design of hospital building
TRANSCRIPT
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
1/43
1
DESIGN OF SLAB
INTERIOR PANEL SLAB:
Step 1:
Room size 4.23mx5.23m
Ly/Lx= 5.23/4.23
=1.24
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
2/43
2
Mx= x.w.lx^2
= 0.045x13.875x4.23^2
=11.17kN.m
My= y.w.lx^2
=0.032x13.875x4.23^2
=7.94 kN.m
M max = 0.138.f ck.b.d^2
d^2 = M max/ 0.138.f ck.b
= 11.17x10^6/(0.138x25x1000)
d = 56.9< 170 mm
hence safe.
Step 4:
Check for shear,
Ly/Lx = 1.24
Co-efficient for shear = x in ly direction= 0.33
=x in lx direction = 0.393
Max .design shear = x.w.lx
= 0.398x13.875x4.23
=23.4kN.
V/bd = 23.4x10^3/(1000x170)
= 0.138
Safe minimum: shear for M25 concrete is equal to 0.29 and hence slab is safe and shear.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
3/43
3
Step5:
Area of steel,
d = 170mm.
steel for short direction.
M/bd^2 = (11.17x10^6)/(1000x170^2).
= 0.39
{From SP 16, table3:}
Pt = 0.11%
As=(0.11x1000x170)/100
= 187.34mm^2.
spacing = (/4 x 10^2)/187.34
= 419mm.
Spacing = 400mm.
Provide 10mm dia @ 400mm c/c.
Steel for longer direction,
d = 170-10=160mm.
M/(bd^2) = 7.94x10^6/(1000x160^2)
= 0.087.
Ast = (0.087x1000x160)/100
= 139.2 mm^2.
Spacing = ((/4 x10^2)x1000)/139
= 565 mm.
Spacing = 550mm.
Provide 10 mm dia @ 300 mm c/c.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
4/43
4
Step 6:
Check deflection ,
Span depth ratio = 20.
Pt = 0.11%.
F1 = 2.
Allowable l/d ratio = 20x2 = 40.
Actual span/depth ratio = 4.23/0.170
= 24.9.
There fore assumed span depth ratio is enough to control deflection.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
5/43
5
INTERIOR PANEL SLAB
Step 1:
Thickness of slab and durability consideration
Lx = 4230mm.
Ly = 5230mm.
Cover for mild exposure= 15mm
As the span is large and loading heavy , assume a span depth ratio of 25 instead of usual 35.
d= 4230/25
= 169.2mm
= 170mm.
h = 170+6+15=191mm.
step 2:
Design of loads.
Dead load= 0.19x25x1= 4.75 kN /m^2
Floor finish = 1kN/m^2
Live load = 4 kN/m^2
Total load = 9.775kN/m^2
Factored load = 1.5x9.775 = 14.66kN/m^2.
Step 3:
Checking for depth:
Ly/Lx = 5.23/4.23 = 1.24.
From the table ,
x = 0.045.
y = 0.032.
Mx= x.w.lx^2
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
6/43
6
= 0.045x14.66x4.23^2
=11.8kN.m
My= y.w.lx^2
=0.032x14.66x4.23^2
=8.394 kN.m
Check for depth from maximum. bending moment
M max = 0.138.f ck.b.d^2
d2 = M max/ 0.138.f ck.b
= 11.8x10^6/(0.138x25x1000)
d = 58.5< 170 mm
hence safe.
Step 4:
Check for shear,
Ly/Lx = 1.24
Co-efficient for shear
x in ly direction= 0.33
x in lx direction = 0.393
Max .design shear = x.w.lx
= 0.398x14.66x4.23
=24.687kN.
V/bd = 24.68x10^3/(1000x170)
= 0.145
Safe min: shear for M25 concrete is equal to 0.29 and hence slab is safe and shear.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
7/43
7
Step5:
Area of steel,
steel for short direction.
d = 170mm.
m/bd2 = (11.8x10^6)/(1000x170^2).
= 0.408.
{From sp 16, table3:}
Pt = 0.11%
As=(0.11x1000x170)/100
= 187.34mm^2.
spacing =1000x( (/4 x 10^2)/187.34)
= 419mm.
Spacing = 400mm.
