design philosophy for transformer pit

10
Design Philosophy for Transformer Pit In this page I will talk about how to determine the size of oil containment for transformer. Following is a typical picture of a transformer and its foundation with oil containment. Now, you will follow the below steps to determine the foundation and size of spilled oil containment. Step-1 : Review of Transformer drawing (Vendor Equipment Drawing) You need to review transformer drawings from foundation design point of view and check whether you have all the following information: Transformer Erection weight (D e ) Transformer Operating weight (D o ) Plan dimension of Transformer base Height of transformer and location of oil tank Total volume of oil in the oil tank Transformer Center of Gravity location in empty condition and operating condition for Seismic load calculation and application

Upload: umer-aleem

Post on 08-Dec-2015

273 views

Category:

Documents


4 download

DESCRIPTION

as subject

TRANSCRIPT

Page 1: Design Philosophy for Transformer Pit

Design Philosophy for Transformer Pit  

In this page I will talk about how to determine the size of oil containment for transformer. Following is a typical picture of a transformer and its foundation with oil containment.

Now, you will follow the below steps to determine the foundation and size of spilled oil containment.

Step-1 :  Review of Transformer drawing (Vendor Equipment Drawing)

You need to review transformer drawings from foundation design point of view and check whether you have all the following information:

Transformer Erection weight       (De) Transformer Operating weight    (Do) Plan dimension of Transformer base Height of transformer and location of oil tank Total volume of oil in the oil tank Transformer Center of Gravity location in empty condition and

operating condition for Seismic load calculation and application Anchor bolt detail (size, location, projection, etc..) and transformer

supporting details

Page 2: Design Philosophy for Transformer Pit

Step-2 :  Verification of foundation location, elevation and external fittings loads

You need to review Plot plan, Equipment location drawings and 3-D Models and check whether you have all the following information:

Verify the area available for foundation and containment. Verify transformer Foundation and containment location and Elevation  Electrical and Instrument duct banks Bus duct support and foundation

detail, on and around the transformer pit  Locations of underground pipes  Location of fire hose and sprinkler around the transformer  Locations and extent of fire wall and construction type of fire wall  Verify the location and extent of new/existing foundations not shown in

3D model or plot plan.

Step-3 :  Soil / Geotechnical  information:

Following Geotechnical information are required to start the foundation and spilled oil containment:

Soil allowable Bearing pressure or pile capacity (Tension, compression and Lateral force capacity)

Soil density Active soil pressure co-efficient of soil Earthquake soil pressure co-efficient Ground water table location Frost depth (for winter snow)

Page 3: Design Philosophy for Transformer Pit

Step-4 :  Transformer Pedestal sizing criteria:

Transformer pedestal shall be sized according to the following criteria: 

Face-to-face pedestal size shall be the larger of the following:

(a)      Bolt c/c distance + 175mm

(b)      Bolt c/c distance + 8 x bolt diameters

(c)      Bolt c/c distance + sleeve diameter + 150mm

(d)     Size of base frame + 200mm

(e)     Bolt c/c distance + 2 x (minimum bolt edge distance)

 It is desirable to make the pedestal deep enough to contain the anchor bolts and keep them out of the mat.

Step-5 :  Transformer spilled oil containment sizing criteria:

Containment size shall be calculated for worst condition. It is assumed that worst condition will be happened when total oil is in the containment + Transformer on fire + Heavy rain fall. So, total containment volume will be, addition of following items:

Volume of transformer oil (mentioned in the equipment drawing) Transformer on fire:  When transformer is on fire (refer IEEE-980 annex-

B or NFPA-850 chapter-6) the entire hose pipe (deluge system) will spray the water on all four sides and top of the transformer.  So total volume of water will be: Water volume = (Total surface area of the transformer (all 4 sides) + top plan area of transformer) x rate of water flow from hose pipe per unit area x total fire rating time.

Rain water:  Total volume of rain water shall be calculated for total fire time. So volume of rain water = Rain fall intensity (mm/hr) x Plan area of containment  x total fire rating time.

Generally, you will find that containment area is full of stones (40 mm down). In this case, we consider that 35% void is available to accommodate the above volume of oil and water mix. So, you need to increase the capacity of the containment accordingly. 

Page 4: Design Philosophy for Transformer Pit

Step-6 :  Anchor Bolt Check:

Design of anchor bolts shall be based on the following considerations. Corrosion allowance should be considered when required by the project design criteria.

Tension Check: The maximum tension force in the anchor bolts (Tmax) may be calculated according with following formula:

Tmax  =  M / (Ny x BCD)  -  (De / Do) / Nb

Where,  M = total maximum moment on foundation              BCD = Bolt c/c distance              Ny = No. of  bolt row              Nb = no. of anchor bolt 

Use De or Do whichever is critical.

Shear Check:When anchor bolts are utilized to resist shear, the unit shear per bolt shall be calculated as follows:

Vmax = V / Nb    where, V = total shear force on anchor bolt.

Frictional resistance to shear between the transformer base plate and the concrete or grouted bearing surface shall be utilized to resist shears induced by wind or by other static loads.  Frictional resistance shall not be employed to resist shear induced by seismic loads.  For seismic-induced shear, adequate mechanical means shall be provided to resist horizontal shear, either by means of properly detailed anchor bolt / bolt hole arrangements or through a combination of anchor bolts, shear lugs, or other anchorage devices.  The static coefficient of friction between steel and concrete or between steel and cementitious grout shall be considered as 0.4 or specified in project design criteria.

Tension Shear Interaction check:When anchor bolts are subjected to combined shear and tension loads, the design shall be based on satisfying  interaction formula (say Appendix-d of ACI 318).

Please note that anchor bolt edge distance, spacing and load capacity shall be as per project design criteria.

Page 5: Design Philosophy for Transformer Pit

Step-7 :  Load combinations for foundation sizing / Pile loads and Foundation design:

You need to create the load combination per your project design criteria. However, I have created this load combination based on ACI 318:Load combination for Foundation sizing and Pile load calculation (un-factored load calculation): 

LC1:  Do  LC2:  (De) + Wind LC3:  De + Seismic LC4:  Do + Wind LC5:  Do + Seismic

Load combination for Pedestal and containment mat foundation design (factored load calculation): 

LC6:  1.4*(Do) LC7:  0.75 [1.4 De] +1.6 Wind LC8:  1.2 De +1.0 E LC9:  0.75 (1.4 Do ) + 1.6 Wind LC10:  1.2 (Do)  + 1.0 E

The weight of the foundation and of the soil on top of the foundation shall be included as dead load in all of these load combinations. 

Page 6: Design Philosophy for Transformer Pit

Step-8 :  Loads on containment wall

Containment wall  shall be designed for following loads and load combinations:

Active soil pressure on the wall Surcharge load on wall due to live load on soil. You need to discuss with

construction about any site crane movement around the transformer pit. Earthquake load on wall due to soil movement. Use Monobe

Okabe Equation for Earthquake load calculation.

For requirement of firewall refer NFPA-850 chapter-5.

Now from above steps, you have learnt the following:

Different types of loads on foundation Different criteria  for the pedestal sizing Maximum tension and shear force on each anchor bolt A sample load combinations.

To complete the foundation design, your work will be to create following calculation sheets:

A calculation sheet for anchor bolt embedment length check (ex: ACI 318 appendix-D).

A calculation sheet for foundation sizing (considering soil bearing pressure, Sliding, Buoyancy, uplift of foundation due to frost and overturning) or pile load (tension, compression and shear on each pile) calculation and check with soil consultant for acceptable values.

A calculation sheet for foundation, pedestal and containment wall reinforcement calculation per your project design criteria.