DETAILED ESTIMATE
Project:-
Proposed Construction of Assam Type Building of Cane and Bamboo Cluster Nonipara, Selsella, West Garo Hills, Meghalaya.
(As per the Schedule of Rates PWD Building for the Year 2015-16)
ITEM NO
ITEM DESCRIPTION
Unit Nos. MEASUREMENT
Quantity Rate Amount Length Breadth Depth
1/1.1 Earthwork in excavation upto a depth of 2m below the existing ground level for foundation trenches of foundations, footing of column / walls, retaining walls, septic tank etc. including bailing out water where necessary and removal of surplus earth with all lead and lifts as directed and specified for the following classification of soils.
(a) In ordinary soil
Isolated footing -F1
Cu.m 1 x 14 x 0.750 x 0.750 x
1.000 = 7.875
Plinth Wall trenches
Cu.m 1 x 8 x 3.600 x 0.500 x
0.450 = 6.480
G/Total Quantity Cu.m = 14.355
/ m3 =
2/4.1 Providing brick soling in foundation and under floor with stone/best quality picked jhama brick, sand packed and laid to level and in panel after preparing the subgrade as directed including all labour and materials and if necessary dewatering, complete.
(c) Stone soling of thickness 100mm
Isolated footing
F1 Sq.m 1 x 14 x 0.750 x 0.750 = 7.875
Sq.m 1 x 1 x 16.000 x 12.000 = 192.000
G/Total Quantity Sq.m = 199.875
/ m2 =
3/2.1 Plain cement concrete works with coarse aggregate of sizes 13mm to 32mm in foundation bed for footing steps, walls, brick work etc, as directed and specified including dewatering if necessary, and curing complete (shuttering where necessary shall be measured and paid separately.
(a) In prop. 1:3:6 (1
cement:3 coarse
sand:6 coarse agg.
By volumn (using
mixture machine)
Isolated Footing - F1
Cu.m 1 x 14 x 0.750 x 0.750 x
0.100 = 0.788
Plinth wall trenches
Cu.m 1 x 8 x 3.600 x 0.500 x
0.100 = 1.440
G/Total Quantity Cu.m = 2.228
/ m3 =
4/ 2.8
Supplying, fitting and fixing in position reinforcement bars upto 1st floor level, conforming to relevent I.S. Code for RCC work.RB walling including straightening, cleaning, cutting and bending to proper shapes and length as per details, supplying and binding with 20G annealed black wire and placing in position with proper blocks, supports, chairs, spacers etc complete. (Rates inclusive of all wastage, lappage, hooks, chairs, anchorage etc and no measurements for the same is required)
(a) (i) TMT Corrosion resistant steel
Isolated Footing F1 10mm dia @100mm c/c bothways
Kg 14
x 16 x 0.750 x 0.620 = 104.160
Columns upto Plinth tie top
C1 12 mm dia Kg 14 x 4 x 2.100 x 0.890 = 104.664
Stirrups 8 mm dia Kg 14 x 10 x 0.750 x 0.390 = 40.950
Plinth tie 10 mm dia Kg 2 x 4 x 16.000 x 0.620 = 79.360
Extra bottom bar 10 mm dia Kg 2 x 4 x 12.000 x 0.620 = 59.520
Stirrups 8 mm dia Kg 2 x 100 x 0.900 x 0.390 = 70.200
Stirrups 8 mm dia Kg 2 x 80 x 0.900 x 0.390 = 56.160
Lintel 10 mm dia Kg 2 x 100 x 0.900 x 0.620 = 111.600
Kg 2 x 80 x 0.900 x 0.620 = 89.280
Stirrups 8 mm dia Kg 2 x 100 x 0.900 x 0.390 = 70.200
Stirrups 8 mm dia Kg 2 x 80 x 0.900 x 0.390 = 56.160
Post plate tie 10 mm dia Kg 2 x 100 x 0.900 x 0.620 = 111.600
Kg 2 x 80 x 0.900 x 0.620 = 89.280
Stirrups 8 mm dia Kg 2 x 100 x 0.900 x 0.390 = 70.200
Stirrups 8 mm dia Kg 2 x 80 x 0.900 x 0.390 = 56.160
Column - upto First floor level
C1 - 12 mm dia Kg
14 x 4 x 3.600 x 0.890 = 179.424
Stirrups 8 mm dia Kg 14 x 24 x 0.750 x 0.390 = 98.280
G/Total Quantity Kg = 1447.198
Total
Quantity Qtl = 14.472
/ Qtl =
5/2.10 Providing formwork of ordinary timber planking of thickness not less than 25mm and removal of the same for concrete members so as to give a rough finish including centering, shuttering, strutting and propping etc. for height of propping and centering of supporting floor to the soffit of the concrete member not exceeding 4.0 M as specified for the following items:
(a) Foundation, footings, bases of columns, pile cap, raft and mess concrete works etc.