Provide 10mm dia @ 400mm c/c.
Steel for longer direction,
d = 170-10=160mm.
M/(bd^2) = 8.394x10^6/(1000x160^2)
= 0.328.
Pt = 0.092.
Ast = (0.092x1000x160)/100
= 147.2mm^2.
Spacing = ((/4 x8^2)x1000)/147
= 340 mm.
Spacing = 340mm.
Provide 8 mm dia @ 340 mm c/c.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
8/43
8
Step 6:
Check deflection :
Span depth ratio = 20.
Pt = 0.11%.
F1 = 2.0
Allowable l/d ratio = 20x2 = 40.
Actual span/depth ratio = 4.23/0.170
=24.88.
There fore assumed span to depth ratio is enough to control deflection.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
9/43
9
ONE LONG EDGE DISCONTINUOUS SLAB
Step 1:
Thickness of slab and durability consideration
Lx = 4230mm.
Ly = 5230mm.
{From IS 456-2000} Cover for mild exposure= 15mm
As the span is large and loading heavy , assume a span to depth ratio of 25 instead of usual 35.
d= 4230/25
= 169.2mm
= 170mm.
h = 170+6+15=191mm.
step 2:
Design of loads :
Dead load = 0.19x25x1= 4.75 kN /m^2
Floor finish = 1kN/m^2
Live load = 4 kN/m^2
Total load = 9.775kN/m^2
Factored load = 1.5x9.775 = 14.66kN/m^2.
Step 3:
Checking for depth:
Ly/Lx = 5.23/4.23 = 1.24.
From the table 26 {IS 456-2000}
x = 0.054.
y = 0.037.
Mx= x.w.lx^2
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
10/43
10
= 0.054x14.66x4.23^2
=14.16N.m
My= y.w.l-+^2
=0.037x14.66x4.23^2
=9.7 kN.m
Check for depth from max. bending moment
M max = 0.138.f ck.b.d^2
d^2 = M max/ 0.138.f ck.b
= 14.16x10^6/(0.138x25x1000)
d= 64.1< 170 mm
hence safe.
Step 4:
Check for shear,
Ly/Lx = 1.24
Co-efficient for shear {from IS 456-2000}
x in ly direction= 0.33
x in lx direction = 0.393
Max .design shear = x.w.lx
= 0.398x14.66x4.23
= 24.687kN.
V/bd = 24.68x10^3/(1000x170)
= 0.145
Safe min: shear for M25 concrete is equal to 0.29 and hence slab is safe and shear.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
11/43
11
Step5:
Area of steel,
steel for short direction.
d = 170mm.
M/bd2 = (14.16x10^6)/(1000x170^2).
= 0.49.
{From sp 16, table3:}
Pt = 0.138%
As=(0.138x1000x170)/100
= 234.6 mm^2.
spacing =1000x( (/4 x 10^2)/234.6)
Spacing = 300mm.
Provide 10mm dia @ 300mm c/c.
Steel for longer direction,
d = 170-10=160mm.
M/(bd2) = 9.7x10^6/(1000x160^2)
= 0.34.
{from IS 456-2000} Pt = 0.096.
Ast = (0.096x1000x160)/100
= 163.2mm^2.
Spacing = ((/4 x8^2)x1000)/163
= 308 mm.
Spacing = 300mm.
Provide 8 mm dia @ 300 mm c/c.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
12/43
12
Step 6:
Check deflection :
Span depth ratio = 20.
{from IS 456-2000} Pt = 0.138%.
F1 = 2.0
Allowable l/d ratio = 20x2 = 40.
Actual span/depth ratio = 4.23/0.170
=24.88.
There fore assumed span depth ratio is enough to control deflection.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
13/43
13
DESIGN OF BEAMS
DESIGN OF T- BEAM:
Step 1:
Datas
L = 5.23m.
Spacing =4.23m.
Df= 190mm.
Fck= 20 N/mm^2
Fy = 415 N/mm^2
Step 2:
Cross sectional dimensions,
Basic span/depth ratio for simply supported beam is 20
For tee beams, assuming the width of rib = 230mm and flange width = 4.23m.
the ratio of web width to flange width is equal to
230/4230 = 0.054.
