detailed feasibility studies: transmission projects in ... · framework used by nepal electricity...
TRANSCRIPT
Draft Feasibility Study Report Transmission Projects in Nepal
Volume 6
Monitoring and Evaluation
Prepared for: Millennium Challenge Corporation
1099 14th Street NW, Suite 700 Washington, DC 20005-3550
MCC-16-CL-0002
Prepared by: 1320 North Courthouse Road, Suite 600
Arlington, VA 22201 Tel 703.387.2100, Fax 703.243.0953
December 6, 201
Task 6 – Monitoring and Evaluation
Detailed Feasibility Studies: Transmission Projects in Nepal
MCC-15-BPA-0032, MCC-16-CL-0002
March 2017
Volume 6 (Report)
Detailed Feasibility Study: Nepal Priority Transmission Projects
Volume 6 Report Task 6: Monitoring and Evaluation
Prepared for: Millennium Challenge Corporation
1099 Fourteenth Street, NW Suite 700
Washington, DC 20005
MCC-15-BPA-0032, MCC-16-CL-0002
Prepared by: Tetra Tech ES, Inc.
1320 N. Courthouse Road, Suite 600 Arlington, VA 22201
March 2017
Consultants Team
David Keith BPA Program Manager Rakesh Kumar Goyal Project Manager
Rakesh Kumar Goyal Task Leader
Shahab Alam Team Member
Apoorv Nagpal Team Member
Ujjwal Bhattacharjee Team Member
Ritesh Kumar Singh Team Member
Wynne Cougill Editor
Contents
EXECUTIVE SUMMARY .................................................................................................................................. 2
1. INTRODUCTION ..................................................................................................................................... 3
2. REVIEW OF M&E FRAMEWORKS FOR TRANSMISSION PROJECTS IN NEPAL ........................................ 4
2.1 NEPAL ELECTRICITY AUTHORITY ................................................................................................ 4 2.2 WORLD BANK ...................................................................................................................... 6 2.3 ASIAN DEVELOPMENT BANK .................................................................................................... 6 2.4 MILLENNIUM CHALLENGE CORPORATION .................................................................................... 7
3. RECOMMENDATIONS FOR PERFORMANCE INDICATORS ..................................................................... 8
4. DATA COLLECTION .............................................................................................................................. 27
4.1 DATA FLOW ....................................................................................................................... 27 4.2 DATA COLLECTION ............................................................................................................... 29
5. MEASUREMENT AND REPORTING ...................................................................................................... 32
5.1 MEASUREMENT .................................................................................................................. 32 5.2 REPORTING........................................................................................................................ 33
6. RESOURCE REQUIREMENTS ................................................................................................................ 35
List of Tables Table 1. World Bank Indicators ............................................................................................................... 6 Table 2. Asian Development Bank .......................................................................................................... 7 Table 3. MCC: Common Indicators for Power ........................................................................................ 7 Table 4. Recommended Performance Indicators ................................................................................... 8 Table 5. Importance of Performance Indicators ................................................................................... 10 Table 6. Flow of Data for the Measurement of Performance Indicators ............................................. 27 Table 7. Report Generated through Performance Indicators ............................................................... 33 Table 8. M&E Budget ............................................................................................................................ 36
List of Figures Figure 1. M&E Framework Hierarchy...................................................................................................... 8 Figure 2. Data Collection Architecture during Compact Period. ........................................................... 29 Figure 3. Approach to Measure Post-Compact Indicators .................................................................... 31 Figure 4. Measurement of PIs ............................................................................................................... 32
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 1
Acronyms
ADB Asian Development Bank
GIS Gas-insulated switchgear or geographic information system
GOD Grid Operation Department of NEA
IEE Initial Environmental Examination
ITT Indicator tracking table
MCC Millennium Challenge Corporation
M&D Monitoring and evaluation
MIS Management information system
MVA Mega-volt ampere
NEA Nepal Electricity Authority
OMCN Office of Millennium Challenge/Nepal
PI Performance indicator
PMC Project Management Consultant
RTU Remote telemetry units
SAIDI System Average Interruption Duration Index
SAIFI Average interruption frequency per year
SCADA Supervisory control and data acquisition
WB World Bank
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 2
Executive Summary
The Millennium Challenge Corporation’s (MCC) proposed power transmission project must be
implemented within a five-year timeframe and will cover about 600 km of 400 kV and 220 kV
transmission lines, and 14 associated substations. The project will include the first gas-insulated
switchgear (GIS) substation and first 400 kV transmission network in Nepal. It is anticipated that
MCC’s compact will produce a five-fold increase in cross-border electricity trade with India, increase
per capita electricity consumption, and accelerate economic and social development in Nepal.
An effective monitoring and evaluation (M&E) framework is needed to measure the compact’s
progress/process, outputs and outcomes in an objective fashion. To meet this requirement, we have
recommended 33 performance indicators (PIs): 18 process indicators, 7 output indicators, and 8
outcome indicators. Outcome indicators were developed primarily to measure the post-
implementation impacts of the transmission system. The recommended PIs are based on the M&E
framework used by Nepal Electricity Authority, Asian Development Bank, and World Bank for their
transmission projects, the guidance provided in MCC’s Common Power Indicators document, and
the discussions that have taken place with MCC, Office of Millennium Challenge/Nepal, and other
stakeholders.
The M&E framework provides details on the data needed to measure the 2 PIs, and how data will
flow to help calculate/determine the PIs. Efforts have been made to collect most of the data needed
from MCA office software and the SCADA (supervisory control and data acquisition) of the Load
Dispatch Center without human interference. However, some site-specific data will be collected
manually from project sites and will be entered into the management information system (MIS)
through a web-based window.
This report also provides details on measuring and reporting the 33 PIs. Monthly, quarterly, bi-
annual and annual reporting is recommended, depending on the frequency of the measurement of
the PIs. In addition, two full-time resources are recommended for the development and operation
of the suggested M&E framework. The total estimated cost, including the cost of these two
resources and development of specific MIS software, is USD 684,306.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 3
1. Introduction
Monitoring and evaluation (M&E) serves as a guide for project implementation and management by
supporting an understanding of the progress made towards the achievement of objectives and
results. It identifies the variance between targets and actual achievements during implementation.
Therefore, we sought to develop and recommend performance indicators (PIs) that can serve as a
basis for tracking the progress of activities (e.g., construction) and the achievement of results (e.g.,
decreased outages or increased availability of power) for this compact. The PIs were developed
based on the objectives of the compact, anticipated challenges in its implementation, and MCC’s
Power Common Indicators.
We have suggested a holistic and robust M&E framework for this MCC compact. It consists of
performance indicators, data flows for the determination of PIs, measurement of PIs, reporting of
PIs, and resources required for the implementation of this M&E framework. The performance
indicators recommended are measurable and reliable, and provide an accurate representation of the
project conditions and actions. Other considerations made for PI development were ease and
accuracy of measurability.
In developing the M&E framework, we have studied the existing M&E frameworks for the
transmission projects of the Nepal Electricity Authority’s (NEA), Asian Development Bank (ADB), and
World Bank, and the Common Power Indicators of MCC. Information was collected from these
sources through desk research and discussions with NEA, ADB, World Bank, Office of Millennium
Challenge/Nepal (OMCN), MCC and other stakeholders. While developing the performance
indicators, we also considered the compact’s objectives and the anticipated challenges and risks in
implementing this compact.
Section 2 of this report reviews the M&E framework used by NEA, ADB and World Bank for
transmission projects; it also provides an understanding of the MCC Common Power Indicators for
transmission projects. Section 3 provides details for the PIs recommended for this compact, Section
4 is describes the data collection efforts, Section 5 addresses measurement and reporting, and
Section 6 describes resource requirements.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 4
2. Review of M&E Frameworks for Transmission Projects in Nepal
Most transmission projects in Nepal are executed by NEA, ADB and the World Bank. Their M&E
frameworks, including performance indicators, data collection, measurement methodology and
reporting mechanisms are summarized in this section. They are analyzed here against the MCC
Common Power Indicators by: 1) process Indicators, to track the project’ implementation progress,
2) output indicators, to track whether or not the project is delivering the desired outputs, and 3)
outcome indicators, to track that whether or not the project is producing the desired impacts.
2.1 Nepal Electricity Authority
NEA’s monitoring and evaluation of the transmission sector is implemented by two entities within
the transmission directorate of NEA:
Grid Operation Department: collects data and prepares M&E reports on existing
transmission lines and substations
Monitoring and MIS Section under NEA’s Transmission Directorate: collects data and
prepares M&E reports on transmission lines and substations under various phases of
development/construction.
