design of slow sand filter final
DESCRIPTION
Excel file for Design of Slow sand filterTRANSCRIPT
Adavisomanal and 30 Villages Jal NIrmal Project
Detalied Scheme Report Niketan Consultants
Design of Slow sand filterAdavisomanal & 30 Villages
As per CPHEEO manual clause the economical cost design of slow sand filter to be adopted
Total quantity of water per day to be treated 3600 Cum / day
Since slow sand filters work for 24 hrs a day the quantity to be filter per hour
= 3600 = 150 Cum / per hour24
The rate of filtration for slow sand varies between 0.1 M to 0.2 M per hour. Since sedimentation process followed by Raw water storage tank (3 hrs - storage) has been provided, the rate of filtration in this can be adopted 0.150 M / hr.
= 150 = 1000 Sqm0.150
As per CPHEEO manual 6 Nos of filter beds are to be provided.As per economical cost design (page - 241)
= 2 A Wheren + 1 l = Length of wall
b = breadth of wallb = ( n + 1 ) l A = Total surface area of filter bed
2 n n = Nos of filter beds
A = n l b
As surface works out Less than 1200 Sqm.As per CPHEEO manual, number filter beds required is 5 But provide 8 Nos.
Therefore, A = 8 l x b
= 2 x 10008 + 1
= 2000 = 222.222222229
l = 14.90711985Say = 15.00 M
Therefore, A = 8 x l x b
1000 = 8 x 15.00 x bb = 1000
15 x 8b = 8.3333333333
Say b = 8.5 M
Therefore, The area of slow sand filter bed requirement
l 2
l 2
l 2
Adavisomanal and 30 Villages Jal NIrmal Project
Detalied Scheme Report Niketan Consultants
Therefore,Area provided is 15.00 x 8.5 m 8 No of BedsTherefore, Each bed will have Length = 15 M
breadth = 8.5 M
Surface area of each bed = 127.5 Sqm
Total Surface area of 8 bed = 127.5 x 8 = 1020 > 1000 Sqm
Hence OkCheak for Over loading
Let us assume 1 Filter bed is Washed at a time
Filteration capacity of each filter = 150 = 0.2 Cum /hr = .2 Cum /hr15 X 8.5 x 7
Hence Ok
The schematic lay out of slow sand filter bed be as under
Design of Filter Bed
Let filter bed be as under with over all depth of filter bed = 2.70 mt
0.20mt Free board
1.0mt supernatant water
2.71.0mt Initial loading of filter Sand
0.40 mt Gravel
0.10 mt Under drain
Sand Spcification
Size of sand = 0.2- 0.3 mm
Uniformity co-eff = 5
Graval Spcificat = 5.0 layers (0.4 m)
Size of garval = 2.0 mm 40 mm
Size of garval i = 2.0 5 10 20 40
depth in mm = 80 80 80 80 80
Adavisomanal and 30 Villages Jal NIrmal Project
Detalied Scheme Report Niketan Consultants
Design of under Drain
Area of each filter = 15.00 x 8.5 = 127.5 Sq Mts
ratio of area of perforation to area of filter = 0.15% to 0.3 %
Provide area of perforation = 0.15 / 100 x 127.5
= 0.19125 Sqm 1912.5 Sqcm
Ratio of total perforation to total C/S area of latral
for perforation of 12 mm = 2 to 1 % cross sectional area
Total Cross sectional area of latrals = 1.5 x 1913
= 2868.8 Sqcmt
Area of central manifold = 1.5 x 2868.75
= 4303.125 Sqcmt
Cross section of center manifold with depth of 100 cmt
therefore width of central manifold = 4303 Cm
Provide central manifold of 60 cmt depth ,75 cmt wide
Design of Lateral:-
Assuming 63 mm dia of PVC cmt latral
Now internal Dia of 63 mm dia PVC Pipe = 58.1 mm
No. of Laterals = Total Area of laterls
C/S Area of one Lateral
= 28.6875 = 110 Nos.
Spacing of Laterals= 15 = 0.273 m
55 Say 250mm C/C
Length of Laterals on each side = Width of filter bed - Width of Manifold
2
= 8.5 - 0.75 = 3.875m
2
Which is Less Than 3.78(60x.063=3.78m) Hence Ok
Design of Orifice:-
Area of Orifice = 0.2 X 15 X 8.5
100
= 0.19125 Sqm
Adopting Spacing Of 18 cm C/C
Total Area of Orifice on each Laterals = 3.875 x 100
= 387.5 Cm
No. of Orifice = 0.1913 x 100 x 100 = 9 Nos.
