design new load shedding scheme considering …
TRANSCRIPT
DESIGN NEW LOAD SHEDDING SCHEME
CONSIDERING POSSIBLE ISLANDING OPERATIONS
IN SRI LANKAN NETWORK
H.P.G.R.N.Chamikara
09/8653
Degree of Master of Science
Department of Electrical Engineering
University of Moratuwa
Sri Lanka
September 2012
DESIGN NEW LOAD SHEDDING SCHEME
CONSIDERING POSSIBLE ISLANDING OPERATIONS
IN SRI LANKAN NETWORK
Henpita Polwatthe Gamarallage Nadun Chamikara
09/8653
Dissertation submitted in partial fulfillment of the requirements for the
Degree Master of Science in Electrical Engineering
Supervised by: Dr.K.T.M.Udayanga Hemapala
Department of Electrical Engineering
University of Moratuwa
Sri Lanka
September 2012
i
DECLARATION
“I declare that this is my own work and this dissertation does not incorporate without
acknowledgement any material previously submitted for a Degree or Diploma in any other
University or institute of higher learning and to the best of my knowledge and belief it does
not contain any material previously published or written by another person except where
the acknowledgement is made in the text.
Also, I hereby grant to University of Moratuwa the non-exclusive right to reproduce and
distribute my dissertation, in whole or in part in print, electronic or other medium. I retain
the right to use this content in whole or part in future works (such as articles or books)”.
……………………….
Signature of the candidate Date:
(H.P.G.R.N.Chamikara)
The above candidate has carried out research for the Masters Dissertation under my
supervision.
…………………………….
Signature of the supervisor Date:
(Dr. K.T.M. Udayanga Hemapala)
ii
ABSTRACT
Under frequency load shedding has been widely used to restore the power system frequency
following a severe generation demand unbalance due to a disturbance. If system frequency is not
counteracted properly system will be led to major blackouts. This frequency decline may be
corrected by shedding certain amount of load so that system is back to stable state. This dissertation
discusses on designing of new under frequency load shedding scheme align with the development
of Sri Lankan power system. Further, due to present network configuration after certain power
System failures some part of the system isolates from the main system and operates in islanding
mode. This islanding operation fails at all the times due to unbalance of the generation and load.
This dissertation also discusses in what way to overcome above situation by rearranging 33 kV
Load Shedding Feeders in the Sri Lankan network.
Whole Sri Lankan power system has been modeled using the PSS®E (Power System Simulator for
Engineers) software. PSS®E dynamic model was validated considering an actual generator tripping
occurred in the system. The Existing Load Shedding scheme was simulated using this model and
identified its drawbacks. Proposed a new Load Shedding scheme and discussed the system
improvements with simulations. The observations and results obtained from the simulations
comprise frequency plots before and after applying the proposed new load shedding scheme.
Further, identified possible islanding operations and analyzed the stability of them with proposed
load shedding scheme. Finally rearrange the 33 kV load shedding feeders in the Sri Lankan
network to facilitate islanding operation by analyzing the stability of the islands using simulation.
This new load shedding schemes with rearranged 33 kV load shedding feeders will improve the
Power System reliability and have a definite positive effect on customers which in turn improve the
wellbeing of the people and economy of the country.
Key words: Load Shedding, Islanding Operations, Simulations, Scheme, Feeders.
iii
ACKNOWLEDGEMENT
First, I pay my sincere gratitude to Dr. K.T.M. Udayanga Hemapala who encouraged and
guided me to conduct this investigation and on preparation of final dissertation.
I extend my sincere gratitude to Prof. J.P. Karunadasa, Head of the Department of
Electrical Engineering and all the lectures and visiting lectures of the Department of
Electrical Engineering for the support extended during the study period.
I would like to thank Mr. N.S.Wettasinghe, Chief Engineer, Protection Development
Branch, Ceylon Electricity Board who gave me the initiative to do the Islanding Operation
study for the Sri Lankan Network.
I also thank to Eng. Eranga Kudahewa who gave me extreme support and valuable
instructions during the simulations and preparation of final dissertation.
I would like to take this opportunity to extend my sincere thanks to Mr.D.D.K.