Reduction factor = 0.8. [from fig 6 IS 456]
Hence, basic span/depth = 20x0.8
= 16.
d = span/16
5230/16 = 326.88mm.
Adopt overall depth = 400mm
Cover = 50mm.
Hence tee beam parameters are,
d = 350mm
D = 400mm
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
14/43
14
bw = 230mm
Df= 190mm
Step 3:
Loads
Self weight of slab = 0.19x25x4.23
= 20.09kN/m
Floor finish = 1x4.23
= 4.23 kN/m
Self weight of rib = 0.23x0.21x25
= 1.21kN/m
Plaster finish = 0.45 kN/m
Water proofing = 2x4.23=8.46 kN/m
Weight of parapet wall = 0.6x0.23x19
= 2.62 kN/m
Total dead load = 37.06 kN/m
Live load = 1.5 kN/m
Design ultimate load = 1.5x(37.06+1.5)
=57.84 kN/m
Step 4:
Ultimate moment and shear force
Mu = (wl^2)/8
= (57.84x5.23^2)/8
= 197.76kN.m
Vu = wl/2 = (57.84x5.23)/2
= 151.25kN
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
15/43
15
Step 5 :
Effective width of flange
1) bf= [Lo/6+bw+6Df]
= [5.23/6+0.23+(6x0.19)]
= 2.24m
2) c/c of rib = (4.23-0.23) = 4m
Hence the least value of 1 & 2is
bf= 2.42m.
step 6:
moment capacity of flange
Muf= 0.36*fck.bf.df.(d-0.42df)
= 0.36x20x2242x190x(350-0.42x190)
= 828.72kN.
Since Mu < Muf, Xu < Df
Hence the section is consider as rectangular width b =bf
Step 7:
Reinforcements
Mu = 0.87.fy.Ast.d(1-[fy.Ast/bdfck])
197.76x10^6= 0.87x415xAstx350x(1-415xAst/2242x350x20)
Ast = 1635.67mm^2.
Provide 4 numbers of 25mm dia (Ast= 1963mm^2) and 2 hanger bars of 12mm dia on compresion force
Step 8:
Shear reinforcement
v = Vu/bw.d
= 151.25x10^3/(230x350)
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
16/43
16
= 1.88 N/mm^2.
Pt = 100 Ast/bw.d
= (100x1963)/230x350
=2.44
c = 0.818
balance shear = Vu c.bw.d
= 151.25x10^3-0.818x230x350
= 85.40kN.
Using 8mm dia two legged strirup the spacing is
Sv = (0.87x415x2x50x350)/85.4x10^3
= 147.97mm
Sv >or= 0.75d
0.75x350 = 262.5mm.
Sv = 300mm.
Whichever is less
Provide 8mm dia two legged strirup at 145mm c/c length of beam.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
17/43
17
DESIGN OF L BEAM
Step 1:
Datas
L = 5m.
Spacing=4.23m.
Df= 190mm.
fck= 20 N/mm^2
fy = 415 N/mm^2
Step 2:
Cross sectional dimensions,
since L beam is subjected to bending torsion and shear force assume a trial section
having span / depth ratio = 12.
d = span/12
5000/12 = 416.67mm.
d = 450mm.
Adopt overall depth D = 500mm
bw = 230mm.
step 3 :
Effective span
Effective span is the least of
1) c/c of supports = 5.23m
2) Clear span + eff.depth = 5+0.45
= 5.45m.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
18/43
18
Step 4:
Loads
Self weight of slab = 0.19x25x0.5x4.23
= 10.05kN/m
Floor finish = 1x0.5x4.23
= 2.13 kN/m
Self weight of rib = 0.23x0.31x25
= 1.78kN/m
Water proofing = 2x0.5x4.23=4.23 kN/m
Weight of parapet wall = 0.6x0.23x19
= 2.62 kN/m
Total dead load = 23.97 kN/m
Live load = 1.5 x0.5x4.23= 3.17kN/m
Step 5:
Effective flange width
1) bf= [Lo/12+bw+3Df]
=[ 5230/12+230+(3x190)]
= 1235.8mm.
2) bf= bw +0.5 time spacing b/n ribs
= 230+(0.5x4000)
= 2230mm
bf = 1235mm.
step 6 :
ultimate bending moment and shear force at support s/c.
