design standard ds 62-01 - watercorporation.com.au · consultant in the detailed design, the design...
TRANSCRIPT
Uncontrolled if Printed
Ver 1 Rev1
Page 1 of 57
© Copyright Water Corporation 2004 -2016
Assets Delivery Group Infrastructure Design Branch
DESIGN STANDARD DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation,
Commissioning and Maintenance Specifications)
VERSION 1
REVISION 1
MARCH 2016
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 2 of 57
© Copyright Water Corporation 2004 -2016
FOREWORD
This publication is the revised version Water Corporation’s standard for Public Safety, Security and
Emergency treatments. The Standard explains the Corporation’s requirements for the Standard for site
security treatments Guidelines for selection, type drawings, installation, commissioning and maintenance
specifications
The Standard has been prepared to achieve uniformity in the above procedures and is intended for use by
officers of the Corporation, Design Engineers and Contract Superintendents.
The Standard is intended for the design of security treatments for Water Corporation assets.
Compilation of the Standard was carried out by the Infrastructure Design Branch assisted by members of
external security and engineering consultants.
It is important to note that Design Managers are required to obtain the site security, fire and public safety
functional scope (the functional scope) for all capital and design projects. The assessment from the “Security
Functional Scope” will determine the level of external consultancy services required in the project. And the
most efficient purchasing and delivery processes. For assets listed as Category A or B from a critical
infrastructure security perspective, the functional scope will be used as the basis for the engaged Water
Corporation approved consultants for detailed design. For assets listed as Category C or lower, the
functional scope can often be used as detailed specifications and directly handed to one of the Water
Corporation approved installers. The assessment shall be approved by the Water Corporation Security
Program Manager with a signed functional scope. If the outcome of the assessment is to engage an external
consultant in the detailed design, the design and specification shall be reviewed and assessed by the Security
Program Manager for acceptance.
The Water Corporation’s centre of expertise for security related issues is the Security Program Manager,
Steve MacCarthy. Steve shall be contacted in the first instance. Steve MacCarthy can be contacted at
[email protected] or on (08) 9420 3879 or 0427 195 536, fax (08) 9420 2656.
Revisions and additions will be made on a needs basis and details will be forwarded to Standard holders as
they occur.
Manager, Infrastructure Design Branch
This document is prepared without the assumption of a duty of care by the Water Corporation. The document is not
intended to be nor should it be relied on as a substitute for professional engineering design expertise or any other
professional advice.
It is the responsibility of the user to ensure they are using the current version of this document.
© Copyright – Water Corporation: This standard and software is copyright. With the exception of use permitted by the
Copyright Act 1968, no part may be reproduced without the written permission of the Water Corporation.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 3 of 57
© Copyright Water Corporation 2004 -2016
DISCLAIMER
This Standard is intended solely for application to the acquisition of water infrastructure in Operating Areas in
Western Australia where the Water Corporation has been licensed to provide water services subject to the terms
and conditions of its Operating License.
This Standard is provided for use only by a suitably qualified professional design engineer and a Water Corporation
approved, WA Police licensed, security consultant who shall apply the skill, knowledge and experience necessary
to understand the risks involved and undertake all infrastructure design and installation specification preparation
work.
Any interpretation of anything in this Standard that deviates from the requirements specified in the project design
drawings and construction specifications shall be resolved by reference to and determination by the design
engineer.
The Corporation accepts no liability for any loss or damage that arises from anything in the Standard including loss
or damage that may arise due to the errors and omissions of any person.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 4 of 57
© Copyright Water Corporation 2004 -2016
REVISION STATUS
The revision status of this standard is shown section by section below:
REVISION STATUS
SECT. VER/
REV
DATE PAGES
REVISED
REVISION DESCRIPTION
(Section, Clause, Sub-Clause)
PREPD/
RVWD
RVWD APPRVD
All 1/0 29.10.04 All Original (First) Version PF JD
All 1/1 11.03.16 All Restructured and rearranged with new
contents
SM ZR SB
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 5 of 57
© Copyright Water Corporation 2004 -2016
DESIGN STANDARD DS 62-01 Site Security Treatment
(Includes Guidelines for Selection, Type Drawings, Installation,
Commissioning and Maintenance Specification)
CONTENTS Section Page
1. PREFACE ...................................................................................................................................... 9
1.1 DEFINITION ............................................................................................................................... 9
1.2 Abbreviations ............................................................................................................................. 13
2 INTRODUCTION ....................................................................................................................... 14
2.1 Criteria ........................................................................................................................................ 14
2.2 Scope ............................................................................................................................................ 14
2.3 Purpose ........................................................................................................................................ 14
2.4 Drawing ....................................................................................................................................... 14
2.5 Manufacturers and Brand Names ............................................................................................ 14
2.6 Design Standards ........................................................................................................................ 14
2.7 Installation Standards ................................................................................................................ 14
2.8 Access to Existing Asset Systems .............................................................................................. 14
2.9 Security Categories .................................................................................................................... 14
3 LEGISLATION ........................................................................................................................... 16
3.1 Statutory legislation ................................................................................................................... 16
3.2 Guidelines ................................................................................................................................... 16 3.2.1 Federal Guidelines ....................................................................................................................... 16 3.2.2 State Guidelines ........................................................................................................................... 16
3.3 Standards .................................................................................................................................... 17 3.3.1 Australian Standards .................................................................................................................... 17 3.3.2 International Standards ................................................................................................................ 20 3.3.3 Other Standards, Specifications and Guidelines .......................................................................... 20
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 6 of 57
© Copyright Water Corporation 2004 -2016
4 SUBMISSION REQUIREMENTS FOR DESIGN ENGINEERS .......................................... 22
4.1 General ........................................................................................................................................ 22
4.2 Licenses & Insurances ............................................................................................................... 22
4.3 Quality Assurance ...................................................................................................................... 22
5 SITE FUNCTIONAL SCOPE ................................................................................................... 23
5.1 Definition..................................................................................................................................... 23
5.2 Scope ............................................................................................................................................ 23
5.3 Process and design and procurement processes ...................................................................... 23
6 SECURITY TREATMENTS CRITERIA ................................................................................ 24
6.1 Introduction ................................................................................................................................ 24
6.2 Selection of Security Treatments .............................................................................................. 24
6.3 Security Design Considerations ................................................................................................ 24 6.3.1 Security Protective Profile ........................................................................................................... 24 6.3.2 Security Design Concepts ............................................................................................................ 25 6.3.3 Risk Management ........................................................................................................................ 25 6.3.4 Security Treatments ..................................................................................................................... 25
6.4 Situational & Environmental Design Considerations ............................................................. 26
6.5 Water Corporations Public Safety & Security Aesthetics Policy – General Design Requirements
……………………………………………………………………………………………………26
6.6 Occupational Safety & Health, and Public Liability .............................................................. 27
7 INSTALLATION REQUIREMENTS ...................................................................................... 28
7.1 General ........................................................................................................................................ 28
7.2 Plans, drawings, approvals, certificates & licenses ................................................................. 28 7.2.1 Plans & Drawings ........................................................................................................................ 28 7.2.2 Approvals ..................................................................................................................................... 28 7.2.3 Manufacturers and Statutory Authority ....................................................................................... 28 7.2.4 Licenses ........................................................................................................................................ 29 7.2.5 Fire Doors .................................................................................................................................... 29
7.3 Works & Inspections ................................................................................................................. 29
7.4 Excavations and Installations.................................................................................................... 29 7.4.1 Damage ........................................................................................................................................ 30
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 7 of 57
© Copyright Water Corporation 2004 -2016
7.5 Submissions................................................................................................................................. 30
8 COMMISSIONING REQUIREMENTS .................................................................................. 31
8.1 Commissioning ........................................................................................................................... 31
8.2 Testing requirements (Physical & Mechanical) ...................................................................... 31
8.3 Testing requirements (Electrical) ............................................................................................. 31
8.4 Testing Format ........................................................................................................................... 31
8.5 Pre-commissioning ..................................................................................................................... 32
8.6 Continuous testing ...................................................................................................................... 32
8.7 Commissioning testing ............................................................................................................... 32
9 TESTING DURING COMMISSIONING ................................................................................ 33
9.1 Electronic Systems ..................................................................................................................... 33
9.2 Intruder Alarm and Access Control System ........................................................................... 33 9.2.1 Alarm Panel.................................................................................................................................. 33 9.2.2 Detection Devices ........................................................................................................................ 33
9.3 As Installed Drawings and Manuals ......................................................................................... 34
9.4 Operating and Maintenance Instructions ................................................................................ 34
9.5 Training....................................................................................................................................... 34 9.5.1 Operators Course .......................................................................................................................... 34
9.6 Environmental Testing .............................................................................................................. 34
9.7 Certificates .................................................................................................................................. 34
10 MAINTENANCE REQUIREMENTS ...................................................................................... 35
10.1 General ........................................................................................................................................ 35
10.2 Maintenance requirements ........................................................................................................ 35
10.3 Maintenance inspections ............................................................................................................ 35 10.3.1 Frequency ..................................................................................................................................... 36 10.3.2 Warranty Period ........................................................................................................................... 36 10.3.3 Maintenance during Defects Liability Period .............................................................................. 36 10.3.4 Callouts during Defects Liability Period ...................................................................................... 36
10.4 Long Term Monitoring and Maintenance ............................................................................... 37
10.5 Completion .................................................................................................................................. 37
10.6 Maintenance Service & Contract ............................................................................................. 37
10.7 Spare Parts (Recommended) ..................................................................................................... 37
10.8 Spare Parts (Maintenance) ........................................................................................................ 37
11 DOCUMENTATION AND TRAINING REQUIREMENTS ................................................. 38
11.1 Format ......................................................................................................................................... 38
11.2 Standard Documentation .......................................................................................................... 38 11.2.1 Electronic ..................................................................................................................................... 38 11.2.2 Physical/Structural ....................................................................................................................... 38
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 8 of 57
© Copyright Water Corporation 2004 -2016
11.3 Review Procedure for Customised Documents ....................................................................... 39
11.4 Training....................................................................................................................................... 39
ANNEXURE-1: DRAWINGS........................................................................................................................ 40
Introduction .................................................................................................................................................... 40
General Drawing Requirements .................................................................................................................... 40
Example Drawings .......................................................................................................................................... 41
APPENDIX 1- EXTERNAL ADVICE AND STORAGE PROTOCOLS FOR DS 62 ............................. 42
APPENDIX 2 - INTERNAL ADVICE REGARDING SECURITY MATTERS ..................................... 44
APPENDIX 3 - INDICATIVE ASSET SECURITY CATEGORISATION AND SECURITY TREATMENT
SCHEDULES .................................................................................................................................................. 45
APPENDIX 4 - WATER CORPORATION SECURITY PANEL LIST ................................................... 51
APPENDIX 5 – STATUTORY DECLARATION PROFORMA .............................................................. 52
APPENDIX 6 – DS 62 EXTERNAL STORAGE DECLARATION .......................................................... 53
APPENDIX 7 - EXAMPLE OF SECURITY FUNCTIONAL SPECIFICATION ................................... 54
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 9 of 57
© Copyright Water Corporation 2004 -2016
1. PREFACE
1.1 DEFINITION
In this Standard the following words and expressions shall have the following meanings assigned to
them. These meanings do not necessarily comply with the meanings given in the Water Corporation
Act and other Water Corporation publications.
Access Point
Any opening or accessible opening in the perimeter of a site, building, structure or cabinet. All access
points are to be considered and assessed for security and safety treatments.
Alarm (Security)
A signal generated usually by electronic or mechanical means which alerts personnel onsite and/or
offsite or sequential systems that a specific prescribed/designated condition has occurred. The signal
transmitted offsite may be received by either a Licensed Police approved and graded (Grade One)
security monitoring station or a Water Corporation control room.