110 x 2
Diameter of Orifice d= 0.19125 x 4 = 0.49 Cm
3.142
0.785x0.05812
Adavisomanal and 30 Villages Jal NIrmal Project
Detalied Scheme Report Niketan Consultants
Thus provide 9mm Orifice at 180 mm C/C
Adavisomanal And 30 Villages Jal Nirmal Project
Detailed Scheme Report Niketan Consultants
Design Of Sedimentation tank Total demand = 3600 Cum/Day
=With 20 hrs pumping = 180 Cum/Day
Detention provide = 3 Hrs
Capacity Sedimentation Tank = 3 X 180 = 540 Cum
If two units provided
capacity of each unit =
540= 270 Cum
2
with average water depth in tank as 3.0 mts, Surface area of tank = 270
= 90 Sqm3
Length to Width ratio is 1 : 3 = 3B2 = 90 SqmB = 5.48Say 5.5 M
L = 3 x 5.50 = 16.5MtsSo, Provide 16.5 Mts X 5.5 Mts of each unit Total Area Provided = 90.75 Sqm > 90 Sqm Ok
Total area provided = 2 (16.5 x 5.5 x 3.0) = 544.5cum > 540 Cum Hence, OK
16.5 Mts
Unit 15.5 Mts
Unit 2 5.5 Mts
16.5 Mts
Check for Surface loading = 3600
= 19.840 Cum/Sqm/Day < 36 Cum/Sqm/Day90.75 x 2.0
Hence Ok
Overall Depth of each Unit with 3.0 mts standing water depth (SWD) = 3 + 0.3 0 (FB) + 0.3 (Sluddge) += 3.6 Mts
Inlet And out let Weir
Inlet weir (Influent channel with bottom openings )
keeping velocity of water in channel = 0.3 m/sec
and keeping width of channel as = 0.3 m
For discharge of 180 Cum/hr i.e. = 0.05 Cum/sec
Depth of channel in each unit = 1/2 x
0.05 = 0.28 Mts0.3 x 0.3 Say 30 cmt
With FB of 20 cmt , total depth of weir be = 50 cmt
Adavisomanal And 30 Villages Jal Nirmal Project
Detailed Scheme Report Niketan Consultants
The cross section of Influent channel = 0.3x 0.3 mCheck for weir loading Length of wier in eah unit = 5.5 MtsFlow per unit per day = 3600 /2 = 180 Cum /hrTherefore weir loading = 1800/ 5.5 = 327.27 cum / mt /day Between 100 -300 cum /mt / day As it ismore 300Cum/m/ day Let us incrseth length of weir to 6.5 m Now The Modified dimension for the Sedimentation Tank is Length of Sedimentation Tank = Area of C/s
=90
=13.846
Breadth 6.5Say 14 M
Check for weir loading Length of wier in eah unit = 6.5mFlow per unit per day = 3600 /2 = 180 Cum/hrTherefore weir loading = 1800/ 6.5 = 276.93 cum / mt /day Between 100 -300 cum /mt / day
Hence Ok
Check for Surface loading = 3600
= 19.780 Cum/Sqm/Day < 36 Cum/Sqm/Day91 x 2.0
Hence OkThus the Final Dimension Are = 2 Sets 14 m x 6.5m
14.0 Mts
6.5 Mts
6.5 Mts
14.0 Mts
Bottom floor slope 1 : 12
Hydraulic Design of baffle wall
Flow in each Tank = 180 Cum/hr = 0.05 Cum/Sec
Velocity of Flow of flow of water for dispersal = 0.15 /Sec
Area of opening required – in baffle wall = 0.15 = 0.333 Sqm
3 0.15
Opening below baffle wall for movement of sludge and water, provided 45
cm considering sludge deposit of 25 cm before flushed one.
Therefore opening available below for flow of water (45-25)_ 20 Cm
The baffle wall is supported over 20 x 20 Cm columns 3 Nos.
Hence length of opening available = 6.25 - (0.2x3)
= 5.65 M
Area of opening available = 5.65 x 0.2 = 1.13 Sqm.
Hence bottom opening adequate.
But to make proper dispersal at higher level
For Sludge removal, let is divide the Box Slab in each tank into 2 halves longitudinally and slope be provided in word to make into to two hopper of 30 x 30 m in the center and sludge removed by by sludge pipe. To economies construction cost, let the tanks be constructed back to back longitudinally to ensure equal flow into sedimentation tank a distribution box with rectangular weir and flush type inlet valve to each tank.