Mu = 1.5(23.97x5.23^2)/12
= 81.93kN.m
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
19/43
19
Vu = 1.5(0.5x23.97x5.23) = 94 kN.
At centre span s/c
Mu = 1.5(23.97x5.23^2)/24
= 40.98 kN.m
Step 7 :
Torsional moments at support s/c.
(Working load /mrip s.w)= (23.97-1.78)
= 22.19 Kn/m.
Total ultimate load on slab = 1.5(22.19x5.3)
= 176.4 kN.
Total ultimate shear force = 0.5x176.4
= 88.21 kN.
Distance of centroid of shear force from c/c = (0.5x1235-190)
= 427.5mm.
Ultimate torsional moment Tu = (88.21x0.427)
= 37.67 kN.m
Step 8:
Equivalent bending moment and shear force :
{Is 456:2000 clause 41.42}
Mel = (Mu+Mt)
Mt = Tu[1+(D/b)/1.7]
= 37.67[1+(500/230)/1.7]
= 70.3 kN.m
Mel = (81.93+70.3)
= 152.3 kN.m
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
20/43
20
Ve = Vu +1.6(Tu/B)
= 94+1.6(37.67/0.23)
= 356.1 kN.
Step 9:
Main longitudinal reinforcement
Mel = 152.3 kN.m
Mu,lim = 0.138.f ck.b.d^2
= 0.138x20x230x450^2
= 128.5 kN.m
Mel < Mu,lim
Mel = 0.87.fy.Ast.d[1-Ast.fy/bd.fck]
152.3x10^6 = 0.87x415xAstx450[1-415xAst/230x450x20]
Ast = 1251mm^2.
Provide 3nos of 25mm dia (Ast = 1472mm^2)
Ast min = (0.85.bw.d/fy)
= (0.85x230x450/415)
= 212mm^2.
= 212/(/4x12^2)
= 1.85 = 2nos.
Provide 2 nos of 12mm dia (Ast = 226mm^2)
Step 10:
Shear reinforcement :
ve = (ve/bw.d)
=(356.1x10^3/(230x450))
= 3.4N/mm^2.
Pt = (100Ast/bw.d)
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
21/43
21
= (100x1472/230x450)
=1.4
c= 0.7N/mm^2 < ve .
hence shear reinforcement are required.
Using 10mm dia and 25mm side covers and bottom cover 50mm.b1 =
180mm, d1 = 400mm,Asv = 157mm^2.
1).Sv = 92mm.
2).Sv = 91.3mm.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
22/43
22
DESIGN OF COLUMN
Step 1:
Slenderness ratio consideration :
Le/D = (0.65x3600)/230
= 10.17
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
23/43
23
Step 4:
Pu = 440.1 kN.
b = 230mm.
D = 230mm.
Fck= 20N/mm^2.
Fy = 415N/mm^2.
Step 5:
Assume Pt = 3%.
Pt = 100xAst/b.d
Ast = (3x230x190)/100
= 1311mm^2.
Provide 5 nos of 20mm dia bars (Ast=1570mm^2)
Ag = 230x230
= 52,900mm^2.
Ac = Ag- Ast
= 52,900-1570
= 51,330mm^2.
Pu = 0.4 fck. Ac + 0.67.fy.Ast
= 0.4x20x51,330 + (0.67x415x1570)
= 859.7 kN > 440.1Kn.
Step 6:
Detail of longitudinal steel.
Use cover = 40mm
Steel spacing = 230-40-40-20
= 130mm.
= 130/2 = 65mm.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
24/43
24
Clear spacing between bars = 65-20
= 45 < 230.
Step 7:
Transerverse steel :
Dia of link not less than ,20/4 or 6mm.
Use 10mm, spacing not less than
1) Dimension of column = 230mm.
2)16 times dia of long steel = 16x20
=320mm.
3) 300mm.
Adopt 300mm spacing between each link.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
25/43
25
DESIGN OF COLUMN
Step 1:
Slenderness ratio consideration :
Le/D = (0.65x3600)/230
= 10.17
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
26/43
26
Step 4:
Pu = 288.83 kN.
b = 230mm.