Karunarathne, Deputy General Manager (TD & E), Mr.T.D.Handagama, Deputy General
Manager (System Control), Mr.D.S.R.Alahakoon, Chief Engineer (System Operations),
Mr. J.Nanthakumar Chief Engineer (Operation Planning), Mr. G.R.H.U.Somapriya,
Electrical Engineer (Protection Development Branch), Mr. R.G. Jayendra, Electrical
Engineer (AGSAREP Project), Mr. L.A.A.N.Perera, Electrical Engineer (Transmission
O&Ms Branch – Colombo Region) and all the Office Staff of Protection Development
Branch of Ceylon Electricity Board who gave their co-operation to conduct my
investigation work successfully.
It is a great pleasure to remember the kind co-operation extended by the colleagues in the
post graduate program, friends, my mother, father, sister Chathurika Ruchirani, brother-in
law Sameera Manusanka and specially my wife Nirmani Rajapakshe who helped me to
continue the studies from start to end.
iv
TABLE OF CONTENTS
Declaration of the candidate & Supervisor i
Abstract ii
Acknowledgements iii
Table of content iv
List of Figures vi
List of Tables vii
List of Appendices viii
1. Introduction 1
1.1 Background 1
1.2 Importance of the Load Shedding Scheme 1
1.3 Identification of the Problem 2
1.4 Motivation 3
1.5 Objective of the Study 3
1.6 Methodology 4
2. Existing Load Shedding Scheme 5
2.1 Load Shedding Scheme 5
2.2 Existing Load Shedding Scheme 7
2.3 System Response to the System Disturbances 8
2.3.1 Tripping of Norochcholai coal Power Plant 8
2.3.2 Tripping of Kerawalapitiya Power Plant 8
2.4 Analyze of Existing Load Shedding Scheme 9
3. Power System Simulation 10
3.1 The Power System Simulator, PSS®E 10
3.2 Planning Criteria 10
3.2.1 Voltage criteria 10
3.2.2 Thermal criteria 10
3.2.3 Security criteria 11
3.2.4 Stability criteria 11
3.3 Validation of PSS®E simulation with actual system disturbance 12
3.4 Selecting initial System condition for Load Shedding Studies 13
3.4.1 HMDP (Hydro Maximum Day Peak) 14
v
3.4.2 TMDP (Thermal Maximum Day Peak) 15
3.4.3 HMNP (Hydro Maximum Night Peak) 16
3.4.4 TMNP (Thermal Maximum Night Peak) 16
3.4.5 HMOP (Hydro Maximum Off Peak) 17
3.4.6 TMOP (Thermal Maximum Off Peak) 18
4. Proposed Load Shedding Scheme 19
4.1 Formulating a Load Shedding Scheme 19
4.2 Maximum anticipated overload 19
4.3 Number of load-shedding steps 20
4.4 Time Delay 20
4.4.1 Simulation 1 21
4.4.2 Simulation 2 22
4.4.3 Simulation 3 25
4.5 Size of the load shed at each step 26
4.5.1 Simulation 4 27
4.5.2 Simulation 5 28
4.5.3 Simulation 6 29
4.5.4 Simulation 7 30
4.5.5 Simulation 8 31
4.6 Frequency settings 32
4.7 Proposed Load Shedding Scheme 32
5. Islanding Operation 34
5.1 Possible Islanding Operation 34
5.2 Tripping of 132 kV New Laxapana – Balangoda Line 1 and 2 34
5.3 Tripping of 132 kV Pannipitiya – Matugama Line and 45
Pannipitiya – Horana Line
6. Conclusion and Recommendation 52
Reference List 55
Appendix A: Load Flow Network Diagram of HMOP condition 57
Appendix B: Dispatch Scenario during HMOP Condition 58
Appendix C: Technical Details of Load Shedding relay 59
Appendix D: 33 kV Circuit Breaker Timing Test Results 60
vi
LIST OF FIGURES
Page
Figure 2.1 System Frequency variation with the Load Shedding operation 6
Figure 2.2 System Frequency variation on 07th of June 2011 at 12.17 PM 8
Figure 2.3 System Frequency variation on 27th of July 2011 at 09.17 AM 9
Figure 3.1 Simulated frequency response due to tripping of AES 163 MW 12
Figure 3.2 Actual frequency response due to tripping of AES 163 MW 12
Figure 3.3 Frequency response of the System at HMDP condition 15
Figure 3.4 Frequency response of the System at TMDP condition 15
Figure 3.5 Frequency response of the System at HMNP condition 16
Figure 3.6 Frequency response of the System at TMNP condition 17
Figure 3.7 Frequency response of the System at HMOP condition 17
Figure 3.8 Frequency response of the System at TMOP condition 18
Figure 4.1 Frequency response of the System for Simulation 1 21
Figure 4.2 Frequency response of the System for Simulation 2 22
