development of new sampling
TRANSCRIPT
-
7/30/2019 Development of new Sampling
1/19
CHAPTER 5
DEVELOPMENT OF NEW PROCESS
5.1 Introduction
From the study conducted on existing process revels it has identified several things, important
are, the cycle time for the production of cub-frame and coolant channel are 1.75 Hrs/component
and 1.25 Hrs/component respectively, manual strain of the labors are more because marking time
more for the guarding and also the quality of the components produced in the existing process is
less and the cycle time can be reduced by adopting the following methods
(i) Modification of production process of cub-frame will results in decreases the cycle time and
inventory cost materials.
(ii) Modification of production process of coolant channel will results in decreases the cycle time
and inventory cost of the materials.
5.2 Cub-frame Production Process
Cub-frame manufactured at SMD is depicted in the Figure 5.1. The various operations involved
in the manufacturing of cub-frame are cutting, bending, welding and finishing. The sequences of
operations in cub-frame production process are depicted in Figure 5.2.
Raw materials for Cub-frame manufacturing: High carbon steel contains from 0.7 to 1.00%
C with manganese ranging from 0.5to 0.9% this steel commonly known as spring steels. These
steels are generally operated at very high stress and heat treated to obtain the maximum elastic
limits and fatigue resistance without becoming sufficient brittle to cause sudden failure inservices. Harden ability of spring steel is very important because only fully hardened spring have
the maximum resistance to take a permanent set (sagging).
-
7/30/2019 Development of new Sampling
2/19
Figure 5.1 Finished Cub-frame
-
7/30/2019 Development of new Sampling
3/19
Figure 5.2 Proposed Cub-frame Production Process
CNC Laser cutting
of Cub frame parts Bending of Cub
frame partsWelding of Cub
frame parts
Inspection of cubframe
Finishing of Cub
frame parts
C\T for
cutting=10min
C\T for
Bending15min
C\Tforw
elding=20min
C\T for Finishing=10min
C\T for
Inspection is
5min
-
7/30/2019 Development of new Sampling
4/19
CNC Laser Cutting operation: FANUC- CO2 CNC laser cutting machine is used to cut the
sheet metal for the production of cub-frame components. Each cub-frame component consists of
cutting operations of different lengths and the total cutting involves 5875 mm in length. The laser
cutting operation is computer controlled which gives high production rates and also high
accuracy of 0.025 mm. The cycle time required for this operation is 10 min.
Bending operation: CNC bending is a process where cub-frame is bent to an angle using,
typically a V shaped punch and die. The sheet is placed between the punch and die which presses
down on the sheet. It provides a low cost method to product 3D shapes from 2D sheets and it is a
suitable for processing most ductile metals and primarily for sheet metal designs with one or
more bends. A large percentage of sheet metal parts are bent along some lines to get them into
the desired shape for use. The sheet metal part before it is bent is called a blank. The cycle time
required for this operation is 15 min.
Welding operation: Spot welding process is used for Cub-Frame welds in SMD and the
different parts of cub-frames are welded with the help of welding fixture. The cycle time
required for this operation is 20 min.
Finishing: Hand grinders are used for final finishing operation process for cub-frame,
accompanied by a certain amount of metal removal and high surface finishing. The cycle time
required for this operation is 10 min.
Inspection: Inspection is carried out to check for the required dimension on all the cub-frame
components, after the completion of all the above process. In case of any deviation in the
dimensions frames will be sent back for rework. If the required dimensions are achieved it will
further sent to the painting division. The cycle time for the inspection process is 5 min. Figure5.4. The cycle time analysis for the production of Cub-frame components are given the Table 5.1
and the graphs of cycle time verses processes are show in the Figure 5.5.
-
7/30/2019 Development of new Sampling
5/19
5.2.1 Operating cycle time of cub-frame
Basically, there are five processes are involved in the production process of cub-frame Sheet
metal guarding for a CNC Machine centers. Cycle time presently used in all the production
processes were noted which are given in the Table 5.1. The cycle time required to complete one
component of cub-frame is 60 min/ 1.00 Hrs and bar chart of cycle time is depicted in Figure 5.3.