2.1.1 Grid Operation Department
The Grid Operation Department (GOD) produces the following “Energy Transaction Reports”:
1. Monthly Energy Report of Substations
2. Monthly Outage Report
3. Monthly Power Transformer Loading Report
4. Monthly Voltage Variation Report
5. Weekly Report on Loading Status, Tripping and Planned Outages.
Annex A provides samples of these reports for Ashadh 2073 (15 June to 15 July 2016). These reports
measure transmission system parameters such as loads, outages, voltages, and energy flows. Data
for the reports are collected manually (generally in hard copy and CDs) from log sheets and are
recorded in Excel files by the branches/divisions of GOD. Substation data are collected by GOD
branches/divisions.
GOD has only two staff members on its M&E team. One is responsible for collecting data from the
branches/divisions, while the other converts the data into Excel reports. The reports are circulated
to the Ministry of Energy and NEA’s Finance Department.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 5
2.1.2 Monitoring and MIS Section
One of the eight departments in NEA’s Transmission Directorate is devoted to M&E, reflecting the
importance the Authority places on monitoring. This department generates monthly, quarterly, and
annual reports. The monthly reports provide details on the activities carried out during the month
against the plan for each project. Annex B1 provides a sample of a typical monthly report for the
Kabele corridor 132 kV transmission line project.
The more detailed quarterly reports monitor the following parameters to determine: 1) the
percentage of expenses against the quarterly/annual budgets, 2) total expenses to date, 3)
the percentage of time elapsed, and 4) physical progress in percentages:
1. Program capital expenditures
2. Substation construction
3. Transportation
4. Other activities (consultancy services, social responsibilities, and rural electrification)
5. Environmental studies (terms of reference, initial environmental examination (IEE) draft, IEE
approval, etc.)
6. Availability of land/right of way compensation/agricultural crop compensation.
The status of these six parameters is determined by measuring several sub-parameters. A typical
sample quarterly report is contained in Annex C (also for the Kabele corridor), while a sample annual
report can be found in Annex D. The formats for the monthly and annual reports are the same, and
were developed by the National Planning Commission of Nepal for NEA’s Transmission Directorate.
In addition, the Ministry of Energy prepares a trimester report that tracks physical and financial
progress, milestones achieved, and problems faced, while making recommendations for the
problems’ resolution (see Annex E).
Package managers are responsible for providing the data for these reports to the MIS Section in
Excel format. The MIS Section then reviews the information collected from each project package,
and consolidates and processes it. The Section then submits the reports to the National Planning
Commission, Ministry of Energy and other NEA departments.
The MIS Section has only one staff member. A few years’ ago, NEA procured locally-developed
management information system software. However, it is not used because the software was not
user friendly, staff lacked computer literacy, there were few efforts to build its capacity in this
regard, and a general lack of willingness to adopt new practices.
The NEA faces several main challenges in its M&E activities:
Delays in report generation due to the manual collection of data.
The field units’ use of different formats in transmitting data.
Lack of capacity building at all levels.
Need for additional staff in the MIS Section.
1 The reports in Annexes B through 6-E were translated from Nepali; Tetra Tech takes no responsibility for the accuracy of
the translation.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 6
Absence of graphs in the reports.
Targets and delays are not properly highlighted in the reports
Reporting is not based on gender and other socio-economic parameters.
2.2 World Bank
Table 1 presents the World Bank indicators, which were identified from Bank-funded power
transmission projects in Nepal (by discussion) and some of the transmission projects sponsored by
the World Bank (WB) in other countries such as China and Zambia. These projects were also linked
with other activities, such as institutional reform and distribution sector reform. We have also
observed that performance indicators, particularly outcome indicators, depend largely on project
objectives.
Table 1. World Bank Indicators
Process Indicators Output Indicators Outcome Indicators
Transmission line
upgraded or built
Transmission
substation capacity
added
Increase in power
transfer capacity
Average interruption frequency per
year (SAIFI)
Direct project beneficiaries, male
(Number)
Direct project beneficiaries, female
(Numbers)
Employment generation during
construction phase
Avoidance of load shedding.
New methodology and
software for planning/grid
operation and maintenance
Competition in generation
sector
2.3 Asian Development Bank Table 2 shows the indicators employed by the Asian Development Bank. These indicators have been identified from ADB’s Manual for Calculating Energy Output Indicators and from discussions on ADB-funded power transmission projects in Nepal, the Philippines, Cambodia and Azerbaijan. We have also observed that performance indicators, particularly outcome indicators, depend largely on project objectives. ADB normally uses following five indicators to review infrastructure projects with equal 20% weightage to each:-
Contract award according to schedule
Disbursement of fund
Financial management / audit
Technical issue
Safeguard Under safeguard, there are following three sub categories to monitor specifically environmental and social aspects of the project:-
EMP (Environment Management Practice), Resettlement Plan and Indigenous people plan.
Projects are reviewed quarterly on the basis of above. If the project score less than 70% it is considered in red zone, (not satisfactory); above 70-90% yellow, (good progress) and above 90% green, (excellent).
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 7
However, the energy indicators are generally classified under three other categories: 1) Promoting
Energy Efficiency and Renewable Energy, 2) Maximizing Access to Energy for All, and 3) Promoting
Energy Sector Reform, Capacity Building and Governance.
For ease of comparison, we have classified indicators relevant for this Compact, under MCC
Guidance on Common Indicator (Process, Output and Outcome).
Table 2. Asian Development Bank
Process Indicators Output Indicators Outcome Indicators
Transmission line
upgraded or built
Transmission substation
capacity added
Increase in power transfer
capacity
Funds disbursement
Contract award
Average interruption frequency per
year (SAIFI)
Reduction in overloading of the
transmission lines
Increase in rural electrification
Recommended social and
environmental mitigation measures
Number of training programs
Local complaints about
compensation
Increase in the supply of
electricity
Increase in power
generation
Annual net CO2 emission
reductions
Impact on local people
2.4 Millennium Challenge Corporation
Table 3 lists the relevant indicators for the monitoring and evaluation of power transmission
projects, as suggested in MCC’s Guidance on Common Indicators.2
Table 3. MCC: Common Indicators for Power
Process Indicators Output Indicators Outcome Indicators
[P-1] Value of signed infrastructure feasibility
and design contracts
[P-2] Present disbursement of power
infrastructure feasibility and design contracts
[P-3] Value of signed power infrastructure
construction contracts
[P-4] Present disbursement of power
infrastructure construction contracts
[P-5] Temporary employment generated by
power infrastructure construction
[P-7] Transmission line
upgraded or built
[P-8] Transmission
throughput capacity added
[P-9] Transmission
substation capacity added
[P-18] Transmission
system technical losses (%)
The standard MCC procedure for M&E uses an indicator tracking table (ITT). The ITT is formulated
using MCC’s “Guidance on the Indicator Tracking Table” in its general implementation guidelines.
The ITT consists of various indicators that are used to track the progress of a project. The ITT is an
Excel-based model that can be also created in a management information system (MIS). MCA has
the responsibility of preparing the ITT and submitting it to MCC each quarter. The MIS software
recommended here for development will have that feature.
2 https://www.mcc.gov/resources/doc/guidance-on-common-indicators
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 8
3. Recommendations for Performance Indicators
This section provides our recommendations for the performance indicators. In order to maintain
continuity, we propose to follow the same classification and numbering of indicators as provided in
MCC’s Common Power Indicator document. We do not propose any changes to the transmission
indicators provided in that document. However, in order to address the specific objectives and
challenges of this compact, we propose to add a few more indicators. They are numbered A-1, A-2,
etc. in Table 4. Further, we feel while MCC and MCA will like to monitor the progress at the compact
level, MCA package managers will want to monitor the project’s progress at the package level, and
on a more granular level, as depicted in Figure 1. We have suggested indicators specific to their
requirements, which are designated P-1.1, P2.1, A-1.1, etc. in the exhibits that follow.
Figure 1. M&E Framework Hierarchy
Once the proposed transmission line is functional, we suggest post-compact indicators from PC-1 to
PC-6 to evaluate the impact/success of the compact. We understand that one of the compact’s
conditions is that during the post-compact period, the host country would measure and report to
MCC on the performance indicators identified by MCC. Our complete recommendation for the
performance indicators are presented in Table 4.