Figure 4.3 Pickup and operated time of each stage of existing scheme 24
Figure 4.4 Pickup and operated time of each stage of new scheme 25
Figure 4.5 Frequency response of the System for Simulation 3 25
Figure 4.6 Frequency response of the System for Simulation 4 27
Figure 4.7 Frequency response of the System for Simulation 5 28
Figure 4.8 Frequency response of the System for Simulation 6 29
Figure 4.9 Frequency response of the System for Simulation 7 30
Figure 4.10 Frequency response of the System for Simulation 8 31
Figure 5.1 Network Configuration of the Island 34
Figure 5.2 Load Flow diagram of Balangoda 132 kV Busbar 40
Figure 5.3 Frequency response of the System 41
Figure 5.4 Frequency response of the System after modification of Load
Shedding Feeders. 43
Figure 5.5 Voltage response of the Busbars 43
Figure 5.6 Network Configuration of the Island 45
Figure 5.7 Frequency response of the System 49
Figure 5.8 Frequency response of the System after modification of Load
Shedding Feeders. 50
vii
LIST OF TABLES
Page
Table 2.1 Existing Load Shedding Scheme 7
Table 2.2 MW Rejection from Existing Load Shedding Scheme 7
Table 3.1 Allowable voltage variation in 220 kV and 132 kV systems 10
Table 3.2 Rate of Change of Frequency for different system conditions 18
Table 4.1 Proposed Load Shedding Scheme with new delay time settings. 26
Table 4.2 Proposed Load Shedding Scheme with new step size. 32
Table 4.3 Proposed New Load Shedding Scheme 33
Table 5.1 Night Peak load analysis of Balangoda GSS 35
Table 5.2 Night Peak load analysis of Deniyaya GSS 36
Table 5.3 Night Peak load analysis of Embilipitiya GSS 36
Table 5.4 Night Peak load analysis of Galle GSS 37
Table 5.5 Night Peak load analysis of Hambantota GSS 37
Table 5.6 Night Peak load analysis of Matara GSS 38
Table 5.7 Night Peak load analysis of Ratnapura GSS 38
Table 5.8 Generation Capacity of the Island 39
Table 5.9 Load Demand of the Island 39
Table 5.10 Load Shedded capacity of each GSS 40
Table 5.11 Under Frequency Trip Settings 41
Table 5.12 Load Shedded capacity of each GSS after modification 42
Table 5.13 Proposed Load Shedded capacity of each GSS in the island 44
Table 5.14 Night Peak load analysis of Ambalangoda GSS 46
Table 5.15 Night Peak load analysis of Horana GSS 47
Table 5.16 Night Peak load analysis of Mathugama GSS 47
Table 5.17 Generation Capacity of the Island 48
Table 5.18 Load Demand of the Island 48
Table 5.19 Load Shedded capacity of each GSS 48
Table 5.20 Load Shedded capacity of each GSS after modification 49
Table 5.21 Proposed Load Shedded capacity of each GSS in the island 51
Table 6.1 Proposed New Load Shedding Scheme 52
Table 6.2 Saved Load from Proposed New Load Shedding Scheme 53
Table 6.3 Saved Load from proposed feeder arrangement in each island 53
Table 6.4 Proposed Load Shedded capacity of each GSS in the islands 54
viii
LIST OF APPENDICIES
Page
Appendix A Load Flow Network Diagram of HMOP condition 57
Appendix B Dispatch Scenario during HMOP Condition 58
Appendix C Technical Details of Load Shedding relay 59
Appendix D 33 kV Circuit Breaker Timing Test Results 60
Page 1 of 60
Chapter 1
INTRODUCTION 1.1 Background
Power System reliability has gained utmost concern in modern era since it is one of the key
elements of modern development. Main parts of the Power System are Generation,
Transmission and Distribution. Each one of them has their own reliability improvement
methods such as Protection systems, Condition Monitoring Systems, etc. but when we
consider the system as a whole “Load shedding” is the main controlling method to keep up
the system alive when it goes to unstable state which National Control Center unable to
rectify. So having advanced Load shedding scheme is the prime importance in modern
days and these Load shedding schemes should also capable to facilitate Islanding operation
when system separates into regions due to limitations in the Network configuration during
system faults.