It is observed that the cycle time required for manual drilling and tapping operation is completely
eliminated and it is adopted with the laser cutting machine by taking the advantages of laser
cutting and high accuracy.
5.3 Coolant channel Production process in proposed method
Coolant channel manufactured at SMD is depicted in the Figure 5.4. The various operations
involved in the manufacturing of coolant channel are cutting, bending, welding and finishing.
The sequences of operations in Coolant channel production process are depicted in Figure 5.5.
Raw materials for Coolant channel manufacturing: High carbon steel contains from 0.7 to
1.00% C with manganese ranging from 0.5to 0.9% this steel commonly known as spring steels.
These steels are generally operated at very high stress and heat treated to obtain the maximum
elastic limits and fatigue resistance without becoming sufficient brittle to cause sudden failure in
services. Harden ability of spring steel is very important because only fully hardened spring have
the maximum resistance to take a permanent set (sagging).
CNC Laser Cutting operation: FANUC- CO2 CNC laser cutting machine is used to cut the
sheet metal for the production of Coolant channel components. Each Coolant channel component
consists of cutting operations of different lengths and the total cutting involves 1206 mm in
length. The laser cutting operation is computer controlled which gives high production rates and
also high accuracy of 0.025mm. The cycle time required for this operation is 5 min.
-
7/30/2019 Development of new Sampling
6/19
Table 5.1 Cycle Time in Proposed Production Process for Cub-frame
Sl no Sequence of Operations Cycle Time in min Cycle per batch
1 CNC laser cutting Operation 10 min 1200 min
2 CNC bending Operation 15 min 1800 min
3 Welding Operation 20 min 2400 min
4 Finishing Operation 10 min 1200 min
5 Inspection Operation 5 min 600 min
Total Cycle Time for Cub frame 60 min/1 Hrs 7200 min/120 Hrs
-
7/30/2019 Development of new Sampling
7/19
Figure 5.3 Proposed Process Cycle Time for Cub-frame
0
5
10
15
20
25
CT for
Laser
Cutting
CT for
Bending
CT for
Welding
CT for
Finishing
CT for
Inspection
CycleTimein
min
Processes
Cub-frame
-
7/30/2019 Development of new Sampling
8/19
Figure 5.4 Photo Graph of Coolant Channel
-
7/30/2019 Development of new Sampling
9/19
Figure 5.5 Proposed Process Flow Diagrams for Coolant Channel
CNC Laser cutting
operation
Bending of Coolant
channel parts
Welding of
Coolant channel
parts
Inspection of
Coolant channel
Finishing of
Coolant channel
CT for
cutting
=10min
CT for
Bending
= 15min
CTforWelding10min
CT for
Finishing
=5min
CT for
Inspection
=5min
-
7/30/2019 Development of new Sampling
10/19
Bending operation: CNC Bending machines are used for bending operation Coolant channel
production involve any one bending operation. A large percentage of sheet metal parts are bent
along some lines to get them into the desired shape for use. The sheet metal part before it is bent
is called a blank. The cycle time required for this operation is 15 min.
Welding operation: Spot welding process is used for Coolant channel welds in this division
with the help of fixture. The cycle time required for this operation is 20 min to completely weld.
Finishing: Hand grinders are used for final finishing operation process of Coolant channel
accompanied by a certain amount of metal removal. The cycle time required for this operation is
5 min.
Inspection: Inspection is carried out to check for the required dimension on all the Cub-frame
components, after the completion of all the above process. In case of any deviation in the
dimensions frames will be sent back for rework. If the required dimensions are achieved it will
further sent to the painting division. The cycle time for the inspection process is 5 min.
5.3.1 Operating cycle time for coolant channel
Basically, there are five processes are involved in the production process of coolant channelsheet metal guarding for a CNC Machine centers. Cycle time presently used in all the production
processes were noted which are given in the Table 5.2. The cycle time required to complete one
component of coolant channel is 45 min/ 0.75 Hrs and bar chart of cycle time is depicted in
Figure 5.6. The flat piece is replaced by circular bush with the inner thread cut and the welding
length is reduced.
