development of a sectoral infrastructure procurement strategy sean phillips 25 march 2010

21
1 DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010 SUPPORT PROGRAMME FOR ACCELERATED INFRASTRUCTURE DELIVERY

Upload: milagro-unzues

Post on 03-Jan-2016

27 views

Category:

Documents


0 download

DESCRIPTION

SUPPORT PROGRAMME FOR ACCELERATED INFRASTRUCTURE DELIVERY. DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010. Problem Statement: why is a procurement strategy required?. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

1

DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY

Sean Phillips

25 March 2010

SUPPORT PROGRAMME FOR ACCELERATEDINFRASTRUCTURE DELIVERY

Page 2: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

2

Problem Statement: why is a procurement strategy required?

Improved selection of procurement strategy will result in improved delivery outcomes.

CIDB has produced a range of standards, practice notes and guides Contain large number of options for procurement approaches and contracting options

Currently no overall guide of how to choose from myriad of available options for a particular expenditure programme

Organs of state (with some exceptions) generally only utilise time honored and familiar procurement approaches regardless of changing circumstances

Tend to be highly resource intensive-intensive for the client Implementing agents often cannot cope with workload using these approaches Leads to poor outcomes: under-expenditure, poor contract management

Page 3: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

3

Development of a methodology for sector infrastructure procurement strategies

Support Programme for Accelerated Infrastructure Delivery (SPAID) Joint project between BT and Presidency President’s Big Business Working Group requested BT to identify creative ways in which the public and private sectors

could cooperate to support infrastructure delivery

Discussions between BT, NT and DOE led to project to develop social infrastructure procurement strategy methodology

Limpopo DOE volunteered to be the test site

National steering committee: NT (PPP, IDIP, TAU), LT, LDOE, national DOE and Health, CIDB

Generic methodology has been developed and tested in Limpopo

Now being implemented in Limpopo and approach is being rolled out to other provinces (Education and Health), as part of IDIP

A national initiative to develop a methodology for producing a social infrastructure procurement strategy has been piloted in Limpopo.

Page 4: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

4

Strategic planning and investment planning

Procurement is preceded by strategic planning and investment planning Provincial strategic planning is guided by Treasury Regulations and strategic

planning guidelines Social infrastructure investment planning is guided by CIDB Toolkit for

Infrastructure Delivery Management, developed as part of NT Infrastructure Delivery Improvement Programme (IDIP)

Limpopo DOE IDIP five-year infrastructure plan was reviewed Contains prioritised lists of projects to be funded over five years

Findings: Logical and reasonably robust methodology Appears to be directing expenditure towards most urgent needs Infrastructure plan will generally not result in procurement of ‘wrong things’ Project should proceed to next phase of developing procurement and contracting

strategy to enable infrastructure plan to be procured in the right way

The existing education infrastructure plans, planning processes and quality ofunderlying data in Limpopo were reviewed.

Page 5: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

All procurement and contracting options are considered equally valid

Methodology does not say that some approaches better than others (eg does not say that some forms of contract document are better than others)

Different options are most suitable under different conditions

5

Underlying principle of the generic methodology

“Procurement strategy” = Choosing the most appropriate procurement and contracting approaches to meet your objectives.

Page 6: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

6

Gather information on local conditions and formulate objectives

Spend and category analysis – what are the characteristics of what is being procured, from a procurement point of view?

Categorise needs in terms of types of output and other commonalities

Organisation analysis What capacity and approach to risk does the organisation have and wish to have?

Market analysis – what capacity is in the market?

What are the organisation’s primary procurement objectives, e.g. budget / cost quality and performance characteristics required from the completed work

And secondary procurement objectives, e.g. BBBEE

The choice of options is dependent on local conditions.

Page 7: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

7

Meeting needs through a programme of projects or a series of independent projects

Meeting needs through PPP

  Meeting needs through implementing agent(s)

Meeting needs through framework agreements

Packaging of the work

Decision tables are used to match options to local conditions.