1.2 Importance of the Load Shedding Scheme
When a Power System is in stable operation at normal frequency, the total mechanical
power input from the prime movers to the generators is equal to the sum of all the
connected loads which also includes all real power losses in the system [1]. If any
significant unbalance occurs such as tripping of main generator in the system or tripping of
main transmission line in the system will causes a frequency variations. These frequency
variations occur due to slow down or speed up the rotors in the system. Normally rotors are
massive rotating masses which have immense kinetic energy. When one of the main
generators in the system trips, system will experience lack of generation than the loads so
rotors slow down and kinetic energy converted into electric energy and supply to the
system. As a result system frequency will drop. When main transmission line in the system
trips, system will experience excess of generation than load so rotors speed up to absorbing
energy. As a result system frequency will increase.
Governors in the generators sense small changes in speed resulting from gradual load
changes in the normal system. These governors adjust the mechanical input power to the
Page 2 of 60
generating units in order to maintain normal frequency operation [1]. But sudden losing of
large generator can produce a severe generation and load unbalance, resulting in a rapid
frequency decline. If the governors cannot respond quickly enough, the system may
collapse. So rapid and selective shedding of loads can make system recovery possible and
avoid prolonged system outage and restore customer service with minimum delay.
1.3 Identification of the Problem
Several procedures and criteria must be considered when designing load shedding scheme
for specific systems. These include [1]:
a) Maximum anticipated overload
b) Number of Load Shedding Steps
c) Size of the Load Shed at each Step
d) Frequency Setting
e) Time Delay
f) Location of the frequency relays
So detailed study of existing Load Shedding scheme of Sri Lankan Power System with
above settings is important.
When analyzing the historical data related to existing Load Shedding scheme; some of the
above settings were not updated according to the system expansion (as an example during
the period 2005 to 2012, Frequency setting and Time delay setting of Load Shedding
scheme is not changed but Sri Lankan transmission network significantly expanded,
generators such as Kerawalapitiya and Norochcholai connected to the system during the
same period), some were implemented by foreign consultants according to their own
standards without much concern about our network, some of the setting were implemented
purely to overcome the blackout situations and further some of the setting were
implemented case by case study with the similar system failures.
Due to above mentioned reasons and also analyzing the system behavior in last few years
during system disturbance, it can be identified that proper analysis and implementation of
new Load Shedding scheme is prime important in the present Power System point of view.
Page 3 of 60
Further, due to the present Network configuration after certain Power System failures some
part of the System isolates from the main system and operates in islanding Mode. This
Islanding operation fails at all the times due to unbalance of the Generation and Load. So
there is a necessity of rearrange the Load Shedding Feeders of each GSS to facilitate the
possible Islanding operations in Sri Lankan Network.
1.4 Motivation
The outcome of this project will be to develop a Load shedding scheme which facilitate
system recovery with minimum impact to the customers. Further, in the event of separation
of the system into regions it will facilitate Islanding operation which enables to supply
electricity to all the separated regions with minimum impact in their customers.
This Load shedding schemes will improve the Power System reliability and have a definite
positive effect on customers which in turn improve the wellbeing of the people and
economy of the country.
1.5 Objective of the Study
There are four objectives in this study,
1. Analyze Existing Load Shedding Setting such as,
• Maximum anticipated overload
• Number of Load Shedding Steps
• Size of the Load Shed at each Step
• Frequency Setting
• Time Delay
2. Propose suitable Load Shedding Setting for Sri Lankan Network.
3. Identify possible Islanding operations due to present Sri Lankan Network
configuration.