Isolated footings - F1
Sq.m
1
4 x 4 x 0.75 x 0.10 = 4.200
Sq.m
1
4 x 4
x 0.75
x 0.20
= 8.400
Column upto plinth level - C1
Sq.m
1
4 x 4 x 0.20 x 0.05 = 0.560
G/Total Quantity Sq.m
= 13.160
/ m2 =
(b) Sides of tie beams, grade beams etc. at or below ground level requiring formwork at sides only.
Plinth beam Sq.m 1 x 2 x 15.00 x 0.20 = 6.000
Plinth beam Sq.m 1 x 2 x 11.20 x 0.20 = 4.480
G/Total Quantity Sq.m = 10.480
/ m2 =
(c) Columns, pillars, posts, struts, etc.
(i) Square, Rectangualr, etc.
(0.20 x 0.20) - C1 Sq.m
14 x 4 x 0.20 x 3.60 = 40.320
G/Total Quantity Sq.m = 40.320
/ m2 =
(d) Sides and soffits of beams haunchings lintels, cantilevel etc.
(i) For depth not exceeding 1.0m.
Lintel Sq.m 2 x 2 x 15.00 x 0.15 = 9.000
Lintel Sq.m 2 x 2 x 11.20 x 0.15 = 6.720
Post plate tie Sq.m 2 x 2 x 15.00 x 0.15 = 9.000
2 x 2 x 11.20 x 0.15 = 6.720
G/Total Quantity Sq.m = 31.440
/ m2 =
6/2.5.1
In Foundation and sub-structure including footing, columns with base, tie and plinth beam, pile cap, raft slab, base slab, RCC walls, retaining walls, walls of septic tank, inspection pit and the like and other works not less than 100mm thick up to plinth level
( b) M20 or Prop. 1:1.5:3
Isolated footings - F1
Cu.m
14
x 1 x 0.750 x 0.750 x 0.20
0 = 1.575
Trapezoidal portion
Cu.m
14
x 1 x (0.75x0.75)/2+(0.20x0.20)/2 x 0.20
0 = 0.844
Columns upto plinth level
(0.20 x 0.20) Cu.m 1 x 14 x 0.200 x 0.200 x
1.050 = 0.588
Plinth beam Cu.m 1 x 2 x 15.000 x 0.250 x
0.200 = 1.500
Plinth beam Cu.m 1 x 2 x 11.200 x 0.250 x
0.200 = 1.120
G/Total Quantity Cu.m = 5.627
/ m3 =
7/4.3 Brick work in cement mortar with 1st class brick including racking out joists and curing complete in sub-structure upto plinth level etc.
(c) In prop. 1:5
Plinth Wall
Cu.m
14 x 1 x 3.600 x 0.250 x
0.450 = 5.670
G/Total Quantity Cu.m = 5.670
/ m3 =
8/1.4.1
Earth work in filling in plinth laying not exceeding 150 mm thick
(a) With earth/stone dust obtained by carriage up to 8 Km.
Floor:
Cu.m 1 x 1 x 16.000 x 12.000 x
0.450 = 86.400
G/Total Quantity Cu.m = 86.400
/ m3 =
9/3.4 65 mm thick cement concrete floor consisting of 50 mm under layer of cement concrete in prop. 1:3:6 and 15 mm thick wearing layer in cement concrete in prop. 1:1:2 laid in panels and finished with a floating coat of neat cement finish i/c curing etc. complete as directed.