Table 4. Recommended Performance Indicators
Process Indicators Output Indicators Outcome Indicators
[P-1] Value of signed infrastructure feasibility
and design contracts (for compact)
[P-1.1] Value of signed infrastructure
feasibility and design contracts (for project
package)
[P-7] Transmission line
upgraded or built (for
compact)
[P-7.1] Transmission line
upgraded or built (for project
package)
[P-18] Transmission system
technical losses (%)
[A-6] Number of capacity
building programs
disaggregated based on
sex.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 9
Table 4. Recommended Performance Indicators
Process Indicators Output Indicators Outcome Indicators
[P-2] Present disbursement of power
infrastructure feasibility and design contracts
(for compact)
[P-2.1] Present disbursement of power
infrastructure feasibility and design contracts
(for project package)
[P-3] Value of signed power infrastructure
construction contracts
[P-4] Present disbursement of power
infrastructure construction contracts
[P-5] Temporary employment generated by
power infrastructure construction
disaggregated based on sex.
[A-1] Percent completion of Environmental
and Social Management Systems
[A-2] Number of environmental or social
problems associated with the project
reported and not yet resolved (for compact)
[A-2.1] Number of environmental or social
problems associated with the project
reported and not yet resolved (for project
package)
[A-3] Number of land transfers effected
[A-3.1] Number of land transfers effected
(for project package)
[P-7.2] Number of tower foundations
constructed (for project package)
[P-7.3] Number of towers constructed (for
project package)
[P-9.1] Transformers available at package
(for project package)
[P-9.2] Transformers available at package
(for project package)
[P-9.3] Breakers and Isolators available at
package (for project package)
[P-9.4] Switchgear panels available at
package (for project package)
[P-8] Transmission
throughput capacity added
[P-9] Transmission substation
capacity added
[A-4] No. of transmission
substations rehabilitated
[A-5] Area of land acquired
[A-7] Capacity Utilization
Factor of a transmission line
[PC-1] Increase in Energy
Consumed per Unit of
Capita
[PC-2] Alleviation of
Electricity Shortage (load
shedding)
[PC-3] Change in System
Average Interruption
Duration Index (SAIDI)
[PC-4] Change in System
Average Interruption
Frequency Index (SAIFI)
[PC-5] Percent Households
Electrified
[PC-6] Increase in power
flow (import and export)
from neighboring
countries.
Our recommendations for the use of performance indicators (PI) by MCC, MCA and MCA package
managers and their frequency of measurement are provided in Table 5. In the table we have
indicated their importance by classifying them under high, medium and low categories:
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 10
Table 5. Importance of Performance Indicators
0 PI
Number Performance Indicator
Indicator
Type Importance
MCA
Package
Manager
MCA MCC Frequency
1 P-1
Value of signed
infrastructure feasibility
and design contracts (for
compact)
Process High √ √ Monthly
2 P-1.1
Value of signed
infrastructure feasibility
and design contracts (for
project package)
Process High √ Monthly
3 P-2
Present disbursement of
power infrastructure
feasibility and design
contracts (for compact)
Process High √ √ Monthly
4 P-2.1
Present disbursement of
power infrastructure
feasibility and design
contracts (for project
packages)
Process High √ Monthly
5 P-3
Value of signed power
infrastructure
construction contracts
Process Low √ √ Quarterly
6 P-4
Present disbursement of
power infrastructure
construction contracts
Process Low √ √ Quarterly
7 P-5
Temporary employment
generated by power
infrastructure
construction
disaggregated based on
sex
Process Medium √ √ Quarterly
8 A-1
Percent completion of
Environmental and Social
Management Systems
Process High √ Monthly
9 A-2
Number of environmental
or social problems
associated with the
project reported and not
yet resolved (for
compact)
Process Medium √ Monthly
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 11
Table 5. Importance of Performance Indicators
0 PI
Number Performance Indicator
Indicator
Type Importance
MCA
Package
Manager
MCA MCC Frequency
10 A.2.1
Number of environmental
or social problems
associated with the
project reported and not
yet resolved (for a
package)
Process Medium √ Monthly
11 A-3 Number of land transfers
effected (for compact) Process High √ Monthly
12 A-3.1
Number of land transfers
effected (for project
package)
Process High √ Monthly
13 P-7
Transmission line
upgraded or built (for
compact)
Output High √ √ Monthly
14 P-7.1
Transmission line
upgraded or built (for a
Package)
Output High √ Monthly
15 P-7.2 Number of tower
foundations constructed Process Low √ Monthly
16 P-7.3 Number of towers
constructed Process Low √ Monthly
17 P-8 Transmission throughput
capacity added Output High √ √ Quarterly
18 P-9 Transmission substation
capacity added Output Low √ √ Quarterly
19 P-9.1 Length of entry road
constructed Process Medium √ Quarterly
20 P-9.2 Transformers available at
package Process Medium √ Quarterly
21 P-9.3 Breakers and isolators
available at package Process Medium √ Quarterly
22 P-9.4 Switchgear panels
available at package Process Medium √ Quarterly
23 A-4 No. of transmission
substations upgraded Output High √ Quarterly
24 A-5 Area of land acquired Output High √ Monthly
25 P-18 Transmission system
technical losses (%) Outcome High √ √
Rolling
quarterly
26 A-6
Number of capacity
building programs,
disaggregated based on
sex
Outcome Medium √ Quarterly
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 12
Table 5. Importance of Performance Indicators
0 PI
Number Performance Indicator
Indicator
Type Importance
MCA
Package
Manager
MCA MCC Frequency
27 [A-7] Capacity Utilization Factor
of a transmission line Output Medium
√ √ Quarterly
28 [PC-1]
Increase in energy
consumed per unit of
capita
Outcome High √ Yearly
29 [PC-2] Alleviation of electricity
shortage (load shedding) Outcome High √ Yearly
30 [PC-3]
Change in system average
interruption duration
index (SAIDI)
Outcome High √ Quarterly
31 [PC-4]
Change in system average
interruption frequency
index (SAIFI)
Outcome Medium √ Quarterly
32 [PC-5] Percent households
electrified Outcome High √ Yearly
33 [PC-6]
Increase in power flow
(import and export) from
neighboring countries
Outcome High √ Yearly
Next, we describe each of the above 33 recommended PIs in the format specified in MCC’s Guidance
on Common Indicators. We have added a few additional fields: data required, data source, data
quality, baseline, interim target and reporting frequency to the MCC template for completeness.
Data required specifies the data needed to determine that PI, data source specifies from where
these data will come from, and data quality has been categorized under reliable (data coming from
the system is classified as reliable) and dependable (data coming by manual intervention are
generally classified as dependable). In many places for data source, we have mentioned the MCA
system. Here we have assumed in MCA there will be some computerized system where all contracts,
payments, etc. will be entered and this will be installed as part of the MCA office’s establishment.
For the indicators from MCC Common Indicator document units, definition, guidance, level,
classification and disaggregation are repeated from the MCC document.
[P-1] Value of Signed Infrastructure Feasibility and Design Contracts (for Compact)
Unit: US Dollars
Definition: The value of all signed feasibility, design, and environmental impact assessment
contracts, including resettlement action plans, for power infrastructure investments using
609(g) and compact funds.
Guidance: The target for this indicator should be the original value of the contract when first
signed. If the value of a contract changes, the contract modification amount should be
reported in the indicator tracking table (ITT) in the quarter when the change occurred. The
“Actual to Date” should reflect the current contract value, including all modifications. Costs
associated with pre-feasibility studies (if done by MCC) should not be included, nor should the
cost of supervision and project management.
Level: Process indicator.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 13
Classification: Cumulative.
Disaggregation: Based on packages
Data Required: Original value of the contract and any contract modification; it includes all
costs.
Data Source: The value for the required data will be taken from the MCA system or from the
contract document.
Data Quality: Reliable
Baseline and Target: Baseline = 0, Target = Budget for Signed Infrastructure Feasibility and
Design Contracts (X).
Interim Target:
Year 1: 50% of
X
Year 2: 80% of
X
Year 3: 90% of
X
Year 4: 100% of
X
Year 5: 100% of
X
Reporting Frequency: Monthly.
[P-1.1] Value of Signed Infrastructure Feasibility and Design Contracts (for project package)
This indicator is the same as [P-1], but will be measured for the specific project package.
[P-2] Present Disbursement of Power Infrastructure Feasibility and Design Contracts (for Compact)
Unit: Percentage.
Definition: The total amount of all signed feasibility, design, and environmental impact
assessment contracts, including resettlement action plans, for power infrastructure disbursed
divided by the total current value of signed contracts.
Guidance: Numerator = value disbursed of power infrastructure feasibility and design
contracts. Value disbursed should be defined as: the amount disbursed of all signed feasibility,
design, and environmental impact assessment contracts, including resettlement action plans,
for power infrastructure using 609(g) and compact funds. Denominator = value of signed
power infrastructure feasibility and design contracts.
Level: Process indicator.
Classification: Level.
Disaggregation: Based on project package.
Data Required: Payment/disbursement made against all contracts.
