determination of the transition point from open pit to … · · 2016-11-22j chung, m asad, e...
TRANSCRIPT
J Chung, M Asad, E Topal, AK Ghosh
Department of Mining Engineering and Metallurgical Engineering
Western Australian School of Mines, Curtin University
Western Australia
The Ninth AusIMM Open Pit Operators’ Conference 2016
2016 Kalgoorlie, Western Australia
Determination of the transition point from open
pit to underground mining
Strategic Mine planning and Optimisation for Combination Mining Method
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Presentation Outline
1. Introduction
2. Problem Definition & Objectives
3. Underground Mining System
4. Modelling the Transition Problem
5. Case Study
6. Conclusions & Recommendations
7. References
Ninth Open Pit Operators’ Conference 2016 Page 2
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Introduction
• Haulage cost and stripping ratio in OP mining will
increase when the pit goes deeper.
• As the stripping cost goes over UG mining cost and
OP mining becomes uneconomical, UG mining
emerges as a viable option.
• Transition from OP to UG required.
Ninth Open Pit Operators’ Conference 2016 Page 3
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Introduction: Combination Mining
4
In combination
mining, all involved
mining strategies need
to be considered
simultaneously in the
mine planning and
optimisation process
to ensure global
optimality achieved.
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Introduction
• ‘Transition Problem’ is the determination of the
optimal transition point with the aim of maximisation of
project’s value and resource utilisation.
• ‘Transition Point’ is where the decision has to be
made whether expand the pit or make the transition from
OP to UG.
Page 5
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Problem Definition & Objectives
Conservative/Simplest approach: The transition is considered
near or after the exhaustion (secondary) of the available reserves
inside the ultimate pit (Finch 2012).
Ninth Open Pit Operators’ Conference 2016 Page 6
Disadvantages:
1. UG mining could have been
the optimal strategy for some
of the OP reserves, but were
planned for OP mining
2. Evaluates OP and UG mining
options separately
3. Ignores the variation in mining
layout from one UG mining
method to the other.
4. Defines the crown pillar (CP)
is an arbitrary location.
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Problem Definition & Objectives
Objectives of this study are:
Present an implementation of an integer programming (IP)
based mathematical model
Evaluates possible variations in transition point from OP to
UG mining for sublevel stoping and block caving methods.
Demonstrates the impact of OP to UG mining strategies
and different UG mining methods on the overall value of
the project.
Ninth Open Pit Operators’ Conference 2016 Page 7
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
UG Mining System
• Block Caving Mining Method
High production rate and low mining cost
Highly depend on cave-ability of the ore and host rock
Dilution
Costly if caving cannot be maintained
• Stoping Mining Method
Minimum dilution if hanging wall is strong
Stopes can be filled with waste rock, paste fill to recover
pillar
Early production is possible
Safe working environment
Ninth Open Pit Operators’ Conference 2016 Page 8
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Mathematical Modelling for Transition Problem
IP model for OP & UG stoping combined method:
Objective function: Maximises the undiscounted profit
from both OP mining and UG mining.
Constraints:
(i) OP slope or block precedence constraint
(ii) UG mine design constraints
(iii) Reserve restriction constraints
(iv) CP design constraint that ensures the placement of CP is
underneath the pit
(v) The provision of required number of level needed for CP is in
accordance to the geotechnical requirement.
Ninth Open Pit Operators’ Conference 2016 Page 9
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Mathematical Modelling for Transition Problem
IP model for OP & UG block caving combined method:
Objective function: Maximises the undiscounted profit
from both OP mining and UG mining.
Constraints:
(i) OP slope or block precedence constraint
(ii) UG mine design constraints
(iii) Reserve restriction constraints
(iv) CP design constraint that ensures the placement of CP is
underneath the pit
(v) The provision of required number of level needed for CP is in
accordance to the geotechnical requirement.
Ninth Open Pit Operators’ Conference 2016 Page 10
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Mathematical Modelling for Transition Problem
Issues:
Size
Big data handling
Computer/Hardware capability
What if they are solved:
Accuracy
Precision
Effectiveness and efficiency
Adapting to Change
Ninth Open Pit Operators’ Conference 2016 Page 11
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Case Study
Case study profile and parameters
Three-dimension (3-D) hypothetical gold deposit.
41,472 blocks with block size of 25𝑚 × 25𝑚 × 25𝑚.
Design stope size 2 × 2 × 2 𝑏𝑙𝑜𝑐𝑘𝑠.
Two levels need to be retained as crown pillar.
IP problem written by Microsoft Visual Basic (VB.net) and solved by using CPLEX solver.
Ninth Open Pit Operators’ Conference 2016 Page 12
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Result Discussions
Ninth Open Pit Operators’ Conference 2016 Page 13
Scenarios IP model results ($billion)
Scenario 1: OP – UG stoping method 21.657
Scenario 2: OP – UG block caving method 26.020
Scenario 3: OP mining method only 18.396
Scenario 4: UG stoping method only 12.541
Scenario 5: UG block caving method only 13.123
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Case Study
• OP-UG stoping and OP-UG block caving methods have the
highest values.