For uniform dispersal of flow of water provide perforated baffle wall in front of inlet pipe at 1.2 M away from the wall.
Adavisomanal And 30 Villages Jal Nirmal Project
Detailed Scheme Report Niketan Consultants
Let us provide 15 x 15 Cm Square opening in the wall as under.
Adavisomanal and 30 Villages Jal Nirmal Project
Detailed Scheme Report Niketan Consultants
Design of Pipe from Raw Water Sump To Distribution BoxNo. of Filter Beds= 8 NosQty of water to be Treated= 150 Cum/HrQty of water to be Treated by pipe= 150 Cum/Hr
= 0.04167 Cum/SecAssuming the Velocity of flow In the pipe as= 0.5 M/sec
Dia of pipe= 0.04167 x 40.5 x 3.142
= 0.3257Provide 250 mm Dia CI Pipe
Now, Velocity in pipe V=Q/AV= 0.04167
0.785 X 0.25 X 0.25= 0.85 M/sec
Hence OkCalculation Of Head Losses in pipe:
Length of pipe= 30 mHazen Willam Constant= 100
Area of Cross Section in pipe A= 3.142 X 250 X 250 = 490944
Wetted perimeter = 3.142 x 250 = 785.5 mmHydraulic Mean Radius r = 62.5 mm = 0.0625 m
Now, Accroding to Hazen Willams Formula 0.63 0.54
0.85 = 0.854 x 100 x 0.0625 x SS = 0.00498 m/m
Frictional Losses= 0.164 mOut let RL at Raw water Sump= 595.2 Minlet RL at Distribution Chamber= 595.036 M
Design Of interconnecting From Distribution tank(Inlet Equidistrbution Retangular Weir) For Slow sand Filters Since Separate pipes Are Tobe Give From Distribution Tank to SSFDischage In each Filter= 0.00521 Cum/SecAssuming the Velocity of flow In the pipe as= 0.5 M/sec
Dia of pipe= 0.00521 x 40.5 x 3.142
= 0.1152Provide 100 mm Dia CI Pipe
Now, Velocity in pipe V=Q/AV= 0.00521
0.785 X 0.1 X 0.1= 0.66
Hence OkCalculation Of Head Losses in pipe:For SSF 1,SSF 4 on either side
Length of pipe= 30 mHazen Willam Constant= 100
Area of Cross Section in pipe A= 3.142 X 100 X 100 = 78554
Wetted perimeter = 3.142 x 100 = 314.2 mmHydraulic Mean Radius r = 25 mm = 0.025 m
Now, Accroding to Hazen Willams Formula 0.63 0.54
0.66 = 0.854 x 100 x 0.025 x SS = 0.00498 m/m
Frictional Losses= 0.16434 mOut let RL at Distribution Box= 595.03 Minlet RL at Distribution Chamber= 594.86566 M
mm2
V= Q/A=0.854XCX r.63xS0.54
mm2
V= Q/A=0.854XCX r.63xS0.54
Adavisomanal and 30 Villages Jal Nirmal Project
Detailed Scheme Report Niketan Consultants
For SSF 2,SSF 3 on either sideLength of pipe= 15 m
Hazen Willam Constant= 100
Area of Cross Section in pipe A= 3.142 X 100 X 100 = 78554
Wetted perimeter = 3.142 x 100 = 314.2 mmHydraulic Mean Radius r = 25 mm = 0.025 m
Now, Accroding to Hazen Willams Formula 0.63 0.54
M = 0.854 x 100 x 0.025 x SS = 0.00498 m/m
Frictional Losses= 0.08217 mOut let RL at Distribution Box= 595.03 Minlet RL at Distribution Chamber= 594.948 M
Design Of interconnecting From Slow sand Filters Out let to Rure Water Sump One of Slow Sand Filter = 8 Nos.Qty of water to be Treated= 143.75 Cum/HrQty of water to be Treated by each pipe= 17.9688 Cum/Hr
= 0.00499 Cum/Seca. From SSF 1 to Junction SSF2Since pipes Are inter connceted from SSF 1 to SSF2Discharge in pipe = 0.0049913 Cum/SecAssuming the Velocity of flow In the pipe as= 0.5 M/sec
Dia of pipe= 0.00499 x 40.5 x 3.142
= 0.1127Provide 100 mm Dia CI Pipe
