DIAMOND HARBOUR HIGHWAY DIVISION, PW(R) D, WB Joynagar(Burorghat)-Moydah-
Jibonmondal-Mahismarihat Road
Road / Bridge project
i Name of project :
ii District covered : South 24 Paraganas
iii Project outlay (Rs. Crore) : 13.6629
S.NoItem Remarks
(Yes /
No)
1 General
i Whether the project is prioritized by the State Govt. Yes
ii Whether the project submited through the Nodal Dept. Yes
iii Whether the project included in the State Plan. Yes
2 Clearances from ( wherever applicable )
i Ministry of Enviroment & Forests Does not arise
ii Ministry of Railways Does not arise
iii Administrative Approval To be done aftter NABARD sanction
iv Technical Sanction To be done aftter NABARD sanction
v Land Acquisition - Extent status and time frame . Not Required
3 Technical Aspects
i General
aWhether master plan prepared by state Govt. and
proposed project are as per Master plan. As per department/district Plan
bWhether proposed project are new or Strengthening of
existing roads. Strengthening of existing Road
c
Whether proposed project have been designed as per
IRC standards . Reasons for deviation , if any should be
spelt out. Yes
dType of road project - Village Roads, Other District
Road, Major Rural Road .MDR (Major District Road)
eWhether fair weather connectivity is proposed reasons
for same to be elucidated. No
ii Road Project
a
Depth of roadway , Damage way , pavment making of
formation, sub-base , base courses, black toping,
culvert and small bridges in existing and proposed
conditions to be furnished in relevant Annexures . Reffered later
bExtent of cement Concrete sections, wherever provided
to be detailed . No
c
Justifications for widening / strengthening should be
supported by relevant data along with year of
construction.
Inadequate Pavement thickness,
Improvement of Riding Quality
iii Bridge project
Strengthening of Joynagar(Burorghat)-
Moydah-Jibonmondalhat-Mahishmarihat
Road(0KMP TO 18.53KMP) under Diamond
Harbour Highway Division in the district of
South 24 Paraganas, under the loan
assistance from NABARD, RIDF XIX
Check list for prepration of Detailed project Report to be submitted for
loans under Rural Infrastructure Development Fund
IMPROVEMENT AND STRENGTHENING OF ROAD FROM 0.000KMP TO 18.530KMP
DIAMOND HARBOUR HIGHWAY DIVISION, PW(R) D, WB Joynagar(Burorghat)-Moydah-
Jibonmondal-Mahismarihat Road
Road / Bridge project
i Name of project :
ii District covered : South 24 Paraganas
iii Project outlay (Rs. Crore) : 13.6629
S.NoItem Remarks
(Yes /
No)
Strengthening of Joynagar(Burorghat)-
Moydah-Jibonmondalhat-Mahishmarihat
Road(0KMP TO 18.53KMP) under Diamond
Harbour Highway Division in the district of
South 24 Paraganas, under the loan
assistance from NABARD, RIDF XIX
Check list for prepration of Detailed project Report to be submitted for
loans under Rural Infrastructure Development Fund
a
Hydraulic data, geo-technical details of foundations,
design details and drawings to be furnished. Does not arise as this is entirely Road
Scheme
bBridge project with detailed investigations should only
be proposed.
4 Financial Aspects
i Schedule of rates adopted (where updated to current
costs)
Yes/Year 2008-2009 as applicable on
01.09.2011 upto 7th corrigendumii
If not, Whether cost proposed will be sufficient to creat
the assets
Does not arise
iii. Cost Estimate
a Item wise cost of project Reffered later
b Item wise expenditure incurred Do
c Item wise cost of balance works Does not arise
d Item wise RIDF loan 80%
e Item wise State Govt. contribution 20%
f
Year wise phasing of RIDF loan and State and Govt.
Contribution (2 year Phasing allowed, reasons for 3
years phasing , wherever required)
To be done after sanction
g Specific justification for high cost of development. To be done after sanction
5
Benefits and justification
Overall impact of the project need to assessed and
detailed
Potential (road in km and bridge
in m span) Reduction in distance
(km) population benefited. Access to
Marketing / tourist / pilgrimage
conters ( numbers to be finished )
PCU data with likely savings in VOC
etc Non recurring and recurring
employment generation .
income 'Without' and 'With' project
and cash statement to be furnished
IMPROVEMENT AND STRENGTHENING OF ROAD FROM 0.000KMP TO 18.530KMP
DIAMOND HARBOUR HIGHWAY DIVISION, PW(R) D, WB Joynagar(Burorghat)-Moydah-
Jibonmondal-Mahismarihat Road
Road / Bridge project
i Name of project :
ii District covered : South 24 Paraganas
iii Project outlay (Rs. Crore) : 13.6629
S.NoItem Remarks
(Yes /
No)
Strengthening of Joynagar(Burorghat)-
Moydah-Jibonmondalhat-Mahishmarihat
Road(0KMP TO 18.53KMP) under Diamond
Harbour Highway Division in the district of
South 24 Paraganas, under the loan
assistance from NABARD, RIDF XIX
Check list for prepration of Detailed project Report to be submitted for
loans under Rural Infrastructure Development Fund
6 Operation and Maintenance
Arrange for O/M of projects after completions. Through Departmental Budgetary
Provision7 Infrastructure Facilities
i. Organizational structure of the implementing Dept. EE/AE/SAE's office to look after
ii.
Capacity and preparedness of the implementing
Dept. and status of implementation of earlier
sanctioned and mechanism. Adequate
iii. Quality control infrastructure and mechanism Adequate
iv. Availability of labour Adequate
v. Budget provision
a. For contribution of State Share Adequate Yearwise allocation is made
b. For subsequent O & M
c. For repayment of loans - Principal and interest.
8 Project Risks
i. Land acquisition Not Required.
ii. Forest clearance Not Required.
iii. Railway / road crossings Does not arise
iv. Construction hazards Nil
v. Any other risks Nil
9Convergence with any other programme
No.
IMPROVEMENT AND STRENGTHENING OF ROAD FROM 0.000KMP TO 18.530KMP
RURAL ROAD PROJECTS -TECHNICAL DETAILS- RIDF XIX
State : West Bengal
Length (km) 18.530 Existing Proposed Increase
Na
me
of P
roje
ct
Dis
tric
t
De
pa
rtm
en
t
Ca
teg
ory
Ro
ad
wa
y w
idth
(m
)
Ca
rria
ge
wa
y w
idth
(m)
Pa
ve
me
nt
Th
ickn
ess (
m)
Sh
ou
lde
rs w
idth
(m
)
CB
R v
alu
e %
Sta
tus o
f d
am
ag
e
Ro
ad
La
nd
wid
th
(m)
Ca
rria
ge
wa
y w
idth
(m)
Pa
ve
me
nt
Th
ickn
ess (
m)
Ha
rd S
ho
uld
ers
wid
th (
m)
CB
R v
alu
e %
Ro
ad
wa
y w
idth
(m
)
Ca
rria
ge
wa
y w
idth
(m)
Pa
ve
me
nt
Th
ickn
ess (
m)
No
of C
D w
ork
s
Na
ture
of S
urf
ace
Str
ength
enin
g o
f
Joynagar(
Buro
rghat)
-Moydah-
Jib
onm
ondal-M
ahis
marihat
Road(0
KM
P T
O 1
8.5
3K
MP
) under
Dia
mond H
arb
our
Hig
hw
ay D
ivis
ion
in t
he d
istr
ict
of
South
24
Para
ganas,
South
24 P
ara
ganas
PW
(Roads)
Directo
rate
MD
R
7 5.5
0.3
35
0.7
5
3%
Should
ers
Unsta
bili
zed,I
nadequate
Pavem
ent
Thic
kness
15
5.5
0.6
1
0.6
3% 2 0
0.2
75
0
Bitum
inous
Strengthening of Joynagar(Burorghat)-Moydah-Jibonmondal-Mahismarihat Road(0KMP TO 18.53KMP) under Diamond Harbour Highway Division in the district of South 24 Paraganas,
under the loan assistance from NABARD, RIDF XIX
RURAL ROAD PROJECTS -TECHNICAL DETAILS- RIDF XIX
State : West Bengal Block: JOYNAGAR-I&II Length: 18.53 km Others (in Rs.) SoR
Na
me
of P
roje
ct
Dis
tric
t
Ea
rth
wo
rk
Pic
kin
g u
p e
xis
tin
g r
oa
d
su
rfa
ce
Su
b-b
ase
WM
M
WB
M II
WB
M III
BM
BT
CD
Pro
tective
Wo
rk
Dra
ins
Oth
ers
Ce
ss @
1%
Co
ntin
ge
ncy @
3%
Pro
ject p
rep
ara
tio
n @
0.5
%
Gra
nd
To
tal
De
pa
rtm
en
t
Da
te o
f E
ffe
ct
Str
ength
enin
g o
f
Joynagar(
Buro
rghat)
-Moydah-
Jib
onm
ondal-M
ahis
marihat
Road(0
KM
P T
O 1
8.5
3K
MP
) under
Dia
mond H
arb
our
Hig
hw
ay
Div
isio
n in t
he d
istr
ict
of
South
24
Para
ganas,
South
24 P
ara
ganas
3616557.0
0
293154.0
0
6585138.0
0
52669530.0
0
789883.0
0
0.0
0
41929456.0
0
22515930.0
0
0.0
0
3085111.0
0
0.0
0
569108.0
0
Rate
s a
re inclu
siv
e o
f C
ess
39,2
2,3
92.0
0
6,5
3,7
32.0
0
13,6
6,2
9,9
91.0
0
P.W
(RO
AD
S).
D
05.0
1.0
9 o
f 2008-0
9
Strengthening of Joynagar(Burorghat)-Moydah-Jibonmondal-Mahismarihat Road(0KMP TO 18.53KMP) under Diamond Harbour Highway Division in the district of South 24 Paraganas,
under the loan assistance from NABARD, RIDF XIX
Annexure
DETAILS OF CALCULATION OF ECONOMIC ANALYSIS
State :West Bengal Block: Joynagar I & II Length: 18.530km Traffic details(Average Daily Traffic)* (Amount Rs. in lakh )
Serial N
os.
Nam
e o
f S
chem
e
Dis
tric
t
Pote
ntial
GC
A (
in H
a)
Tota
l C
ost
No.
of
vill
egers
benefitt
ed
No.
of
farm
ers
benefitt
ed
Popula
tion b
enefitt
ed
No.
of
Mark
eting c
entr
es
Non-
rec e
mp.
Genera
tion (
in lakh
man d
ays)
Rec.
em
p.
Genera
tion (
no.
of
jobs)
Dis
tance*
reduction (
in k
m)
Cycle
Cycle
ric
kshaw
Hand c
art
Hors
e v
ehic
le
Bullo
ck c
art
Moto
r cycle
/ S
coote
r
Car/
Pic
kup V
an/
Auto
ric
kshaw
Tra
cto
r/ L
CV
Bus/
Tru
ck
Tru
ck -
Tra
ilor/
Tra
cto
r T
raile
r
Are
a b
enefitt
ed
Valu
e o
f pro
duce p
er
Ha
Mark
et
Surp
lus
Bett
er
price r
ealis
ation
Wasta
ge s
avin
g
Contr
ibution t
o G
DP
(per
HA
)
1
Str
en
gth
en
ing
of
Ro
ad
So
uth
24
Pg
s
Hig
h
13
,66
,29
,99
1.0
0
80
,00
0
80
,00
0
1,2
0,0
00
7
52
1
46
9
0 0 15
32
2
29
4
79
75
76
Improvement & Strengthening of Joynagar(Burorghat)-Moydah-Jibonmondal-Mahismarihat Road(0KMP TO 18.53KMP) under Diamond Harbour Highway Division in the district of South 24 Paraganas,
under the loan assistance from NABARD, RIDF XIX
DIAMOND HARBOUR HIGHWAY DIVISION , P.W(ROADS) DIRECTORATE
LAKSHMIKANTAPUR HIGHWAY SUB-DIVISION
(RIDF Scheme with Loan Assistance from "NABARD")
REPORT
1 NAME OF WORK
2 INTRODUCTION
2.1 Project Background
2.2 Location
Sub-Division
Block Joynagar I , Joynagar II, Kultoli
Mouza
2.3 Classification of Road and its Status
Hatpara,Shahjadapur,Chandipur,Maydah,Naypukuria,Mayakholi,Khoimara,Dara,Ta
ranagar,Kripakhali
Strengthening of "Joynagar(started from Burorghat)-Moydah-Jibonmondalhat-Mahishmarihat
Road"(from 0km-18.530km) under Diamond Harbour Highway Division in the district of South 24
paraganas.