Data Source: The value for the required data will be taken from MCA from the contract
document.
Data Quality: Reliable
Baseline and Target: Baseline = 0%, Target = 100%.
Interim Target:
Year 1: 20% Year 2: 40% Year 3: 80% Year 4: 90% Year 5: 100%
Reporting Frequency: Monthly
[P-2.1] Present Disbursement of Power Infrastructure Feasibility and Design Contracts (for project
package)
This indicator is the same as [P-2], but will be measured for the specific project package.
[P-3] Value of Signed Power Infrastructure Construction Contracts
Unit: US Dollars.
Definition: The value of all signed construction contracts for power infrastructure investments
using compact funds.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 14
Guidance: The target for this indicator should be the original value of the contract when first
signed. If the value of a contract changes, the contract modification amount should be
reported in the ITT in the quarter in which the change occurred. Cost sharing by others (e.g.,
the non-MCC funding component of any co-financing with other donors or governments)
should not be included. However, costs associated with supervision or project management
should be included.
Level: Process indicator.
Classification: Cumulative.
Disaggregation: Based on packages
Data Required: Original value of the contract, contract modification amount, and cost
associated with construction contract.
Data Source: The value for the required data will be taken from MCA from the contract
document and modified contract document, if any, for all construction contracts.
Data Quality: Reliable.
Baseline and Target: Baseline = 0%, Target = value of signed power infrastructure construction
contracts (A).
Interim Target:
Year 1: 20% of
A
Year 2: 40% of
A
Year 3: 80% of
A
Year 4: 90% of
A
Year 5: 100%
of A
Reporting Frequency: Quarterly.
[P-4] Percentage Disbursement of Power Infrastructure Construction Contracts
Unit: Percentage.
Definition: The total amount of all signed construction contracts for power infrastructure
investments disbursed divided by the total current value of all signed contracts.
Guidance: Numerator= value disbursed of power infrastructure construction contracts. Value
disbursed should be defined as: the amount disbursed of all signed construction contracts for
power infrastructure investments using compact funds. Denominator = value of signed power
infrastructure construction contracts.
Level: Process indicator.
Classification: Level.
Disaggregation: Based on packages
Data Required: Amount disbursed of all signed construction contracts for power infrastructure
using compact funds and total value of all the signed construction contracts.
Data Source: The value for the required data will be taken from MCA system. The payment
made for construction contracts against the total value of the signed construction contracts.
Data Quality: Reliable.
Baseline and Target: Baseline = 0%, Target = 100%.
Interim Target:
Year 1: 20% Year 2: 40% Year 3: 80% Year 4: 90% Year 5: 100%
Reporting Frequency: Quarterly.
[P-5] Temporary Employment Generated by Power Infrastructure Construction
Unit: Number.
Definition: The number of people temporarily employed or contracted by MCA-contracted
construction companies to work on the construction of new power infrastructure or
reconstruction, rehabilitation, or upgrading of existing power infrastructure.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 15
Guidance: This indicator counts the unique number of people contracted, not the amount of
time that those people were temporarily employed. Even if a person was contracted for 1 day,
he/she should be counted. Both local and foreign workers should be included but identified
separately. Foreign workers are any workers who require a resident permit to work in the
country; anyone considered a national in the country should be counted as a local worker.
Those performing labor that requires specialized training or a learned skill-sets to perform the
work should be counted as skilled workers. Those performing labor that requires some skill
that may not be performed by an unskilled worker, but does not require highly specialized
skills, should be counted as semi-skilled workers. Those performing labor that does not require
special training or skills should be counted as unskilled workers. Informal employment
generated by construction activities is not included. However, if an individual worked on the
project in one quarter, stopped working, and rejoined later, s/he should only be counted once.
Therefore, tracking this indicator requires a process for uniquely identifying workers, which
should be required in the scope of work for relevant contractors.
Level: Process indicator.
Classification: Cumulative.
Disaggregation: Male/female, foreign/local, skilled/semi-skilled/unskilled, poverty level3.
Data Required: No. of people contracted, gender of the worker, no. of skilled workers
contracted, no. of foreign workers contracted.
Data Source: The required data will be collected from the contractors who have been assigned
to implement the project. A segregation will be needed between skilled-unskilled and
national-international manpower engaged in the execution of the project.
Data Quality: Dependable.
Baseline and Target: Baseline= 0, Target = to be decided in discussions with construction
contractors.
Interim Target: To be decided in discussions with construction contractors.
Reporting Frequency: Quarterly.
[A-1] Percent Completion of Environmental and Social Management Systems (ESMS)
Unit: Percent.
Definition: Completion of environmental and social management system, including health and
safety issues vs. total completion.
Guidance: An environmental and social management system consists of several activities. Each
activity will be assigned a weight depending upon its importance. The percentage completion
will be determined on the basis of the weighted average of the number of activities
completed. A partially completed activity will be counted as incomplete. The summation of all
the activities completed multiplied by their weights, divided by sum of total activities, and
multiplied by their weights.
Level: Process indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: List of activities in the ESMS with the importance and status of each activity.
Data Source: ESMS Consultant/Manger, Monthly progress reports and MCA package manager
Data Quality: Dependable.
3 As per the national living standards survey conducted in 2010-2011, a family is considered to be below poverty level if earning is less than US$14 in a month. https://www.ruralpovertyportal.org/country/home/tags/nepal
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 16
Baseline and Target: Baseline = 0, Target = 100%.
Interim Target: The activity is proposed to be completed before the compact comes into force.
Reporting Frequency: Monthly.
[A-2] Number of Environmental, Social or Resettlement Problems Associated with the Project Reported and Not Yet Resolved (for Compact)
Unit: Number
Definition: Percentage of the total number of environmental, social or resettlement problems
associated with the project reported and not yet resolved. The percentage of number of
problems unresolved divided by the total number of environmental, social or resettlement
problems associated with the project that are reported.
Guidance: This will help to determine the effectiveness of the grievance/problem resolution
mechanism for environmental, social or resettlement problems. The mechanism is described
in Task 3 report for resettlement issues. The mechanism for environment and social issues will
be covered in ESIA and ESMP. This percentage should come down and ideally become zero
before the start of package activities.
Level: Process indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Total problems received and the number of problems unresolved for
environment, social and for resettlement issues.
Data Source: Engineer and/or from MCA package manger.
Data Quality: Dependable.
Baseline and Target: Baseline= The number of complaints received not resolved within 45
days (45 days are here for illustration. Actual value should be fixed based on ground
conditions), Target = 0.
Interim Target:
Year 1: 0 Year 2: 0 Year 3: 0 Year 4: 0 Year 5: 0
Reporting Frequency: Monthly.
[A-2.1] Number of Environmental, Social or Resettlement Problems Associated with the Project
Reported and Not Yet Resolved (for a package)
This indicator is same as [A-2], but will be measured for specific project package by the MCA
package manager.
[A-3] Number of Land Transfers Effected (for Compact)
Unit: Number
Definition: The total current number of acquisitions for the project divided by the total
number of land parcels to be acquired.
Guidance: Several parcels of land are to be acquired for the project; their deeds are to be
transferred and then physical possession of the land is to be obtained. Land transfer effected
means the physical transfer of land to MCA. This is a challenging task. This indicator will help in
tracking the progress of this critical activity.
Level: Process indicator.
Classification: Cumulative.
Disaggregation: Based on project package and type of land, such as private/ government/
agriculture/ forest and based on income groups, poverty level.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 17
Data Required: Total number of parcels of land to be acquired and number of parcels for
which physical possession has been obtained.
Data Source: ESMS Consultant/Manager, monthly progress reports and MCA package
manager
Data Quality: Dependable.
Baseline and Target: Baseline = 0, Target = to be determined after identification of land owner
(B)
Interim Target:
Year 1: 80% of
B
Year 2: 100%
of B
Year 3: 100%
of B
Year 4: 100%
of B
Year 5: 100%
of B
Reporting Frequency: Monthly.
[A-3.1] Number of Land Transfers Effected (for a package)
This indicator is same as [A-3], but will be measured for specific project package by the MCA
package manager.
[P-7] Transmission Lines Upgraded or Built For all packages
Unit: Kilometers.
Definition: The sum of linear kilometers of new, reconstructed, rehabilitated, or upgraded (by
higher capacity of conductor/tower) transmission lines that have been energized, tested and
commissioned with MCC support.
Guidance: Electrical lines of 66 kV or above shall be classified as transmission lines.
Transmission consists of all lines connecting the generation packages to transmission
substations.
Level: Output indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Length of the transmission line constructed.
Data Source: The required data will be gathered from the package contractor responsible for
the construction of the transmission line and monthly progress report.
