new footbridge and lift foundations. This upgrade is being undertaken as part of Queensland Rail’s $212 million station upgrade program.

Page 2: Dinmore Project Update (June 2016) Word vsn · Web viewProject update – June 2016 Excavation works have begun at Dinmore station to allow for the new footbridge and lift foundations

Construction impactsCustomers and residents adjacent to Dinmore station may experience:

noise associated with heavy machinery use of reversing beepers mobile lighting towers changed traffic and parking conditions increased vehicle movements around the work

zone.

Residents and other stakeholders will be given advance notification of construction activities likely to cause impacts, including after-hours work (nights and Sundays, if required).

Keeping you informedFor more information on this project, please contact the Stakeholder Engagement team on 1800 722 203 (free call), email [email protected] or visit www.queenslandrail.com.au