• CP for scenario 1 is at Level 17-18 and scenarios 2 is Level
16-17.
• OP-UG block caving generates a higher value -- low mining
cost, high production rate and economy of scale.
• Proved that if the deposit can be mined through a combination
mining method, optimality can be achieved through strategic
mine planning.
Ninth Open Pit Operators’ Conference 2016 Page 14
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Case Study
• If OP mining is selected for the shallow deposit without
considering the potential transition to UG mining, the ultimate
pit will extend deeper than the final pit generated.
• The IP model
– includes opportunity cost of all available mining strategies.
– Avoid the delays in production during the transition – plan the
development in the early stage.
– Maximised resource and reserve utilisation.
Ninth Open Pit Operators’ Conference 2016 Page 15
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Conclusions & Recommendations
• OP, UG and CP concurrently during the strategic mine
planning strategy is important – global optimisation.
• UG mining method selection plays an important role in
combination method as it will affect the mining layout
and project’s value directly.
• IP models are presented to optimise the mine planning
of combination mining method
Ninth Open Pit Operators’ Conference 2016 Page 16
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Conclusions & Recommendations
• Technical limitations:
– Production rate,
– Equipment requirements
– Variation of labour skills
• Limitations:
– Timing of transition: Production scheduling
– Problem size reduction strategy: Nature of IP model
Ninth Open Pit Operators’ Conference 2016 Page 17
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
References1. Alford, C, 1995. Optimization in underground mine design, in Proceedings of 25th International APCOM Symposium 1995, pp 213-218
(Australasian Institute of Mining and Metallurgy,Melbourne: Brisbane, Australia).
2. Asad, M and Topal, E, 2011. Production scheduling of open pit mining operations through cutoff grade optimization. South African Institute of Mining and Metallurgy, 111(11):741-750.
3. Bakhtavar, E and Shahriar, K, 2007. Optimal ultimate pit depth considering an underground alternative, in Proceedings of Fourth AACHEN International Mining Symposium-High Performance Mine Production 2007, pp 213-221 (AIMS: Germany).
4. Bakhtavar, E, Shahriar, K and Mirhassani, A, 2012. Optimization of the transition from open-pit to underground operation in combined mining using (0-1) integer programming. J. South. Afr. Inst. Min. and Metall., 112(12):1059-1064.
5. Brazil, M, Thomas, D A, Weng, J F, Rubinstein, J H and Lee, D H, 2005. Cost optimisation for underground mining networks. Optimization and engineering, 6(2):241-256.
6. Camus, J P, 1992. Open pit optimization considering an underground alternative, in Proceedings of 23th International APCOM Symposium 1992, pp 435-441 (SME: Tucson).
7. Chung, J, Topal, E and Erten, O, 2015. Transition from open-pit to underground - using integer programming considering grade uncertainty, in The 17th annual conference of the International Association for Mathematical Geosciences 5-13 September 2015 2015, (Schaeben, H, Delgado, R T, Boogart, K G and Boogart, R), pp 268-277 (IAMG: Freiberg, Germany).
8. Chung, J, Topal, E and Ghosh, A G, in press. Where to make the transition from open-pit to underground? - using integer programming. South African Institute of Mining and Metallurgy.
9. Dagdelen, K and Traore, I, 2014. Open pit transition depth determination through global analysis of open pit and underground mine scheduling, in Orebody Modelling and Strategic Mine Planning 24-26 November 2014 2014, (Dimitrakopoulus, R), pp 195-200 (The Australasian Institute of Mining and Metallurgy: Perth, Australia).
10. Dimitrakopoulos, R, Martinez, L and Ramazan, S, 2007. A maximum upside/minimum downside approach to the traditional optimization of open pit mine design. Journal of Mining Science, 43(1):73-82.
11. IBM CPLEX Optimization Solver, 2013. Version 12.6. IBM CPLEX ILOG Corp.
12. Johnson, T B, 1968. Optimum open pit mine production scheduling. Berkeley: DTIC Document.
13. Lerchs, H and Grossman, F I, 1964. Optimum design of open-pit mines, in Operations research 1964, pp.
14. Opoku, S and Musingwini, C, 2013. Stochastic modelling of the open pit to underground transition interface for gold mines. Int. J. Min. Reclam. and Environ., 27(6):407-424.
15. Soderberg, A and Rausch, D O, 1968. Pit planning and layout, pp 142-143 (The American Institute of Mining, Metallurgical, and Petroleum Engineers, Inc: New York).
16. Topal, E and Ramazan, S, 2012. Strategic mine planning model using network flow model and real case application. International Journal of Mining, Reclamation and Environment, 26(1):29-37.
Ninth Open Pit Operators’ Conference 2016 Page 18
Curtin University is a trademark of Curtin University of TechnologyCRICOS Provider Code 00301J
Introduction
Mine Planning & Optimisation
Exploration stage
Search mineralization
zone
Block model generation
Geological block model
Economic block model
Determination appropriate mining method
Shallow deposit
Open pit mining method
Deep deposit
Underground mining method
Near surface orebody extend vertically to a considerable depth
Combination mining method
Transition problem
Transition point
Ninth Open Pit Operators’ Conference 2016 Page 20