Floor:
Sq.m 1 x 1 x 16.000 x 12.000 = 192.000
G/Total Quantity Sq.m = 192.000
/ m2 =
10/2.5.3 In columns, pillars, post, struts, suspended floor, landing shelf and support, balcony, etc.
(b) M20 or Prop. 1:1.5:3
Columns upto floor level
Column C1 Cu.m
1 x 14 x 0.200 x 0.200 x 3.60
0 = 2.016
Floor Beam:
Lintel Cu.m
1 x 2 x 15.000 x 0.125 x 0.12
5 = 0.469
Lintel Cu.m
1 x 2 x 11.200 x 0.125 x 0.12
5 = 0.350
Post plate tie Cu.m
1 x 2 x 15.000 x 0.150 x 0.15
0 = 0.675
Post plate tie Cu.m
1 x 2 x 11.200 x 0.150 x 0.15
0 = 0.504
G/Total Quantity Cu.m
= 4.014
/ m3 =
11/4.4 Brick work in cement mortar with 1st class brick including racking out joists and curing complete in sper-structure above plinth level upto 1st floor level etc.
(c) In prop 1:5
Sq.m
1 x 14 x 3.800 x 3.60 = 191.520
Sq.m
2 x 1/2 x 12.000 x 2.50 = 30.000
Deduct D & W Openings (-)
D1 Sq.m
-1 x 1 x 1.400 x 2.10 = -2.940
D2 Sq.m
-1 x 1 x 1.000 x 2.10 = -2.100
D3 Sq.m
-1 x 3 x 0.800 x 2.10 = -5.040
W Sq.m
-1 x 21 x 1.200 x 1.30 = -32.760
V Sq.m
-1 x 3 x 0.600 x 0.45 = -0.810
G/Total Quantity Sq.m
= 177.870
G/Total Quantity Cu.m
177.87
0 x 0.125 = 22.234
/ m3 =
12/5.2 15 mm thick cement plaster in single coat on rough side of single half brick wall for interior plastering upto 1st floor level etc.
(c) In C.M. 1:5
Sq.m
2 x 1 x 16.000 x 3.60 = 115.200
Sq.m
2 x 1 x 12.000 x 3.60 = 86.400
Sq.m
2 x 1/2 x 12.000 x 2.50 = 30.000
Deduct D & W Openings (-)
D1 Sq.m
-1 x 1 x 1.400 x 2.10 = -2.940
W Sq.m
-1 x 21 x 1.200 x 1.30 = -32.760
V Sq.m
-1 x 3 x 0.600 x 0.45 = -0.810
Plinth Wall Sq.m
1 x 2 x 16.200 x 0.45 = 14.580
Sq.m
1 x 2 x 12.200 x 0.45 = 10.980
G/Total Quantity Sq.m
= 220.650
/ m2 =
13/3.3 40mm thick cement concrete floor consisting of 25 mm under layer of c.c. In prop. 1:3:6 and 15 mm thick wearing layer in c.c. In prop. 1:1:2 finished with a floating coat of neat cement finish using cement slurry for bond @ 2.75 kg. Per square metre of floor area, wearing layer is to be laid in panels i/c curing etc. complete as directed.
Sq.m
1 x 1 x 16.000 x 12.00 = 192.000
G/Total Quantity Sq.m
= 192.000
/ m2 =
14/8.2
Providing wood work in frame (chowkats) of doors, winodws, c/windows and other similar work etc.
(a) Salwood
D1 M 1 x (
2.10 x 2 ) +
1.40 )=
5.60
D2 M 1 x (
2.10 x 2 ) +
1.00 )=
5.20
D3 M 1 x (
2.10 x 2 ) +
0.80 )=
5.00
Total Quantity = 15.80
G/Total Quantity Cu.m
15.8
0 x 0.08 x 0.100 = 0.1264
/ m3 =
15/8.19
Providing, fitting and fixing full panelled doors/windows including oxidised M.S. butt hinges etc.