Asset Owner
The designated individual or section responsible for the operation of the specified Asset.
Commissioning
Commissioning is defined as the process of planning, testing, proving and finally verification that an
asset or asset system functions and performs in accordance with specified requirements.
The Commissioning process starts by production of a plan in the project activation stage and is
normally completed by Project Practical Completion (PPC).
Control Panel
The central operating hardware and software interphase for an access control/security or fire systems.
The control panel requires a high level of protection.
Corporation
Either:
The body corporate known as the Water Corporation of Western Australia, or
A representative nominated by the Water Corporation acting on behalf of the Water Corporation.
Completion Certificate
The single document provided and signed by a Licensed Security Contractor at successful
commissioning designating the manufacturing, construction and installation standards and other
related matters as required by the Corporation relating to the security equipment.
Contract
The agreement between the Contractor and the Corporation for the execution of works.
Contractor
The person or organization bound to execute the works under a contract.
Contract Superintendent
The person appointed by the Superintendent to administer the Contract.
Country Area
The area of the State of Western Australia located outside of the Water Corporation’s Perth Region.
Detector
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 10 of 57
© Copyright Water Corporation 2004 -2016
An item of electronic hardware which transmits designated signals (Fire or movement) under specified
environmental conditions to a Control Panel. Detectors must be specified to ensure compatibility with
the local environmental and operational conditions.
Developer
The person or organization that has made an agreement with the Corporation to provide asset
infrastructure.
Direct Dialler
Communications equipment from an intruder alarm or similar systems which uses a telephone line to
communicate to a central monitoring station.
Engineer
A person qualified to be a Chartered Professional Engineer, and who has appropriate experience.
Engineering Firm
An organization which has in its employment an Engineer.
Design Engineer
The Engineer or engineering firm appointed by the Corporation or Developer to prepare an asset
design system for submission to the Corporation.
Example Drawing
A generic drawing prepared by the Corporation. The drawing provides the minimum requirements to
which Design Engineers shall comply.
Integrate
The conceptual and physical linkage between the planning aspects of protective monitoring systems.
E.g.; Fire systems linked to intruder alarm systems and linked to access control systems, with common
interphase and signalling under prescribed conditions.
License
An approved professional practice certificate provided by an appropriate regulatory agency required
by a contractor or consultant prior to specifying, planning, providing or installing electrical, security,
communications or other related systems components. E.g.
Security Agents License (WA Police)
Security Consultants Licence (WA Police)
Security Installers License (WA Police )
Electrical contractors licence
Austel cablers licence (Communications connections)
Documentary evidence of the currency and appropriateness of the license must be physically
sighted prior to any design guidance and/or works approvals being provided.
Lumen
A measurement of light output from a lamp, often called a tube or a bulb. All lamps are rated in
lumens. For example, a 100-watt incandescent lamp produces about 1750 lumens.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 11 of 57
© Copyright Water Corporation 2004 -2016
Master Locksmith
A member of the Master Locksmiths association and a WA Police Service licensed installer of locks.
Only Water Corporation approved Master Locksmiths shall be used.
Metropolitan Area
The area encompassed by the boundary of the Perth Metropolitan Region Planning Scheme.
Monitoring Station
An accredited, WA Police, Licensed security monitoring station. Only Grade 1 Western Australia
based security monitoring stations shall be used.
Public Access Area
The area outside the designated secure area and normally outside the fenced area.
Alarm Response
The type and timeframe of physical response to a nominated site to enable an informed management
decision in response to an alarm or other alert.
Secure Area
The designated area, within the identified perimeter or asset/site boundary required to be secured using
the integrated deterrence and detection systems. The systems, processes and procedures considered for
the site shall be focused on protection of this area with deterrence and delay measures considered as
priority items, balanced against the ability to appropriately respond to identified perimeter and internal
breaches.
Security
Where the word security is used in this document to describe treatments to Water Corporation assets it
implies treatments for the purpose of loss prevention, public safety, site security, asset safety, fire and
emergency management and business continuity.
Security Agent
A WA Police licensed individual who is the representative of an organisation which provides
commercial security services. All security companies and organisations providing security works and
advice to the Water Corporation shall be licensed, and shall provide their complete licensing
documentation for verification.
Security Consultant
A WA Police licensed individual who provides security advice. All security companies and
organizations providing security works to the Water Corporation shall provide their licensing
documentation for verification, and individuals providing advice shall be individually licensed and
shall provide their individual documentation for verification.
Security Installer
A WA Police licensed individual who provides security installation services. The licenses shall be
appropriately endorsed with the class of work to be provided (i.e.: electrical, alarms, safes, locks etc.)
All security companies and organisations providing security works to the Water Corporation shall
provide their licensing documentation for verification.
Security Officer
A WA Police licensed individual who provides security guarding, patrol and alarm response services.
The licenses shall be appropriately endorsed with the class of work to be provided (i.e.: security
officer) All security companies and organisations providing security works to the Water Corporation
shall provide their licensing documentation for verification.
Security treatments – Interim
Security treatments installed by the Corporation in lieu of other works.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 12 of 57
© Copyright Water Corporation 2004 -2016
Security treatments – Permanent
Security treatments which when installed will form an integral component of the ultimate asset
infrastructure.
Security treatments – Temporary
Security treatments which when installed will not form an integral component of the ultimate asset
infrastructure, and may be considered during construction periods or following emergency events.
Shall
A mandatory requirement. The requirement can only be varied with Corporation approval.
Should
A requirement to be adopted unless circumstances justify a variation.
Standard Drawing
A drawing prepared by the Corporation to cover items which are similar on all security treatments of
the same type. It is intended to reduce the amount of work involved in the preparation of drawings but
some additions may be required before submission.
Standards
Australian and international standards as prescribed and published by Standards Australia and other
appropriate organisations
Sub-Contractor
A person engaged by a Contractor to execute part of the works.
Supervisor
The person employed by the Contractor to be responsible for the supervision of the works.
The Corporation prefers a person whose qualifications are acceptable for graduate membership of the
Institution of Engineers, Australia.
A person with extensive supervisory experience in security installations may be acceptable as the
supervisor, alternately a specialist WA Police licensed security consultant will be required to manage
the security components of the project.
Surveyor
An Engineering Surveyor eligible for membership of the Institute of Mining and Engineering
Surveyors, or a Licensed Surveyor eligible for membership of the Institution of Surveyors Australia.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 13 of 57
© Copyright Water Corporation 2004 -2016
1.2 Abbreviations
In this Standard the following abbreviations shall have the following meanings assigned to them:
AS Australian Standard
ASIO Australian Security Intelligence Organisation
AUSTEL Australian telecommunications Authority
IAS Intruder Alarm System
PE Photo electric
PIR Passive Infra-Red
FIB Fire Indicator Board
EWIS Emergency Warning Intercommunication System
CPTED Crime Prevention through Environmental Design
CCTV Closed Circuit Television
MRS Magnetic Reed Switch
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 14 of 57
© Copyright Water Corporation 2004 -2016
2 INTRODUCTION
2.1 Criteria
The criteria in this Standard are subject to continuous revision. Users should ensure that they are in
possession of the latest version.
2.2 Scope
This Standard contains the requirements for the design of permanent and temporary public safety,
emergency, site security and asset safety treatments.
2.3 Purpose
The Standard is intended to provide a basic reference for the design of asset security treatments and
additional specialist advice from an appropriately licensed security professional will be required to
ensure compatibility and effectiveness of protective security plan and treatments.
2.4 Drawing
The attached drawings contain information which is complementary to the information contained in
the text. The drawings should be read in conjunction with the corresponding parts of the text.
Design Engineers and Contract Superintendents should ensure that they have the latest issue of the
drawings.
2.5 Manufacturers and Brand Names
Where a manufacturer is specified it is indicative only and provided at the time of the construction of
the Standard, it does not automatically imply endorsement of the manufacturer and their products by
the Corporation, nor does it imply that these are the only manufacturers supplying products and
equipment which will satisfy the design and treatment requirements.
Where a brand name is indicated, an equivalent material or product may be used if it has been
authorized for use by the Corporation.
2.6 Design Standards
The Design Engineer shall be responsible for the design of the works irrespective of the requirements
of this Standard which represents minimum standards.
2.7 Installation Standards
Where compliance with Australian or Corporation Standards is required, the information in this
Standard represents the minimum acceptable standard and does not preclude the use of materials and
workmanship of a higher standard.
2.8 Access to Existing Asset Systems
Corporation asset installations shall not be opened or entered without the prior approval of the
Corporation.
2.9 Security Categories
The Corporations critical infrastructure security category identification shall apply and is fundamental
to the selection of appropriate protective safety and security designs, treatments and standards.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 15 of 57
© Copyright Water Corporation 2004 -2016
The Security Program Manager, in conjunction with Scheme Managers and Asset Owner are
responsible for defining the security category to meet business continuity needs and the operational
environment. Additional factors shall also guide the final determination of asset protective measures
and includes:
Geographic locality
Demographic environment
Emergency, Police, security and medical response services
Related site incident histories
Loss impact and contingency response capability
Interdependencies with critical external infrastructure
A complex site may have an overall high rating with specific components with differing ratings
dependent upon their criticality.
The following table is an extract from SG 081 Site safety and security and provides guidance to the
Asset Owners in the selection of the Security Category. Most treatments in this Standard (DS 62)
refer to these asset categories:
Security
Category Description Loss Effect
A
Critical operational site or component.
Identified by External and internal
stakeholders as critical for operational, loss
effect, community perception and national
defence or strategic requirements. Critical to
the control and operational integrity of the
integrated services/supply
Community commercial and industrial
loss. Major contingency effort to
continue operations. Major media and
Government attention. Regulator
investigation and potential action.
B
Key operational site. Key link in the
Integrated supply system. Significant source
or single source. Maybe Remote with
extended travel times or no local community.
Located close to high-density population
area. Essential supply link to an important
national defence or Strategic asset.
Potential Community commercial and
industrial loss. Significant contingency
effort to continue operations. Media
and Ministerial attention. Regulator
investigation and potential regulator
action.
C Operational site. Loss effect is short and
mitigated by normal emergency response
actions.
Community and Commercial loss
effect is minimal. Media attention is
limited. Regulator routine
investigation.
D
Non-essential site. Loss effect is minimal as
operations will not adversely affect supply
services and integrated system will negate
loss effect.
Limited or no tangible community
effect. Regulator enquiry
E Non-essential site. Loss effect is negligible. No tangible Community service effect,
no regulator interest.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 16 of 57
© Copyright Water Corporation 2004 -2016
3 LEGISLATION
3.1 Statutory legislation
The following statutory legislation (Acts and related Regulations, guidelines and Codes of Practice)
has direct application to the safety and security applications referred to in this standard, the list may
not be exhaustive.
Bush Fires Act 1954
Occupational Safety & Health Act 1984
Occupational Safety & Health Regulations 1996
Occupiers Liability Act 1985
Security & Related Activities (Control) Act 1996
Surveillance Devices Act 1998
Emergency Management Act 2005
Dangerous Goods Act
Telecommunications Act 1991
Environmental Protection (Clearing of Native Vegetation) – Regulations 2004
Local Government regulations and by-laws(as applicable to the designated site)
Building Code of Australia
3.2 Guidelines
3.2.1 Federal Guidelines
The following Federal CIP guidelines are relevant to the risk assessment and standards required under
this Design Standard:
(a) Water Industry Risk Context Statement
(b) Infrastructure information in the public domain
(c) ENA 015-2006 National Guidelines for Prevention of Unauthorised Access to Electricity
Infrastructure
(d) Commonwealth – Security equipment catalogue
(e) Attorney Generals Critical Infrastructure security risk and design guideline
(f) National Security – Critical Infrastructure Owners & Operators Responsibilities
(g) CIERMA – Critical Infrastructure Risk Management Assurance guideline (EMA)
3.2.2 State Guidelines
The following State guidelines are relevant to the risk assessment and standards required under this
Design Standard:
(a) Western Australia Department of Planning - Designing Out Crime – Planning Guidelines
(b) Western Australia Department of Planning - Designing Out Graffiti – Planning Guidelines
(c) Western Australia – Critical Infrastructure Owners & Operators responsibilities
(d) WA Police – Alarm response guidelines
(e) Premiers Directives (Bushfire; Graffiti)
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 17 of 57
© Copyright Water Corporation 2004 -2016
(f) State CCTV Policy & Guidelines
3.3 Standards
Design shall comply with the following standards as a minimum requirement.