D = 230mm.
Fck = 20N/mm^2.
Fy = 415N/mm^2.
Step 5:
From IS 456-2000 Assume Pt = 3%.
Pt = 100xAst/b.d
Ast = (3x230x190)/100
= 1311mm^2.
Provide 5 nos of 20mm dia bars (Ast=1570mm^2)
Ag = 230x230
= 52,900mm^2.
Ac = Ag- Ast
= 52,900-1570
= 51,330mm^2.
Pu = 0.4 fck. Ac + 0.67.fy.Ast
= 0.4x20x51330 + (0.67x415x1570)
=785.08 kN > 288.3Kn.
Step 6:
Detail of longitudinal steel.
Use cover = 40mm
Steel spacing = 230-40-40-20
= 130mm.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
27/43
27
= 130/2 = 65mm.
Clear spacing between bars = 65-20
= 45 < 230.
Step 7:
Transerverse steel
Dia of link not less than ,20/4 or 6mm.
Use 10mm, spacing not less than
1) Dimension of column = 230mm.
2)16 times dia of long steel = 16x20
=320mm.
3) 300mm.
Adopt 300mm spacing between each link.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
28/43
28
Design of column on ground floor
Step 1:
Slenderness ratio consideration :
Le/D = (0.65x3600)/230
= 10.17
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
29/43
29
Total load = (2x151.23)+137.6+440.1
= 880.2 kN.
Step 4:
Pu = 880.2 kN.
b = 230mm.
D = 230mm.
Fck= 20N/mm^2.
Fy = 415N/mm^2.
Step 5:
Assume Pt = 4%.
Pt = 100xAst/b.d
Ast = (4x230x190)/100
= 1748 mm^2.
Provide 6 nos of 20mm dia bars (Ast=1885mm^2)
Ag = 230x230
= 52,900mm^2.
Ac = Ag- Ast
= 52,900-1885
= 51,015mm^2.
Pu = 0.4 fck. Ac + 0.67.fy.Ast
= 0.4x20x51,015 + (0.67x415x1885)
= 932.24kN > 880.2. kN
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
30/43
30
Step 6:
Detail of longitudinal steel.
Use cover = 40mm
Steel spacing = 230-40-40-20
= 130mm.
= 130/2 = 65mm.
Clear spacing between bars = 65-20
= 45 < 230.
Step 7:
Transerverse steel
Dia of link not less than ,20/4 or 6mm.
Use 10mm, spacing not less than
1). Dimension of column = 230mm.
2).16 times dia of long steel = 16x20
=320mm.
3). 300mm.
Adopt 300mm spacing between each link.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
31/43
31
DESIGN OF FOOTING
Step 1:
Pu = 932 kN.
b = 230mm.
D = 230mm.
P = 200kN/m^2.
Fck= 20N/mm^2.
Fy = 415N/mm^2.
Step 2:
Load on column = 932 kN.
Assume s.w of footing (10%) = 93.2 kN.
Total factored load Wu = 1025.2 kN.
Footing area = [1025.25/(1.5x200)]
Area = 3.42 m^2.
L x B = 3.42 m^2.
(1.5BxB) = 3.42 m^2.
1.5B^2 = 3.42 m^2.
B = 1.5m.
L = 1.5 x B
= 1.5x1.5
L = 2.25m.
Factored soil pressure at base is computed as
Pu = [932.2/(1.5x2.25)]
= 276.2 kN/m^2.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
32/43
32
1.5x200 = 300 > 276.2 kN/m^2.
Hence the footing area is adequate since the soil pressure developed at base is less
than the factored bearing of soil.
Step 3:
Factored B.M :
Cantilever projection from the
short side face on column} = 0.5(2.25-0.23)
= 1.01m.
Cantilever projection from the
long side face on column} = 0.5(1.5-0.23)
= 0.635m.
B.m at short side face of column is (0.5.Pu.L^2) = 0.5x276.2x1.01^2
= 140.8 kN.m
B.m at short side face of column is = (0.5x276.2x0.635^2)
= 55.69 kN.m
Step 4:
Depth of footing :
a) From moment consideration we haveMu = 0.138.fck.b.d^2.
d = 225.9mm.
b) From shear stress consideration use have the critical s/c for one way shear is
located at a distance d from the face of column.