(a) With teak wood/Sissu wood (i) 35 mm thick
D1 Sq.m
1 x 1 x 1.40 x 2.10 = 2.940
D2 Sq.m
1 x 1 x 1.00 x 2.10 = 2.100
D3 Sq.m
1 x 1 x 0.80 x 2.10 = 1.680
G/Total Quantity Sq.m
= 6.720
/ m2 =
16/3.43
Providing Antiskid Tiles of approved quality size shape not less than 8 mm on floor skirting etc.
3.43.1 Ceramic Antiskid range.
(b) Premium Range
W.C. Sq.m
1 x 1 x 1.50 x 1.50 = 2.250
W.C. Sq.m
1 x 1 x 1.20 x 1.50 = 1.800
W.C. Sq.m
1 x 1 x 1.30 x 1.50 = 1.950
Skirting Sq.m
1 x 2 ( 1.50 + 1.500 ) x
0.20 = 1.200
Skirting Sq.m
1 x 2 ( 1.20 + 1.500 ) x
0.20 = 1.080
Skirting Sq.m
1 x 2 ( 1.30 + 1.500 ) x
0.20 = 1.120
Deduct Doors Openings (-)
D3 Sq.m
1 x 3 x 0.80 x 0.20 = -0.480
G/Total Quantity Sq.m
= 8.920
/ m2 =
17/3.26
Providing polished ceramic walls tiles of Somany/Rrient/Nitco etc.
3.26.1 Exectuvie Range - 1 (Size
200 mm x 300 mm above)
(b) Premium Range
WC Sq.m
1 x 2 ( 1.50 + 1.500 ) x
1.00 = 6.000
WC Sq.m
1 x 2 ( 1.20 + 1.500 ) x
1.00 = 5.400
WC Sq.m
1 x 2 ( 1.30 + 1.500 ) x
1.00 = 5.600
Deduct Doors Openings (-)
D3 Sq.m
1 x 3 x 0.80 x 2.10 = -5.040
G/Total Quantity Sq.m
= 11.960
/ m2 =
18/15.61 Applying priming coat over new wood and wood based/surfaces over 100 mm in girth/width etc.
(a) With ready mixed paint, wood primer (Pink/White)
D1 Sq.m
1 x 1.40 x 2.10 x 2.60 = 7.644
D2 Sq.m
1 x 1.00 x 2.10 x 2.60 = 5.460
D3 Sq.m
3 x 0.80 x 2.10 x 2.60 = 13.104
G/Total Quantity Sq.m
= 26.208
/ m2 =
19/15.63 Painting two coats (excluding/priming coat) on new wood and wood based surface with enamel paint of approved brand and manufacture (Asian Paint/Berger Paint etc.)
G/Total Quantity Sq.m
Qty. B.F. Item No. 18/15.61
= 26.208
/ m2 =
20/15.18 Distempering with dry distemper of approved brand and manufacture (two coats) and of required shade on new wall surface to give an even shade, over and after thoroughly brushing the surface free from mortar droppings and other foreign matter and i/c preparing surface even and sand papered smooth.
Interior Wall
Sq.m
1 x 2 ( 16.0
0 + 12.000
) x
3.60 = 201.600
WC Sq.m
1 x 2 ( 1.50 + 1.500 ) x
3.60 = 21.600
WC Sq.m
1 x 2 ( 1.20 + 1.500 ) x
3.60 = 19.440
WC Sq.m
1 x 2 ( 1.30 + 1.500 ) x
3.60 = 20.160
Deduct D & W Openings (-)
D1 Sq.m
-1 x 1 x 1.400 x 2.10 = -2.940
D2 Sq.m
-1 x 1 x 1.000 x 2.10 = -2.100
D2 Sq.m
-1 x 3 x 0.800 x 2.10 = -5.040
W Sq.m
-1 x 21 x 1.200 x 1.30 = -32.760
V Sq.m
-1 x 3 x 0.600 x 0.45 = -0.810
G/Total Quantity Sq.m
= 219.150
/ m2 =
21/15.28 Applying one coat of cement primer of approved brand and manufacture on new wall surface after thoroughly brooming the surfaces free from mortar droppings and other foreign matter and i/c preparing the surface even and sand papered smooth.