Data Quality: Reliable.
Baseline and Target: Baseline = 0, Target = 642 km (A).
Interim Target:
Year 1: 5% of
A
Year 2: 20% of
A
Year 3: 50% of
A
Year 4: 80% of
A
Year 5: 100% of
A
Reporting Frequency: Monthly.
[P-7.1] Transmission Lines Upgraded or Built (For a package)
This indicator is same as [P-7], but will be measured for specific project package.
[P-7.2] Number of Tower Foundations Constructed (For a package)
Unit: Number.
Definition: The number of foundations constructed for transmission towers.
Guidance: The tower foundation is a critical item both for technical and land acquisition
purposes. Once the tower foundation is successfully built, the chances of any land or right of
way issue arising are unlikely to occur. The data will be for the number of foundations
constructed divided by the total number of foundations to be constructed.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 18
Level: Process Indicator.
Classification: Cumulative.
Disaggregation: None
Data Required: Number of foundations constructed for transmission towers.
Data Source: The required data will be gathered from the package contractor responsible for
the construction of the transmission line foundation and by package inspections. The data can
also be gathered from monthly progress report.
Data Quality: Dependable.
Baseline and Target: Baseline = 0, Target = 1860 (A)
Interim Target:
Year 1: 10% of
A
Year 2: 50% of
A
Year 3: 81% of
A
Year 4: 95% of
A
Year 5: 100%
of A
Reporting Frequency: Monthly.
[P-7.3] Number of Towers Constructed
Unit: Number.
Definition: The number of transmission towers constructed.
Guidance: The tower construction is a critical item in the construction of the transmission line.
Typically, tower construction means 60 to 70% completion of the transmission line work. Once
the tower is successfully erected, the chances of any land or right of way issue arising are
unlikely to occur while the conductor is being strung. Number of towers constructed will be
the number of foundations constructed divided by the total number of foundations to be
constructed.
Level: Process Indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Number of foundations constructed for transmission towers.
Data Source: The required data will be gathered from the package contractor responsible for
the construction of the transmission line foundation and by site inspection.
Data Quality: Dependable.
Baseline and Target: Baseline = 0, Target = 1860 (A).
Interim Target:
Year 1: 8% of A Year 2: 40% of
A
Year 3: 75% of
A
Year 4: 85% of
A
Year 5: 100%
of A
Reporting Frequency: Monthly.
[P-8] Transmission Throughput Capacity Added
Unit: Megawatts.
Definition: The increase in throughput capacity, measured in megawatts, added by new,
reconstructed, rehabilitated, or upgraded transmission lines that have been energized, tested
and commissioned with MCC support.
Guidance: The target for the indicator should be informed by feasibility and load flow studies
of the relevant MCC investment in the transmission network, and should reflect the increase in
capacity of the network to transmit electricity between key transmission and distribution
nodes. At minimum, the indicator should be reported as an overall change in network
throughput capacity. However, as feasible and appropriate, the value of the indicator should
be disaggregated by voltage level. Values reported across separate investments in higher-
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 19
capacity lines at different parts of the network are not additive with each other, so reporting
on the indicator cannot be easily aggregated across the whole network, although more
detailed modeling may allow for this. The value of this indicator should ideally be informed by
load flow analysis after the new or upgraded lines have been energized, tested and
commissioned. The throughput capacity data will be collected with the help of feasibility and
load flow studies done for the transmission system.
Level: Output indicator.
Classification: Level.
Disaggregation: Based on packages.
Data Required: New transformation capacity added.
Data Source: The data can be collected from the package manager based on the
transformation capacity of the substation added or upgraded. The substation capacity added
into the Nepal grid will only be counted here. It can be later verified by load flow studies.
Data Quality: Reliable.
Baseline and Target: Baseline = 0, Target = 778 MW (For the year 20234)
Interim Target: To be decided by more detailed load flow study.
Reporting Frequency: Quarterly.
[P-9] Transmission Substation Capacity Added
Unit: Megavolt amperes (MVA).
Definition: The total added transmission substation capacity, measured in megavolt amperes
that is energized, commissioned and accompanied by a test report and supervising engineer’s
certification resulting from new construction or refurbishment of existing substations that is
due to MCC support.
Guidance: This indicator shall include the total capacity installed at a substation. As this is an
output indicator, and not an outcome indicator, it will not take into account mitigating
circumstances that may lower the capacity available at a substation, such as percentage of use
or reserve capacity in substations.
Level: Output indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Total capacity of transformers added and upgraded (after energization).
Data Source: The data can be collected from the package manager or from Grid Operation
Department of the NEA.
Data Quality: Reliable
Baseline and Target: Baseline = 0, Target = 3840 MVA (A)
Interim Target:
Year 1: 5% Year 2: 30% Year 3: 45% Year 4: 65% Year 5: 100%
Reporting Frequency: Quarterly.
[P-9.1] Length of Entry Road Constructed
Unit: KM.
Definition: The length of entry road constructed to approach the substation.
4 Based on PSSE load flow study for the year 2023 for all counterfactual base case and all MCC projects. For further details refer section 3.1.8 of volume 1 report
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 20
Guidance: The length of entry road constructed to approach substation including widening of
roads is an important activity. The transformer can only be transported to the side when the
proper entry road is ready.
Level: Process Indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Length of entry road constructed.
Data Source: The required data will be gathered from the package contractors responsible for
the construction of the entry road and by site inspection. It will be the road in meters
completed divided by the total road in meters to be constructed.
Data Quality: Dependable.
Baseline and Target: Baseline = 0, Target = 21 KM (to be amended when the detailed design is
ready).
Interim Target:
Year 1: 40% Year 2: 90% Year 3: 100% Year 4: 100% Year 5: 100%
Reporting Frequency: Quarterly.
[P-9.2] Transformers Available at Package
Unit: Number.
Definition: Number of transformers at project package.
Guidance: The number of transformers available at the project package that are ready for
commissioning.
Level: Process Indicator.
Classification: Cumulative.
Disaggregation: None.
Data Required: Number of transformers at the project package.
Data Source: The required data will be gathered from the MCA package manager.
Data Quality: Reliable
Baseline and Target: Baseline = 0, Target = to be decided later based on delivery schedule of
the contractor
Interim Target: to be decided later based on delivery schedule of the contractor.
Reporting Frequency: Quarterly.
[P-9.3] Breakers and Isolators Available at Package
Unit: Number.
Definition: Number of beakers and isolators at the project package.
Guidance: The number of beakers and isolators available at the project package that are ready
for commissioning.
Level: Process Indicator.
Classification: Cumulative.
Disaggregation: None.
Data Required: Number of beakers and isolators at the project package.
Data Source: The required data will be gathered from the MCA package manager.
Data Quality: Reliable.
Baseline and Target: Baseline = 0, Target = to be decided later, based on the delivery schedule
of the contractor
Interim Target: To be decided later based on delivery schedule of contractor.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 21
Reporting Frequency: Quarterly.
[P-9.4] Switchgear Panels Available at Package
Unit: Number.
Definition: Number of switchgear panels at the project package.
Guidance: The number of switchgear panels available at the project package that are ready for
commissioning.
Level: Process Indicator.
Classification: Cumulative.
Disaggregation: None.
Data Required: Number of switchgear panels at the project package.
Data Source: The required data will be gathered from MCA package manager.
Data Quality: Reliable.
Baseline and Target: Baseline = 0, Target = to be decided later, based on the delivery schedule
of the contractor
Interim Target: To be decided later, based on the delivery schedule of the contractor
Reporting Frequency: Quarterly.
[A-4] Number of Transmission Substations Upgraded
Unit: Number.
Definition: The number of transmission substations reconstructed, rehabilitated, or upgraded
under the project.
Guidance: Transmission substations of 66 kVA or above shall be classified as transmission
substations. The number of transmission substations reconstructed, rehabilitated, or upgraded
under the project.
Level: Output indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: No. of transmission substations reconstructed, rehabilitated or upgraded.
Data Source: Quarterly Progress Report and Inspection Reports
Data Quality: Dependable.
Baseline and Target: Baseline = 0, Target = 6
Interim Target:
Year 1: 0 Year 2: 0 Year 3: 4 Year 4: 5 Year 5: 6
Reporting Frequency: Quarterly.
[A-5] Area of Land Acquired
Unit: Percent.
Definition: The total area acquired for the project in sq. km divided by the total sq. km area of
land required for the project.
Guidance: Land acquisition is a critical activity for the project. Therefore, it needs to be
monitored both in terms of area and in number of land parcels (Ref. A-3). Sq. km of land for
which physical possession has been obtained divided by total sq. km of land to be acquired.