-
7/30/2019 Development of new Sampling
11/19
Table 5.2 Cycle Time for Production Process for Coolant Channel
Sl no Sequence of Operations Cycle Time in min Cycle time per batch
1 CNC laser cutting Operation 10 min 1500 min
2 CNC bending Operation 15 min 2250 min
3 Welding Operation 10 min 1500 min
4 Finishing Operation 5 min 750 min
5 Inspection Operation 5 min 750 min
Total Cycle Time for Coolant channel 45 min/ 0.75 hrs 6750 min/112.5 Hrs
-
7/30/2019 Development of new Sampling
12/19
Figure 5.6 Cycle Time of Proposed Production Process for Coolant Channel.
10
5
10
5 5
0
2
4
6
8
10
12
CT for laser
Cutting
CT for
Bending
CT
forWelding
CT
forFinishing
CT for
Inspection
CycleTimei
nmin
Processes
coolant channel
-
7/30/2019 Development of new Sampling
13/19
5.4 Comparing the Cycle Time in Existing Process with the
Proposed Method of Cub-frame Production Process
Comparing the cycle time and manufacturing cost of the cub-frame process in SMD were carried
out, after incorporating the new production flow process and reported that there is a substantial
improvement in the cycle time and also in the manufacturing cost of the component, by
eliminating the drilling and tapping operation in the sheet metal division and the operation is
incorporated with the CNC laser machine and the details is depicted in the Figure 5.11. The
purpose of comparison of existing process with the new process development for the
manufacturing cost reduction in this process, 66% of the cost is reduced with the new process
and also the 45 min of cycle time is reduced, details of this as shown in the Table 5.7 and alsoproduct cost V/s batch size as shown in the Figure 5.12.
5.5 Comparing the Cycle Time in Existing Process with the
Proposed Method of Coolant channel
Comparing the cycle time and manufacturing cost of coolant channel assembly in ACE designers
Ltd were carried out, after incorporating the new production flow process and reported. There is
a substantial improvement in the cycle time and also in the manufacturing cost of the component,
details is depicted in the Figure 5.13 For the purpose of comparison of existing process with the
new process development for the manufacturing cost reduction in this process 55% of the cost is
reduced with the new process and also the 30 min of cycle time is reduced, details of this as
shown in the Table 5.9 and also product cost V/s batch size is depicted in the Figure 5.14 show
the cost comparison of Coolant channel the existing process consumes cost Rs 4050 and the new
process consumes cost Rs 2700 with the reduction of cycle time 20 min and the elimination of
the drilling time in the existing process of Coolant channel manufacturing and 60% of the cost is
reduced and monthly saving is Rs 2847 and the details of about this is as show in the table, the
table shows the elimination of flat piece welding length, drilling and threading operation by
incorporating the circular bush with inner thread, the cost of the bush is low compare to the flat
welding operation.
-
7/30/2019 Development of new Sampling
14/19
Sl no OPERATIONS BEFORE AFTER
1 RAW MATERIAL COST 0.5
2 CUTTING LENGTH IN MTS 2.693
3 NO OF BENDS 2
4 GRINDING LENGTH
5 NO OF BUSHES 4
DRILL AND TAPPING TIME IN Min 45 MIN 0.0
1 LASER CUTTING COST
Rs 88.00
Rs 37.20
2 RAW MATERIAL COST Rs 22
3 BENDING COST Rs. 4.00
4 WELDING COST Rs. 0.00
5 LABOUR COST Rs. 0.00
6 BUSH COST Rs. 10.00
7LABOUR COST PER DRILL AND
TAP WITH SUITINGS
Rs 48 0
TOTAL COST IN Rs. 136.1 74.0
TOTAL SAVING PER COMPONENT Rs. 62.10
NO. OF COMPONENTS PER MONTH 120 COMPONENTS
SAVING PER MONTH Rs. 7,452
SAVING PER YEAR Rs. 89,424
Table 5.3 Cost comparison as per the company standards for Cub-frame production
-
7/30/2019 Development of new Sampling
15/19
5.7 Cycle Time Comparison for Cub-frame Production Process
5.8 Batch Size Cost Comparison for Cub-frame Production Process
10
45
1520
105
10
0
15
20
10
5
05
10152025303540
4550
CycleTimeinmi
n
Processes
Cycle TimeComparision for Cub-
Frame
Existing method of Cub
frame
Proposed method of Cub
frame Manufacturing
2722
5444
8166
10888
13610
16332
1480
2960
4440
5920
7400
8880
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20 40 60 80 100 120
ProductcostinRs
Batch size
Cost Comparision for Cub-frame
Cub frame before