South 24 Parganas , a coastal district in the south of the State of West Bengal is bounded by
Kolkata and North 24 Parganas on North, Hoogly river on West, Bangladesh on East and Bay of
Bengal on South.
This district is having a geographical area of 8165.05 sq comprising vast rural area, Sundarban
forest area and also urban city area (part of Kolkata Metropolises).
Large road network spread over the district is still deficient in respect of requirement .With growth
of traffic in terms of volume and load many of the existing road which are built on poor road bed of
lower Gangetic alluvial soil are suffering from capacity constraint and structural inadequacy
resulting in deterioration of road pavement mainly due to financial stringency timely improvement
of the roads. A large number of rivers and channels including irrigation and canals provide gaps
blocking thorough movement along many of the road.
While expanding road network particularly in the sector of district has become a necessity, stress
has been given to complete the incomplete roads, strengthening of high density sections of
important traffic corridors which already have been taken up and completion of bridge projects
approved for implementation.
In view of the above, Public Works Department, Government of West Bengal takes a plan for
strengthening of existing carriage way to standard intermediate lane carriage way to meet the
requirement of present and future traffic.
The proposed road is a Major District Road.The road serves as the prime connectivity between
Joynagar Station with the habitations of the above mentioned mouzas.The road is 18.53 km with
average crust thickness of 335 mm and an average wearing coarse of 25mm (bituminous) with
earthen shoulders.
The RURAL INFRASTRUCTURE DEVELOPMENT FUND (RIDF) is a Scheme Dedicated for
infrastructural development in rural areas with a objective of providing better comunication facilities
in rural areas and ensuring reduction of poverty in rural areas. As per assignment of the RIDF
Scheme, the National Bank for Agriculture and Rural Development has envisaged development of
infrastructure in rural area (i.e. Improvement or Upgradation of rural roads) in the state of West
Bengal.
DIAMOND HARBOUR HIGHWAY DIVISION , P.W(ROADS) DIRECTORATE
LAKSHMIKANTAPUR HIGHWAY SUB-DIVISION
(RIDF Scheme with Loan Assistance from "NABARD")
2.4 Length of the Road
2.5 Nature of Locality and Inhabitants
2.6 History
3 NECESSITY & BENEFIT
Social Aspects:
Health Center/Hospital : 2 Nos. Bank and Panchyet : 12 Nos.
Sub-Hospital : 1 No. Other Offices : 5 Nos.
Markets and Economic activities :
Major Produces are Paddy,Flower,Fruits,Vegetables,Sweet Water Fisheries and Breeding Units.
Traffic Status:
Fast Moving Vehicles : Nos.
Slow Moving Vehicles : Nos.
Termination point = Mahismarihat. Co-ordinates are 22o11'17.03'' N, 88
o34'19.77''
Length of the road = 18.530km
The road Terrain is classified as plain terrain.The climatic condition of this region is tropical humid.
Winter starts early in November and ends in the middle of February. Summer lasts till the middle
of June. Soon after this the rainy season commences and continues till the end of August. January
is the coldest month in this region. The mean minimum temperature in the month of January
varies from 100C to 15
0C. The highest temperature is often registered in May (Near about 42
0 C),
which is the hottest month. The average rainfall in this region is above 1500mm.There are two
harvesting seasons in area, one from middle of March to end of May(75 days) and other is from
start of October to middle of December (75 days)
The propsed road originates at Burorghat (T junction), 1.8 km from Joynagar on the PWD road
connecting Joynagar and Kultoli and terminates at Mahishmari Hat. The road passes through
areas mostly inhabitated by farmers and fisherman. The region around Joynagar, Kutoli was a rich
province and carries historical heritages and importance.
Starting Point = The propsed road originates at Burorghat (T junction), 1.8 km from Joynagar on
the PWD road connecting Joynagar and Kultoli.
Co-ordinates are 22o09'56.35'' N , 88
o25'41.44''E
846
1005
The proposed road contributes immensly to the the connectivity of the Joynagar and Baruipur.This
road runs parallel to the rail route connecting rail stations namely Dakshin Barasat , Baharu,and
Joynagar. This region is thickly populated with population around 1.2 lakhs considering all the
Blocks and mouzas that it connects on the way. Thus this road serves the population from 10
Mouzas. This road runs through agricultural areas,a good number of farm houses,brick fields (21
number approx),schools ,colleges, banks hospitalsand connects 6 number of markets namely
Chandipur,Maydah Kalibari, Jibon Mondal Haat, Pitambarer More, Dara, Mahish Mari Haat. So
quite a considerable number of commercial vehicle ply everyday. Besides this since the region is
known to be one of the major producers of vegetable which was daily required to be brought to the
urban area to meet its daily need.Thus this road has a tremendous socio-economic impact on the
rural population.
Markets at Chandipur,Maydah Kalibari, Jibon Mondal Haat, Pitambarer More, Dara, Mahish Mari
Haat and 21 number brick-fields.
DIAMOND HARBOUR HIGHWAY DIVISION , P.W(ROADS) DIRECTORATE
LAKSHMIKANTAPUR HIGHWAY SUB-DIVISION
(RIDF Scheme with Loan Assistance from "NABARD")
4 PRESENT STATUS OF THE ROAD
a) The proposed road is under Major District Road category of intermediate lane with poor BT.
b) Total length is : Kilometer
c) Project length is : Kilometer
d) Carriageway width of existing bituminous road is 5.5m(Average) for a total length
e) Average height of the Finished surface level 1.0m & is 0.6m over the normal HFL of the area .
f) Average crust thickness of 335 mm with an average wearing coarse of 25mm (bituminous).
g) The roadway width is 6.5 m to 7.0 m average with Road land width 15.0 m to 30.0 m.
h) Existing alignment does not suffer from any major deficiency in road geometry .
i)
5 TOPOGRAPHICAL SURVEYS
6 SOIL AND MATERIAL SURVEY
i). Sieve Analysis
ii). Atterberg’s Limits
iii). Standard ProctorTest
iv). Soaked & Unsoaked CBR test
7 TRAFFIC CENSUS
7.1 Classified Traffic Volume Counts
The classified traffic count (7 days in both ways) survey was conducted on the same road . The
count was conducted for 24 hours (0.00 Hour to 24.00Hour) of the day.
Topographic survey true to ground realties have been done using precision instruments like Total
Stations and Auto levels, and bringing out data in digital form (x,y,z format) for developing DTM .
Traverse has been done by total station having angular measurement accuracy of ± 1 sec. All
leveling for establishing Benchmark are to be carried out as per method adopted by Survey of
India. All leveling are to be carried out with Auto Level having accuracy ± 2.5 mm/ km. In absence
of GTS benchmark in the nearby location of the road, arbitrary level (R.L) has been assumed and
fixed on TBM pillars accordingly.All data from topographic survey recorded by Auto Level were
takenup and final alignment, plan, profile were prepared and presented in AutoCAD Format.
Soil survey has been done by collecting samples of local soils from the embankment / sub-grade
of the proposed road in accordance to the guidelines of IRC :SP: 20-2002. The important tests
carried out on the soil intended for use for subgrade are as under
From the test results it is clear that the soil type is Silty Clay with fine sand and the designed CBR
for the soil along the proposed road is 3%. for the total length.
18.530
Present surface condition is undulated , broken Crust, inadequate flanks width and eroded at
many stretches.
18.530
DIAMOND HARBOUR HIGHWAY DIVISION , P.W(ROADS) DIRECTORATE
LAKSHMIKANTAPUR HIGHWAY SUB-DIVISION
(RIDF Scheme with Loan Assistance from "NABARD")
7.2 Traffic Forecast
8 TECNNICAL SPECIFICATION
8.1 Preparation of Ground before Construction of Embankment
8.2 Wet Mix Macadam
Patching of pot holes
8.3 Construction of Bituminous course
Prime Coat
600mm wide hard shoulder is proposed on both sides through out the length of the road except for
areas of concrete surfaces as in case of cross drainage structures. Shouldering is done with single
layer of 75mm compacted thickness of brick-bats over which a single layer of 75mm thick jhama-
metal is to be laid to attain an over-all compacted thickness of 150mm .
The sequence of laying of the primer should be as detailed in the IRC specification.
This work shall consist of application of single coat of low viscosity liquid bituminous material to a
porous granular surface preparatory to any superimposition of bituminous treatment or mix. Single
coat of Prime coat with low viscosity should be applied over the granular surface MOST gives
guidelines for requirements of viscosity and quantity of bituminous material for priming purpose.
Since the surface is granular the kinematics viscosity of the primer at 600 should be in the range of
30-60 centistokes and quantity bitumen should be 0.75 kg per sq.m.
Where the existing surface is granular, all loose materials shall be removed and the surface lightly
watered where the profile corrective course to be provided as a separate layer. Where the profile
corrective course of bituminous material is to be laid over the existing granular surface, the latter
shall, after removal of all loose materials, be primed with as per the stipulations of prime coat over
granular base
The present day traffic has to be projected for the end of design life at growth rates as per IRC 37-
2001. The design traffic in terms of the cumulative number of standard axle to be carried out
according to Cl. 3.3.6 of IRC 37-2001 , page 14. The traffic in the year of completion of the road
project has been estimated as per equation 3.3.6.1 of the above page 15 of IRC 37 : 2001
mentioned clause.
Laying ,spreading & compacting approved stone aggregates to Wet Mix Macadam specification
including screening of aggregates and granular materials, mixing the materials in proper grading
using mechanical mixer, adding water to achieve required OMC, laying the mixed materials in
uniform thickness of 75 mm each layer over prepared surface, rolling with 8-10t roller in stages to
proper grade, camber, until the desired density is achieved, as per direction of Engineer-in-
Charge complete, including cost of quality control. WMM is laid in three layers to attain a desired
thickness of 225 mm.
Existing potholes and cracks shall be repaired and sealed following the conventional methods or
as directed by the Engineer-in-Charge.
Widening of the embankment layers shall be done with earthen layers of thickness not exceeding
200mm in compacted thickness. The soil used in the embankment shall conform to the technical
specifications. At the time of placing the Earth work, layers not more than 300mm thick (loosened
earth) shall be placed only after checking the in-situ moisture content.It is compacted by power
Roller / vibratory Roller to attain the desired MDD at OMC compared to 100% standard proctor
density (i.e. degree of compaction of soil) in slope of embankment including breaking all clods
required quantity of watering as per OMC, filling depression making sufficient number benches on
existing embankment, crest width to proper profile with 2.5% cambering at sub-grade level in
accordance with the procedure of earth work.Clods or hard lumps of earth shall be broken to have
maximum size of 75 mm. when being placed in the embankments and a maximum size of 50 mm.
when being placed in the sub-grade.
DIAMOND HARBOUR HIGHWAY DIVISION , P.W(ROADS) DIRECTORATE
LAKSHMIKANTAPUR HIGHWAY SUB-DIVISION
(RIDF Scheme with Loan Assistance from "NABARD")
8.4 Bituminous Macadam
8.5 Premixed Carpet and Seal Coat
8.6 Mastic Asphalt
9 CROSS DRAINAGE WORKS
10 PROTECTIVE WORKS AND ROAD FURNITURE
After thorough investigation of the road with Engineer-in-charge provision of mastic asphalt have
been made in water-logged areas,market places . The total length for mastic asphalt is 945m.