Level: Output indicator.
Classification: Cumulative.
Disaggregation: Based on project package and type of land such as
private/government/agriculture/ forest.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 22
Data Required: Total sq. km of land required and sq. km of land acquired.
Data Source: EASMs consultant /manger, monthly progress reports and MCA package
manager
Data Quality: Dependable.
Baseline and Target: Baseline = 0, Target = 83.7 Hectare (A)5.
Interim Target:
Year 1: 40% of
A
Year 2: 80% of
A
Year 3: 100%
of A
Year 4: 100%
of A
Year 5: 100%
of A
Reporting Frequency: Monthly.
[P-18] Transmission System Technical Losses (%)
Unit: Percentage.
Definition: 1- [Total megawatt hours transmitted out from transmission substations / Total
megawatt hours received from generation to transmission substations].
Guidance: Quarterly estimates should be reported if available; however, data on losses are
often unavailable due to insufficient monitoring equipment, and estimates are often made
based on periodic loss characterizations or load flow studies. Data quality reviews can also
serve to improve estimates at the baseline while recommending steps to improve the accuracy
of estimates during the compact. In some cases, this indicator may not be appropriate to use if
there are separate incorporated entities responsible for operating the transmission network,
where the utility company may only be responsible for distribution – especially if the compact
is only focusing on one subsector (e.g., distribution).
Level: Outcome indicator.
Classification: Level.
Disaggregation: Based on packages.
Data Required: Total MW hours fed into the grid and total MW hours supplied by the grid.
Data Source: Periodic substation reports and aggregation of the energy input and output from
various feeders through SCADA.
Data Quality: Reliable.
Baseline and Target: Baseline = 2.42%6 (For 2023), Target = 2.13%7 (For 2023)
Interim Target: To be fixed by detailed load flow study for each year.
Reporting Frequency: Quarterly.
[A-6] Number of Capacity Building Programs
Unit: Number.
Definition: Sum of capacity building programs conducted for stakeholders, staff, vendors, land
owners, etc.
Guidance: The training will be conducted by different entities, such as MCA, vendors,
consultants etc. for different stakeholders at different locations. Any well announced formal
capacity building program will be counted as one training session. The required numbers will
5 Refer excel sheet – ‘Resettlement Cost Estimate’ of Volume 3 for details. 6 Based on PSSE load flow study for the year 2023 for all counterfactual base case. For further details refer section 3.1.8 of volume 1 report. As per annual report of NEA the Transmission losses for the FY 2015-16 is 4.82%. 7 Based on PSSE load flow study for the year 2023 for all counterfactual base case and all MCC projects. For further details refer section 3.1.8 of volume 1 report.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 23
come from vendors, contractors and training institutes which will be mentioned in periodic
report.
Level: Outcome indicator.
Classification: Cumulative.
Disaggregation: Male/female participants and on poverty level.
Data Required: No. of training sessions held.
Data Source: Workshops and training program reports; quarterly progress reports
Data Quality: Reliable.
Baseline and Target: Baseline = 0, Target = to be decided later
Interim Target: To be decided when target is fixed.
Year 1: Year 2: Year 3: Year 4: Year 5:
Reporting Frequency: Quarterly.
[A-7] Capacity utilization Factor of a Transmission Line
Unit: Percentage (%)
Definition: The ratio of peak loading on the transmission line (in Amperes) segment in a
quarter and design capacity8 of the line.
Guidance: This indicator will measure the capacity utilization of the transmission line segment
vis-à-vis its design capacity. Normally, the design capacity of the line is much higher than the
normal loading to clear the fault currents. Therefore, this indicator should be interpreted
considering this fact. The peak loading in the quarter of a line is the highest value of the
current flown on that line at any instant of time in the quarter. Obviously, transient loading
due to a fault or any other impulse should not be considered for determining the peak value.
Level: Output indicator.
Classification: Level.
Disaggregation: For each transmission line segment.
Data Required: Peak value in a quarter
Data Source: SCADA system installed at the substation to which the line is connected
Data Quality: Reliable.
Baseline and Target: Baseline= 0% Target = 50% (assuming a design safety factor of 2) Reporting Frequency: Quarterly. [PC-1] Increase in Energy Consumed per Capita
Unit: kWh/capita
Definition: Increase in number of unit of electricity consumed per capita.
Guidance: This indicator will measure the difference in energy consumed per person. This
indicator will indicate the improvement in livelihood of the country. The Increase in energy
consumed will be calculated by identifying the difference in energy consumption in the
measurement year and base year. To calculate the energy consumed per capita this difference
will be divided by population.
Level: Outcome indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Per capita energy consumed at base year; per capita energy consumed in the
measuring year; population of country.
8 The design capacity of the transmission lines, in Amperes, are: 4558 (NR1, T8 and XB1) / 914 (T2’) / 747 (T3)/ 870 (NR3) /962 (NR4). The name of the line segments has been mentioned in brackets.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 24
Data Source: NEA report.
Data Quality: Dependable.
Baseline and Target: Base Line= 133 kWh (2015)9
Target = to be decided based on the master plan of transmission and distribution system.
Interim Target: to be decided based on the master plan of transmission and distribution
system
Reporting Frequency: Yearly.
[PC-2] Alleviation of Electricity Shortage (Load Shedding)
Unit: GWh
Definition: The deliberate shutdown of electric feeders, generally to prevent the failure of the
entire power system when power supply is lower than demand at transmission level.
Guidance: This indicator can be calculated by identifying the change in load shedding period in
the measuring year and base year.
Level: Outcome indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Duration of load shedding in base year; Duration of load shedding in the year
of measurement.
Data Source: SCADA and NEA Reports.
Data Quality: Dependable.
Baseline and Target: Baseline = 3925 GWh (For 2023)10, Target = 1562 GWh (For 2023)11
Interim Target: to be decided based on the master plan of transmission and distribution
system.
Reporting Frequency: Yearly.
[PC-3] Change in System Average Interruption Duration Index (SAIDI)
Unit: Hours.
Definition: SAIDI is the average outage duration for each customer served and is commonly
used as a reliability indicator. (For transmission)
Guidance: SAIDI can be calculated by dividing duration of interruption in minutes by number
of customers.
Level: Outcome indicator.
Classification: Cumulative.
Disaggregation: Based on packages.
Data Required: Duration of interruption in minutes; number of customers.
Data Source: In the SCADA system, data will be based on the feeders energized or de-
energized leaving the cases of scheduled maintenance.
Data Quality: Reliable.
9 http://mof.gov.np/ieccd/pdf/Energy_NPPR_2015.pdf 10 Based on PSSE load flow study for the year 2023 for all counterfactual base case. For further details refer section 3.1.8 of volume 1 report. 11 Based on PSSE load flow study for the year 2023 for all counterfactual base case and all MCC projects. For further details refer section 3.1.8 of volume 1 report.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 25
Baseline and Target: Baseline = 251.81 Hours12,
Target: to be decided based on the master plan of transmission and distribution system.
Interim Target: To be decided based on the master plan of transmission and distribution
system.
Reporting Frequency: Quarterly.
[PC-4] Change in System Average Interruption Frequency Index (SAIFI)
Unit: Numbers.
Definition: SAIFI measures the average number of interruptions experienced by each
customer. All planned and unplanned interruptions are used in calculating the index. (For
transmission)
Guidance: SAIFI can be calculated by dividing number of interruptions during one year by
number of customers.
Level: Outcome indicator.
Classification: Cumulative.
Disaggregation: None.
Data Required: Number of interruptions during one year; number of customers.
Data Source: In the SCADA System, data will be based on the feeders energized or de-
energized leaving the cases of scheduled maintenance.
Data Quality: Reliable.
Baseline: 23511
Target: To be decided based on the master plan of transmission and distribution system.
Interim Target: To be decided based on the master plan of transmission and distribution
system.
Reporting Frequency: Quarterly.
[PC-5] Percent Households Electrified
Unit: Percentage.
Definition: The process by which access to electricity is provided to households or villages
located in the isolated or remote areas of a country.
Guidance: The ratio of number of households electrified with total number of houses.
Level: Outcome indicator.
Classification: Cumulative.
Disaggregation: Urban/rural, poverty level.
Data Required: Total number of households; number of households electrified.
Data Source: Central Bureau of Statistics, Nepal; third party surveys.
Data Quality: Dependable.
Baseline and Target: Base line= 67% (2011)13
Target = To be decided based on the master plan of transmission and distribution system.
Interim Target: To be decided based on the master plan of transmission and distribution
system.
Reporting Frequency: Yearly.