Now, Velocity in pipe V=Q/AV= 0.00499
0.785 X 0.1 X 0.1
= 0.636 M/secHence Ok
Calculation Of Head Losses in pipe:
Length of pipe= 15 mHazen Willam Constant= 100
Area of Cross Section in pipe A= 3.142 X 100 X 100 = 78554
Wetted perimeter = 3.142 x 100 = 314.2 mmHydraulic Mean Radius r = 25 mm = 0.025 m
Now, Accroding to Hazen Willams Formula 0.63 0.54
0.64 = 0.854 x 100 x 0.025 x SS = 0.00498 m/m
Frictional Losses= 0.08217 mOut let RL at Slow Sand Filter = 593.88 M RL at Outlet of SSF 2 = 593.798 M
b. From SSF 2 to Junction SSF3Since pipes Are inter connceted from SSF 2to SSF3Discharge in pipe = 0.0099826 Cum/SecAssuming the Velocity of flow In the pipe as= 0.5 M/sec
Dia of pipe= 0.00998 x 40.5 x 3.142
= 0.1594
mm2
V= Q/A=0.854XCX r.63xS0.54
mm2
V= Q/A=0.854XCX r.63xS0.54
Adavisomanal and 30 Villages Jal Nirmal Project
Detailed Scheme Report Niketan Consultants
Provide 150 mm Dia CI Pipe Now, Velocity in pipe V=Q/A
V= 0.009980.785 X 0.15 X 0.15
= 0.565 M/secHence Ok
Calculation Of Head Losses in pipe:
Length of pipe= 15 mHazen Willam Constant= 100
Area of Cross Section in pipe A= 3.142 X 150 X 150 = 176744
Wetted perimeter = 3.142 x 150 = 471.3 mmHydraulic Mean Radius r = 37.5 mm = 0.0375 m
Now, Accroding to Hazen Willams Formula 0.63 0.54
0.57 = 0.854 x 100 x 0.0375 x SS = 0.00498 m/m
Frictional Losses= 0.08217 m RL at Outlet of SSF 2 = 593.798 M RL at Outlet of SSF 3= 593.716 M
c. From SSF 3 to Junction SSF4Since pipes Are inter connceted from SSF3 to SSF4Discharge in pipe = 0.014974 Cum/SecAssuming the Velocity of flow In the pipe as= 0.5 M/sec
Dia of pipe= 0.01497 x 40.5 x 3.142
= 0.1953Provide 150 mm Dia CI Pipe
Now, Velocity in pipe V=Q/AV= 0.01497
0.785 X 0.15 X 0.15
= 0.848 M/secHence Ok
Calculation Of Head Losses in pipe:
Length of pipe= 30 mHazen Willam Constant= 100
Area of Cross Section in pipe A= 3.142 X 150 X 150 = 176744
Wetted perimeter = 3.142 x 150 = 471.3 mmHydraulic Mean Radius r = 37.5 mm = 0.0375 m
Now, Accroding to Hazen Willams Formula 0.63 0.54
0.85 = 0.854 x 100 x 0.0375 x SS = 0.00498 m/m
Frictional Losses= 0.16434 mOut let RL at Raw water Sump= 593.716 Minlet RL at Distribution Chamber= 593.551 M
mm2
V= Q/A=0.854XCX r.63xS0.54
mm2
V= Q/A=0.854XCX r.63xS0.54
Adavisomanal and 30 Villages Jal Nirmal Project
Detailed Scheme Report Niketan Consultants
d. From SSF 4 to pure Water SumpSince pipes Are inter connceted from SSF3 to SSF4Discharge in pipe = 0.0199653 Cum/SecAssuming the Velocity of flow In the pipe as= 0.5 M/sec
Dia of pipe= 0.01997 x 40.5 x 3.142
= 0.2255Provide 200 mm Dia CI Pipe
Now, Velocity in pipe V=Q/AV= 0.01997
0.785 X 0.2 X 0.2= 0.636 M/sec
Hence OkCalculation Of Head Losses in pipe:
Length of pipe= 30 mHazen Willam Constant= 100
Area of Cross Section in pipe A= 3.142 X 200 X 200 = 314204
Wetted perimeter = 3.142 x 200 = 628.4 mmHydraulic Mean Radius r = 50 mm = 0.05 m
Now, Accroding to Hazen Willams Formula 0.63 0.54
0.64 = 0.854 x 100 x 0.05 x SS = 0.00498 m/m
Frictional Losses= 0.16434 m RL at Outlet of SSF 3 = 593.551 M RL at inlet Level of Sump = 593.387 M
mm2
V= Q/A=0.854XCX r.63xS0.54