The existing CD structures are in good condition and are present in sufficient numbers. The list of
existing CD structures are presented alongwith.
25mm thick mastic asphat wearing coarse will be applied on the treated BM top layer. Approved
quality coarse aggregate,fine aggregate,filter material,binder and bitumen in specified proportions as
reffered to in the IRC specification.
This work shall consist of laying and compacting an open graded carpet of 20 mm thickness in a
single course composed of suitable small sized aggregates premixed with a bituminous binder on
a previously prepared base, in accordance with the requirements of these specifications to serve
as a wearing course. The underlying base on which the bituminous carpet is to be laid shall be
prepared shaped and conditioned to the specified lines, grade and cross section as directed by the
Engineer-in-Charge. A tack coat shall be applied as required by the Contract documents, or as
directed by the Engineer-in-Charge.
The binder shall be bitumen of a suitable grade appropriate to the region, traffic, rainfall and other
environmental conditions as directed by the Engineer-in-Charge, and satisfying the requirements
of IS: 73.
This work shall consist of construction, in a single course, of 50 mm compacted thickness of
compacted crushed aggregates premixed with a bituminous binder, laid immediately after mixing,
on a base prepared previously in accordance with the requirements of the specifications, and in
conformity with the lines, grades and cross-sections shown on the drawings or directed by the
Engineer-in-Charge.
Tack coat shall be applied in all bituminious layers starting from BM,Premix and Mastic asphalt. In
case of application of tack coat mechanical means adopted for BM and Premixed carpet where as
for mastic asphalt it is to be laid manually.Tack coat in the form of Bituminous emulsion shall be
applied as 0.30 kg/sq.m.
The bitumen shall be paving bitumen of suitable penetration grade within the range S 35 to S 90 or
A 35 to A 90 (30/40 to 80/100) The aggregates shall consist of crushed stone, crushed gravel
(shingle) or other stones retained on 2.36 mm sieve. They shall be clean, strong, durable of fairly
cubical shape and free of disintegrated piece, organic and other deleterious matter, and adherent
coatings. The aggregates shall preferably be hydrophobic and of low porosity. Where crushed
gravel is used as aggregates, not less than 90% by weight of crushed materials retained on 4.75
mm sieve shall have at least two fractured faces. The aggregates shall be proportioned and
blended to produce a uniform mixture complying to the specifications. The binder content shall be
within a tolerance of ± 0.3 % by weight of total mixture.A tack coat shall be applied as required by
the Contract documents, or as directed by the Engineer-in-Charge.
Protective works are carried out to stabilise the shoulders and embankment particularly in areas
where water bodies are located adjacent to the embankment. It is carried out using Eucalyptus
Ballah of 100mm and 150mm dia as required upon depending on the depth of the water body. The
list for protective works to be carried out ,chainage wise have been attached alongwith.
Road furnitures in the form of Ordinary km stone, 5th km stone and 200m RC post, guard post
and other regulatory traffic sign have been installed.
DIAMOND HARBOUR HIGHWAY DIVISION , P.W(ROADS) DIRECTORATE
LAKSHMIKANTAPUR HIGHWAY SUB-DIVISION
(RIDF Scheme with Loan Assistance from "NABARD")
11 PAVEMENT COMPOSITION
Existing Pavement Composition : 185 mm Jhama Metal+ Brick Bats
150 mm WBM Grade II
Proposed Pavement Composition
Considering strengthening :
(General) 225 mm Wet Mix Macadam
50 mm BM
20 mm Premix Carpet & Seal Coat
(Mastic Asphalt 945m) 225 mm Wet Mix Macadam
50 mm BM
25 mm Mastic Asphalt
Total 610 mm
12 ANALYSIS OF RATES
12.1 Rate Analysis
Pradip Kumar Pal Malay Ghosh Arup Ratan Mukhopadhyay
Assistant Engineer Superintending Engineer Executive Engineer
Lakshmikantapur Highway Sub-Division State Highway Circle No.1 Diamond Harbour Highway Division
P.W.(Roads) Directorate P.W.(Roads) Directorate P.W.(Roads) Directorate
Govt. Of West Bengal Govt. Of West Bengal Govt. Of West Bengal
Rates have been adopted for various items of work from the schedule of Rates for Road works,
culverts & Carriage PW(Roads)D Schedule 2008 -2009 Effective from 05.01.09
DIAMOND HARBOUR HIGHWAY DIVISION
RIDF XIX th Scheme with Loan assistance from "NABARD"
EXISTING CROSS-DRAINAGE STRUCTURESRoad Name : - Joynagar to Mahismarihat
Length of the road = 18.530KM Block : - Joynagar I & II, Kultoli District : - South 24 - Parganas
SL No. Chainage Type No. Dia./Width Length Condition Necessary
(KM) (m) (m) Action
1 1+430 PIPE CULVERT 1 0.900 10.275 Functioning
2 1+920 PIPE CULVERT 1 0.900 10.275 Functioning
3 2+870 PIPE CULVERT 1 0.900 10.500 Functioning
4 3+520 PIPE CULVERT 1 0.900 10.500 Functioning
5 3+680 PIPE CULVERT 1 0.900 10.500 Functioning
6 4+080 PIPE CULVERT 1 0.900 10.500 Functioning
7 4+250 PIPE CULVERT 1 0.900 10.500 Functioning
8 4+400 PIPE CULVERT 1 0.900 10.500 Functioning
9 4+750 PIPE CULVERT 1 0.900 10.000 Clogged Cleaning
10 4+850 BOX CULVERT 1 3.500 8.250 Good No Action
11 5+020 PIPE CULVERT 1 0.900 10.000 Functioning
12 5+098 PIPE CULVERT 1 0.900 10.500 Functioning
13 5+880 PIPE CULVERT 1 0.900 10.750 Functioning
14 6+620 PIPE CULVERT 1 0.900 11.000 Functioning
15 7+610 PIPE CULVERT 1 0.900 11.000 Functioning
16 8+090 PIPE CULVERT 1 0.900 11.000 Functioning
17 8+580 PIPE CULVERT 1 0.900 11.000 Functioning
18 8+950 BRIDGE 1 47.000 10.000 Good Condt. No Action
19 9+145 PIPE CULVERT 1 0.900 12.500 Clogged Cleaning
20 9+350 PIPE CULVERT 1 0.900 10.500 Clogged Cleaning
21 9+570 PIPE CULVERT 1 0.900 10.000 Clogged Cleaning
22 9+850 PIPE CULVERT 1 0.900 9.500 Functioning
23 10+150 PIPE CULVERT 2 0.900 10.500 Functioning
24 10+670 PIPE CULVERT 1 0.900 10.500 Functioning
25 10+950 PIPE CULVERT 2 0.900 10.500 Functioning
26 12+360 HUME PIPE 1 0.900 9.750 Functioning
26 12+630 PIPE CULVERT 1 0.900 9.750 Functioning
26 12+790 PIPE CULVERT 1 0.900 10.500 Functioning
26 13+205 HUME PIPE 1 0.900 8.250 Functioning
26 13+350 HUME PIPE 1 0.900 9.750 Functioning
26 13+450 BOX CULVERT 1 1.500 9.750 Functioning
26 14+110 BOX CULVERT 1 3.500 7.750 Good Condt. No Action
26 15+050 HUME PIPE 1 0.900 10.000 Functioning
26 15+360 HUME PIPE 1 0.900 10.000 Functioning
26 15+860 PIPE CULVERT 1 0.900 10.000 Clogged Cleaning
26 16+350 PIPE CULVERT 2 0.900 10.250 Functioning
26 16+880 PIPE CULVERT 2 0.900 10.750 Functioning
26 17+150 PIPE CULVERT 1 0.900 10.500 Functioning
26 17+260 PIPE CULVERT 1 0.900 10.500 Functioning
26 17+750 PIPE CULVERT 1 0.900 10.500 Functioning
26 17+960 BOX CULVERT 1 5.500 7.750 Good Condt. No Action
26 18+110 PIPE CULVERT 1 0.900 10.000 Functioning
26 18+250 PIPE CULVERT 2 0.900 10.000 Functioning
No Action, Temporary
Maintenance
only,Removal of
unwanted vegetative
growth
No Action, Temporary
Maintenance
only,Removal of
unwanted vegetative
growth
No Action, Temporary
Maintenance
only,Removal of
unwanted vegetative
growth
No Action, Temporary
Maintenance
only,Removal of
No Action, Temporary
Maintenance
only,Removal of
unwanted vegetative
growth
No Action, Temporary
Maintenance
only,Removal of
9000
C L of Proposed Carriageway
1750 2750 2750 1750
Earthen Earthen
Shoulder Shoulder
2.5 % 3.5 % 3.5 % 2.5 %
2 2
1 1600 (TYP)
Existing Embankment
75MM JHAMA
75MM BRICK-BATS
20MM Premix Carpet 225MM WMM
50MM BM
PROPOSED CROSS SECTION IN STRAIGHT SECTION FOR FLEXIBLE PAVEMENT
8000
C L of Proposed Carriageway
1250 2750 2750 1250
Subgrade
25MM Wearing Course 150mm WMM (2 Layers)
85mm Brick Bats 100 mm Jhama-metal
EXISTING CROSS SECTION IN STRAIGHT SECTION FOR FLEXIBLE PAVEMENT
Length Of the Road = M Width = 5.5 m
Length with concrete surface = M WMM = 0.225 m
M BM = 0.05 m
Picking up of Existing Bituminous layer
1 X 18451.8 X 5.50 = 101485.00 M2
Add 2.00% as curve and Bellmouth 2030.00 M2
103515.00 M2
Repairing Pot holes
( Assuming 6.5% of surface area are potholes and average loose net thickness is 100mm)
1 X 18451.75 X 5.50 X = 101485.00 M2
Add 2.00% as curve and Bellmouth 2030.00 M2
103515.00 M2
Volume of potholes = X 6.50% X 0.1 = 673.000 M3
Hard shouldering
Width = 600 mm
Thickness = 150 mm
75 mm thick single-layer brick-bat used for shoudering = 1660.6575 M3
Add 2.00% as curve and Bellmouth 33.00 M3
1693.6575 M3
75 mm thick single-layer Jhama-metal used for shoudering = 22142.1 M2
Add 2.00% as curve and Bellmouth 443.00 M2
22585.1 M2
Wet Mix Macadam 150mm thick
1 X 18451.75 X 5.50 X 0.225 = 22834.00 M3
In Jibanmondalhat Bazar 1 X 145.00 X 3.80 X 0.15 = 83.00 M3
22917.00
Add 2.00% as curve and Bellmouth 458.00 M3
23375.00 M3
Priming coat
18530.00 X 5.50 = 101915.00 M2
In Jibanmondalhat Bazar 145.00 X 3.80 = 551.00 M2
102466.00 M2
ITem No -1
ITem No -5
ITem No -6
ITem No -4
Calculation Of Quantity.