Match options to local conditions

Page 8: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

8

Gather information

Formulate objectives

Make strategic delivery management decisions

Meet needs through PPP

Meet needs through

Implementing AgentMeet needs through own

organisation

Package works

Delivery management strategy

Decide on contracting strategy

Decide on procurement arrangements

Contracting strategy

Procurement arrangements

Conduct annual evaluation of infrastructure spend on projects and programmes

Implement procurement strategy

Page 9: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

9

Identify contracting strategy per procurement category for contractors and PSPs

Contractual arrangements

Pricing strategy

Form of contract

Identify procurement arrangements per procurement category for contractors and PSPs

Quality strategy

Procurement procedure

Prequalifications

Targeted procurement strategy

Tender evaluation procedure

 

Page 10: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

10

Consideration Options Decision criteria for PPP

Non-PPP PPP The pre-requisites for using this option are that: the private party assumes substantial financial,

technical and operational risk in the design, financing, building and operation of a project over time

capability and capacity exist or can be put in place to effectively manage the PPP.

the nature of the service to be provide through the PPP is such that the risks can be clearly quantified and priced with certainty i.e. there must be a low level of intangibles e.g. potential for land claims or latent defects in existing infrastructure

the quantum of payments associated with the level of service to be provided through the PPP for the life of the PPP are affordable in the context of the client’s available and forecast budget and identified needs

there is a high level of certainty that the usage of the facility will be required without alteration over the lifetime of the PPP

the needs to be met are spatially located such that the PPP can be efficiently implemented

Contract outcome

Provide infrastructure

Provide assets and services which extend beyond construction for an agreed outcome over time.

Finance On budget Off budget (i.e. private finance required)

Risk Public body retains substantial risk relating to:

cost of construction, operation and maintenance

level of service

Transfer substantial risk relating to:

costs

level of service

to the private sector party

Decision table for PPP

Page 11: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

11

Decision table for framework agreements

Consideration Options Decision criteria for framework agreement

Non-framework

Framework Framework agreements are appropriate where:

The budgets available and the detailed scope of the needs are uncertain.

The potential for additional funds to be made available exists

The need involves repetitive work of a similar nature

A quick response time is required

Long term relationships (3 to 5 year) are desirable to achieve efficiencies

The pre-requisites for using this option are that

enabling procurement policies and procedures are in place, and

capability and capacity exist or can be put in place to effectively manage the framework agreements

Contract outcome

Provide specific construction works

Provide broadly defined construction services over a period of time

Procurement Separate procurement process for each transactional contract

Appoint in terms of pre-approved framework or reopen competition between framework contractors

Flexibility Time frames, scope and level of service defined per transactional contract.

Flexibility in terms of time frames, scope and level of service

Page 12: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

12

Options for contracting strategy for construction services (the methodology contains decision tables for each)

Contractual arrangements

Construction Management

Design and construct

Design, construct, operate and maintain

Develop and Construct

Design by Employer

Management Contract

Third party management support

Pricing strategy

Priced contract

Bills of quantities

Activity schedule

Cost based

Cost reimbursable

Target cost

Standard form of contract

FIDIC –Red Book

FIDIC –Yellow Book

FIDIC – Short Contract

FIDIC –Silver Book

GCC -2004

JBCC Series 2000 – PBA

JBCC Series 2000 - MWA

NEC3 ECC

NEC3 ECSC

Page 13: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

13

Options for procurement arrangements for construction services

Procurement procedure options

Com

petiti

ve s

elec

tion

Nominated

Open

Qualified

Quotation

Proposal procedure using the two-envelope system

Proposal procedure using the two-stage tendering system

Negotiations with a sole contractor

Competitive negotiations (open or restricted)

Targeted procurement procedure options

Preferencing

Incentives for KPI’s

Mandatory subcontracting

Contractual obligations

Tender evaluation options

Method 1: Financial offer

Method 2: Financial offer and preferences

Method 3: Financial offer and quality

Method 4: Financial offer, quality and preferences

Quality strategy options

Specifications

Life cycle costing

Prequalification

Evaluation criteria

Undertakings at tender stage

Preference

Eligibility criteria

Page 14: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

Identified five procurement categories and grouped the 2201 projects in the five year infrastructure plan into the five categories

Category 1: Greenfields Category (high value new buildings), managed by Head Office

Category 2: Brownfields Upgrade and Repair Category (medium value)

Category 3: Water and Sanitation Category, consisting of a mix of small civil and building projects managed by DWAF

Category 4: Routine and Preventative Maintenance Category, managed in consultation with SGB’s

Category 5: Electrification of schools by Eskom

14

Application to LDOE: Spend analysis

Application of the methodology LDOE’s 5 year infrastructure plan resulted in radical changes to its procurement and contracting strategies.

