Disconnect DG Interconnections Checklist (Interconnecting Customer)
Project Name Project No. 1. PRIOR TO SYSTEM IMPACT STUDY (SIS)Application Complete ☐
All required project information has been provided to the T&D Utility. Including PSCAD models, One-line diagrams, site plans, etc. ☐
Scoping meeting complete ☐
System Impact Study Agreement (SISA) Executed ☐
System Impact Study Deposit received by the T&D Utility. ☐
2. PRE-CONSTRUCTION – DESIGN PHASEInterconnection Agreement has been fully executed and project has successfully completed all necessary cluster and impact studies. ☐
Funds for the system impact study and required system upgrades have been provided to the T&D Utility. ☐
ISO-NE PPA (Proposed Plan Application) has been approved or submitted to ISO New England. ☐
ROW has been defined and easements in place, if applicable.
T&D Utility detailed design and construction schedule has been provided with estimated “COD” (Commercial Operations Date) defined. ☐
Construction agreement executed for line work, if applicable. ☐
All necessary permits and approvals obtained; could include but not limited to: • Dig Safe ☐
• Town Permit ☐
• DEP Permit ☐
• Landowner Easements ☐
3. CONSTRUCTIONConstruction Changes have been captured through “RFI” (Request for Information) and deemed acceptable by the T&D Utility Project team. ☐
Construction Completion Certificate has been provided to the T&D Utility. MUST be Signed by the local electrical inspection authority. ☐
Installation is complete and compliant with all national codes and standards (IEEE 1547, UL 1741 SA & ISO-NE SRD etc.). ☐
Copy of the FINAL stamped PE Drawings (As-builts) with final relay/ inverter test report has been provided to the T&D Utility Engineer for review. ☐
4. COMMISSIONINGSite Inspection Complete. (T&D Eng verification of all site data matches planned/ final design requirements, all equipment and devices both utility and interconnecting customer are properly labeled and tagged) ☐
Witness test points have been confirmed, accepted and in accordance with IEEE 1547, ISO-NE SRA and T&D utility requirements. ☐
Relay test reports provided, and match firmware studied or have been captured through “RFI” and accepted by the T&D Utility Project team. ☐
T&D Utility customer service contacted to set up all load billing information. ☐
5. PRE-ENERGIZATION “COD” (COMMERCIAL OPERATIONS DATE)
Certificate of acceptance (Construction Completion Certificate acceptance letter) has been received from the T&D Utility ☐
Liability Insurance requirements have been provided to the T&D Utility. ☐
Reimbursement’s received and/ or final invoice for system upgrades have been provided and paid to the T&D Utility. ☐
Operations Requirements Guide has been provided, reviewed and understood by the interconnecting customer. (Tripping of POI, Important contacts, who to notify, scheduled outage requirements etc.) ☐
NEB (Net Energy Billing) or Procurement Agreement has been fully executed (Must be received 60 days prior to commercial operation). ☐
Versant- DG Interconnections Checklist-Rev 2
☐