ITem No -2
18530.00
78.25
18451.75
103515.00
ITem No -3
Add 2.00% as curve and Bellmouth 2049.00 M2
104515.00 M2
50mm th Bituminous Macadam
1 X 18530.00 X 5.50 = 101915.00 M2
In Jibanmondalhat Bazar 145.00 X 3.80 = 551.00 M2
102466.00 M2
Add 2.00% as curve and Bellmouth 2049.00 M2
104515.00 M2
20mm thick premixed carpet
Area Of 50mm thick B.M. = 104515.00 M2
Less area of Mastic Asphalt 5302.00 M2
99213.00 M2
25mm thick Mastic Asphalt
1 X 945 X 5.50 = 5198.00 M2
Add 2.00% as curve and Bellmouth 104.00 M2
5302.00 M2
Seal Coat type "B"
Area same as Premixd carpet = 99213.00 M2
Eucallyptuc Bullah Pilling = 1425.00 M
Placing of Cement Bag filled with Earth
Using 22 nos of bag per meter length along with bullah pilling
1425.00 X 22.00 = 31350.00
31350.00
Total Earthwork as per C/S drawings = 73903.06
Deduction due to earthcrust = 28466.44
Deduction due to hard Shoulder = 3387.54
42049.08 M3
Less :Built-up areas, homestead areas and markets ,side drain, earthen bundh, river,
ponds and water bodies, and other allied activities = 35 %
Therefore deduction in earthwork = 14717.18 M3
Net earth-work volume = 27331.90 M3
ITem No -12
ITem No -7
ITem No -11
ITem No -8
ITem No -9
ITem No -10
Borrow Pit Earth Work = 40% of 27331.90 m3 = 10932.76 M3
Carried Earth Work = 60% of 27331.90 m3 = 16399.14 M3
ITem No -13
ITem No -14
Diamond Harbour Highway
Division PW(R)D,West Bengal
Joynagar (Burorghat) to Mahishmarihat
(0.00kmp to 18.53kmp)
SUMMARY OF TRAFFIC FOR SEVEN DAYS COUNT (BOTH WAYS)
Laden Un laden Laden Un laden Laden Un laden LadenUn
laden
1 2 3 4 5 6 7 8 7 8 7 8 7 8 10 11 12
12.04.13 00.00 12.04.13 24.00 206 347 0 0 27 27 45 53 10 27 16 510 431
13.04.13 00.00 13.04.13 24.00 327 347 0 0 32 34 56 65 16 29 16 621 625
14.04.13 00.00 14.04.13 24.00 315 311 0 0 35 32 62 48 20 28 19 549 503
15.04.13 00.00 15.04.13 24.00 311 336 0 0 39 42 60 44 21 21 19 509 435
16.04.13 00.00 16.04.13 24.00 312 297 0 0 42 42 56 68 18 27 11 488 429
17.04.13 00.00 17.04.13 24.00 297 291 0 0 43 42 57 65 19 24 13 483 399
18.04.13 00.00 18.04.13 24.00 291 324 0 0 46 40 71 45 24 12 13 487 462
2059 2253 0 0 264 259 407 388 128 168 107 3647 3284
294.14 321.86 0.00 0.00 37.71 37.00 58.14 55.43 18.29 24.00 15.29 521.00 469.14
294 322 0 0 38 37 58 55 18 24 15 521 469
294 161 0 0 114 111 261 248 81 108 120 261 938
Average Daily Traffic 1851
Commercial Vehicle Per Day Total PCU = 2696Laden Un laden
Tractor with trailer 58 55
BUS 0 0
TRUCK 38 37
Total = 96 92
(CVPD) at the time of Census(No. of vehicle weight > 3MT) = 133
Pradip Kumar Pal Arup Ratan MukhopadhyayAssistant Engineer Executive Engineer
Lakshmikantapur Highway Sub-Division Diamond Harbour Highway Division
P.W (Roads) Directorate P.W (Roads) Directorate
Govt. Of West Bengal Govt. Of West Bengal
BUSES ANIMAL
DRAWN
VEHICLES
CYCLES
Passanger's Car Unit
OT
HE
R
(SP
EC
IFY
)
VA
N
RIC
HS
HA
W
Truck
TW
O
WH
EE
LE
RS
Agri-Tractors with
trailers
Other motorised
commercial
vehicles
(CPVD)
Rounding
Average For One Day
CARS,JEE
PS, VANS
Wt <3MT
FROM
DATEHOUR TO DATE
Total for 7 days
HOUR
Diamond Harbour Highway
Division PW(R)D,West Bengal
Joynagar (Burorghat) to Mahishmarihat
(0.00kmp to 18.53kmp)
Computation of traffic in terms of msa as per IRC 37:2001
Ns = 365 x A x ((1+r)^t-1) x F x L / r
A = P x (1 + r ) ^ n
A = No. of commercial vehicles per day at the end of project
A = No. of commercial vehicles per day at the end of "n" years during project r = Annual growth rate 7.5 %
P = No. of commercial vehicles per day at last count t = Design life in yrs 10 yrs
r = Annual growth rate 7.5 % F = Vehicle damage Factor 3.5
n = Nos. of years 2 yrs L = Lane Distribution Factor 0.75
Ns = 365 x 153.698 x ((1+7.5/100)^10-1) x 3.5 x 0.75 x (7.5/100)
Therefore, A = 133 x (1 + 7.5/100)^2 = 153.6981 = 2083329
2.08E+06
Therefore , Ns = 2 msa
CBR = 3 %
PAVEMENT DESIGN
Now Since, Designed CBR is 3 %
Designed msa is 2
Hence, From IRC 37:2001 we, get pavement thickness
Plate 1, Page 22
As per provision the crust is as follow
CBR(%) 3 Pavement Composition Strengthening of Existing Pavement
Cumulative Total Bituminous Coarse Granular Granular
Traffic Pavement Wearing Binder Base Sub-base Existing Crust 335 (185mm Brick Bats & Jhama Metal
Thickness Coarse Coarse Coarse Coarse Strengthening +150mm WMM )
(msa) (mm) (mm) (mm) (mm) (mm) WMM 225 mm
BM 50 mm
2 610 25 50 225 335 Total = 610 mm Hence safe.
20 mm wearing coat
Road From: JOYNAGAR TO MAHISHMARIGHAT
Length of the Road: 18.530 KM
Name of the District: South 24 Parganas
Sl. No. Description of Items Cost in Rupees
1 Cost of Earth Work 3616557.00
2 Cost of Sub-Base 7668175.00
3 Cost of Base Course 52669530.00
4 Cost of Bituminous Work 64445386.00
5 Cost of Road Furniture & Traffic Safety Measures 569108.00
6 Cost of Protective Work
a Cost of UC Bullah Piling 1425 metre 2781956.00
b Cost of Dumping Earth Filled Gunny bags 31350 nos. 303155.00
3085111.00
7 Cost of Cross Drainage Works 0.00Total (Including Cess) Rs. 132053867.00
Total (excluding cess @ 1%) Rs. 130746403.00Add 3.00% as contingency Rs. 3922392.00
Add 0.50% as cost towards Outsource of DPR Rs. 653732.00
Add L.W. Cess @ 1% Rs. 1307464.00
Say Rs. 136629991.00
Say Rs. In Lakhs 1366.29991
Arup Ratan Mukhopadhyay
Govt. of West Bengal
PW(Roads) Directorate PW(Roads) Directorate
Govt. of West Bengal Govt. of West Bengal
Chief Engineer
PW(Roads) Directorate
Sankar Roy Choedhury
Diamond Harbour Highway Division State Highway Circle No. - I
IN THE DISTRICT OF SOUTH 24 PGS.
Executive Engineer Superintending Engineer
IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)- MOIDAH-
JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 KMP)
UNDER DIAMOND HARBOUR HIGHWAY DIVISION
Malay Ghosh
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
V.P.265 It-2 ab (i)
1
Picking up and removing old bituminous layer or sand sealing coat
from old black topped surface and cleaning the exposed surface
by scraping and stacking the material as directed.
(b) By mechanical means : Sqm 82812 3.54 293154.00
( V.p.264,It-16)
2
Patching of potholes by draining water, cutting the pothole area to
rectangular shape with vertical edges, removing all loose
materials, screening and stacking the same for reuse with new
materials as per requirement, filling the pothole area with
additional volume of crushed stone materials / laterite / Jhama /
broken shingles / coated stones of Pakur variety etc. and
screenings as applicable, and compacting the same with static
roller as per Water Bound Macadam Specification, including cost
of all materials and machineries but including the cost of coarse
aggregates and screening.Cum 362.300 2180.19 789883.00
(V.P.191 It-1)
3
Supplying, spreading and consolidation of brick bats (size 45 mm
and down) and medium sand including premixing the material in
suitable mixer conforming the combined material to the Grading – I
of Granular Sub-base Materials and in proportion of 60 : 40 and
rolling at O.M.C. to achieve at least 97% of maximum dry density,
maintaining proper gradient and camber, watering as necessary
and lighting, guarding, barricading and making adequate earthen
bundh on both sides where necessary to protect the edges and
curing with water including all incidental charges for the work and
cost of rolling complete. Cum 1693.6575 1252.30 2120967.00
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
(V.P.259 It-7b))
4
Labour for spreading and consolidating 1st class brick bats/
Jhama metal/Laterite chelly or metal / shingles of specific size
in hard crust to requisite thickness (measured after compaction) in
layers including screening of bats/metals etc. as necessary, hand
packing, sweeping, watering and rolling in stages with power roller
to proper line, grade and camber, lighting, guarding & barricading
and making necessary earthen bundh of one metre width on each
side where necessary to protect edges and preparing the bed by
necessary cutting or filling and rolling all complete including the
cost of all materials and hire and labour charges of all man and
machineries and as per specification and direction of Engineer-in-
chargeincluding the cost of bats/chelly.
(b) Using Brick bats / Jhama metal / Laterite metal of size 63
mm – 45 mm for compacted thickness 75mm. Sqm 22585.100 197.66 4464171.00
( V.p.262,It-9)
5
Labour for spreading & compacting approved stone aggregates to
Wet Mix Macadam specification including screening of
aggregates and granular materials, mixing the materials in proper
grading using mechanical mixer, adding water to achieve required
OMC, carrying the mix to work-site using tipper trucks within a
lead of 10 km , laying the mixed materials in uniform thickness
over prepared surface, rolling with 8-10t roller in stages to proper
grade, camber, until the desired density is achieved, including
supply of all materials, machinery, fuel & lubricants, including
incidental costs for lighting, guarding, barricading, making of
earthen bundfh to protect the edges, controlling traffic, etc. as per
direction of Engineer-in-Charge complete, including cost of quality
control. Cum 23375.02 2253.24 52669530.00
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
( V.p.266,It-4,a)
6
Providing and applying bituminous Primer Coat for priming of
base course with Cationic bituminous emulsion of approved grade
and requisite quantity including preparation of the surface to be
primed, through cleaning and sweeping, uprooting weeds, grass
etc. dampening the surface beforehand spraying the primer using
sprayer mounted on distributor truck or with hand sprayer using
mechanical pump including cost and carriage of bitumen emulsion
and all other incidental costs of work.
(a) For surfaces with low porosity
(@ 7.5 kg / 10 m2). Sqm 104515.32 36.87 3853480.00
(Section 4.7, It-34(B)(b)(ii))
7
Laying Bituminous Macadam of specified grade using Hot Mix
Plant (HMP) and using approved aggregates conforming to
specified grading and bitumen over prepared surface, including
carrying the hot premixed materials by means of tipper truck,
spreading, the mixed material at specified laying temperature over
the prepared surface by means of a suitable paver finisher,
tamping and finishing the mix to specified grade, line and camber,
thorough rolling with suitable power rollers for break down, inter-
mediate and finished rolling as per specification, hand packing and
pinning to give an even surface including cost and carriage of
stone materials & bitumen, and hire charges of HMP and all other
machines and equipments, cost of fuels and lubricants and wages
of operational staff, quality control as per IRC Specification all
complete including cost of applying tack coat.
(B) In Base / Binder Course using 3.4 % binder content by
weight of total mix.(b) 50mm compacted thickness
(iii) Using Drum Mix type HMP of minimum capacity 60-90 TPH. Sqm 104515.32 364.31 38075976.00
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
(Section 4.7, It-38(ii))
8
Providing & Laying 20 mm thick open graded Premixed Carpet
by Hot Mix Plant using 13.2 mm (@ 0.18 m3/m
2) and 11.2 mm
(@ 0.09 m3/m
2) size stone aggregates, including thorough
cleaning of the surface, applying tack coat, screening cleaning and
pre-heating stone chips and fully pre-coating the same with hot
matrix @ 54 kg/m3
of aggregate mix, carrying the mixture by tipper
trucks or by any other suitable arrangements, laying the mixture
uniformly over the surface with paver finisher , including manual
operations as and when required for proper level, grade and
camber, thoroughly rolling by power roller, including the cost and
carriage of stone chips and matrix, heating the matrix, preheating
the aggregates to required temperature and including the hire
charges of Hot Mix Plant and other machineries, pay of operators,
cost of fuel and lubricants etc. all complete including cost of
applying tack coat.