4. Rearrange the 33 kV Load Shedding Feeders in the Sri Lankan Network to
facilitate the possible Islanding operations in Sri Lankan Network.
Page 4 of 60
1.6 Methodology
1. Analyzing the Existing Load Shedding scheme using Power System simulator.
2. Propose suitable Load Shedding scheme using Power System simulator.
3. Identify possible Islanding operations due to present Sri Lankan Network
configuration.
4. Analyzing the stability of the above identified Islands using Power System
simulator (with the proposed Load Shedding scheme)
5. Rearrange the 33 kV Load Shedding Feeders in the Sri Lankan Network to
facilitate islanding operation by analyzing the stability of the islands using Power
System simulator (with the proposed Load Shedding scheme)
This study will help to find a feasible solution for the above section 1.3 mentioned
problems and the results obtained through this study could be used to improve the present
system reliability.
Page 5 of 60
Chapter 2
EXISTING LOAD SHEDDING SCHEME
2.1 Load Shedding Scheme
In the Power System, regular changes in the system load are handled by the frequency
controlling machine. In Sri Lankan network Victoria, Kotmale, New Laxapana and
Samanalawewa are the frequency controlling machines [2]. In generally frequency declines
due to generator deficiency is governed by the combined action of Spinning reserve and
frequency controlling machine. But in the event of rapid frequency decline, governor of the
frequency controlling machine has no time to response quickly. So it is necessary to
intentionally and automatically disconnect a portion of the load equal to or greater than the
overload. After the decline has been arrested and the frequency returns to normal, the load
may be restored in small increments, allowing the spinning reserve to become active and
any additional available generators to be brought on line.
Frequency is a reliable indicator of an overload condition (at a particular time, load on the
system is grater then the Generating capacity) [12]. Frequency sensitive relays which use
Voltage Transformer input to recognize the frequency can therefore be used to disconnect
load automatically. Such an arrangement is referred to as a load shedding scheme and is
designed to reserve system integrity and minimize outages. Although utilities generally
avoid intentionally interrupting service, it is sometimes necessary to do so in order to avoid
major system collapse. In general, noncritical loads, usually residential, can be interrupted
for short periods, minimizing the impact of the disturbance on service.
Automatic load shedding, based on under frequency is necessary since sudden, moderate to
severe overloads can drive a system into a hazardous state much faster than System
operator can react. Under frequency relays are usually installed at distribution substations,
where selected loads can be disconnected.
The object of load shedding is to balance load and generation. Since the amount of
overload is not readily measured at the instant of a disturbance, the load is shed a block at a
Page 6 of 60
time, each controlling its own block of load and each set to a successively lower
frequency. The first line of frequency relays is set just below the normal operating
frequency range. When the frequency drops below this level, these relays will drop a
significant percentage of system loads. It this load drop is sufficient, the frequency will
stabilize or actually increase again. If this first load drop is not sufficient, the frequency
will continue to drop, but at a slower rate, until the frequency range of the second line of
relays is reached. At this point, a second block of load is shed. This process will continue
until the overload is relieved or all the frequency relays have operated. An alternative
scheme is to set a number of relays at the same frequency or close frequencies and use
different tripping time delays [1].
Figure 2.1 – System Frequency variation with the Load Shedding operation.