Page 15: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

Developed a procurement strategy for construction services for each category

Identified PSPs required and developed a procurement strategy for each type of PSP

Introduced framework agreements for small and medium-sized projects and for some professional service providers

Introduced appropriate targeted procurement procedures including preferencing, incentives and contractual obligations to meet secondary procurement objectives Draws on Ethekwini water mains replacement experience

Introduced competitive tendering for professional service providers

15

Application to LDOE: procurement strategy

Application of the methodology LDOE’s 5 year infrastructure plan resulted in radical changes to its procurement and contracting strategies.

Page 16: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

16

Benefits of new procurement strategy:

Total 95 contracts to manage over five years for 2201 projects (excluding professional service providers)

Historically would have had 2201 contracts (excluding professional service providers), each with its own procurement process

Resulted in severe strain on capacity of department and IAs and delivery problems

Much quicker response times using framework contracts

Officials can spend more time on strategic issues and less time on operational issues

Anticipating substantial reduction in costs over current fee on cost of construction pricing strategy – potentially R350 million over five years

LDoE’s new procurement strategy will greatly reduce the workload on officials, reduce costs, and improve response times.

Summary of benefits for LDOE

Page 17: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

17

Contractor development using framework agreements

Status of transformation in contractor market Black owned suppliers make up > 90% suppliers at grades 1 – 5 Supplier market at grades 1 – 5 is probably over supplied

Hence meaningful contractor development entails developing: Black Grade 6/7 contractors to Grade 7/8 Black Grade 3/4/5 contractors into Grade 4/5/6 using the sub-contractor & mentor model

Strategy supports meaningful contractor development programme by: Applying preferential procurement to select Limpopo BEE contractors Large contractors will have to meet contractual obligations

Subcontract a minimum % of work to lower grade BEE contractors Develop black contractors through a predetermined number of grades The 3 year framework agreement will ensure continuity of business and mentorship for

the BEE suppliers, ensuring a more sustained learning curve The CIDB register will be used to track performance and identify sub-contractors

Mentorship by experienced contractors yields best results

Similar model has been applied on the eThekwini contractor development programme

Page 18: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

Objective is to develop more black owned contractors at higher grades

National % black owned

contractorsNumber of Limpopo

contractors

Grade General building General building

1 98% 5011

2 94% 253

3 95% 65

4 89% 81

5 89% 75

6 79% 61

7 67% 19

8 51% 0

9 12% 0

Total 5565

18

Develop Grade 3/4/5 contractors into Grade

4/5/6 using the sub-contractor & mentor model

Develop Grade 6/7 contractors to Grade 7/8

Medium sized contractors > 80% black Medium sized contractors > 80% black ownershipownership

Page 19: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

19

Does not require any special approvals from Treasury – all allowable in terms of the existing SCM and CIDB frameworks

In-sources professional expertise (apart from programme management) IA’s do not need large numbers of engineers, architects, QS, or project managers Just needs small number of open-minded programme managers willing to

familiarise themselves with various contracting and procurement approaches and forms of contract

Envisaged challenges to rolling out a new approach to social infrastructure procurement Client difficulty in deciding on objectives Resistance to change, particularly from professional service providers

Implications of changes

Page 20: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

20

Broader roll-out

National workshops to be held this year

One-on-one engagements with key national stakeholders

Integration into IDIP IDIP technical assistants will help provincial health and education departments to

implement the methodology

 

SPAID is working with NT, nDOE, nHealth and CIDB to roll out the approach in the social sector.

Page 21: DEVELOPMENT OF A SECTORAL INFRASTRUCTURE PROCUREMENT STRATEGY Sean Phillips 25 March 2010

THANK YOU

21