Orange County Public Schools

DOWNTOWN URBAN PS8, Site 131-PS8-SW-5

40% CONSTRUCTION UPDATESEPTEMBER 21, 2016

WINNERWelcome! Please sign in on your mobile device:

http://communitymeeting.ocps.net/

Page 2: device: WINNER

Orange County Public SchoolsOrange County Public Schools

DOWNTOWN URBAN PS8Meeting AgendaSEPTEMBER 21, 2016, OCPS RBELC, 6:00 PM

•Introductions – Principal

•Welcome – Kat Gordon

•Project Update – Facilities Meeting OrganizerArchitect: Baker Barrios Architects/ HKS ArchitectsConstruction Manager: Williams Company Building Division/ ACY

Contractors, LLC

•Questions and Answers

•Adjournment

2

Page 3: device: WINNER

Orange County Public Schools

3

SITE PLAN

Page 4: device: WINNER

Orange County Public Schools

4

SITE PLAN

Page 5: device: WINNER

Orange County Public SchoolsCLASSROOM BUILDING

5

Page 6: device: WINNER

Orange County Public Schools

West Elevation:

MEDIA CENTER

6

Page 7: device: WINNER

Orange County Public Schools

South Elevation:

MUSIC/ CAFETERIA

7

Page 8: device: WINNER

Orange County Public Schools

East Elevation:

GYMNASIUM

8

Page 9: device: WINNER

Orange County Public Schools

North Elevation:

ROSEN PRESCHOOL

9

Page 10: device: WINNER

Orange County Public Schools

Front Entry:

COMMUNITY CLINIC

10

Page 11: device: WINNER

Orange County Public SchoolsBOYS AND GIRLS CLUB

11

Page 12: device: WINNER

Orange County Public Schools

Construction Update & Milestones:

• All foundations are complete. (except building 500).

• ½ of the 321 tilt panels have been poured.

• ½ of building 100 (Classroom Building) tilt panels have been erected.

• Building 400 (Gym) tilt panels have been erected.

• Slab on grade at buildings 100, 400, 700 and 900 are complete.

• Structural steel is underway at buildings 100, 400 and 600.

12

Page 13: device: WINNER

Orange County Public Schools

• Parking garage is in production and is scheduled to arrive in December.

• Underground storm system has been installed at the soccer field.

• Plumbing and electrical underground is underway at buildings 200, 300 and 800.

Construction Update & Milestones:

13

Page 14: device: WINNER

Orange County Public Schools

Milestone Dates

14

Page 15: device: WINNER

Orange County Public SchoolsSite 131-PS8-SW-5 AERIAL PHOTO- APRIL 2016

15

Page 16: device: WINNER

Orange County Public SchoolsSite 131-PS8-SW-5 AERIAL PHOTO- MAY 2016

16

Page 17: device: WINNER

Orange County Public SchoolsSite 131-PS8-SW-5 AERIAL PHOTO- JUNE 2016

17

Page 18: device: WINNER

Orange County Public SchoolsSite 131-PS8-SW-5 AERIAL PHOTO- JULY 2016

18

Page 19: device: WINNER

Orange County Public SchoolsSite 131-PS8-SW-5 AERIAL PHOTO- AUGUST 2016

19

Page 20: device: WINNER

Orange County Public SchoolsSite 131-PS8-SW-5 AERIAL PHOTO- SEPTEMBER 2016

20

Page 21: device: WINNER

Orange County Public Schools

BUILDING 100• Tilt panels have been erected at half of the building• Structural steel is currently underway

CONSTRUCTION UPDATE PHOTOS

21

Page 22: device: WINNER

Orange County Public SchoolsCONSTRUCTION UPDATE PHOTOS

BUILDING 100• Tilt panels have been

erected at half of the building

• Structural steel is currently underway

22

Page 23: device: WINNER

Orange County Public Schools

BUILDING 400• Tilt panels have been erected

at half of the building• Structural steel is currently

underway

23

CONSTRUCTION UPDATE PHOTOS

Page 24: device: WINNER

Orange County Public SchoolsCONSTRUCTION UPDATE PHOTOS

BUILDING 700• Concrete slab has been

poured• Half of the tilt panels have

been poured

24