12 On the basis of NEA’s monthly outage report for the period for June 2015 to May 2016. It includes interruption of any transmission line or its feeders due to any reason including interruptions due to planned shutdown, operation or maintenance, etc. 13 http://conference.ioe.edu.np/ioegc2014/papers/IOE-CONF-2014-34.pdf
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 26
[PC-6] Increase in power flow (import and export) from neighboring countries
Unit: GWh.
Definition: Sale and purchase of electric power between two countries on the basis of demand
and supply.
Guidance: There will be sale and purchase of electricity between two countries through the
power transmission network as per the demand and supply requirements in the countries. The
import and export of the electricity can be measured through net meters.
Level: Outcome indicator.
Classification: Cumulative.
Disaggregation: Import/export.
Data Required: Cross-border trade of electricity.
Data Source: In the SCADA system, data will be based on the power flow through cross border
feeders.
Data Quality: Reliable.
Baseline and Target: Baseline= 6,000, Target = 14,200 in 2023.14
Interim Target: To be determined by more detailed load flow studies for each year.
Reporting Frequency: Yearly.
14 Load flow study for 2023 scenario with base case and all MCC projects. For more details refer “Power System Assessment” section of the Task 1 report.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 27
4. Data Collection
4.1 Data Flow
The data required for the measurement of performance indicators have been specified in Section 3.
However, to develop an IT-enabled automatic M&E framework, it is important to define from where
data will originate, who will collect it, and how the data will flow into an MIS software tool. Table 6
specifies origination points, travel paths, and final destinations for the data required for the
recommended 33 performance indicators.
Table 6. Flow of Data for the Measurement of Performance Indicators
Indicator Data Flow
Description/ Use Cases Origination Via/final destination
P-1 MCA System Central Database
It is assumed that the MCA will set-up an in-house
system as part of their office establishment. The
contracts and payment will be administered and
managed through this system.
The data will flow from this system to web-based
project management software as per the system
logics (it can be instantaneous/daily).
P-1.1 MCA System Central Database
P-2 MCA System Central Database
P-2.1 MCA System Central Database
P-3
MCA
Technical
Consultants
Central Database
P-4
MCA
Technical
Consultants
Central Database
P-5 Site
Contractor
MCA Package Manager to
Central Database
The MCA Package Manager will collect information
from all contractors about the workers employed
(only direct employees) on the project.
P-7 Site
Contractor
MCA Package Manager to
Central Database
The MCA Package Manager will collect information
from the site contractor and verify through visual
inspection the authenticity of the data provided by
the site contractor.
P-7.1 Site
Contractor
MCA Package Manager to
Central Database
P-7.2 Site
Contractor
MCA Package Manager to
Central Database
P-7.3 Site
Contractor
MCA Package Manager to
Central Database
P-8 Site
Contractor
MCA Package Manager to
Central Database The MCA Package Manager will collect data from
the substation commissioning results. P-9
Site
Contractor
MCA Package Manager to
Central Database
P-9.1 Site
Contractor Central Database
The MCA Package Manager will collect information
from the site contractor and verify it through visual
inspection the authenticity of the data provided by
the site contractor.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 28
Table 6. Flow of Data for the Measurement of Performance Indicators
Indicator Data Flow
Description/ Use Cases Origination Via/final destination
P-9.2 MCA package
Manager Central Database
The MCA Package Manager will feed the
information based on visual confirmation. P-9.3
MCA package
Manager Central Database
P-9.4 MCA package
Manager Central Database
P-18 SCADA Central Database
The information will be directly fed from the
SCADA to the Central Database. The information
will flow as per the SCADA logic (it can be
instantaneous/daily).
A-1 Site
Contractors
MCA Technical Consultants
- MCA System - Central
Database
The contractors will follow the ESMS and technical
consultants/ Project Management Consultant
(PMC) will monitor its adherence.
A-2 & A-
2.1
MCA
Technical
Consultants/
PMC
MCA Package
Manager
MCA System - Central
Database
Central Database
The public grievances received at the MCA level
will be entered into the MCA system by the
MCA/technical consultants/ PMC
The public grievances received at the site office will
be entered by the MCA package manager manually
into a web-based tool.
A-3 MCA Package
Manager
PMC - MCA system-
Central Database
The MCA Package Manager will collect information
on the number of land acquisitions for the project
and will provide this information to MCA. The PMC
will enter the information in the MCA system. A-3.1
MCA Package
Manager
PMC - MCA system-
Central Database
A-4 MCA Package
Manager
PMC - MCA system-
Central Database
The MCA Package Manager will collect information
on the number of substations upgraded for the
project and will provide this information to MCA.
The PMC will enter the information in the MCA
system.
A-5 MCA Package
Manager
PMC - MCA system-
Central Database
The MCA Package Manager will collect information
on land acquisitions for the project and will provide
this information to MCA. The PMC will enter the
information in the MCA system.
A-6 MCA System Central Database
It is assumed that the details of all the training
programs from, their conceptualization to their
completion, will be captured in the MCA system.
A-7 SCADA Central Database
The design value has been provided in the
Footnote #8 on Page 23 (Section 3). The quarterly
peak value can be obtained from the quarterly
reports generate through the SCADA of the
substation to which the line is connected.
PC-1 SCADA Central Database It is assumed SCADA at load dispatch center will get
connected to all transmission sub stations. PC-2 SCADA Central Database
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 29
Table 6. Flow of Data for the Measurement of Performance Indicators
Indicator Data Flow
Description/ Use Cases Origination Via/final destination
PC-3 SCADA Central Database
PC-4 SCADA Central Database
PC-5 Survey Central Database
PC-6 SCADA Central Database
4.2 Data Collection
Our high-level approach for the collection of data for each of the recommended performance
indicators can be divided in two parts:
During compact
Post compact.
During Compact: We have tried to capture the maximum amount of data that can be obtained
without relying on human interface (data that can be collected automatically). However, some of the
data, such as number of towers erected, transmission line completed, etc. cannot be system fed. For
such data, a web-based system/window will be provided to MCA package managers. This window
will be part of central MIS system. The data will be processed using project management software
and will generate reports as specified in the M&E plan from central MIS system. The architecture of
data collection during compact period is provided in Figure 2.
*: Please refer to Table 6 for further elaboration
Figure 2. Data Collection Architecture during Compact Period.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 30
Post Compact
After the completion of the compact, the transmission system will be handed over, either to NEA or
to the new transmission entity, which will be responsible for measuring these performance
indicators and reporting to MCC. We have recommended six indicators (From PC-1 to PC-6) for post
compact monitoring. PC-1 and PC-2 are calculated by all utilities and NEA is no exception. PC-1 is
determined on annual basis and published in the annual report of NEA. PC-2 is monitored by utility
on daily basis due to several reasons and report is generated by Load Dispatch Centre every day in
the morning for previous 24 hours. For the MCC purpose it may not be relevant as daily report
reflects more operational issues. From MCC perspective it is important to look at it on annual basis
what was the total number of megawatt-hours of load shedding in the previous year and how has it
changed on an annual basis. Similar is the situation with PC-3, PC-4 and PC-6. It will be possible to
generate reports for PC-2 to PC-4 and for PC-6 at any point of time from new SCADA KfW15 is
installing at NEA’s load dispatch center (LDC). However to have a meaningful assessment of impact
and improvement one year period is reasonable. PC-5 will be captured (data collected from field
units) and published by NEA.
Generally, these indicators will merge with the MIS of the transmission company. The MIS system of
the NEA is described in detail in Section 2.1.
As part of our substation design, we have provided meters and remote telemetry units (RTUs) at
appropriate locations to capture the data required for measuring the performance indicators P-18,
PC-3, PC-4 and PC-6. The data from the substation will be transmitted to the SCADA16 with the help
of the RTU and normal communication links between substations and SCADA. The reports on these
indicators will be generated either at the SCADA level or data will flow from the SCADA to the
transmission company’s MIS for the generation of the reports. The latest SCADAs have provisions for
formatting reports as per the requirements specified. A high-level graphic representation of this is
provided in Figure 3. The substation layout/design provided in the Task 1 (Volume 1) report covers
placement and interconnection of meters and RTUs.
Thus, in terms of resources there is no specific requirement for the suggested post compact
indicators as they will be monitored by NEA (or the transmission company) even without the
Compact. Since these indicators will be measured through on line systems (SCADA) and data stored
in software, there is hardly any scope for improvement of the quality of the data. The improvement
is required in terms utilizing the features of SCADA for generation of reports. This depends upon
several factors such as, LDC staff willingness, MIS demand of the top management and their push for
system generated reports. As far as LDC staff is considered KfW has made sufficient provisions for
capacity building of the NEA staff.