Stage 2
Stage 1
Stage 4
Stage 3
Page 7 of 60
2.2 Existing Load Shedding Scheme
Table 2.1 – Existing Load Shedding Scheme
Stage Load to be
Remarks Tripping Criteria Tripped (%)
I 5 5% Load on only freq. based 48.75 Hz + t=100 ms
II 5 5% Load on only freq. based 48.50 Hz + t=500 ms
III 10
7% Load on only freq. based
48.25 Hz + t=1 s OR
3% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
IV 10
7% Load on only freq. based
48.00 Hz + t=1.5 s OR
3% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
V 10
6% Load on only freq. based
47.50 Hz + t=inst OR
4% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
VI 10 10% Load on df/dt based 49 Hz AND df/ft =
0.85 Hz/Sec
The Existing Load Shedding Scheme is shown in Table 2.1, as per the scheme there are six
Load Shedding stages where first two stages reject 5% of the load each and other stages
reject 10% of the load each. So if all six stages operate 50% of the system load will be
rejected (Half of the system). It is like 30% of load base on Under Frequency which start
when frequency goes below 48.75 Hz and rest of the 20% of the load is based on the rate
of change of frequency. Load rejection amount during Off Peak, Day Peak and Night Peak
can be found in Table 2.2
Table 2.2 – MW Rejection from Existing Load Shedding Scheme
Off Peak Day Peak Night Peak
MW
% from
System Load MW
% from
System Load MW
% from
System Load
Stage 1 42.85 5.53 78.5 5.6 90.25 5.01
Stage 2 41.5 5.35 67.25 4.8 88.7 4.92
Stage 3 83.65 10.79 126.4 9.02 154.25 8.56
Stage 4 60.39 7.79 127.2 9.07 149.72 8.31
Stage 5 75.05 9.68 125.92 8.98 154.95 8.6
Stage 6 81.21 10.48 151.69 10.82 159.13 8.83
Total 384.7 49.62 676.96 48.29 797 44.23
Page 8 of 60
2.3 System Response to the System Disturbances.
Below shows the System Response to the system disturbance with existing load shedding
scheme.
2.3.1 Tripping of Norochcholai coal Power Plant
On 07th of June 2011 at 12.17 PM, Norochcholai coal Power Plant tripped [3]. Due to
tripping 240 MW rejected from the system and four stages of the Load Shedding Scheme
were operated rejecting 40% of the loads. Minimum frequency was 47.601 Hz and rate of
change of frequency (df/dt) is -0.743 Hz/Sec.
Figure 2.2 – System Frequency variation on 07th
of June 2011 at 12.17 PM.
2.3.2 Tripping of Kerawalapitiya Power Plant
On 27th
of July 2011 at 09.17 AM, Kerawalapitiya Power Plant tripped [3]. Due to tripping
137 MW rejected from the system and two stages of the Load Shedding Scheme were
operated rejecting 10% of the loads. Minimum frequency was 48.499 Hz and rate of
change of frequency (df/dt) is -0.046 Hz/Sec.
Page 9 of 60
Figure 2.3 – System Frequency variation on 27th
of July 2011 at 09.17 AM
2.4 Analyze of Existing Load Shedding Scheme
Existing Load Shedding Scheme is analyzed with the simulations and identified the best
settings for Load Shedding and hence proposes a new Load Shedding scheme for Sri
Lankan Network.
Page 10 of 60
Chapter 3
POWER SYSTEM SIMULATION
3.1 The Power System Simulator, PSS®E
The Siemens PTI Power System Simulator (PSS®E) is a package of programs for studies
of power system transmission network and generation performance in both steady-state
and dynamic conditions. PSS®E handles power flow, fault analysis (balanced and
unbalanced), network equivalent construction, and dynamic simulation [4].
3.2 Planning Criteria
The simulation studies are done according to the under mentioned planning criteria of the
Ceylon Electricity Board (CEB). The planning criteria are to ensure quality and reliable
supply under normal operating conditions as well as under contingencies [5].
3.2.1 Voltage criteria
The voltage criterion defines the permitted voltage deviation at any live bus bar of the
network under normal and contingency operating conditions as in Table 3.1 [7].
Table 3.1 – Allowable voltage variation in 220 kV and 132 kV systems
Bus bar voltage Allowable voltage variation (%)
Normal operating condition Single contingency condition
220 kV ±5% -10% to +5%
132kV ±10% ±10%
3.2.2 Thermal criteria
The design thermal criterion limits the loading of any transmission network element, in
order to avoid overheating due to overload.
Page 11 of 60
The loading of elements should not exceed their rated thermal loading values for steady
state conditions [5].
3.2.3 Security criteria
The performance of the transmission system under contingency situation is taken into
consideration in the security criteria. The adopted contingency level for the planning
purposes is N-1, i.e. outage of any one element of the transmission system at a time. After
outage of any one element (i.e. any one circuit of a transmission line or a transformer and
without any adjustment or corrective measure ), the system should be able to meet the
distribution demand while maintaining the bus bar voltage levels and loading of all the
remaining elements should not exceed their emergency ratings specified.
After system readjustment following a disturbance described above, the voltage and
loading of elements should return to their corresponding normal limits [5].