(c) Using Drum Mix type HMP of minimum capacity 60-90 TPH. Sqm 99213.870 148.30 14713417.00
( V.p.276,It-18b))
9
Laying Premixed Seal Coat (Type B) with approved quality
sand/grit @ 0.6 m3/ 100 m
2and hot bitumen binder on
thoroughly cleaned black top surface coated with tack coat,
including heating and mixing cleaned sand/grit (100 % passing
through 2.36 mm sieve and retained on 180m sieve) uniformly with
hot binder (@ 113.5 kg per m3
of grit or sand in suitable pan /
Mobile Hot Mix Plant (Light duty), laying and spreading the mix at
an uniform rate using suitable means, brushing the surface, if
necessary, to ensure uniformity, followed by rolling with power
roller including the cost and carriage of binder and aggregates,
cost of heating the binder and aggregates and all other incidental
charges, cost of fuel and lubricants, including hire charges of
machineries, tools & plants required for construction and quality
control complete including cost of applying tack coat.
(b)Using Mobile Hot Mix Plant (Light duty) Sqm 99213.870 50.12 4972599.00
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
(V.P. 281 Item No 24)
10
Laying a single layer, 25mm thick Mastic Asphalt wearing course
in road pavement using approved coarse aggregate, fine
aggregate, filler material and bitumen, including cost and carriage
of all ingredients, cost of heating aggregates and binder, mixing in
specified proportions ... ... .... .. IRC, including the hire charges of
all tool, plants & machineries, pay of operators, cost of fuel and
lubricants and all other incidental charges and quality control
complete. Sqm 5301.450 533.80 2829914.00
(V.p. 183 Item No 8a))
11
Earthwork in road embankment in ordinary soil to correct profile
as per designed formation level with earth obtained from land
owned /arranged by the Department, depositing in layers of 250
mm thickness including breaking clods ,dressing and compacting
by power roller (not at OMC) etc. complete as per specification,
drawing and direction of Engineer-in-charge from borrow-pits.
(Payment shall be made in m3
on finished work on the basis of
pre-work and post-work level section measurements.(a) In ordinary soil. Cum 10932.760 57.56 629290.00
(V.p. 183 Item No 8a))
12
Earthwork in road embankment in ordinary soil to correct profile
as per designed formation level with earth obtained from land
owned /arranged by the Department, depositing in layers of 250
mm thickness including breaking clods ,dressing and compacting
by power roller (not at OMC) etc. complete as per specification,
drawing and direction of Engineer-in-charge by carried earth with a
lead upto 1 km
(Payment shall be made in m3
on finished work on the basis of
pre-work and post-work level section measurements.
(a) In ordinary soil. Cum 16399.140 182.16 2987267.00
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
13
Drum sheet walling with eucalyptus Bullah 1.8m (av) high on
piling 150 mm dia and 4.50m long driven 2.70m (av) below G.L.
and 500 mm centre to centre including fitting fixing 3 nos. of half
bullah pieces (from 10 cm dia) and drum (empty bitumen) sheet
(approved condition) of height 1.90m , cutting and straightening
drum sheet (each joint must have lap length of min.50mm)
including cost of necessary nails, bolts, nuts etc and providing 2 to
3m long half bullah ties of 10cm dia @ 2.25 m centre to centre
fixed with 10 cm dia bullah posts driven 1.5m below G.L. including
cost of all materials and two coat of coal tarring to all bullah etc
complete as per direction m 1425.00 1952.25 2781956.00
14
Supplying empty cement bags in good condition & filling empty
cement bags with earth and placing them in position including tying
or sewing mouth (cost of thread included) and all incidental
charges complete with Departmental earth carried upto 1 kmNos. 31350 9.67 303155.00
(V.p. 287 Item No 1)
15
Supplying fitting and fixing R.C. guard post 1.37m long with
c.c.1:2:4 with graded stone chips of 13.2mm down casting , curing
complete including cost of providing 4nos.of 12mm dia. rod of
length 1.54m as main reinforcement and 6 nos. of round shaped
8mm dia rods used as binders; the placing of the first binder
should be at 75mm below the top finished surface and the other 5
nos of binders should be placed at 245mm c/c ; the guard post is
of octagonal section with inscribed circle of dia 24cm at the base
tappering to corresponding dimensions of 16cm at the top
including two coats of painting with best quality synthetic enamel
paint of approved make and grade to form 6 nos. horizontal
alternate bands in white/tanery yellow and black to 90 cm length
standing up above ground after mending good damages if any
during striking off shuttering, making hole in ground of 47cm
depth and 30cm minimum dia, fixing the guard posts in the
same holes and repacking the earth properly so as to keep the
guard posts standing properly erect in correct position true to line
and length including carriage of R. C. Guard Post with due care to
the site including loading into the truck and unloading at site
complete in all respect.Each 64 953.44 61020.00
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
(V.p. 288 Item No 2)
16
Supplying, fitting and fixing rectangular R.C. 200 m post of
size 65cm x 15cm x 10cm with cement concrete 1:2:4 with graded
stone chips of 13.2mm down including cost of providing 2 nos. of
inverted U-shaped 6mm dia M.S. rods of length 1.40m and 5 nos.
of 6mm dia M.S. binders spaced at 100mm C/C and of length
37.5cm each in correct position true to line and level and providing
sunk inscription with 30cm embedment into the ground after
making hole into the ground of section 10cm more on all side of
post and repacking the hole with 1:4:8 cement concrete with stone
chips with two coat of painting on the exposed portion of the post
with best quality synthetic enamel paint of approved make and
brand of different shades as directed complete in all respect
including carriage of the post to the site with loading & unloading
and printing of letters and numbers.Each 74 402.99 29821.00
(V.p. 289 Item No 3a))
17
Supplying, fitting and fixing 5th
KM post / KM post as per
standard drawing enumerated in IRC: 8-1980 (for type designs for
Highway Kilometre stone) with cement concrete 1:2:4 with chips of
size 26.5mm down in correct position true to line and level with
60cm embedment into the ground after making hole into the
ground of section 15cm more on all sides of the post and
repacking the with 1:4:8 cement concrete with stone chips with
two coats of painting on the exposed portion of the post with best
quality synthetic enamel paint of approved make and brand of
different shades as directed complete in all respect including
carriage of the post to the site with loading & unloading and
printing of letters and numbers.
(a) 5th Kilometer Post: Each 3 2616.91 7851.00
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
(V.p. 289 Item No 3b))
18
Supplying, fitting and fixing 5th
KM post / KM post as per
standard drawing enumerated in IRC: 8-1980 (for type designs for
Highway Kilometre stone) with cement concrete 1:2:4 with chips of
size 26.5mm down in correct position true to line and level with
60cm embedment into the ground after making hole into the
ground of section 15cm more on all sides of the post and
repacking the with 1:4:8 cement concrete with stone chips with
two coats of painting on the exposed portion of the post with best
quality synthetic enamel paint of approved make and brand of
different shades as directed complete in all respect including
carriage of the post to the site with loading & unloading and
printing of letters and numbers.
(b) Ordinary Kilometer Post: Each 15 2074.54 31118.00
(V.p. 148 Item No 4) of Schedule of Rates of Public Works (Roads) Department , National Highway Wing
19 Retro Reflective Traffic Signs
Providing and Fixing of Retro-reflectorised cautionary, mandatory
and informatory sign as per IRC:67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 1.5 mm
thick supported on a mild steel angle iron post 75 mm X 75mm x 6
mm firmly fixed to the ground by means of properly designed
foundation with M15 grade cement concrete 45 cm x 45 cm X 60
cm, 60 cm below ground level as per approved drawing
(Reference to MORT&H's specification 801)
19.1 (ii) 60 cm equilateral triangle Each 20 3047.05 60941.00
19.2 (iii) 60 cm circular Each 86 4154.69 357303.00
19.3 (iii) 60 cm X 60 cm square Each 0 4826.29 0.00
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
ESTIMATE OF IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)-
MOIDAH-JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 0KMP)
(V.p. 149 Item No 5) of Schedule of Rates of Public Works (Roads) Department , National Highway Wing
Direction and Place Identification Signs upto 0.9 sqm Size Board
20
Providing and ercting direction and place identification retro-
reflectorised sign as per IRC:67 made of high intensity grade
sheeting vide clause 801.3, fixed over aluminium sheeting, 2 mm
thick with area not exceeding 0.9 sqm supported on a mild steel
single angle iron post 75 X 75 X 6 mm firmly fixed to the ground
by means of properly designed foundation with M-15 grade cement
concrete 45 X 45 X 60 cm, 60 cm below ground level as per
approved drawing
(Reference to MORT&H's specification 801) Each 2 10526.87 21054.00
Total (Including Cess) 132053867.00
Total (excluding cess @ 1%) 130746403.00
Pradip Kumar Pal Assistant Engineer
Lakshmikantapur Highway Sub-Division PW (Roads) Directorate
Arup Ratan Mukhopadhyay Executive Engineer
Diamond Harbour Highway Division PW (Roads) Directorate
Malay Ghosh Superintending Engineer
State Highway Circle No. - I PW (Roads) Directorate
S.No. Description of Item Unit Amount
1
Coarse Sand
(Grading Zone - I as per IS:383-1970)
Stacked at Site
cum - 820.00
2
Medium Sand
(Grading Zone - I as per IS:383-1970)
Stacked at Site
cum - 650.00
3
Fine Sand
(Grading Zone - I as per IS:383-1970)
Stacked at Site
cum - 500.00
4Silver Sand
Stacked at Sitecum - 350.00
# Ref. PWD (Roads)Directorates S/R 2008-09,
Annex -II Page 319
BRICK, BATS
1 a).First Class Bricks (Kiln Burnt) nos/1000 - 8000.00
2 b). Picked Jhama Bricks (Kiln Burnt) nos/1000 - 8000.00
3 c). Jhama Metal (Kiln Burnt) cum - 1650.00
4 d). First Class Brick Bats (Kiln Burnt ) cum - 1150.00
# Ref. PWD (Roads)Directorates S/R 2008-09,
Annex -II Page 319
IMPROVEMENT AND STRENGTHENING OF JOYNAGAR (BURORGHAT)- MOIDAH-
JIBONMONDALHAT-MAHISHMARIHAT ROAD (0.000 KMP TO 18.53 KMP)
UNDER DIAMOND HARBOUR HIGHWAY DIVISION
IN THE DISTRICT OF SOUTH 24 PGS.