15 Although such report generation is standard feature of modern SCADA system but in this case we have confirmed with KfW also. 16 The SCADA mentioned in this document refers to the SCADA of Load Dispatch Center.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 31
Figure 3. Approach to Measure Post-Compact Indicators
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 32
5. Measurement and Reporting
5.1 Measurement
The data for all the 33 PIs will come either from site, MCA system, SCADA, or surveys. This section
describes how this data will be used to determine/calculate the PIs. Figure 4 provides a graphic
representation of the measurement approach of PIs.
Figure 4. Measurement of PIs
Data from the Site: The data for performance indicators P-5, A-1, A-2, A-2.1, A-3, A-3.1, P-7.2, P-7.3,
P-9.1, P-9.2, P-9.3 and P-9.4 will come from the site. These data will be entered manually by the
MCA Package Manager in a web-based window that will be connected to the central database of the
MCA. This web-based system can be accessed through the internet with the help of an internet
browser. The MCA Package Manager needs to access the webpage on his laptop/desktop and log in
with his user identity and password. The MIS software installed in the central database will retrieve
these data and determine/calculate appropriate PIs.
Data from the MCA System: Data for the performance indicators P-1, P-1.1, P-2, P-2.1, P-3, and P-4
will be come from the MCA system. The central database is common for all data. Thus, no flow will
take place and these PIs will be determined/calculated as per the logics defined in MIS software.
Data from SCADA: The data for performance indicators A-7, P-18, PC-1, PC-2, PC-3, PC-4, PC-5 and
PC-6 will come from SCADA. This data will enter automatically into the MIS system, which will be
connected to MCA’s central database. The related report will be generated based on the
indicators/parameters.
Data from Survey: To monitor the post-compact indicator PC-5, there will be a need to conduct a
survey. The data from this survey will be entered by the M&E Specialist at MCA with the help of a
web-based window that will be connected to the central database. This web-based system can be
accessed through the internet with the help of an internet browser. The M&E Specialist needs to
access the webpage on his laptop/desktop and login with his user identity and password. The MIS
software installed in the central database will retrieve these data and will determine/calculate PC-5.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 33
5.2 Reporting
For each of the PIs, we have suggested a frequency of measurement: monthly, quarterly, biannually,
and annually. At this stage, we propose to generate only monthly, quarterly, biannual and annual
reports. The PIs to be reported in each of these reports are identified in Table 7. However, the MIS
software is flexible enough to customize any report as per requirements. The requirements of new
types of reports are to be placed with the M&E Specialist. The M&E Specialist will be provided
training to customize the report.
Table 7. Report Generated through Performance Indicators
No. Performance Indicator
Monthly Report
P-1 Value of signed infrastructure feasibility and design contracts (for compact)
P-1.1 Value of signed infrastructure feasibility and design contracts (for project package)
P-2 Present disbursement of power infrastructure feasibility and design contracts (for compact)
P-2.1 Present disbursement of power infrastructure feasibility and design contracts (for project package)
A-1 Percent completion of Environmental and Social Management Systems
A-2 Number of environmental or social problems associated with the project reported and not yet resolved
(for compact)
A.2.1 Number of environmental or social problems associated with the project reported and not yet resolved
(specific project package)
A-3 Number of land transfers effected (for compact)
A-
3.1 Number of land transfers effected (for project package)
P-7 Transmission line upgraded or built (for compact)
P-7.1 Transmission line upgraded or built (for project package)
P-7.2 Number of tower foundations constructed
P-7.3 Number of towers constructed
A-5 Area of land acquired
Quarterly Report
P-3 Value of signed power infrastructure construction contracts
P-4 Present disbursement of power infrastructure construction contracts
P-5 Temporary employment generated by power infrastructure construction
P-8 Transmission throughput capacity added
P-9 Transmission substation capacity added
P-9.1 Length of entry road constructed
P-9.2 Transformers available at site
P-9.3 Breakers and isolators available at site
P-9.4 Switchgear panels available at site
A-4 No. of transmission substations upgraded
A-6 Number of capacity building programs
A-7 Capacity Utilization Factor of a Transmission Line
PC-3 Change in System Average Interruption Duration Index (SAIDI)
PC-4 Change in System Average Interruption Frequency Index (SAIFI)
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 34
Table 7. Report Generated through Performance Indicators
No. Performance Indicator
P-18 Transmission system technical losses (%)
Yearly
PC-1 Increase in Energy Consumed per Unit of Capita
PC-2 Alleviation of Electricity Shortage (load shedding)
PC-5 Percent Households Electrified
PC-6 Increase in power flow (import and export) from neighboring countries.
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 35
6. Resource Requirements
To effectively practice monitoring and evaluation, resources will be needed. The resource
requirement for monitoring and evaluation can be segregated in three broad parts:
1. Manpower
2. Infrastructure
3. Capacity Building.
Manpower: We recommend a team of two full-time persons who will manage the monitoring and
evaluation activities during the entire compact period. They can be recruited in first quarter in which
the compact comes into force.
M&E Specialist: We propose a full-time Monitoring and Evaluation Specialist at the MCA level who
will manage all M&E activities and will be responsible for detailed design, implementation,
coordination with SCADA and operation of the MIS system.
M&E Support: To assist the M&E Specialist with such work as the installation, availability and
operation of a web-based window on the laptop/desk top of the Package Managers. He/she will
follow day-to-day operational guidance to enter data as per requirements and in a timely fashion.
This individual will report directly report to the M&E Specialist. The engagement cost of these two
resources is estimated in the Table 8.
LOE Calculation:
Total man day input in one month – 26 days (considering one day off in a week)
Total man day input in one year – 312 days (26 days*12 months)
Total vacations and holidays in one year – 45 days
Effective man day input in one year – 267 days (312 days – 45 days)
Effective man day input in five years – 1335 days (267 days * 5 years)
Number of Trips:
Quarter 2 (Year 1) –
M&E Specialist – 8 trips (two trips per package)
Assistant M&E Specialist – 12 trips (one trips per package per month)
Total – 20 trips
Quarter 3 (year 1) –
M&E Specialist – 04 trips
Assistant M&E Specialist – 08trips
Total – 12 trips
Rest of the Compact Period
M&E Specialist – 09 trips (one trip per six month)
Assistant M&E Specialist – 18 trips (one trip per quarter)
Total – 27 trips
Detailed Feasibility Studies: Nepal Priority Transmission Projects Volume 6: Monitoring and Evaluation
MCC-15-BPA-0032, MCC-16-CL-0002 March 2017
Page 36
M&E Infrastructure: To monitor the performance indicators, infrastructure will be a critical
component. We propose MIS software that can be developed by any software developers. However,
in order to keep costs low, we suggest using “gold class” subcontractors of big IT firms such as IBM.
They will develop software for the PIs, data flow and measurement architecture specified in the
sections above. This software will be installed in a central database and can be accessed through a
web-based window by MCA Package Managers. The central database will be connected with SCADA
for the flow of required data. The connectivity of SCADA with the central database will be in the
scope of the MIS software development. Here, we have assumed all MCA staff and Package
Manager will be provided with laptop/desk top and internet facility. The cost of this infrastructure is
estimated in Table 8.
Capacity Building: To familiarize the monitoring and evaluation staff, there will be a need for a
capacity building program so that the manpower involved in project execution can effectively
support the M&E activity and can make the best use of it for project progress. We propose to
provide detailed MIS software and operational training to the M&E Specialist and M&E Support. This
training will include changes in PIs and customization of reports and their frequency. One round of
on-site operational training will be provided by the MIS software developer. Subsequently, it will be
provided by the M&E Specialist and his support staff as and when needed.
Miscellaneous Activities: We propose that 10% of the estimated budget be dedicated as additional
funds for miscellaneous activities.
The estimated cost of the Monitoring and Evaluation Components is shown in Table 8.
Table 8. M&E Budget
Sl. No. Name of the Component No of Units Unit Cost (USD) Total Cost
(USD)
Manpower
1 M&E Specialist 1335 320 USD/day 337,920
2 M&E Support 1335 200 USD/day 267,000
3 Travel Cost 59 200 USD/trip 11,800
Infrastructure
4 MIS Software Development 1 25,000 25,000
7 O&M Annual charge 4 1,250 5,000
Capacity Building
9 Capacity Building Lump sum 5,000 5,000
Estimated Cost 651,720
10 Miscellaneous 5% - 32,586
M&E Cost 684,306
1320 North Courthouse Road, Suite 600 Arlington, VA 22201
Tel 703.387.2100, Fax 703.243.0953
For Information/Clarifications David Keith – [email protected] – +1-7033802582
Rakesh Kumar Goyal – [email protected] – +91-9871055119