3.3.1 Australian Standards
Of the Standards listed below, it is understood that the reference includes all current subset documents
and relevant guidance handbooks.
AS 1379 - 2007 Specification and supply of concrete
AS 1657-2013 Fixed platforms, walkways, stairways and ladders - Design,
construction and installation
AS 1939-1990 Degrees of protection provided by enclosures for electrical
equipment (IP Code)
AS 2032:2006 Installation of PVC pipe systems
AS 2700-2011 Colour standards for general purposes
AS/NZS 3500 Set (Parts 0-5):2013 Plumbing and drainage Set
AS 3600-2009 Concrete structures
AS/NZS ISO 31000:2009 Risk Management
AS/NZS 4680:2006 Hot-dip galvanized (zinc) coatings on fabricated ferrous articles
AS/NZS 1680.0:2009 Interior lighting - Safe movement
AS 1680.1-2006 Interior lighting - General principles and recommendations
AS 1680.2.1-2008 Interior lighting - Circulation spaces and other general areas
AS 1680.2.2-2008 Interior lighting - Office and screen-based tasks
AS/NZS 1680.2.4:1997 Interior lighting - Industrial tasks and processes
AS/NZS 1680.4:2001 Interior lighting - Maintenance of electric lighting systems
AS/NZS 1768:2007 Lightning protection
AS 1725.1-2010 Chain link fabric fencing – Security fences and gates – General
Requirements
AS/NZS ISO/IEC 17799:2006 Information technology – Security techniques - Code of practice
for information security management
AS/NZS 2201 set: 2008 Intruder alarm systems Set
AS/NZS 2201.1-2007 Intruder alarm systems - Client’s premises – Design, Installation,
commissioning and maintenance
AS 2201.2-2004 Intruder alarm systems - Monitoring centres
AS 2201.3-1991 Intruder alarm systems - Detection devices for internal use
AS 2201.4-1990 Intruder alarm systems - Wire-free systems installed in client’s
premises
AS 2201.5-2008 Intruder alarm systems - Alarm transmission systems
AS 2630-1983 Guide to selection and application of intruder alarm systems for
domestic and business premises
AS 5039-2008 Security screen doors and security window grilles
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 18 of 57
© Copyright Water Corporation 2004 -2016
AS 5040-2003 Installation of security screen doors and window grilles
AS 5041-2003 Methods of test – Security screen doors and window grilles
AS/NZS 3014-2003 Electrical installations - Electric fences
AS/NZS 3016:2002 Electrical installations - Electric security fences
AS 3555.1-2003 Building elements - Testing and rating for intruder resistance –
Intruder-resistant panels
AS/NZS 3827.1:1998 Lighting system performance - Accuracies and tolerances -
Overview and general recommendations
AS 4145.2-2008 Locksets and hardware for doors and windows - Mechanical
locksets for doors and windows in buildings
AS 4145.3-2001 Locksets - Mechanical locksets for windows in buildings
AS 4145.4-2002 Locksets - Padlocks
AS/NZS 4421:2011 Guards & patrols security services
AS/NZS ISO/IEC 18044:2006 Information technology – security techniques – Information
security incident management
AS/NZS 4255.1:1994 Security seals - Classification
AS/NZS 4255.2:1994 Security seals - Use
HB 231:2004 Information security risk management guidelines
AS 3555.1-2003 Building elements - Testing and rating for intruder resistance -
Intruder- Intruder-resistant panels
AS 3806-2006 Compliance Programs
AS 4100-1009 Steel Structures
AS 4680:2006 Hot-dip galvanised (zinc) coatings on fabricated ferrous articles
AS/NZS 1595:1998.Amdt 1:2014 Cold-rolled, unalloyed, steel sheet and strip
AS/NZS 1554 Set:2011 Structural steel welding Set
AS/NZS 4671:2001 Steel reinforcing materials
AS 2688 Timber doors
AS 2689 Timber Door sets
AS 1909 Installation of Timber Door Sets
AS/NZS 2803.1:1994 - Doors Security Screen
ISO/TR 10476 Doorsets: Assessment of Burglar Proofness
AS/NZ 1905 Components for the Protection of Openings in Fire-resistant
Walls - Fire-resistant Doorsets
AS 2047 Windows in Buildings: Selection and Installation
AS/NZS 2208 Safety Glazing Materials in Buildings
AS/NZS 2343 Bullet-resistant Panels and Elements
AS/NZS 2699 Built-in Components for Masonry Construction
AS 3700 Masonry Structures
SAA HB 39 - 1992 Code of common practice for steel roofing
AS 1170 SAA Loading Code
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 19 of 57
© Copyright Water Corporation 2004 -2016
AS 1562 Design and Installation of Sheet Roof and Wall Cladding
AS/NZS 2179 Specifications for Rain Water Goods, Accessories & Fasteners
AS 2180 Metal Rainwater Goods - Selection and Installation
AS 3566 Screws Self-drilling for the Building and Construction Industries
AS 2331 Methods of test for metallic and related coatings
AS 4145 Locksets
AS 1725.1 2010 Chain link fabric fencing - Security fences and gates
AS/NZS 2803.1:1994 Doors - Security screen - Hinged
AS/NZS 2803.2:1995 Doors - Security screen - Sliding
AS 5040:2003 Installation of security screen doors and Window Grilles
AS/NZS 60598.2.1 2014 Luminaires - Particular requirements - Fixed general purpose
luminaires
AS 3798: 2007 Guidelines on Earthworks for Commercial and Residential
Developments
AS 1725.1-2010 Chain link fabric fencing - Security fences and gates - General
requirements
AS 2423-2002 Coated steel wire fencing products for terrestrial, aquatic and
general use
AS/NZS 3014:2003 Electrical installations - Electric fences
AS/NZS 3016:2002 Electrical installations - Electric security fences
AS 4687-2007 Temporary fencing and hoardings
AS/NZS 1594:2002 Hot-rolled steel flat products
AS/NZS 3679.1:2010 Structural steel - Hot-rolled bars and sections
AS/NZS 1163:2009 Cold-formed structural steel hollow sections
AS 1397-2011 Continuous hot-dip metallic coated steel sheet and strip -
Coatings of zinc and zinc alloyed with aluminium and
magnesium
AS/NZS 2728:2013 Prefinished/pre-painted sheet metal products for interior/exterior
building applications - Performance requirements
AS 2444-2001 Portable fire extinguishers and fire blankets - Selection and
location AS 2419.1-2005 Fire hydrant installations - System
design, installation and commissioning AS/NZS 1221:1997 Fire
hose reels AS 2293.1-2005 Emergency escape lighting and exit
signs for buildings - System design, installation and operation
AS3959:2009 Construction of Buildings in Bushfire prone areas
AS 1905.1-2005 Components for the protection of openings in fire-resistant walls
- Fire-resistant doorsets
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 20 of 57
© Copyright Water Corporation 2004 -2016
3.3.2 International Standards
ASTM A240M: Standard Specification for Chromium and Chromium-Nickel
Stainless Steel Plate, Sheet, and Strip for Pressure Vessels and for
General Applications
BS 1722-1:2006 Fences. Specification for chain link fences
BS 1722-10:2006 Fences. Specification for anti-intruder fences in chain link and welded
mesh
BS 1722-12:2006 Fences. Specification for steel palisade fences
BS 1722-14:2006 Fences. Specification for open mesh steel panel fences
BS 1722-16:2009 Fences. Specification for powder coatings used as a plastics finish to
components and mesh
BS 1722-17:2006 Fences. Specification for electric security fences. Design, installation and
maintenance
BS 1722-18:2011 Fences. Specification for free-standing temporary steel mesh perimeter
fencing panels
3.3.3 Other Standards, Specifications and Guidelines
The following Corporation Infrastructure Design Branch Other Standards shall be read in conjunction
with this Standard.
a) Preliminaries to Works Manual
DS 30 General Design Criteria and Glossary
b) Electrical Design Standards
No. Title
DS 20
DS 22
DS 24 Electrical Drafting
DS 25 Electronic Instrumentation
DS 26 Type Specifications – Electrical
c) Other Water Corporation Standards
DS 60 Distribution Mains
DS 61 Tank Standard
DS 66 Urban Drainage
DS 62 Part 2
DS 71 – Dangerous Goods
d) Standards of the Corporation’s Insurers (Currently FM Global)
S050 Support to State Emergency Management
S081 Site Security and Public Safety
S107 Security Response Guide
S110 Incident Management
S197 Safety and Security Signage Standard
S315 Business Continuity Standard[SB1]
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 21 of 57
© Copyright Water Corporation 2004 -2016
e) Water Corporation Work Instruction S012-W1-01 “Standards for Security Locks and Keys”
Engineering Design Process Manual
Mechanical and Electrical Design Standards
DS 30-02 General Design Criteria Mechanical
DS 80 WCX CAD Standard
S151 Prevention of Falls Standard
WS-1
DS95
Metal Arc Welding
Standard for the selection, Preparation, Application, Inspection
and Testing of Protective Coatings on Water Corporation Assets
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 22 of 57
© Copyright Water Corporation 2004 -2016
4 SUBMISSION REQUIREMENTS FOR DESIGN
ENGINEERS
4.1 General
a) Works undertaken for the Corporation shall be submitted to the Corporation in accordance with
the requirements of the contract.
b) In addition to the information required by the “Developers Manual” or the Corporations contract
the initial submission shall include the following:
c) Confirmation that water, electricity, telephone services and an all-weather access road will be
available in the road reserve in front of the security treatments areas. This is to permit access to
the site and service connections to be made as required. If it is considered that these facilities will
not be available by the time they are required, details of the extensions needed to provide them and
the corresponding costs above normal connection fees shall be given.
d) Copies of letters from the Local Authority and other relevant authorities confirming that the
proposed security perimeter arrangements have been accepted.
4.2 Licenses & Insurances
a) Copies of appropriate licenses and insurances supporting the design input to the plans shall be
provided at the time of submission.
(i) Licenses
Security Agents license
Security Consultants license
Security Installer’s licenses
Austel Cabling license
Electrical contractor’s license.
(ii) Insurances
Public Liability insurances for the corporate entity and the work to be conducted.
Professional indemnity insurances for the corporate entity and/or individuals providing
the design.
4.3 Quality Assurance
Submit evidence that tradesmen are fully trained, experienced and licensed in installation methods.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 23 of 57
© Copyright Water Corporation 2004 -2016
5 SITE FUNCTIONAL SCOPE
5.1 Definition
Site Functional Scope states the physical, procedural and technical compliance requirements with
relevant standards regarding security, fire and public safety.
5.2 Scope
A Site Functional Scope shall be completed for all assets through Assets Acquisition process.