Cub frame after
-
7/30/2019 Development of new Sampling
16/19
OPERATIONS FLAT WELD RsBUSH WELD Rs
Sl No
1 RATE/PIECE 7.6 7.6 5.2 5.2
2WELD LENGTHIN MTS
52 5.2 25.12 2.5
3 DRILL TIME MIN 30 Min 14 0 0
Total 27 Total 8
SAVING PER COMPONENT Rs 19
NO. OF COMPONENTS PER MONTH 150 COMPONENTS
SAVING PER MONTH Rs 2,847
PER YEAR SAVINGS Rs 34,158
Table 5.4 Cost comparison as per the company standards for Coolant channel Production
-
7/30/2019 Development of new Sampling
17/19
5.9 Cycle Time Comparison for Coolant channel Production Process
5.10 Batch size Cost Comparison for Coolant channel Production Process
10
15
10
30
5 5
10
5
10
0
5 5
0
5
10
15
20
25
30
35
Cycle
timeinmin
Production process
Existing method ofCoolant channel
Manufacturing
Proposed method of
Coolant channel
manufacturing
810
1620
2430
3240
4050
540
1080
1620
2160
2700
0
500
1000
1500
2000
2500
3000
3500
4000
4500
30 60 90 120 150
ProductcostinRs
Batch size
Cost comparision for Cub-frame
Coolant channel before
Coolant channel after
-
7/30/2019 Development of new Sampling
18/19
5.6 Future State Mapping
Value stream mapping of the future state identifies the essential and non essential value added
activities in the process. The plant works on a continuous basis for 16 hours a day for complete
year except for major shutdowns and runs as 2 shift per day of 8 hours each. Figure 5.11 & 5.12depicts the future state mapping of value stream related to complete production process for cub-
frame and coolant channel respectively. Small boxes in the map represent the process and each
process has a data box below, which contains cycle time (CT), processing time (PT), changr over
time (C/O), machines and equipments (MAE), overall equipment efficiency (OEE), number of
operators (OP), number of shifts runs per day, production lead time (PLT) at each process. These
data were collected by personal observation in the shop floor and talking to operators at each
work station. The timeline at the bottom of the current state map has two components; first
component is non-value added (NVA) activity, which is sum of each inventory triangle before
each process. The NVA for one triangle is calculated by dividing the inventory quantity into
daily customer requirements. The lead time for one inventory triangle is calculated by dividing
the inventory quantity into the daily customer requirements. Operation wise analysis of NVA,
VA, WIP inventory and other critical aspects are discussed.
5.7 Advantages of Proposed Method
5.7.1 Advantages of the Proposed Method of cub-frame manufacturing
Drilling and tapping is completely removed in Sheet metal department. Cycle time will be reduced with the availability of the new process. Manual strain of the labors will reduced in assembly with the elimination of the drilling
and tapping.
Quality of the materials produced in sheet metal department will be improved withaccurate cutting of hole in the machines with the help of laser cutting machines.
Manufacturing cost is reduced because of implementing the new process. Wastage of the materials will be less designs of drilling holes will be given by the
designing department with that hole will be made according to the design.
Drilling problems like over sized or under sized drill will be eliminated with usage oflaser cutting machine.
-
7/30/2019 Development of new Sampling
19/19
Labor cost also reduced and also highly skilled labors will be eliminated. Marking time for drill a hole will completely remove.
5.7.2 Advantages of the Proposed Method of coolant channel
manufacturing
Cycle time will be reduced with the new process of coolant channel manufacturing. Marking and machining of rectangular plate will be completely eliminated. Welding and automation in welding for new process is less because welding length will
be less compare to the old process and also the manufacturing time will be less.
Manufacturing cost of the component produced is less compare to old process becauseof the machining cost of the rectangular plate will be more compare to the circular bush
Wastage of the material will be completely eliminated with the help of circular threadedbush
Quality of the manufacturing component will more compare to the old process Highly skilled labors are not required