Vu =276.2[1000.23-d].
Assuming the shear strength of c = 0.36 N/mm^2
For M25 grade concrete with Pt = 0.25.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
33/43
33
C = (Vul/b.d)
0.36 = 276.2[1000.23-d] / (1000xd)
0.36x1000xd = 276.2[1000.23-d].
= 434mm.
d = 450mm.
D = 500mm.Step 5 :
Reinfocement in footing :
1). Longer direction
Mu = 0.87.fy.Ast.d[1-Ast.fy/b.d.fck]
140.8x10^6 = 0.87x415xAstx450
. [1-415xAst/ 1000x450x20]
Ast = 896mm^2.
Adopt 16mm dia bars of 5 nos [Ast = 1005mm^2]Spacing = 200mm c/c.
2).shorter direction:
55.69x10^6 = 162472.5 Ast- 5.99 Ast^2.
Ast = 347 mm^2.
Ratio of long to short side
Bc = [2.25/1.5]
= 1.5.
Reinfocement in cement bond width 2m is
[2/B+1] Ast = [2/1.5+1]2x347
= 555.2mm^2.
Min . reinforcement = 0.12/100 x 1000x500
= 600mm^2.
Provide 12mm dia bar 6 nos (Ast = 1206.4mm^2)
Spacing = 150mm.
Step 6 :
Check for shear stress :The critical s/c for one way shear is located at distance d from the face of column . ultimate shear force
per width in the longer direction .
Vu = (276.2x0.635)
= 175.4kN.
100xAst/b.d = 100x1005.5/ (1000x230)
= 0.44.
{Table 19 from IS 456:2000}
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
34/43
34
= ks. c = 2x0.34
= 0.68.
c = Vu/bd
= 175.4x10^3/(1000x450)
= 0.39.
v < Ks. c.Hence safe.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
35/43
35
DESIGN OF FOOTING
Step 1:
Pu = 859.7 kN.
b = 230mm.
D = 230mm.
P = 200kN/m^2.
fck= 25N/mm^2.
fy = 415N/mm^2.
Step 2:
Load on column = 859.7 kN.
Assume s.w of footing (10%) = 85.97 kN.
Total factored load Wu = 945.67kN.
Footing area = [945.67/(1.5x200)]
Area = 3.15 m^2.
L x B = 3.15 m^2.
(1.5BxB) = 3.15 m^2.
1.5B^2 = 3.15m^2.
B = 1.45m.
L = 1.5 x B
= 1.5x1.45
L = 2.175m.
Provide L = 2.5m, B = 2m.
Factored soil pressure at base is computed as
Pu = [945.6/(2.5x2)]
= 189.12 kN/m^2.
1.5x200 = 300 > 189.12 kN/m^2.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
36/43
36
Hence the footing area is adequate since the soil pressure developed at base is less than
the factored bearing of soil.
Step 3:
Factored B.M :
Cantilever projection from the
short side face on column} = 0.5(2.5-0.45)
= 1.025m.
Cantilever projection from the
long side face on column} = 0.5(2-0.30)
= 0.85m.
B.m at short side face of column is (0.5.Pu.L^2) = 0.5x189.12x1.025^2
= 99.35 kN.m
B.m at short side face of column is = (0.5x189.12x0.85^2)
= 80.4 kN.m
Step 4:
Depth of footing :
a) From moment consideration we haveMu = 0.138.fck.b.d^2.
d = 170 mm.
b) From shear stress consideration use have the critical s/c for one way shear is
located at a distance d from the face of column.
Vu =189.12[689.7 -d].
Assuming the shear strength of c = 0.36 N/mm^2
For M25 grade concrete with Pt = 0.25.
c = (Vul/b.d)
0.36 = 189.12[689.7-d] / (1000xd)
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
37/43
37
0.36x1000xd = 189.12[1000.23-d].
= 237.5mm.
d = 300 mm.
D = 350 mm.
Step 5 :
Reinfocement in footing.
1). Longer direction
Mu = 0.87.fy.Ast.d[1-Ast.fy/b.d.fck]
99.35x10^6 = 0.87x415xAstx300
. [1-415xAst/ 1000x300x20]
Ast = 970 mm^2.