5.3 Process and design and procurement processes
Design for Public Safety Fire and Security considerations shall be undertaken in accordance with the
Corporation’s Engineering Design Process Manual. The Site Functional Scope shall be completed in
the Asset Scoping phase, preferably in the requirements. For assets with Security Category A or B
with complex sites, the Site Functional Scope will be completed and used as instruction for designers
in the detailed design of security specifications. For asset with Security Category C or less, or where
so directed by the Corporation’s security manager, the Site Functional Scope can be used directly in
the procurement process to engage Water Corporation approved installers.
Asset commissioning and handover process for security and fire shall be integrated throughout the
requirements specification and design process.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 24 of 57
© Copyright Water Corporation 2004 -2016
6 SECURITY TREATMENTS CRITERIA
6.1 Introduction
a) This Section of the Standard sets out the criteria to be used for the selection and design of security
treatments.
b) The text does not completely specify Corporation requirements and shall be used in conjunction
with the attached standard and example drawings. Design Engineers shall adhere to both the text
and the drawings. If there is a conflict between the text and the drawings an interpretation should
be sought from the Corporation’s Infrastructure Design Branch and the Security Program
Manager.
6.2 Selection of Security Treatments
a) The fundamental basis for the selection of security treatments is based upon the asset
categorization. Refer Section 2.9.
b) The asset owner in consultation with the Security Program Manager is responsible for defining the
asset categorization and the operational environment. Decision as to the security category is based
upon a risk assessment. Additional factors shall also guide the final determination of asset
protective measures.
Geographic locality
Demographic environment
Related site incident histories
Contingency and redundancy response capability
c) A complex site (multiple functions and assets) may have an overall high rating with specific
components receiving differing ratings dependent upon their criticality. In this instance,
hardening of specific assets within a site perimeter should be considered as more practicable than
treating the whole site.
6.3 Security Design Considerations
The security design for all sites is a combination of safety, security and risk requirements, which may
change due to the effluxion of time, and professional advice from Security industry specialist,
(Licensed Security Consultant) may be required to assist with the selection of treatments based upon
the assessed risks at the earliest stages of the design.
6.3.1 Security Protective Profile
The overall security protective profile for the site shall include an assessment of the local environment,
and the general “area of influence” including the following:
Geographic
Meteorological
Demographic
Emergency, Police, security and medical response services
An assessment of the asset categorization of the whole site, and individual components
An assessment of the operations of the site
An assessment of the visible deterrence level required, versus the detection and response capacity
available for the subject site.
The total loss effect, redundancy capacity, depth of contingency planning and repair capacity.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 25 of 57
© Copyright Water Corporation 2004 -2016
6.3.2 Security Design Concepts
The security design shall incorporate all the concepts of business continuity and Crime Prevention
through Environmental Design (CPTED) and in particular shall consider:
a) Perimeter profile
b) Public and private transition areas
c) Access control and surveillance integration opportunities
d) The fundamental concepts of layered defence and defence in depth shall also be integrated into
the design with specific attention given to:
(i) critical infrastructure within the perimeter
(ii) key communication and control nodes
(iii) unique plant and equipment
(iv) access points to water storage areas
(v) chemical storage and equipment
e) All design submissions (where specified) shall consider and allow for:
(i) systems integration
(ii) scalable systems
(iii) automation
(iv) remote control and operation of the asset
6.3.3 Risk Management
The final design submissions shall be wholly based upon the risk assessment principles contained
within AS/NZS ISO 31000:2009, and the qualitative and quantitative ratings used in Water
Corporation S 122, with a documented risk assessment provided which supports the design concepts.
The risk assessment shall qualitatively and quantitatively identify and assess the following risk areas
as a minimum:
a) the external and internal human environment
b) geographic environmental risks
c) collateral systems and operational effects
6.3.4 Security Treatments
a) Security treatments selection, types, brief descriptions and applications are set out in the security
treatments table of SG 081. The table provides brief details of the types of treatments generally
acceptable to the security category rating.
b) Further design information on each of the security treatments types is given in a series of clauses
later in this Standard. This information should be read in conjunction with the appropriate
Australian Standards, related standards and example drawings.
c) Some security treatments have been accepted for standard use by the Corporation. The Design
Engineer can obtain advice of acceptable security treatments by contacting the Infrastructure
Design Branch of the Corporation. Electrical requirements for packaged security treatments shall
be discussed with the Corporation prior to commencement of electrical design. Examples of
Corporation accepted treatments include standardized access control systems and locking systems.
d) The Design Engineer shall have the type of security treatments accepted by the Corporation before
commencing detailed design.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 26 of 57
© Copyright Water Corporation 2004 -2016
e) The physical security design objectives shall meet AS 3555.1 minimum standards for a Level 2 –
10 minute rating and Level 3 – 5 minute rating.
6.4 Situational & Environmental Design Considerations
Where specific situational and environmental effects or potential requirements are applicable they are
to be noted within the specification.
The following specific areas are provided as guidance:
a) Properties adjacent to high volume roads and site subject to sustained construction will require
robust security detection equipment, and if seismic detection equipment is considered, or smoke
detection apparatus where high levels of dust and insect intrusion is probable.
b) Agricultural, semi-rural and high crime areas may require ballistically tolerant lighting fixtures;
CCTV enclosures and detection apparatus.
c) Assets located near schools and places of mass gathering will require greater levels of security
treatment.
d) Urban high density population areas with evidence of repeated site intrusion will require vandal
resistant external lighting, CCTV and detection apparatus fixtures
All external and internal installations shall take account of the extremes of weather over a 100 year
period, including:
Water and flood table levels
Temperature
UV levels
Wind (prevailing and seasonal)
Dust levels
Salinity levels
Condensation cyclic mist and ambient moisture levels
Fire hazards
Seismic movement
The arc of the Sun in relation to detection equipment, PE switching and CCTV location
The installations shall also take consider adjacent foliage and fauna, including:
Insects
Birds
Burrowing large and small animals
Animals with the potential to scale, burrow, or cross low fences.
6.5 Water Corporations Public Safety & Security Aesthetics Policy –
General Design Requirements
Where practicable aesthetic design options are to be incorporated or noted within the design.
(Colours/finishes/containers and housings)
a) Site screening – all internal and perimeter foliage/plantings. Any foliage should grow no higher
than 0.5 metres high and tree branches no lower than 1.5 metres high. Tree trunks should be
clean of all offshoots and saplings etc. should not be planted close together. These conditions
allow a clear unobstructed view from the street of any ill-intentioned persons and unauthorised
activity upon the site by day and night.
b) Trees should be considered for their resistance to simple climbing – no strong lateral branches.
c) Screening foliage should not overhang or penetrate any perimeter fencing by at least one metre
inside the perimeter fence.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 27 of 57
© Copyright Water Corporation 2004 -2016
d) Low foliage should not be planted to create a continuous bush line, which will attract rubbish and
refuse bank up.
e) All foliage should be assessed for fire fuel load and seasonal aesthetic risks, such as leaf fall and
fire fuel load build up against operational or occupied structures and community perimeters.
f) External perimeter fence areas can have ground level surface changes (i.e. coloured gravel, small
stone chips – no larger than 10mm) as a tactile surface can change to provide sensory awareness
of land ownership change.
g) Critical sites and high voltage electrical compounds sites will require appropriate fencing such as
strong barrier/palisade style (colour dependency is not essential). However, regardless of the
fencing chosen, it should be weather and corrosion resistant for the intended life of the fence (a
poorly maintained fence is attractive to ill-intentioned persons).
h) Aesthetic entrance markings on roadways etc. should include tactile surface changes, with light
reflective luminance considered.
i) Any additional garden furniture and leisure area or recreational equipment should have permanent
fixtures (non-portable), no external rubbish bins, no operational bins or structures placed adjacent
to buildings, fences or tanks as to facilitate climbing upon the adjacent structure.
j) All aesthetic lighting should be placed towards reflective walls and access points.
k) Colours used on building perimeters should include a light reflectance rating for ambient and
safety/security lighting.
l) Use of cages for equipment or caged utility cabinets should be minimal with all external
equipment and power cabinets etc. placed within solid/seamless walls, with no unnecessary
fenestrations. To reduce the need for external security grilles on essential sites, the use of
substantial vents, with horizontal and vertical locking pins should be considered together with
internal grilles with apertures no wider than 5mm.
m) There should be no commercial, contractor or private external security signage placed upon the
site perimeter, only Water Corporation colours, markings and logo and signage in accordance
with S197 and Water Corporation signage standards is to be installed.
n) External safety, security and restrictive signage should be simple and clear in the message ‘who
own the site; what risks and proscriptions apply to unauthorised entry and the number to call for
in the event of an emergency and security (131375).
6.6 Occupational Safety & Health, and Public Liability
a) Where specific community and/or operational safety issues are relevant to the placement,
installation, commissioning, operation, maintenance of the asset design they are to be
documented, together with risk mitigation options.
b) Potential hazards and safety considerations warnings are to be noted for signage purposes where
applicable.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 28 of 57
© Copyright Water Corporation 2004 -2016
7 INSTALLATION REQUIREMENTS
7.1 General
The correct and standards compliant installation of security systems is essential to the integrity of the
protective security plan.
The installation standards and process must be carefully managed and inspected before openings and
connections are closed.
Only appropriately Water Corporation approved WA Police licensed security, electrical and Austel
licensed installers are to be used for security installation work. (Exempt fixed non alarmed, electronic
fencing and lighting)
7.2 Plans, drawings, approvals, certificates & licenses
7.2.1 Plans & Drawings
All plans and drawings are to be supplied in accordance with this Design Standard. The plans and
drawings are to include:
In ground works
Trench’s, conduiting and relationships with collocated or associated services.
Cable runs/tying and fixing points
Underground supports.
All equipment locations.
7.2.2 Approvals
The following works approvals are to be obtained where the security works are required to be
approved for fencing and associated environmental works.
State Government (e.g. environmental)
Local government
Land owners
Approvals may also be required for the use of CCTV and lighting when in close proximity to adjacent
buildings and properties.
7.2.3 Manufacturers and Statutory Authority
a) Manufacturers production statements including:
Materials used
Standards of manufacture
Testing compliance
b) Manufacturer’s instructions
Installations approvals for the installing contractor(where required)
Installation instructions
Installation testing
Commissioning testing
Operational instructions
Maintenance instructions
c) Manufacturers Warranties & Guarantees
Manufacturers issued warranties and guarantees
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 29 of 57
© Copyright Water Corporation 2004 -2016
d) Statutory Authorities
Government and other regulatory authority certificates for equipment usage (i.e. electrical,
environmental)
7.2.4 Licenses
a) The following licenses are a mandatory requirement for the installation of Security equipment in
Western Australia.
b) These licenses are to be obtained in hardcopy and provided to the superintendent for approval
prior to works commencing and shall form part of the final handover documentation.
c) The licenses must be the full document with all relevant license information and expiry dates
(Plastic ID cards are not acceptable):
Security Agents (WA Police issued – naming the company)
Security consultants/officers/installers (WA Police licenses – naming the individual who is
performing the work and their specific category of works approval (i.e. safes, locks, alarms
etc.)
Electrical Contractors licence
Austel cabling licence – required for works involving communications equipment
7.2.5 Fire Doors
Doors marked and tagged doors and frames and provide Certification of Compliance and Log Book in
accordance with ASNZ 1905 on completion of work
7.3 Works & Inspections
The works shall be comprehensively supplied by the contractor and include all in ground works,
structural works, rendering, closing, environmental re-surfacing, painting, approvals, trenching,
cutting, connection equipment, wiring, cabling, required to fully support the installation,
programming, testing, commissioning, monitoring and maintenance of the “system.”