Gra
de
I (
90-4
5)
Gra
de
II
(63-4
5)
Gra
de
III
(5
3 -
22.4
)
37.5
mm
26.5
mm
22.4
mm
13.2
mm
11.2
mm
5.6
mm
Type
A
Type
B
cum 906.00 1069.00 1089.00 1109.00 1109.00 1160.00 1174.00 1195.00 1067.00 833.00 727.00 909.00 729.00
cum 62.00 62.00 62.00 62.00 62.00 62.00 62.00 62.00 62.00 62.00 58.00 62.00 58.00
cum 1441.00 1604.00 1624.00 1644.00 1644.00 1695.00 1709.00 1730.00 1602.00 1368.00 1258.00 1444.00 1260.00
cum 46.50 46.50 46.50 46.50 46.50 46.50 46.50 46.50 46.50 46.50 43.50 46.50 43.50
48.00 Km cum 473.00 473.00 473.00 473.00 473.00 473.00 473.00 473.00 473.00 473.00 473.00 473.00 473.00
cum 1425.50 1588.50 1608.50 1628.50 1628.50 1679.50 1693.50 1714.50 1586.50 1352.50 1243.50 1428.50 1245.50
Carriage (Vide P-325 I- 4g)
Carriage From
Ballygunge to D. Barasaat 38.00 Km 0.00 To 5.00 = 5.00 Km @Rs 79.00 Rs. 79.00
D. Barasaat to Moida 3.50 Km 5.00 To 10.00 = 5.00 Km @Rs 10.00 Rs. 50.00
Moida to Site Middle 6.27 Km 10.00 To 20.00 = 10.00 Km @Rs 9.20 Rs. 92.00
20.00 To 48.00 = 28.00 Km @Rs 9.00 Rs. 252.00
47.77 Km
Say 48.00 Km Rs. 473.00
Unit
Size of Aggregates
Rate for Plant work
Loading, Un loading &
stacking (p-302, It
3c.d) (For General
work)
Cost at Ballygunge
Boulder
30/45 kg
Rate for general work
Loading & Unloading
(p-302, It 3c.d) (For
Plant work)
Carriage for
Sto
ne
Du
st
COST OF STONE METAL
Stone ScreeningHand Broken Aggregates Machine Made Chips
Pakur
48.00
Source of Material:
Average lead (km) of Pakur Material from Ballygunj Jn. to
Project CG (By road) considered in the analysis:
Item
Haldia Kolkata
170.00 52.00
Unit
Source Haldia Kolkata Haldia
(A) (V.P.-316 It -4) MT 41423.00 41,903.00 37,400.00
(B) (V.P.-302 It -3a) MT
43.50 43.50
(Vide P-308 I- 11A) 769.00
(Vide P-308 I- 2A)
330.70 897.50
(C) MT 4,142.30 4,190.30 3,740.00
(D)
MT 1,000.00 1,000.00
(E) Rate at Site MT 46,334.30 45,467.50 41,081.00
Carriage of tar or asphalt in drums and similar miscelleneous
materials over pucca roads
Add Contractor's Profit (@ 10% of (A))
(vide Note - 3, Table I-2, page- 316)
Deduct cost of container
(in case of packed bitumen, CRMB or bituminous emulsion
is considered to be used)
Bitumen
(Bulk): VG-
30 (60/70)
FORMAT – B: (Format for anlysis of rates of bitumen / bituminous emulsion / CRMB supplied by Contractor)
Cost of Bitumen including all taxes at the nearest source of
the manufacturer
Loading in to trucks at the lifting point, unloading at
destination, stacking properly in go downs or yard etc. as
directed including carriage by head load up to a lead of 30 m
at each of the two points.
a) Tar or asphalt in drums for plant works
(75% of Rs. 58.00)
Carriage of Bitumen in bulk in insulated tanks from refinery
to work site including loading, unloading the same at hot mix
plant / Bitumen storage tanks / empty bitumen dums / tar
boiler as per direction of the Engineer – in – Charge at
specified temperature including necessary heating
arrangements during transfer & transit with all incidental
charges.
Bitumen
(Packed):
VG- 30
(10/20)
For
rate
s R
efe
r T
ab
le I
- 2
at
pag
e 3
16
& F
orm
at
- B
at
pag
e 3
17
of
Go
vern
me
nt
of
We
st
Be
ng
al ,
Pu
blic
Wo
rks (
Ro
ad
s)
Dire
cto
rate
Sch
ed
ule
of
Ra
tes f
or
Ro
ad
&
Brid
ge
Wo
rks 2
00
8 -
200
9 &
7th
Co
rrig
en
da
, A
dde
nd
a &
Err
ata
of
SO
R o
f S
OR
of
P.W
. (R
oad
s)
Dire
cto
rate
200
8-2
00
9-
Ap
ril, 2
01
2
Source of Material:
Average lead (km) considered in the analysis:
Bitumen
Emulsion
(Packed):
MS TypeItemSl No.
FORMAT – B: (Format for anlysis of rates of bitumen / bituminous emulsion / CRMB supplied by Contractor)
(Vide P-308 I- 11A):
(Vide P-325 I- 4g) Carriage From
Haldia to New Alipur 118.00 Km 0.00 To 100.00 = 100.00 Km @Rs 468.00 Rs. 468.00
New Alipur D. Barasaat 42.00 Km 100.00 To 170.00 = 70.00 Km @Rs 4.30 Rs. 301.00
D. Barasaat to Moida 3.50 Km
Moida to Site Middle 6.27 Km
169.77 Km Rs. 769.00Say 170.00 Km
(Vide P-308 I- 2A):
Carriage From
Kolkata to D. Barasaat 42.00 Km 0.00 To 5.00 = 5.00 Km @Rs 68.00 Rs. 68.00
D. Barasaat to Moida 3.50 Km 5.00 To 10.00 = 5.00 Km @Rs 5.90 Rs. 29.50
Moida to Site Middle 6.27 Km 10.00 To 20.00 = 10.00 Km @Rs 5.80 Rs. 58.00
20.00 To 50.00 = 30.00 Km @Rs 5.50 Rs. 165.00
51.77 Km 50.00 To 52.00 = 2.00 Km @Rs 5.10 Rs. 10.20
Say 52.00 Km Rs. 330.70
(Vide P-308 I- 11A):
(Vide P-325 I- 4g) Carriage From
Haldia to New Alipur 118.00 Km 0.00 To 5.00 = 5.00 Km @Rs 68.00 Rs. 68.00
New Alipur D. Barasaat 42.00 Km 5.00 To 10.00 = 5.00 Km @Rs 5.90 Rs. 29.50
D. Barasaat to Moida 3.50 Km 10.00 To 20.00 = 10.00 Km @Rs 5.80 Rs. 58.00
Moida to Site Middle 6.27 Km 20.00 To 50.00 = 30.00 Km @Rs 5.50 Rs. 165.00
169.77 Km 50.00 To 100.00 = 50.00 Km @Rs 5.10 Rs. 255.00
100.00 To 170.00 = 70.00 Km @Rs 4.60 Rs. 322.00
Say 170.00 Km Rs. 897.50
Carriage
Carriage
Carriage
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
(V.P.265 It-2 b (i))
1
Picking up and removing old bituminous layer or sand
sealing coat from old black topped surface and cleaning
the exposed surface by scraping and stacking the material
as directed.
(b) By mechanical means :
(i) From 25 mm to 50 mm thick. Sqm 1.00 3.50 3.50
A)Sub-Total 3.50
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) % 1.00 0.04
Rate per Sqm= A)+B) 3.54
( V.p.264,It-16)
2
Patching of potholes by draining water, cutting the pothole
area to rectangular shape with vertical edges, removing all
loose materials, screening and stacking the same for
reuse with new materials as per requirement, filling the
pothole area with additional volume of crushed stone
materials / laterite / Jhama / broken shingles / coated
stones of Pakur variety etc. and screenings as applicable,
and compacting the same with static roller as per Water
Bound Macadam Specification, including cost of all
materials and machineries but excluding the cost of coarse
aggregates and screening.
Labour Cost Cum 1.00 270.00 270.00
Add: Cost of Material per cum
Cost of Gr-II Aggregate Cum 1.000 1624.00 1624.00
Cost of Type "B" screening Cum 0.210 1260.00 264.60
A)Sub-Total 2158.60
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 21.59
Rate per Cum= A)+B) 2180.19
(V.P.191 It-1)
3
Supplying, spreading and consolidation of brick bats (size
45 mm and down) and medium sand including premixing
the material in suitable mixer conforming the combined
material to the Grading – I of Granular Sub-base Materials
and in proportion of 60 : 40 and rolling at O.M.C. to
achieve at least 97% of maximum dry density, maintaining
proper gradient and camber, watering as necessary and
lighting, guarding, barricading and making adequate
earthen bundh on both sides where necessary to protect
the edges and curing with water including all incidental
charges for the work and cost of rolling complete.Cum 1.000 173.70 173.70
Add: Cost of Material per cum
Cost of Brick Bats Cum 0.900 1150.00 1035.00
Cost of Medium sand Cum 0.048 650.00 31.20
A)Sub-Total 1239.90
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 12.40
Rate per Cum= A)+B) 1252.30
RATE ANALYSIS
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
(V.P.259 It-7b))
4
Labour for spreading and consolidating 1st class brick
bats/ Jhama metal/Laterite chelly or metal / shingles of
specific size in hard crust to requisite thickness (measured
after compaction) in layers including screening of
bats/metals etc. as necessary, hand packing, sweeping,
watering and rolling in stages with power roller to proper
line, grade and camber, lighting, guarding & barricading
and making necessary earthen bundh of one metre width
on each side where necessary to protect edges and
preparing the bed by necessary cutting or filling and rolling
all complete including the cost of all materials and hire and
labour charges of all man and machineries and as per
specification and direction of Engineer-in-charge but
excluding the cost of bats/chelly.
(b) Using Brick bats / Jhama metal / Laterite metal of
size 63 mm – 45 mm for compacted thickness 75mm. Sqm 1.000 14.20 14.20
Add: Cost of Material per sqm
Cost of Jhama Metal Cum 0.110 1650.00 181.50
A)Sub-Total 195.70
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 1.96
Rate per Sqm= A)+B) 197.66
( V.p.262,It-9)
5
Labour for spreading & compacting approved stone
aggregates to Wet Mix Macadam specification including
screening of aggregates and granular materials, mixing the
materials in proper grading using mechanical mixer,
adding water to achieve required OMC, carrying the mix to
work-site using tipper trucks within a lead of 10 km , laying
the mixed materials in uniform thickness over prepared
surface, rolling with 8-10t roller in stages to proper grade,
camber, until the desired density is achieved, including
supply of all materials, machinery, fuel & lubricants,
including incidental costs for lighting, guarding,
barricading, making of earthen bundfh to protect the
edges, controlling traffic, etc. as per direction of Engineer-
in-Charge complete, including cost of quality control.
Labour Cost Cum 1.00 273.90 273.90
Add: Cost of Material per cum
Cost of stonemetal 37.50 mm size Cum 0.396 1628.50 644.89
Cost of stone chips 13.20 mm size Cum 0.264 1714.50 452.63
Cost of stone chips 5.60 mm size Cum 0.356 1352.50 481.49
Cost of Stone dust Cum 0.304 1243.50 378.02
A)Sub-Total 2230.93
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 22.31
Rate per Cum= A)+B) 2253.24
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
( V.p.266,It-4,a)
6
Providing and applying bituminous Primer Coat for
priming of base course with Cationic bituminous emulsion
of approved grade and requisite quantity including
preparation of the surface to be primed, through cleaning
and sweeping, uprooting weeds, grass etc. dampening the
surface beforehand spraying the primer using sprayer
mounted on distributor truck or with hand sprayer using
mechanical pump including cost and carriage of bitumen
emulsion and all other incidental costs of work.
(a) For surfaces with low porosity
(@ 7.5 kg / 10 m2).
Sqm 1.00 2.40 2.40
Add: Cost of Material per sqm
Cost of C.B. Emulsion for low porosity stone
@ 0.75 Kg / m2 kg 0.75 45.47 34.10
A)Sub-Total 36.50
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 0.37
Rate per Sqm= A)+B) 36.87
(Section 4.7, It-34(B)(b)(ii))
7
Laying Bituminous Macadam of specified grade using
Hot Mix Plant (HMP) and using approved aggregates
conforming to specified grading and bitumen over
prepared surface, including carrying the hot premixed
materials by means of tipper truck, spreading, the mixed
material at specified laying temperature over the prepared
surface by means of a suitable paver finisher, tamping and
finishing the mix to specified grade, line and camber,
thorough rolling with suitable power rollers for break down,
inter-mediate and finished rolling as per specification, hand
packing and pinning to give an even surface including cost
and carriage of stone materials & bitumen, and hire
charges of HMP and all other machines and equipments,
cost of fuels and lubricants and wages of operational staff,
quality control as per IRC Specification all complete
excluding cost of applying tack coat.