Exterior Wall
Sq.m
1 x 1 x 16.00 x 3.60 = 57.600
Sq.m
1 x 1 x 12.00 x 3.60 = 43.200
Sq.m
2 x 1/2 x 12.00 x 2.50 = 30.000
Sq.m
1 x 1 x 6.90 x 3.60 = 24.840
Sq.m
1 x 1 x 6.30 x 3.60 = 22.680
Deduct D & W Openings (-)
D1 Sq.m
-1 x 1 x 1.400 x 2.10 = -2.940
W Sq.m
-1 x 21 x 1.200 x 1.30 = -32.760
V Sq.m
-1 x 3 x 0.600 x 0.45 = -0.810
G/Total Quantity Sq.m
= 141.810
/ m2 =
22/15.29 Finishing wall with water proofing cement paint of approved brand and manufacture and of required shade on new wall etc.
G/Total Quantity Sq.m
Qty. B.F. Item No. 21/15.28
= 141.810
/ m2 =
23/11.1 Providing, fitting and fixing steel windows/ventilators (openable) of standard rolled steel sections as per relevant I.S Code-1038 joints mitred and welded with 15mm x 3mmx100mm lugs embedded in cement concrete block of M-10 grade i/c providing and fixing of projecting hinges etc.
W Sq.m
1 x 21 x 1.20 x 1.30 = 32.760
V Sq.m
1 x 3 x 0.60 x 0.45 = 0.810
G/Total Quantity Sq.m
= 33.570
/ m2 =
24/15.69 Painting two coats (excluding/priming coat) on new steel with enamel paint of approved brand and manufacture (Asian paint/Berger paint/ICI paint etc)
(a) Surfaces over 100mm in width or girth
(i) General purpose (Asian paint/Berger paint etc.)
G/Total Quantity Sq.m
Qty. B.F. Item No. 24/11.1
= 33.570
/ m2 =
25/17.4 Providing fitting, fixing and fixing of roof trusses i/c fabricated using iron hollow section conforming to relevant I.C code as per approved design and drawings i/c providing M.S. Cleats, base plates, bolts and nuts and one coat of red oxide zinc chormate primer and two coats of approved anemel paints complete i/c fitting necessary cleats etc. for fixing ceiling joist as per design and drawings as directed.
Using TATA make Circuler Hollow section of Grade YST-310 conforming to IS Specification : 1161-1998
Collar Tie 60.30 mm x 4.50 mm (Heavy)
Kg 1 x 5 x 12.00 x 6.17 x = 370.200
Principal Rafter Kg 2 x 5 x 7.00 x 6.17 x = 431.900
King Post Kg 1 x 5 x 2.50 x 6.17 x = 77.125
Strut 42.40 mm x 4.05 mm (Heavy)
Kg 2 x 5 x 2.50 x 3.84 x = 96.000
Kg 2 x 5 x 1.70 x 3.84 x = 65.280
Kg 2 x 5 x 1.90 x 3.84 x = 72.960
Kg 2 x 5 x 1.10 x 3.84 x = 42.240
Kg 2 x 5 x 0.70 x 3.84 x = 26.880
Kg 2 x 5 x 0.80 x 3.84 x = 30.720
Kg 2 x 5 x 0.50 x 3.84 x = 19.200
Kg 2 x 5 x 0.30 x 3.60 x = 10.800
Purlin 48.30mm x 4.05mm (Heavy)
Kg 2 x 6 x 17.00 x 4.43 x = 903.720
G/Total Quantity Kg = 2147.02
5
Qtl = 21.470
/ Qtl =
26/7.35 Providing pre-painted galvanised Iron sheet roofing (PPGI) (Dyna Roof/Shathyam etc).
(e) 60 mm thick
Sq.m
1 x 2 x 17.00 x 7.00 = 238.000
G/Total Quantity Sq.m
= 238.000
/ m2 =
G/Total Amount
Add 8.5% Electrification on Total Amount
Add 7.5% Sanitary Installation and Water Supply on Total Amount
N/Total Amount
SAY
(Rupees ………………………………………………………………………………….) only.