7.4 Excavations and Installations
a) All excavations required shall be carried out in accordance with AS3798:2007. The contractor
shall ensure that full information is obtained regarding any underground services in the vicinity of
any excavation for footings or underground conduits, and that care is taken during the progress of
the work to avoid any possibility of damage to any Corporate or public utility.
b) Any trenching near identified services shall be carried out manually.
c) Any damage caused by activities of the contractor shall be made good by the contractor. If made
good by others, the cost of the repair shall be recoverable from the contractor.
d) The exact location of services which are in the vicinity of any excavation shall be accurately
determined with the assistance of the relevant authority. These include:
Main Roads Western Australia (lighting, electrical and draining conduits),
Water Corporation or supply provider (Water mains, reticulation, valves sewerage & power),
Alinta Gas (gas mains),
Telstra and Optus (communication cables,
Local Authority (reticulation)
Corporate Services including:
o Communications links
o Fuel lines
o Power and electrical services
o Water, reticulation and sewerage services – including fire services
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 30 of 57
© Copyright Water Corporation 2004 -2016
7.4.1 Damage
a) Any damage caused by activities of the contractor shall be made good by the contractor.
b) If made good by others, the cost of the repair shall be recoverable from the contractor.
7.5 Submissions
a) Submit the following for inspection by Superintendent before installation:
b) Plans, drawings, manufacturer’s documentation, testing programmes, project timeline,
inspections times, licences, approvals, authorities, commissioning dates and targets.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 31 of 57
© Copyright Water Corporation 2004 -2016
8 COMMISSIONING REQUIREMENTS
8.1 Commissioning
All physical and electronic security works shall be commissioned by a qualified, competent
superintendent’s representative. The Security Program Manager will provide advice on request as to
the appropriate level of commissioning standards. Where external (non-Water Corporation) project
advice is received a competent WA Police licensed security consultant experienced in the security
works and installations specified is to be used.
8.2 Testing requirements (Physical & Mechanical)
The installing contractor shall submit documents required for commissioning and any mechanical and
inspection statements to the Superintendent for review and acceptance at least two weeks prior to the
conduct of the tests.
The procedure shall include as a minimum for each test:
Inspection and Test identification.
The aim of the inspection or test.
Detailed of the inspection or test procedure or actions.
Expected test outcome or responses.
8.3 Testing requirements (Electrical)
The installing contractor shall submit written procedures for testing and inspection the systems to the
Superintendent for review and acceptance at least two weeks prior to the conduct of the tests.
The procedure shall include as a minimum for each test:
Test identification.
The aim of the test.
Detailed test procedure or actions.
Expected system responses by all parts of the system.
8.4 Testing Format
At the Superintendent’s discretion, full and comprehensive testing shall be conducted by the contractor
in the following form:
a) Confirmation and conduct of all recommended manufacturer testing prior to installation.
b) Where systems are integrated with existing or new equipment, offsite bench testing shall be
conducted, with certificates of presented to the superintendent for review.
c) Site testing shall be conducted, to include individual and separable equipment testing, for both
stand alone and integrated systems.
d) Installation testing of systems shall be conducted for all forms of communication, signals and
operation.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 32 of 57
© Copyright Water Corporation 2004 -2016
8.5 Pre-commissioning
Full and comprehensive, documented pre-commissioning systems testing shall be conducted, in the
following format:
Preparation of testing documentation for approval by superintendent.
Documented Site works inspections, to include standard of installation.
Comprehensive system and individual item testing of each and every installed system and item,
under operational conditions.
System behaviour to random and specified operator actions.
System response to hardware failures.
Systems responses to all normal operational signals.
System responses to fault signals.
System responses to remote and local power and other utility failure.
System response to tamper signals.
System response to random operator control.
System response to deliberate damage.
8.6 Continuous testing
Continuous testing shall start at the satisfactory completion of pre-commission testing, and shall be
conducted over a period agreed between the Superintendent and the Contractor. The contractor shall
provide fault identification sheets and review these sheets on a daily basis during this period. A
written response to corrective actions shall be supplied to the Superintendent for each fault identified
and corrected during this period.
8.7 Commissioning testing
Commissioning testing shall not be conducted until the complete works have been completed by the
contractor, and all items identified for correction during other types of testing have been rectified, and
individually tested.
Commissioning testing shall be conducted as for pre-commissioning testing.
Any operation or performance which does not comply with the agreed method of operation shall be
logged, together with a description of the subsequent repair. At the discretion of the Superintendent,
either a portion of the tests or the entire test sequence shall be repeated to verify the corrections.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 33 of 57
© Copyright Water Corporation 2004 -2016
9 TESTING DURING COMMISSIONING
9.1 Electronic Systems
The Contractor shall supply all labour, materials and equipment required to fully commission and test
the site installation, and the monitoring of the system alarm output functions via the selected
commercial 24-hour security remote monitoring service approved by the Water Corporation and the
Water Corporation’s propriety 24-hour monitoring centre located in Leederville.
The commissioning process shall provide a computer generated print out record from each monitoring
centre to confirm ALL the activity generated from the system testing and commissioning has been
received and acknowledged from both monitoring centres, these computer generated print out records
shall form part of the documentation required for the purpose of the issuing of a Certificate of
Practical Completion, all commissioning and system testing shall be to the satisfaction of the
Superintendent.
On completion of the work the Contractor shall satisfy the Superintendent that the intruder alarm
system operates correctly and complies with the specification and drawings. Carry out all tests as
required by the Superintendent to ensure that the system and other work conform to the specification.
The Contractor shall replace any equipment, which fails to operate correctly.
The tests shall be carried out in the presence of the Superintendent.
A written notice of intention to test shall be provided to the Superintendent not less than 14 days prior
to the carrying out of such tests.
Installation and/or equipment will be accepted only after satisfactory completion of the
commissioning.
If a test procedure is unsuccessful due to faulty equipment the equipment shall be replaced and re-
programmed, if there is a failure of the system due to defective installation practices that section of the
system shall be re- installed to ‘best practice ‘ and subjected to retesting and commissioning and
proven to be operational to the satisfaction of the Superintendent.
9.2 Intruder Alarm and Access Control System
9.2.1 Alarm Panel
Test the operation of all, sectors and panel functions.
Test entry/exit functions and access control functions.
Test functions/levels to both monitoring centres.
9.2.2 Detection Devices
Test the operation of each detection device in all conditions.
Where necessary, intrusion conditions shall be simulated.
The size and rate of movement of objects and/or persons used to simulate intrusion conditions
shall be as defined in the current relevant SAA Standard Specifications.
Where Standard Specifications do not exist, the size and movement of targets shall be as defined
in the equipment manufacturer’s standard manuals.
Test the tamper device of each detection device.
Calculate and test the time for the standby supply.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 34 of 57
© Copyright Water Corporation 2004 -2016
9.3 As Installed Drawings and Manuals
Drawings shall comply with AS. 1100 “Technical Drawing - General Principles”.
Provide three (3) copies of all additions to the operating and maintenance manuals. Marked up
drawings shall show as installed position of all detectors, panels, etc.
Document Required Number of Sets
a) Concise operating and maintenance instructions Three (3)
b) Detailed operating and service manuals Three (3)
c) “As installed” drawings Three (3)
d) Connection diagram for the intruder alarm system Three (3)
e) “As installed” intruder alarm control panel circuit index Three (3)
9.4 Operating and Maintenance Instructions
Provide a concise system and panel operating and maintenance Instructions as follows.
Non-technical plain English concise instructions are required for issue to systems operators, and shall
be submitted to the Superintendent for approval at least two weeks before the intended commissioning
date.
Commissioning tests will not commence until after approval of such instructions has been granted.
9.5 Training
The Contractor shall include in the tender price the cost of providing the following training courses:
9.5.1 Operators Course
The courses shall be held on site and shall cover all aspects of site operation of the system; duration of
the training shall not exceed 2 hours for each staff member.
Provide training for the staff in the use and operation of this system. Training to be presented to each
of the staff on an individual basis (maximum of 4 persons) Training is to be provided by a technical
person fully conversant with the system and the equipment installed.
9.6 Environmental Testing
The contractor shall submit to the Superintendent methods for simulating seasonal and environmental
conditions which prevail at the site, for testing purposes. If approved these methods shall be
incorporated within the pre-commissioning, continuous testing and commissioning phases.
9.7 Certificates
The contractor shall supply fully completed and approved commissioning certificates for the complete
works clearly stating the following as a minimum:
Manufacturing standards
Installation standards
Testing Standards
Relevant statutory or Australian Standards compliance
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 35 of 57
© Copyright Water Corporation 2004 -2016
10 MAINTENANCE REQUIREMENTS
10.1 General
The integrity of the installed security treatments is dependent upon comprehensive ongoing
maintenance.
10.2 Maintenance requirements
The contractor is to supply details of all maintenance requirements, including maintenance schedules
applicable to all the installed equipment.
A schedule of the following is required as a minimum:
a) Manufacturers documented maintenance requirements
b) Australian standards or international standards maintenance requirements
c) Corporation maintenance requirements taking into account:
(i) Anticipated usage
(ii) Environmental effects
10.3 Maintenance inspections
Site safety and security inspections shall be integrated with routine operational site attendance and
documented with the detail contained at attachment seven of the Water Corporations SG081 –
Occupiers Liability Compliance.
Non-essential routine maintenance works should be incorporated into the routine maintenance
program and essential safety and security high-risk anomalies with onsite systems should be identified
for priority maintenance or further review.
Evidence of serious, deliberate, unsafe, criminal or ill-intentioned acts, noted at any time should be
recorded on the Water Corporation site safety and security incident report and site incident register.
Corporate governance and due diligence good practice and risk management requires that any site
controls for safety and security are maintained in good order to ensure their operational effectiveness.
The principles of AS 3806:1998 Compliance Programs and life cycle maintenance are recognised
within this process.
This ongoing maintenance process is not restricted to simple housekeeping, and includes both passive
and active protective and preventative mechanisms and systems.
Examples of ongoing regular site checks would include:
the operation and testing of electronic and emergency safety and security systems, signage,
fencing and signage,
locks,
doors and door closers,
grilles,
hatches,
foliage, undergrowth or overgrowth.
It is accepted that notice would be taken where a designated security and safety control is in place,
however where evidence of non-effectiveness is apparent (e.g. safety and security fencing where
cutting, crossing or burring is evident on a regular and repeated basis), this shall be reported
immediately using the normal operational maintenance process. Where the ineffective control may
have an individual safety impact this shall be reported as a priority item.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 36 of 57
© Copyright Water Corporation 2004 -2016
Safety and security system maintenance should be fully integrated into the normal site operational
routine and conducted as an adjunct to a routine site operational attendance.
Any new assets must be supplied with an appropriate checklist for regular Safety, Security and
Environment (SSE) inspections. The inspection should be fully documented against the site records for
future reference. Simple checklists with appropriate additional explanatory notes suffice, with a
transparent linkage to any site safety and security works arising from any identified improvements.
10.3.1 Frequency
The frequency of maintenance inspections would be commensurate with the level of normal
attendance at the site.
As a guide:
a) Category A sites would require monthly documented inspections including alarm testing.
b) Sites attended more frequently than six monthly would attract a quarterly documented inspection
as a minimum.
c) Six monthly-attended sites would be inspected at the time of attendance.
10.3.2 Warranty Period
The installation including labour and equipment and associated works supplied and installed by the
contractor shall be warranted for a period of 12 months after the date of the Certificate of Practical
Completion.
10.3.3 Maintenance during Defects Liability Period
The Contractor shall provide all maintenance for the works during the Defects Liability Period (52
weeks).
10.3.4 Callouts during Defects Liability Period
During the Defects Liability Period the security contractor shall attend site within two hours (2) of
notification of a failure of the system. The call out requirement shall apply on a 24 hour 7day a week
basis.
The security contractor shall advise in writing all the names and contact numbers of the service
representatives to be used to provide this service.