(B) In Base / Binder Course using 3.4 % binder content
by weight of total mix.(b) 50mm compacted thickness(iii) Using Drum Mix type HMP of minimum capacity 60-90
TPH.Sqm 1.00 67.40 67.40
Add: Cost of Material per sqm
Cost of stonechips 22.4 mm size Cum 0.0177 1693.50 29.97
Cost of stone chips 11.2 mm size Cum 0.0177 1586.50 28.08
Cost of stone chips 5.6 mm size Cum 0.0248 1352.50 33.54
Cost of stonedust Cum 0.0106 1243.50 13.18
Cost of 60/70 Bitumen for mixing Kg 3.74 46.33 173.29
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
Add: (V.P.265,It-3b)-ii)
Providing and applying tack coat using Cationic bituminous
emulsion of approved grade conforming to IS : 8887-1978,
over prepared surface including cleaning of surface with
mechanical broom, moistening the surface, applying tack
coat including cost and carriage of emulsion, hire charges
of machineries and labour, cost of fuel and lubricants all
complete as per specification and direction of the Engineer-
in-charge.
(b) Over black topped surface @ 3.0 kg per 10 m2 :
(ii) By mechanical means. Sqm 1.00 1.60 1.60
Add: Cost of Material per sqm
Cost of C.B. Emulsion for tack coat Kg 0.30 45.47 13.64
A)Sub-Total 360.70
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 3.61
Rate per Sqm= A)+B) 364.31
(Section 4.7, It-38(ii))
8
Providing & Laying 20 mm thick open graded Premixed
Carpet by Hot Mix Plant using 13.2 mm (@ 0.18 m3
/m2
)
and 11.2 mm (@ 0.09 m3/m
2) size stone aggregates,
including thorough cleaning of the surface, applying tack
coat, screening cleaning and pre-heating stone chips and
fully pre-coating the same with hot matrix @ 54 kg/m3
of
aggregate mix, carrying the mixture by tipper trucks or by
any other suitable arrangements, laying the mixture
uniformly over the surface with paver finisher , including
manual operations as and when required for proper level,
grade and camber, thoroughly rolling by power roller,
including the cost and carriage of stone chips and matrix,
heating the matrix, preheating the aggregates to required
temperature and including the hire charges of Hot Mix
Plant and other machineries, pay of operators, cost of fuel
and lubricants etc. all complete excluding cost of applying
tack coat.(iii) Using Drum Mix type HMP of minimum capacity 60-90
TPH.Sqm 1.00 18.80 18.80
Add: Cost of Material per sqm
Cost of Stonechips 13.2 mm size Cum 0.018 1714.50 30.86
Cost of Stonechips 11.2 mm size Cum 0.009 1586.50 14.28
Cost of 60/70 Bitumen for mixing Kg 1.46 46.33 67.65
Add: (V.P.265,It-3b)-ii)
Providing and applying tack coat using Cationic bituminous
emulsion of approved grade conforming to IS : 8887-1978,
over prepared surface including cleaning of surface with
mechanical broom, moistening the surface, applying tack
coat including cost and carriage of emulsion, hire charges
of machineries and labour, cost of fuel and lubricants all
complete as per specification and direction of the Engineer-
in-charge.
(b) Over black topped surface @ 3.0 kg per 10 m2 :
(ii) By mechanical means. Sqm 1.00 1.60 1.60
Add: Cost of Material per sqm
Cost of C.B. Emulsion for tack coat Kg 0.30 45.47 13.64
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
A)Sub-Total 146.83
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 1.47
Rate per Sqm= A)+B) 148.30
( V.p.276,It-18b))
9
Laying Premixed Seal Coat (Type B) with approved
quality sand/grit @ 0.6 m3/ 100 m
2and hot bitumen
binder on thoroughly cleaned black top surface coated
with tack coat, including heating and mixing cleaned
sand/grit (100 % passing through 2.36 mm sieve and
retained on 180m sieve) uniformly with hot binder (@
113.5 kg per m3
of grit or sand in suitable pan / Mobile Hot
Mix Plant (Light duty), laying and spreading the mix at an
uniform rate using suitable means, brushing the surface, if
necessary, to ensure uniformity, followed by rolling with
power roller including the cost and carriage of binder and
aggregates, cost of heating the binder and aggregates and
all other incidental charges, cost of fuel and lubricants,
including hire charges of machineries, tools & plants
required for construction and quality control complete
excluding cost of applying tack coat.
(b)Using Mobile Hot Mix Plant (Light duty) Sqm 1.00 9.90 9.90
Add: Cost of Material per sqm
Cost of stone aggregates 5.6 mm Cum 0.006 1368.00 8.21
Cost of 60/70 Bitumen for mixing Kg 0.680 46.33 31.51
A)Sub-Total 49.62
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 0.50
Rate per Sqm= A)+B) 50.12
(V.P. 281 Item No 24)
10
Laying a single layer, 25mm thick Mastic Asphalt wearing
course in road pavement using approved coarse
aggregate, fine aggregate, filler material and bitumen,
including cost and carriage of all ingredients, cost of
heating aggregates and binder, mixing in specified
proportions ... ... .... .. IRC, including the hire charges of all
tool, plants & machineries, pay of operators, cost of fuel
and lubricants and all other incidental charges and quality
control complete. Sqm 1.00 181.80 181.80
Add: Cost of materials
Cost of 5.6 mm Coarse Aggregates Cum 0.0078 1352.50 10.55
Cost of 11.2 mm Coarse Aggregates Cum 0.0078 1586.50 12.37
Cost of 13.2 mm Coarse Aggregates Cum 0.0005 1714.50 0.86
Cost of Bitumen (10/20) Kg 5.5000 41.08 225.95
Cost of Bitumen (60/70) Kg 0.0150 46.33 0.70
Cost of Lime Stone Powder Kg 10.3000 6.32 65.10
Cost of Stone Dust Cum 0.0110 1243.50 13.68
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
Add: (V.P.265,It-3b)-ii)
Providing and applying tack coat using Cationic bituminous
emulsion of approved grade conforming to IS : 8887-1978,
over prepared surface including cleaning of surface with
mechanical broom, moistening the surface, applying tack
coat including cost and carriage of emulsion, hire charges
of machineries and labour, cost of fuel and lubricants all
complete as per specification and direction of the Engineer-
in-charge.
(b) Over black topped surface @ 3.0 kg per 10 m2 :
(ii) By manual means. Sqm 1.00 3.60 3.60
Add: Cost of Material per sqm
Cost of S.R. Bitumen (applied hot) Kg 0.30 46.33 13.90
A)Sub-Total 528.51
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 5.29
Rate per Sqm= A)+B) 533.80(V.p. 183 Item No 8a))
11
Earthwork in road embankment in ordinary soil to
correct profile as per designed formation level with earth
obtained from land owned /arranged by the Department,
depositing in layers of 250 mm thickness including
breaking clods ,dressing and compacting by power roller
(not at OMC) etc. complete as per specification, drawing
and direction of Engineer-in-charge. (Payment shall be made in m
3on finished work on the
basis of pre-work and post-work level section
measurements.
(a) In ordinary soil. Cum 1.00 17.10 17.10
Add: (V.p.181,It-1a))
Earthwork in excavation from borrow pits (land
owned/arranged by the Department) and depositing in
layers of 250 mm. Including breaking clods and to fill up
back of abutments depressions and ruts with an initial lead
up to 50 m and initial lift up to 1.5 m making bunds at top
as directed dressing complete. (For petty emergent
works).(a) In ordinary soil.
Rates to be evaluated considering 100 m3
of borrow pit
earth = 115 m3
of embankment earth = 92 m3
of compacted earth.
i.e. Cost of 1 m3
equivalent earth is 100/92= 1.09 m3
of
earth Cum 1.087 36.70 39.89
A)Sub-Total 56.99
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 0.57
Rate per Cum= A)+B) 57.56
(V.p. 183 Item No 8a))
12
Earthwork in road embankment in ordinary soil to
correct profile as per designed formation level with earth
obtained from land owned /arranged by the Department,
depositing in layers of 250 mm thickness including
breaking clods ,dressing and compacting by power roller
(not at OMC) etc. complete as per specification, drawing
and direction of Engineer-in-charge by carried earth
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
(Payment shall be made in m3
on finished work on the
basis of pre-work and post-work level section
measurements.
(a) In ordinary soil. Cum 1.00 17.10 17.10
Add: Land owned/ arranged by the Contractor Cum 1.087 20.00 21.74
Add: (V.p.181,It-1a))
Earthwork in excavation from borrow pits (land
owned/arranged by the Department) and depositing in
layers of 250 mm. Including breaking clods and to fill up
back of abutments depressions and ruts with an initial lead
up to 50 m and initial lift up to 1.5 m making bunds at top
as directed dressing complete. (For petty emergent
works).
(a) In ordinary soil.
Rates to be evaluated considering 100 m3
of borrow pit
earth = 115 m3
of embankment earth = 92 m3
of compacted earth.
i.e. Cost of 1 m3
equivalent earth is 100/92= 1.09 m3
of
earth Cum 1.087 36.70 39.89
Add: (V.p.308,It-1A.)
Carriage of Earth over pucca road upto 1 km
Rates to be evaluated considering 115 m3
of embankment
earth = 92 m3
of compacted earth.
i.e. Carriage Cost of 1 m3
equivalent earth is 115/92=
1.25 m3 of earth
Cum 1.25 61.00 76.25
Add: (V.p.302,It-3c))Loading in to trucks at the lifting point, unloading at
destination, stacking properly in go downs or yard etc. as
directed including carriage by head load up to a lead of 30
m at each of the two points.
(c) Sand, Cinder, Lime, Moorum and similar materials.
Rates to be evaluated considering 115 m3
of embankment
earth = 92 m3
of compacted earth.
i.e. only Unloading Cost of 1 m3
equivalent earth is
115/92= 1.25 m3 of earth
Rates to be evaluated considering only Unloading i.e. 35%
of Rs. 58.00Cum 1.25 20.30 25.38
A)Sub-Total 180.36
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 1.80
Rate per Cum= A)+B) 182.16
13
Drum sheet walling with eucalyptus Bullah 1.8m (av) high
on piling 150 mm dia and 4.50m long driven 2.70m (av)
below G.L. and 500 mm centre to centre including fitting
fixing 3 nos. of half bullah pieces (from 10 cm dia) and
drum (empty bitumen) sheet (approved condition) of height
1.90m , cutting and straightening drum sheet (each joint
must have lap length of min.50mm) including cost of
necessary nails, bolts, nuts etc and providing 2 to 3m long
half bullah ties of 10cm dia @ 2.25 m centre to centre
fixed with 10 cm dia bullah posts driven 1.5m below G.L.
including cost of all materials and one coat of coal tarring
to all bullah etc complete as per direction
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
Taking Output = 50 mAdd: (V.p.229,It-37c))
Supplying Eucalyptus-bullah piles at work site,
including dressing and making one end pointed.
(c) 15 cm. diameter pile.
Total no of bullah reqd. = 101 Nos.
Total Length = 101 * 4.5 m = 454.50 m m 454.50 124.00 56358.00
Add: (V.p.229,It-37a))
Supplying Eucalyptus-bullah piles at work site,
including dressing and making one end pointed.
(b) 10 cm. diameter pile.
For Runner
50 X 3 / 2 = 75.00 m
For Post
Total No of bullah reqd. = 50 / 2.5 + 1 = 21 Nos.
Total Length = 21 * 1.65 m = 34.65 m
For Tie
21 X 2.5 / 2 = 26.25.00 m
Total Length reqd. = 135.9 m i.e. 136 m (approx) m 136.00 56.00 7616.00
Add: (V.p.245,It-67))
Labour for driving Sal-bullah / Eucalyptus bullah piles
by monkey in sorts of soil including hoisting and placing
piles in position, protecting the pile head with iron ring and
cutting and shaping heads before and after driving and
including hire and labour for necessary driving appliances
and all tackles
b) When work under considerable (i.e. above 1 m.)
standing water is involved.iii) 150mm. diameter
Total Length = 101 * 2.7 m = 272.70 m m 272.70 46.00 12544.20
i) 100mm diameter (It- 67a)
Total Length = 21 * 1.5 m = 31.50 m m 31.50 31.00 976.50
Add: (V.p.248,It-80))
Coal tarring on wooden surfaces including cost of
materials. (It- 80a)
a) Double coat.