Adopt 16mm dia bars of 5 nos [Ast = 1008mm^2]Spacing = 200mm c/c.
2).shorter direction:
80.4x10^6 = 108315 Ast - 5.99 Ast ^2.
Ast = 775 mm^2.
Ratio of long to short side
Bc = [2.5/2]
= 1.25.
Reinfocement in cement bond width 2m is
[2/B+1] Ast = [2/1.5+1]2x775
= 1240 mm^2.
Min . reinforcement = 0.12/100 x 1000x230
= 276 mm^2.
Provide 10mm dia bar 4 nos (Ast = 314.16mm^2)
Spacing = 285mm.
Provide 10mm dia @ 250mm c/c.
Step 6 :
Check for shear stress :
The critical s/c for one way shear is located at distance d from the face of column . ultimate shear force
per width in the longer direction .
Vu = (189.12x0.885)
= 167.4kN.
100xAst/b.d = 100x1008/ (1000x300)
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
38/43
38
= 0.336.
{Table 19 from IS 456:2000}
= ks . c = 2x0.41
= 0.82.
c = Vu/bd
= 167.4x10^3/(1000x300)= 0.56
v < Ks. c.
Hence safe.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
39/43
39
DESIGN OF STAIR CASE
Data:
Types of stair case Dog-legged
Tread T =250mm
Rise R = 150mm
Fck=20N/mm2
Fy=415 N/mm2
Width of each flight = 1.6m
Height of each flight=5/2=2.5m
Number of rises required =2.5/0.15=17
Number of tread flight =17-1=16
Space occupied by tread =16250=4000mm=4.0m
Keep the landing with=2m
Passage=1.5m
Effective span:
The loading on each flight
The loading slab is assumed to span in the some direction as the stairs and is considered to
act together to form a single slab
Bearing of the slab =300mm
The effective span =4+1.5+0.300/2=5.65m
Loads:
Assume the waist slab thickness =200mm
Weight of slab w on slope =0.2125000
=5000N/m2
Dead weight of horizontal span
W=Ws /T =
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
40/43
40
=5000 /0.250
=3830.95N/m
Dead weight of step is given by
W= (R /21000)125000
=(150/2000)125000
W =1875N/m2
Weight of finishing =1000N/m
Live load =5000N/m
Total load= 5830.95+1875+1000+5000
=13706N/m
Factored load =1.513706
=10559N/m
Bending moment:
M =Wul2/8=205595.652/8
=82036.55N-m
Check depth of waist slap:
D=/0.138Fckb
= 3/0.138201000
Main reinforcement :
Mu=0.87Fy Astd [1-Ast Fy/bd Fck]
93.505106 = 0.87415Ast180[1- Ast415/100023020]
=1042.75mm2
Numbers of bars needed in 1.6m width
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
41/43
41
=1.61042.75//4122
= 15 No's
Adopt 15 No's of 12mm rod
Spacing =1600/15=107mm100mm
Provide 15 No's of 12mm bars at 100mm c/c in main reinforcement
Distribution reinforcement:
=0.12 % cross area
=0.12/1001000200=240mm2
Adopt 10mm bars
Spacing =1000ast/Ast=1000/4102/240=327mm
Provide 10mm bars @300mm c/c
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
42/43
42
CONCLUSION
This project deals with the design considering thevertical loads alone. The extent of the project can be
done by considering the earthquake load. More forces will be considered based on the strength criteria
in our codal provisions.
The HOSPITAL BUILDING is framed structure and designed by LIMIT STATE METHOD and the
structure provided to be safe. The drawings were prepared using AUTO-CAD.
Thus the object of the project has been successfully achieved and evaluated in all aspects.
The project has enlightened us in the field of analysis and design.
-
8/2/2019 DESIGN OF HOSPITAL BUILDING
43/43
BIBLIOGRAPHY
IS 456-2000 Indian Standard Plain and Reinforcement Concrete of Practice. SP-16 Design Aids for Reinforcement Concrete to IS 456-2000.
References:
Varghes.P.C, (2002) Limit State Design of Reinforced Concrete. Krishna Raju.N, (2003) Design of Reinforced Concrete Structures.