The contractor without additional costs renew any works which prove faulty from workmanship or
materials and ‘fully maintain and service’ the whole installation for a period of fifty two weeks (52)
weeks after the date of the Certificate of Practical Completion
‘Fully maintain and Service’ shall include:
a) Six monthly inspections of the system to test and verify the continued operation of the system in
accordance with the system parameters specified.
b) Assessment of the system reports to ensure the continued reliability of the system.
During the Defects Liability Period perform such corrective works as may be instructed in writing by
the superintendent within seven days (7) of such notice, or on failure, the superintendent reserves the
right to engage others to finish such works without further notice and the cost of the same shall be a
debt of the contractor.
Such action shall not vitiate the contractor’s responsibility.
Costs of the maintenance within the defects period shall be included in the installation costs.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 37 of 57
© Copyright Water Corporation 2004 -2016
10.4 Long Term Monitoring and Maintenance
Submit with the tender a proposal for the long term monitoring and maintenance of all elements of the
system based upon the following:
a) Inspection and testing of the system at 2 x (6) monthly periods
b) Long term maintenance for one year
c) Long term maintenance for three years
10.5 Completion
The system shall be left complete, fully programmed and ready for the client’s immediate use.
10.6 Maintenance Service & Contract
The installing contractor is to supply copies of their maintenance contract for the supply of
maintenance services for the complete installation for a period of three to five years.
This contract is to include all inclusions, exclusions, methods and standards for the implementation
and monitoring of the maintenance contract.
Detailed costs are to be supplied on a schedule as separate items for this proposed work.
10.7 Spare Parts (Recommended)
The maintenance contract and the contractor at the time of commissioning is to provide:
a) Recommended list of spare parts to be held by the Water Corporation to cover the first
maintenance inspection period.
b) Confirmed documentation indicating the availability and lead times to supply parts if not held by
the Water Corporation
c) Price schedule for critical spare parts.
10.8 Spare Parts (Maintenance)
The installing contractor is to note and supply all necessary spare parts within the pricing schedules
supplied.
The spare parts are to be all those parts normally required for the maintenance of the equipment being
installed for a period of no less than twelve months and other such period as agreed.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 38 of 57
© Copyright Water Corporation 2004 -2016
11 DOCUMENTATION AND TRAINING
REQUIREMENTS
11.1 Format
a) The Contractor shall supply documents and drawings. The Contractor is encouraged to provide
documents in electronic form (Microsoft Word 97 or later versions, IBM Compatible.)
b) All drawings submitted by the Contractor shall be in accordance with the applicable Water
Corporation and Australian Standards
c) Adequate contrast shall be maintained between drawing detail and background, and the clarity
and quality of the drawings shall enable the Principal to microfilm the prints (refer to AS 1203)
and to reproduce by photographic process clear and legible A3 copies for record purposes.
d) The drawings shall clearly state in the title block, the number and title of the Contract, as well as
details to identify the drawing, its contents, revision status and date of issue – in compliance with
the WCX standard.
11.2 Standard Documentation
11.2.1 Electronic
All manufacturers’ standard operating and maintenance manuals for all equipment supplied as set out
below:
a) Configuration of Equipment and Central/control Panel.
b) Configuration of Alarm Gathering Panels.
c) Configuration of Access Levels.
d) Operator Manual.
e) Layout Drawings.
f) Alarm Schedules.
g) Termination Schedules.
h) (Termination Drawings.
i) Training Schedule and Content.
j) Project Administration
(i) Quality plan,
(ii) Time Schedule,
(iii) Works schedule.
11.2.2 Physical/Structural
All manufacturers’ standard design and maintenance manuals for all equipment supplied as set out
below:
a) Design and manufacturing certificates
b) Installation plans
c) Connection details to other systems or structures
d) Underground construction details.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 39 of 57
© Copyright Water Corporation 2004 -2016
11.3 Review Procedure for Customised Documents
a) Customized documentation or any document or drawing written specifically or substantially
modified for the project, shall be subject to review in its entirety by the Superintendent with
emphasis on content, layout and style. Nevertheless the Contractor shall ensure the accuracy of all
documents and drawings.
b) The Contractor shall revise and re-issue documents, identified by the Superintendent to be
incorrect or inappropriate for the Contract, at no cost to the Principal and with no schedule impact
to other Contract tasks. The necessity for revision and re issue of documents shall not be
considered as grounds for claims for program extensions or monetary reimbursement.
c) The Superintendent will review each document and return its comments to the Contractor with a
document status indicated as follows:
(i) “Reviewed” The document is acceptable as presented. The Contractor may proceed to
finalise the document.
(ii) “Reviewed with Corrections Noted” The document is acceptable with the inclusion by
the Contractor of the corrections or amendments noted. The Contractor may proceed to
finalise the document.
(iii) “Rejected” The document as presented contains serious errors, omissions, breaks of
form, or other problems that require correction. The Contractor shall correct and resubmit
the document for further review by the Superintendent. Other work, dependent on the
content of such a document, should not proceed without prior consultation with and
approval by the Superintendent.
11.4 Training
a) The Contractor shall provide high quality and in depth training of the nominated personnel to
enable them to become self-sufficient in the operation of the system and other associated
equipment.
b) The Contractor shall provide formal training or courses in the following areas:
Operation and performance of the system.
Maintenance requirements and testing of the System.
Operation of any other installed integrated or associated equipment.
The instruction shall be taught by experienced personnel, and shall include:
Instruction using current “Best Practice” & “Train the Trainer” training methods.
All necessary instructional materials.
Practical demonstrations.
Use the operational manuals supplied with the equipment.
Conducted in English.
Conducted at the Site, with the installed equipment.
The conduct of trainee testing at the conclusion.
The provision of fully documented lesson plans, tests, student diagrams.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 40 of 57
© Copyright Water Corporation 2004 -2016
ANNEXURE-1: DRAWINGS
Introduction
This Section of the Standard specifies the Corporation’s requirements for drawings and documentation.
General Drawing Requirements
a) Drawings shall be similar to the examples contained in this standard. The drawings shall comply with the
requirements of this Clause and contain all the data shown on the examples if relevant to the particular
project in hand.
b) Initial drawing submissions shall be submitted on A1 size paper prints using Corporation standard drawing
sheets. The Design Engineer shall ensure that all drawings produced for the Corporation are in accordance
with the WCX CAD Standard (DS80). Adhering to this standard will ensure that drawings will be compliant
with the Corporation’s Drawing Management System (DMS). The WCX CAD Standard (includes CD and
Guidelines Manual) can be obtained from Infrastructure Design Branch. Electrical drawings shall be
prepared in accordance with the above requirements and be in accordance with the requirements of DS 24.
c) The final drawings shall be submitted on A1 or A2 size paper prints. An electronic copy of the final
drawings shall also be supplied.
d) The standard of linework and lettering on drawings shall be suitable for legible reproduction from microfilm.
Lettering shall be in upper case with a minimum height of 2.5 mm.
e) The Corporation file number and the security treatments name and number shall be shown on each drawing.
A space 150 mm x 30 mm shall be provided on each drawing for acceptance stamp and plan number.
f) Levels shall be based on the Australian Height Datum (AHD).
g) The invert levels, sizes and positions of existing and proposed works and obstructions shall be shown.
h) Existing and proposed works shall be separately identified.
i) The location, lot number and dimensions of the land shall be shown where applicable.
j) Drawings -
k) Section and plan horizontal scale shall be appropriate to the nature of the detail described.
l) The position of all equipment; conduiting, cabling and connections shall be on the plan and section.
m) Where required demarcation points for the funding responsibility for the works shall be shown on
appropriate drawings.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 41 of 57
© Copyright Water Corporation 2004 -2016
Example Drawings
The following is list of the example drawings for security and general fencing. The drawings show the minimum
requirements of the Water Corporation as stated in the standard. The details in the example drawings contain
information which is complementary to that contained in the text and shall therefore be read in conjunction with the
corresponding parts of the standard. These example drawings provide details of information to be included in the
design / fabrication drawings. The designer and contract Superintendent shall ensure that they have the latest issue
of the drawings.
Drawing Number Issue Drawing Title
GX54-001-001-01
A 2.4m HIGH PALISADE SECURITY FENCE
SUITABLE FOR SECURITY CATEGORY A & B
SITES
GX54-002-001-01
A 2.1m STEEL SHEETED SECURITY FENCE
WITH BARBED EXTENSION
SUITABLE FOR SECURITY CATEGORY B
SITES
GX54-003-001-01
A ACCESS TRACK SECURITY GATE
GX54-004-001-01
A STOCKPROOF RINGLOCK FENCES
SUITABLE FOR SECURITY CATEGORY D & E
SITES
GX54-004-002-01 A POOL TYPE, POST & RAIL AND TWO RAIL
CHAINWIRE FENCES
SUITABLE FOR SECURITY CATEGORY D & E
SITES
GX54-004-003-01
A CHAINMESH 'TYPE 1' AND FREE STANDING
FENCES
SUITABLE FOR SECURITY CATEGORY D & E
SITES
GX54-005-001-01
B 1.8M CHAINWIRE FENCE WITH BURIED
SELVEDGE, BARBED EXTENSION & RAZOR
WIRE AT TOP & GROUND LEVEL
GX54-006-001-01
C 1.8M CHAINWIRE FENCE WITH BURIED
SELVEDGE, BARBED EXTENSION & RAZOR
WIRE AT TOP
GX54-007-000-01
B EXTERNAL STAIRWAYS - TANKS AND
SIMILAR STRUCTURES
GUIDANCE NOTES FOR TYPES OF SECURITY
BARRIERS
GX54-007-001-01
C EXTERNAL STAIRWAYS
FIRST PLATFORM LEVEL SECURITY
BARRIER
GX54-007-002-01
C EXTERNAL STAIRWAYS
GROUND LEVEL SECURITY BARRIER
GX54-007-003-01
C EXTERNAL STAIRWAYS
FENCED COMPOUND AND FIRST PLATFORM
LEVEL SECURITY BARRIER
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 42 of 57
© Copyright Water Corporation 2004 -2016
APPENDIX 1- EXTERNAL ADVICE AND STORAGE PROTOCOLS
FOR DS 62
The distribution concept is that frequently engaged Panel Consultant designers as well as the four Security Panel
Consultants will be issued with a controlled hard copy of the "physical" sections (DS 62-01). The
"electrical/electronic" sections (DS 62-02, e.g. alarms, CCTV) will only be distributed to the Security Panel
Consultants when they are first requested to quote, once again as a controlled hard copy.
External individuals and consulting teams who are required, by virtue of the working relationship with the Water
Corporation, to retain a DS 62 hardcopy shall comply with the following handling and storage protocols:
a) Complete a Confidentiality Undertaking (if not already in hand – see attached proforma in Appendix C).
b) No copies shall be made of the document for any reason.
c) The consultant shall nominate the controlling person who shall be responsible for the document prior to its
issue. This person shall complete the Statutory Declaration stating that no copies have been made or retained
upon the return of the document to the Water Corporation (refer Item 12 and Appendix D). This
responsibility shall not be delegated.
d) Access to and use of the document shall be controlled by a person who holds a current WA Police Service
Security Consultants licence under the Security & Related Activities (Control) Act 1996.
e) When not in actual use, the document shall be secured within a lockable security container which satisfies
the guidelines of an ASIO T4 approved "C" class security container.
f) Minimal transport and handling of the document shall occur at all times and the document is not at any time
to be secured in an unattended motor vehicle or other unattended form of transport.
g) Couriers, mail services or others who are not a party to the statutory declaration shall not be used for the
transport of the document.
h) The document shall not to be secured at a private residence at any time.
i) The document shall be secured within a physically robust commercial office with secure profile keying
systems; multi-layer physical office access control to the document area, and covered by an AS 2201
compliant, multi sector, externally monitored, fully functional and operating intruder alarm system.
j) Any actual losses of the document, attempted or actual unauthorised access to storage containers, where the
document is secured shall be immediately reported to the Water Corporation and the WA Police Service.
k) The document storage requirements and protocols are subject to reasonable discretionary audit by Water
Corporation and WA Police Service.
l) Upon return of the hard copy of the document (for example when a new version is issued) the controlling
person shall sign a Statutory Declaration stating compliance with these protocols (see attached proforma in
Appendix D).