15 cm bullah
454.50 X π X0.15 = 214.21 m2
Post
34.65 X π X0.10 = 10.89 m2
Runner
75 X π X0.10 = 23.57 m2
3 X 50 X0.10 = 15.00 m2
Tie
26.25 X π X0.10 = 8.25 m2
2 X 26.25 X0.10 = 5.25 m2
Total Area = 277.17 m i.e. 277.00 m2 (approx) Sqm 277.00 7.90 2188.30
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
Add: (V.p.246,It-70))
Labour for fitting and fixing 10 cm. to 13 cm. diameter
sal-bullah as ties and runners including necessary nails,
bolts and nuts.
Runner = 75 m
Tie = 26.25 m
Total Length reqd. = 101.25 m m 101.25 10.50 1063.13
Supply of drum sheet
50m x 1.70m = 85.00 m2
85/1.20 =70.83No Say= 17 No. No. 71.00 200.00 14200.00
Fitting of Drum Sheet Sqm 85.00 20.00 1700.00
Total 96646.13
Rate per Metre of Piling 1932.92
A) Sub- Total 1932.92
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 19.33
Rate per m= A)+B) 1952.25
14
Supplying empty cement bags in good condition & filling
empty cement bags with earth and placing them in position
including tying or sewing mouth (cost of thread included)
and all incidental charges complete but excluding cost of
sand and gunny bags
Add: (V.p.250,It-97)
Supplying empty cement bags in good condition. Nos. 100 385.00 385.00
Add: (V.p.250,It-96)
Labour for filling empty cement bags with sand and placing
them in position including tying or sewing mouth (cost of
thread included) and all incidental charges complete but
excluding cost of sand and gunny bags. Nos. 100 190.00 190.00
A) Rate per number of bag 5.75
Add: (V.p.181,It-1a))
Earthwork in excavation from borrow pits (land
owned/arranged by the Department) and depositing in
layers of 250 mm. Including breaking clods and to fill up
back of abutments depressions and ruts with an initial lead
up to 50 m and initial lift up to 1.5 m making bunds at top
as directed dressing complete. (For petty emergent
works).
(a) In ordinary soil.
Rates to be evaluated considering 100 m3
of borrow pit
earth = 115 m3
of embankment earth
i.e. Cost of 1 m3
equivalent earth is 100/115= 0.87 m3
of
earth Cum 0.870 36.70 31.91
Add: (V.p.308,It-1A.)
Carriage of Earth over pucca road above upto 1 km Cum 1.00 61.00 61.00
Add: (V.p.302,It-3c))Loading in to trucks at the lifting point, unloading at
destination, stacking properly in go downs or yard etc. as
directed including carriage by head load up to a lead of 30
m at each of the two points.
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
(c) Sand, Cinder, Lime, Moorum and similar materials.
Rates to be evaluated considering only Loading and
Unloading i.e. 75% of Rs. 58.00Cum 1.00 43.50 43.50
Rate per cum 136.41
B) Cost of earth per bag Cum 0.028 136.41 3.82
C) Sub- Total = A) + B) 9.57
D) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 0.10
Rate per number= C)+D) 9.67
(V.p. 287 Item No 1)
15
Supplying fitting and fixing R.C. guard post 1.37m long
with c.c.1:2:4 with graded stone chips of 13.2mm down
casting , curing complete including cost of providing
4nos.of 12mm dia. rod of length 1.54m as main
reinforcement and 6 nos. of round shaped 8mm dia rods
used as binders; the placing of the first binder should be at
75mm below the top finished surface and the other 5 nos
of binders should be placed at 245mm c/c ; the guard post
is of octagonal section with inscribed circle of dia 24cm at
the base tappering to corresponding dimensions of 16cm
at the top including two coats of painting with best quality
synthetic enamel paint of approved make and grade to
form 6 nos. horizontal alternate bands in white/tanery
yellow and black to 90 cm length standing up above
ground after mending good damages if any during striking
off shuttering, making hole in ground of 47cm depth
and 30cm minimum dia, fixing the guard posts in the
same holes and repacking the earth properly so as to keep
the guard posts standing properly erect in correct position
true to line and length including carriage of R. C. Guard
Post with due care to the site including loading into the
truck and unloading at site complete in all respect.
Each 1.000 944.00 944.00
A) Sub- Total 944.00
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 9.44
Rate per number= A)+B) 953.44
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
(V.p. 289 Item No 3a))
16
Supplying, fitting and fixing rectangular R.C. 200 m
post of size 65cm x 15cm x 10cm with cement concrete
1:2:4 with graded stone chips of 13.2mm down including
cost of providing 2 nos. of inverted U-shaped 6mm dia
M.S. rods of length 1.40m and 5 nos. of 6mm dia M.S.
binders spaced at 100mm C/C and of length 37.5cm each
in correct position true to line and level and providing sunk
inscription with 30cm embedment into the ground after
making hole into the ground of section 10cm more on all
side of post and repacking the hole with 1:4:8 cement
concrete with stone chips with two coat of painting on the
exposed portion of the post with best quality synthetic
enamel paint of approved make and brand of different
shades as directed complete in all respect including
carriage of the post to the site with loading & unloading
and printing of letters and numbers.Each 1.000 399.00 399.00
A) Sub- Total 399.00
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 3.99
Rate per number= A)+B) 402.99
(V.p. 289 Item No 3a))
17
Supplying, fitting and fixing 5th
KM post / KM post as
per standard drawing enumerated in IRC: 8-1980 (for type
designs for Highway Kilometre stone) with cement
concrete 1:2:4 with chips of size 26.5mm down in correct
position true to line and level with 60cm embedment into
the ground after making hole into the ground of section
15cm more on all sides of the post and repacking the with
1:4:8 cement concrete with stone chips with two coats of
painting on the exposed portion of the post with best
quality synthetic enamel paint of approved make and
brand of different shades as directed complete in all
respect including carriage of the post to the site with
loading & unloading and printing of letters and numbers.
(a) 5th Kilometer Post: Each 1.000 2591.00 2591.00
A) Sub- Total 2591.00
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 25.91
Rate per number= A)+B) 2616.91
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
(V.p. 289 Item No 3b))
18
Supplying, fitting and fixing 5th
KM post / KM post as
per standard drawing enumerated in IRC: 8-1980 (for type
designs for Highway Kilometre stone) with cement
concrete 1:2:4 with chips of size 26.5mm down in correct
position true to line and level with 60cm embedment into
the ground after making hole into the ground of section
15cm more on all sides of the post and repacking the with
1:4:8 cement concrete with stone chips with two coats of
painting on the exposed portion of the post with best
quality synthetic enamel paint of approved make and
brand of different shades as directed complete in all
respect including carriage of the post to the site with
loading & unloading and printing of letters and numbers.
(b) Ordinary Kilometer Post: Each 1.000 2054.00 2054.00
A) Sub- Total 2054.00
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996) 20.54
Rate per number= A)+B) 2074.54(V.p. 148 Item No 4) of Schedule of Rates of Public Works (Roads) Department , National Highway Wing
Retro Reflective Traffic Signs
19
Providing and Fixing of Retro-reflectorised cautionary,
mandatory and informatory sign as per IRC:67 made of
high intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 1.5 mm thick supported on a mild
steel angle iron post 75 mm X 75mm x 6 mm firmly fixed
to the ground by means of properly designed foundation
with M15 grade cement concrete 45 cm x 45 cm X 60 cm,
60 cm below ground level as per approved drawing
(Reference to MORT&H's specification 801)
19.1 (ii) 60 cm equilateral triangle Each 1.000 2033.70 2033.70
Add: Cost of Material per number as per chapter A Sl. No. 8.4
Add: Overhead Charges @ 10% % 10 203.37
A) Sub- Total 2237.07
Add: Contractor's Profit @ 10% % 10 223.71
B) Sub- Total 2460.78
Cost of 1:2:4 cement concrete (Refer Sub-analysis) Cum 0.12 4669.39 560.33
C) Sub- Total 3021.11
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996 on
cost of 1:2:4 cement concrete and Cost of 60 cm
equilateral Triangle
25.94
Rate per number= A)+B) 3047.05
19.2 (iii) 60 cm circular Each 1.000 2941.60 2941.60
Add: Cost of Material per number as per chapter A Sl. No. 8.4
Add: Overhead Charges @ 10% % 10 294.16
A) Sub- Total 3235.76
Add: Contractor's Profit @ 10% % 10 323.58
B) Sub- Total 3559.34
Cost of 1:2:4 cement concrete (Refer Sub-analysis) Cum 0.12 4669.39 560.33
C) Sub- Total 4119.67
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996 on
cost of 1:2:4 cement concrete and Cost of 60 cm Circular35.02
Rate per number= A)+B) 4154.69
Sl
No. Description Unit Quantity
Rate
(Rs)
Amount
(Rs)
RATE ANALYSIS
19.3 (iii) 60 cm X 60 cm square Each 1.000 3492.10 3492.10
Add: Cost of Material per number as per chapter A Sl. No. 8.4
Add: Overhead Charges @ 10% % 10 349.21
A) Sub- Total 3841.31
Add: Contractor's Profit @ 10% % 10 384.13
B) Sub- Total 4225.44
Cost of 1:2:4 cement concrete (Refer Sub-analysis) Cum 0.12 4669.39 560.33
C) Sub- Total 4785.77
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996 on
cost of 1:2:4 cement concrete and Cost of 60 cm X 60 cm
square
40.52
Rate per number= A)+B) 4826.29
Sub-Analysis:
(V.p. 222 Item No 32)
Providing and laying Design Mix concrete for reinforced
concrete work in any part of bridge (excluding bottom
plugging) with coarse aggregates of appropriate nominal
size and grading, fine aggregate (sand) conforming to
proper grading zone, both of approved quality and cement,
as necessary, including labour, cost and carriage of all
materials and including preparation of design mix,
approval of the same by the Engineer-in-Charge and cost
for quality control, sampling, testing etc. all complete but
excluding cost of labour and materials for formwork &
reinforcement works.(a) 1:2:4 concrete using concrete mixer. Cum 1 3213.00 3213.00
Add: Cost of Material per cum
Cost of 22.4 mm Coarse Aggregates (@ 60% of 0.88m3) Cum 0.528 1693.50 894.17
Cost of 11.2 mm Coarse Aggregates (@ 40% of 0.88 m3) Cum 0.352 1586.50 558.45
Extra Cost of cement 3.77
A) Sub- Total 4669.39
(V.p. 149 Item No 5) of Schedule of Rates of Public Works (Roads) Department , National Highway Wing
Direction and Place Identification Signs upto 0.9 sqm Size Board
Providing and ercting direction and place identification
retro-reflectorised sign as per IRC:67 made of high
intensity grade sheeting vide clause 801.3, fixed over
aluminium sheeting, 2 mm thick with area not exceeding
0.9 sqm supported on a mild steel single angle iron post
75 X 75 X 6 mm firmly fixed to the ground by means of
properly designed foundation with M-15 grade cement
concrete 45 X 45 X 60 cm, 60 cm below ground level as
per approved drawing(iii) 60 cm X 60 cm square Each 1.000 8164.70 8164.70
Add: Cost of Material per number as per chapter A Sl. No. 8.4
Add: Overhead Charges @ 10% % 10 816.47
A) Sub- Total 8981.17
Add: Contractor's Profit @ 10% % 10 898.12
B) Sub- Total 9879.29
Cost of 1:2:4 cement concrete (Refer Sub-analysis) Cum 0.12 4669.39 560.33
C) Sub- Total 10439.62
B) Add 1.00% as per "Workers' Welfare Cess Act, 1996 on
cost of 1:2:4 cement concrete and Cost of 60 cm X 60 cm
square
87.25
Rate per number= A)+B) 10526.87
20