The distribution concept is that frequently engaged Panel Consultant designers as well as the four Security Panel
Consultants will be issued with a controlled hard copy of the "physical" sections (DS62-01). The "electrical/
electronic" sections (DS62-02, e.g. alarms, CCTV) will only be distributed to the Security Panel Consultants when
they are first requested to quote, once again as a controlled hard copy.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 43 of 57
© Copyright Water Corporation 2004 -2016
External individuals and consulting teams who are required, by virtue of the working relationship with the Water
Corporation, to retain a DS 62 hardcopy shall comply with the following handling and storage protocols:
a) Complete a Confidentiality Undertaking (if not already in hand – see attached proforma in Appendix C).
b) No copies shall be made of the document for any reason.
c) The consultant shall nominate the controlling person who shall be responsible for the document prior to its
issue. This person shall complete the Statutory Declaration stating that no copies have been made or retained
upon the return of the document to the Water Corporation (refer Item 12 and Appendix D). This
responsibility shall not be delegated.
d) Access to and use of the document shall be controlled by a person who holds a current WA Police Service
Security Consultants licence under the Security & Related Activities (Control) Act 1996.
e) When not in actual use, the document shall be secured within a lockable security container which satisfies
the guidelines of an ASIO T4 approved "C" class security container.
f) Minimal transport and handling of the document shall occur at all times and the document is not at any time
to be secured in an unattended motor vehicle or other unattended form of transport.
g) Couriers, mail services or others who are not a party to the statutory declaration shall not be used for the
transport of the document.
h) The document shall not to be secured at a private residence at any time.
i) The document shall be secured within a physically robust commercial office with secure profile keying
systems; multi-layer physical office access control to the document area, and covered by an AS 2201
compliant, multi sector, externally monitored, fully functional and operating intruder alarm system.
j) Any actual losses of the document, attempted or actual unauthorised access to storage containers, where the
document is secured shall be immediately reported to the Water Corporation and the WA Police Service.
k) The document storage requirements and protocols are subject to reasonable discretionary audit by Water
Corporation and WA Police Service.
l) Upon return of the hard copy of the document (for example when a new version is issued) the controlling
person shall sign a Statutory Declaration stating compliance with these protocols (see attached proforma in
Appendix D)
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 44 of 57
© Copyright Water Corporation 2004 -2016
APPENDIX 2 - INTERNAL ADVICE REGARDING SECURITY
MATTERS
Design Managers are able to provide advice on the appropriate process to follow for public safety, fire and security
design including setting of requirements and the accepted design process in accordance with the Corporation’s
Engineering Design Process Manual. The Security Manager is also able to provide example requirements
specifications and other design specifications that can be used as guidelines for any designs produced. A typical
example is attached in this appendix.
Internal requests for advice regarding security matters should be forwarded to the Security Program Manager.
When DS 62 is not in actual use, the responsibility for keeping the IDB hard copy in a secure location, within a
lockable security container which satisfies the guidelines of an ASIO T4 approved "C" class security container.
Request for viewing DS 62 by Water Corporation officers such as Design Managers shall be made to the
Infrastructure Design Branch, fully explaining the reasons for the request. If approved, the officer shall be
provided with a hard copy of DS 62 to view in a secure conference room. The viewer is permitted to make notes,
however, no copies of any part of the document are to be made for any reason. Upon completion of viewing the
viewer shall return the hard copy and sign a viewing sheet to declare that no copies of the document have been
made.
Your participation and assistance in the ongoing review and development of this Standard is valued. Comments and
suggestions should be forwarded to the Security Program Manager.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed Ver 1 Rev1
Page 45 of 57
© Copyright Water Corporation 2004 -2016
APPENDIX 3 - INDICATIVE ASSET SECURITY CATEGORISATION AND SECURITY
TREATMENT SCHEDULES
Indicative Asset Security Categorisation and Security Treatment Schedules Confirm site categorisation with Security Program Manager (Stephen MacCarthy, [email protected], tel (08) 9420 3879, 0427 195 536, fax
(08) 9420 2656)[LM2]
Asset Types
(Indicative)
A B C D E
Description
of Assets.
Refer to
Asset
Category
Rating table
Important
Dam/Reservoirs
Major Pumping
Stations
Important
Communications/Dat
a Facilities
Operation Centres
Major WTP/WWTP
Critical office
complex.
Minor
Dam/Reservoirs
Storage Tanks
Semi Major PS’s
Important PRV’s
Important borefields
and ancillary
equipment
Important WTP’s &
GWTPs
Minor WWTPs
Regional office &
major operations
depots
Important
communication
towers/nodes
Minor Storage Tanks
PRV’s
Important WPS’s and
WWPS(Riverwise)
Minor Borefields and
ancillary equipment
Minor WTP’s & GTWPs
Major office complex
incorporating an operations
depots
Individual Bores
Minor communication
towers
Small operations depots
Minor PS’s
Minor PRV’s
Drainage Basins
Steep sided open drains
Small borefields and
ancillary equipment
Bridges & Drainage
drop structures easily
accessed by public
Pipe reserves
Swale drains
Recreational type
basins
Pits in isolated
locations
Flood protection
structures with valves
that release water
Drainage monitoring
stations
Physical Category B plus
Consider multiple
barriers and/or levels of
hardened physical
protection.
Category C plus,
Consider strong deterrent
fencing considered
(palisade, electric, razor
wire.)
Category D plus,
Door plates of substantial
thickness.
Hinges enclosed or intruder
resistant.
Category E plus,
Basic fencing 1.8 m chain
mesh with barbed wire top
and bottom and/or inherent
exclusion provision from
Public safety/Child
exclusion fencing where
appropriate (1.2m chain
mesh)
Child safety barriers on
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed Ver 1 Rev1
Page 46 of 57
© Copyright Water Corporation 2004 -2016
Asset Types
(Indicative)
A B C D E
or
Substantially engineered
structures and operating
equipment enclosures with
substantial engineered
preventive mechanism
placed on access and entry
points.
Consider vehicle penetration
and perimeter bollards or
similar controls
considered to prevent damage to buildings and
operating equipment.
Drinking water storage
hatches to be alarmed.
Dam offtake tower bridge:
Substantial antic climb
protective barriers
above and below the
access structure
Dams – hardened locking,
hinge fittings & door/grill
access to gallery & tunnel.
Consider intruder alarm on
major external valve pits &
control cubicles.
Chain mesh fencing higher
than 2.1 m.
Secure profile keying to critical
site elements.
Fencing installed to minimum 1.8
m high with three strands of barbed
wire; or
Buildings, structures and operating
equipment provided with hardened
protection.
Drinking water storage hatches to
be alarmed, where practicable.
Single emergency action egress
to all perimeter and internal
doors
operational units
Install equipment in pits
with manhole covers,
cabling in conduit, light
covers locked
Drinking water storages to
have ADWG compliant -
secure profile locks and
locked (padlocks to be
covered) hatches
structures.
Design out of unsafe
features i.e. use of swale
drains and other velocity
minimisation techniques
Pits covered where
necessary.
Graffiti resistant
treatments
Restricted profile locks
on all access hatches
Lighting Category B plus,
Strong comprehensive
and building permanent
perimeter lighting.
Category C plus,
Movement sensor
switched lighting to key
access areas with short
strike activation.
Category D plus;
Where appropriate, all night
building perimeter lighting on
all primary access doors and
emergency access points.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed Ver 1 Rev1
Page 47 of 57
© Copyright Water Corporation 2004 -2016
Asset Types
(Indicative)
A B C D E
Installed where practicable in
environmentally robust &
vandal resistant containers
Electronic Category B plus,
Consider CCTV
integrated with
photoelectric external
perimeter beams with
offsite control
Category C plus,
AS 2201.1 compliant
Monitored intruder
alarms to asset physical
perimeter and /or critical
buildings and operational
equipment.
Consider external
intruder alarm beams and
technology
Consider remote
monitored – alarm
integrated CCTV &
access control to entrance
points where appropriate.
Dams – intruder alarms:
At offtake building
Gallery & tunnel
entrances
Category D plus,
Monitored intruder alarms to
buildings and operational
equipment where assessed.
Multisector activation detectors
to be installed.
Monitored smoke/heat
detection alarm installed, where
appropriate.
All exposed externally run
communications cabling
and wiring enclosed in
vandal resistant and fire
resistant conduit.
Fire Category D plus:
Consider requirement for
separate integrated Fire
panel and detection/alert
systems with direct
Brigade alarms(DBA)
Consider FRL separation
for wall and floor
Category D plus:
Structures all built to principles
of AS 3959
Ember screens requirement and
heat survivability assessed
Active, externally reporting fire
detection systems installed to
Category E plus:
Flammable materials
cabinets installed where
required
Fire fuel load, hazard
separation requirements
assessed
Maximum distance
regulatory required fire
breaks and Asset Fire
Protection Zones installed
to State and AS3959
standards
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed Ver 1 Rev1
Page 48 of 57
© Copyright Water Corporation 2004 -2016
Asset Types
(Indicative)
A B C D E
structures.
Consider independent fire
suppression systems
requirement
Consult with Corporation
insurers
electronic systems (Intruder
Alarm)
Fire Hose/Hydrant requirement
assessed
Consider AS compliant fire
rated door requirements
Building structure
flammability, hazard
separation requirements
assessed
Fire thermal barrier
requirement for isolated
assets risk assessed
Fire Extinguishers assessed
and installed to AS 2444
Emergency exits and
emergency exit signs Community Category B plus,
Regular regional and
district Police and
emergency services
liaison.
Regular active utility and
stakeholder liaison
occurring (Police;
Rangers etc)
Category C plus;
Active local “Community
Watch” operating.
Regular “Community
Watch” stakeholder
briefings occur.
Category D
Signage identifies all hours
emergency and security
number
Access
Control Category B plus,
Site access restricted to
operational and
necessary access only, at
all times.
Category C plus,
Specific site access
control management
procedures apply.
Consider electric (auto)
gates at treatment plants
and major depots.
Category D plus,
Active identification pass
system in place where intruder
alarms exist.
All contractors and visitors
require entry authorisation and
notification.
Information Category B plus,
Signage/community
Category C plus,
Plans on site to be
Category D plus,
Clear perimeter ownership and
Category E plus,
Perimeter signage restricted
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed Ver 1 Rev1
Page 49 of 57
© Copyright Water Corporation 2004 -2016
Asset Types
(Indicative)
A B C D E
based corporate
information reviewed for
sensitive operational
information.
Site plans and
operational procedures
and processes are all
available and marked for
sensitivity and actively
controlled.
secured and controlled.
All emergency plans and
manifests secured within
a designated building
within the perimeter.
deterrent signage on all
perimeter fence panels or
buildings and structures, where
no fence exists, which are
readily viewable by the
community (min 100 metres
apart – recommend 50 metres)
All emergency manifests
secured within the external
perimeter.
to ownership and specific
hazard warning
information.
Documented security
systems plans, alarm
response measures,
commissioning certificates
and maintenance
requirements.
Response Category B applies
plus,
Onsite static security
guards when advised.
Contingency plan
integrated and actively
practised with
emergency services and
response agencies.
Contingency resources
readily available and
routinely checked.
Category C applies plus,
24 x 7 response applies,
Enhanced response from:
Onsite security alarm
Police
Emergency services
Corporation staff, if
safe
Detailed and practiced
active contingency plan.
Category D, plus
Corporation security response
in tandem with contract security
response.
Category E plus,
Reactive response only
based on local information
or reports.
Security response when
advised of confirmed
security breach.
Procedural Category B plus
Site operations and
safety strictly controlled.
Site visits closely
monitored and
controlled.
Specific safety training
required where
applicable.
Category C plus
Site-specific safety and
security briefing.
Site entry and exit
reporting and
documented.
Contractor independent
attendance documented
and monitored.
Category D plus
Site specific annually reviewed
site safety and security
assessment conducted and
documented.
Routine documented safety
and security assessment
conducted with documented
safety procedure where
required.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed Ver 1 Rev1
Page 50 of 57
© Copyright Water Corporation 2004 -2016
Asset Types
(Indicative)
A B C D E
Annual protective
systems testing and
review program.
Maintenance Category C applies
Any security systems
and physical control
failures to be
investigated, documented
and rectified as a priority
maintenance item.
Category C applies Category D plus
Review of designated physical
security controls (ie: fences;
gates and locks) and security
systems to ensure they are
covered as part of the automatic
annual maintenance plan.
Active annual maintenance
program.
Compliant to Australian or
industry standards.
Documented maintenance
requirements.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 51 of 57
© Copyright Water Corporation 2004 -2016
APPENDIX 4 - WATER CORPORATION SECURITY PANEL LIST
The Water Corporation has three panels that designers, project managers and commissioning managers can access
to get services regarding security design, installation and maintenance:
Site security & risk consultancy;
security system installers; and
lock ‘Bilocks’ products.
Designers, project managers and commissioning managers can access the panel lists from the Procurement
Operations Section in the Property & Procurement Branch. Contact details of the Property & Procurement Branch
are available from the WaterNet homepage.
Externals contractors (including designers, consultants, etc.) shall, in collaboration with Water Corporation
personnel, ensure that only members listed on the panels are used to deliver relevant services.
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 52 of 57
© Copyright Water Corporation 2004 -2016
APPENDIX 5 – STATUTORY DECLARATION PROFORMA
WESTERN AUSTRALIA
THE EVIDENCE ACT, 1906
STATUTORY DECLARATION
I,
of
do, solemnly and sincerely declare that I have read and fully understand my statutory commercial, personal and
legal obligations hereunder detailed by this declaration and my solemn declaration to this effect.
CONFIDENTIALITY DECLARATION
DS 62 means Water Corporation Design Standard No. 62, all associated plans, drawings, photographs and other
material provided in support of the DS 62 manual.
“The Water Corporation” means the person, place, business entity, incorporated company, partnership or any other
arrangement, authorised representative or agent, recognised under Australian law, for whom, and where the
services are to be provided, either individually or collectively.
I, the person whose name and address is set out in the statutory declaration hereto, acknowledge that, in the course
of performing or providing duties or services to or for The Water Corporation, I was provided with Design
Standard DS 62, and supporting plans and associated documents.
I declare that I have not made copies, facsimiles, or reproduced by any method the document and supporting
documents.
I declare that I have maintained the security of the document at all times, and that I have not provided it to any
other persons, not authorised to view the document, and that I have not provided any opportunity for any other
person to reproduce the document.
I declare that I have returned the original Design Standard DS 62 document as provided to us, and that I have not
retained any part of the information.
These undertakings shall be of full force and effect, and shall operate at all times hereafter, notwithstanding that I
have ceased to perform or provide any duties or services to The Water Corporation.
And I make this solemn declaration conscientiously believing the same to be true and by virtue of Section 106 of
the “The Evidence Act 1906.”
DECLARED AT
in the State of Western Australia,
this ......……………… Day of ……............................................…………. 20...……….
Signed: (by the person whose name and address are set out in the schedule hereto)
Before me: (witness)
Address
Signature (witness)
Schedule
Full Name of Signatory:
Design Standard DS 62-01
Site Security, Public Safety and Emergency Treatments
(Includes Guidelines for Selection, Type Drawings, Installation, Commissioning and Maintenance Specifications)
Uncontrolled if Printed
Ver 1 Rev1
Page 53 of 57
© Copyright Water Corporation 2004 -2016
APPENDIX 6 – DS 62 EXTERNAL STORAGE DECLARATION
Reference:
A. DS 62 – Guidance Notes (Extract Attached)
B. ASIO Security Equipment Catalogue – July 2004
The following details are provided to support the requirement to secure the Water Corporation DS 62 – Site
Security Treatments manuals.
Company …..Name of Company Receiving DS 062………………………………………………………………………………………………………………
Area Details
1 Name of person controlling the use and
security of the document.
2 WA Police Service Security Consultants
Licence No: (Copy to be attached)
3 Street address where document is secured
4 Keying system (Office)
5 Alarm system Yes/No Details:
5.1 Fully operational Yes/No Details:
5.2 Maintained annually Yes/No Details:
5.3 Installed by a licensed security installer Yes/No Details:
5.4 AS 2201 fully compliant – commissioning
certificate available Yes/No
Details:
5.5 Multi sector (i.e.: perimeter and internal) Yes/No Details:
5.6
Externally monitored (AS 2201 compliant,
WA Police approved security central
monitoring station; 24 hour continuous
monitoring)
Yes/No
Details:
6 Secure container: Yes/No Details:
6.1 Type/style/manufacturer
6.2 Locking system
6.3 Covered by movement detector Yes/No
I confirm that these details are correct and will remain as stated until the DS 62 document is returned. Witness:
..................................................................…….. .................................................................……………
[Signature] [Date] ........ / ........ / ........ Signature] [Date] ........ / ........ / ........
..................................................................…….. .................................................................……………
[Print full name] [Print full name]
CW### – ABC Reservoir complex
Agreement of Scope of Public Safety, Fire and Security Works Functional Scope SECURITY IN CONFIDENCE
Uncontrolled if Printed Ver 1 Rev1
Page 54 of 57
© Copyright Water Corporation 2004 -2016
APPENDIX 7 - EXAMPLE OF SECURITY FUNCTIONAL SPECIFICATION
Assets: ABC Water Reservoir
Risk Assessment Risks are protection of drinking water quality, chemical safety, local bushfire, vandalism, public safety
Security Category C
Relevant legislation and standards:
Occupational Safety & Health Act 1984; Occupiers Liability Act 1985; Security & Related Activities (Control) Act 1996; Emergency Management Act 2005; Surveillance
Devices Act 1999; Dangerous Goods Act.
Federal & WA State “Critical Infrastructure Owners & Operators Guidelines”; “Australian Drinking Water Quality Guidelines”; DFES guidelines; WA Dept of the Premier &
Cabinet Directives; “Designing out Crime guidelines” ;SEMC Policy 2.9
Relevant Australian Standards (Fire, Emergency, Security, Dangerous Goods, Safety, Risk)
Water Corporation standards: including S 081; DS 61, DS 62, S107, S 110, S 197, S136, S 406, Business Continuity Guidelines, Security & Fire Process Handover Guideline,
Asset Commissioning Guideline and Asset Handover Guideline.
Asset Type Requirement Rationale / Comments
ABC Water Reservoir
Fencing and Layout
(if additional fencing is
required)
Nil fencing required as existing fencing is to minimum standard
Any new fencing is to be to - In accordance with IDB Design Standards:
plans GX54-5-1 (chain wire fence).
Chain wire fence to be black PVC coated.
Clearing (where required) Local fire risk. In accordance with WA
Department of Premier & Cabinet Directive 2012/02.
Architectural
Reservoir doors to have fully enclosed hinges and fully protected door
locking covers to fully enclose GSR bilock padlocks)
Roof designed to not allow accumulation to fire hazard and leaf litter with
no guttering and drainage. Local fire risk. In accordance with AS3959 and DFES guidelines.
Hinges fully enclosed or intruder resistant. In accordance with DS 62. Preference for hinge bolts or hinges selected
with no externally removable pins and tamper proof fixtures.
CW### – ABC Reservoir complex
Agreement of Scope of Public Safety, Fire and Security Works Functional Scope SECURITY IN CONFIDENCE
Uncontrolled if Printed Ver 1 Rev1
Page 55 of 57
© Copyright Water Corporation 2004 -2016
The leading edge of the doors to have a robust protective stripe installed to
fully cover the gap and the door locking hardware when the door is closed,
or strike protection plates installed to door locking hardware. Industrial
strength automatic closes to be installed to the opening doors.
In accordance with DS 62. Plate or door physical design to fully cover
external leverage points.
Locks to gates and doors. Restricted profile bi-locks (GSR bilock profile)
on all access hatches and doors. Provide strike protection plates across all
exposed door locking equipment and points along door edges where
mechanical advantage may be used.
Key to main access (regional bi-lock on door and gate) to GSR bi-lock
locking profile.
No external door handle to be fitted
Locks in accordance with GSR Water Assets bi-lock locking standard.
(Locksmith – Bullant Security).
Vehicle impact protection bollards
Where a risk exists of vehicle impact against electrical or other critical
infrastructure, or an unmarked bend with a sharp gradient, a reflective
robust protective vehicle (truck) bollard is to be installed.
Technical
Security alarm system
Existing alarm system to chlorination module to be upgraded to a Tecom
Challenger panel. Installation in accordance with AS 2201.1 (DS 62) by
Water Corporation approved, police licensed security alarm installer.
AS compliant screamer inside; all with 36 hour battery backup power.
Installation in accordance with AS 2201.1 (DS 62) by Water Corporation
approved, police licensed security alarm installer.
Magnetic reed switch alarms to all Reservoir doors and hatches, external
electrical and control cabinet doors integrated into the tank compound
security panel.
Separate Signals via SCADA to Water Corporation Operations Centre
All exposed externally run communications and security cabling and
wiring enclosed in vandal and fire resistant conduit.
Provide fire and lightning protection to the communications equipment
and backup batteries.
Other security items to standards (DS 61 and DS 62).
No external lighting at any of these sites.
Signage Signage to be installed in accordance with S197. Perimeter fencing signage, Hazmat signs and security alarm warning
signs
Fire Bush Fire Brigade fire-water connection to be provided near entrance gate.
Connection to be compatible with Bushfire Brigade standard connection.
The connection to be visible from gate (locate between structures and
gate) and flush to ground with a visible marker.
CW### – ABC Reservoir complex
Agreement of Scope of Public Safety, Fire and Security Works Functional Scope SECURITY IN CONFIDENCE
Uncontrolled if Printed Ver 1 Rev1
Page 56 of 57
© Copyright Water Corporation 2004 -2016
Check with region as this connection may not be required if another
connection point is accessible within the locality.
Design & Project
Standards
All design and installation to be conducted using:
Water Corporation approved, police licensed security consultants (not
required – SPM included in project) , with
Final approvals by the Corporation Security Program Manager.
Installation standard to be in accordance with DS 62, Australian
Standards and WA Government standards.
Installation by Water Corporation approved Police licensed security
installers
Commissioning
Commissioning and handover.
Commissioning and handover to be in accordance with the Water
Corporation Security & Fire Process Handover Guideline, with
final approvals by the Corporation Security Program Manager.
Provide documented security systems plans, alarm response measures,
commissioning certificates and maintenance requirements.
All Hazmat, manifests and ERP (emergency plans) secured in a
designated building and/or container within the secure perimeter.
Approved by Name Signature Date
Security Program Manager Stephen MacCarthy
Uncontrolled if Printed
Ver 1 Rev1
Page 57 of 57
© Copyright Water Corporation 2004 -2016
END OF DOCUMENT