3.2.4 Stability criteria
Stability criteria should ensure the system stability during and after a system disturbance.
For all pertaining equipment in service, the system should remain stable in case of [5]:
• Three-phase fault at any one overhead line terminal, cleared by the primary
protection with successful and unsuccessful auto re-closing
• Loss of any one generation unit
• Load rejection by loss of any transformer
Page 12 of 60
3.3 Validation of PSS®E simulation with actual system disturbance.
On 24th
of December 2009 AES plant tripped rejecting 163MW (15.8 % of system
generation prior to generation loss)
Below figures illustrate simulated and actual frequency responses for the above incident.
Figure 3.1: Simulated frequency response due to tripping of AES 163 MW
Figure 3.2: Actual frequency response due to tripping of AES 163 MW
Page 13 of 60
In both cases frequency reached to below 48 Hz and thus under frequency load shedding
operated up to stage IV. Initial rate of change of frequency is in simulation and actual case
is 0.9 Hz/s and 0.65 Hz/s respectively. The time reached to minimum frequency is 4
seconds in the simulation and 5.5 seconds in the actual case after the disturbance. 166 MW
load rejection from all four stages at the simulation and 148 MW load rejection due to
under frequency load shedding in actual situation. Shape of the frequency variation is
almost similar in both cases.
Ultimately simulation results can be considered almost same as real system behavior.
3.4 Selecting initial System condition for Load Shedding studies
The basic characteristic of the frequency change of a power system is derived from the
following equation [9].
+ (1)
Where;
H - System inertia constant on system base (seconds)
df/dt - Rate of change of frequency, Hz/s
Pm(pu) - Remaining generation after generation loss in remaining system generation
base
Pe(pu) - System load prior to generation loss in remaining system generation base
f0 - Base frequency, 50 Hz
D - Power system load damping constant in pu/Hz
∆f - Change in frequency, Hz
Pm – Pe
Pm
- Amount of overload in remaining generation base
df
dt =
Pm(Pu) – Pe(pu)
2 x H
x f0
2H
D x ∆f
Page 14 of 60
Generally load damping (D) of a power system depends on the load mix and varying
around 1-2 %. An exact value of D can only be determined by observing the variation of
load with frequency on the system under consideration. For the illustration purpose let
consider the D as zero. So the equation will be simplify as follows,
(2)
From above equation, it can be identified that lower the System inertia, higher the rate of
change of frequency in the system and higher the possibility of collapsing the system.
Therefore to recognize the best initial System condition for Load Shedding studies, System
was simulated using PSS®E software under following six scenarios to identify the highest
Rate of change of frequency decline by tripping the 20% of the total demand of the system.
1. HMDP (Hydro Maximum Day Peak)
2. TMDP (Thermal Maximum Day Peak)
3. HMNP (Hydro Maximum Night Peak)
4. TMNP (Thermal Maximum Night Peak)
5. HMOP (Hydro Maximum Off Peak)
6. TMOP (Thermal Maximum Off Peak)
3.4.1 HMDP (Hydro Maximum Day Peak)
System was simulated with Load and Generation balance of 1525 MW and after 2 seconds
20% Generation (305 MW) was removed from the system. Three stages of the Load
Shedding Scheme were operated. Minimum frequency was 47.92 Hz and initial rate of
change of frequency is -0.734 Hz/Sec.
df
dt =
Pm(Pu) – Pe(pu)
2 x H
x f0
Page 15 of 60
Figure 3.3: Frequency response of the System at HMDP condition.
3.4.2 TMDP (Thermal Maximum Day Peak)
System was simulated with Load and Generation balance of 1525 MW and after 2 seconds
20% Generation (305 MW) was removed from the system. Three stages of the Load
Shedding Scheme were operated. Minimum frequency was 47.95 Hz and initial rate of
change of frequency is -0.676 Hz/Sec.
Figure 3.4: Frequency response of the System at TMDP condition
Page 16 of 60
3.4.3 HMNP (Hydro Maximum Night Peak)
System was simulated with Load and Generation balance of 1904 MW and after 2 seconds
20% Generation (380 MW) was removed from the system. Two stages of the Load
Shedding Scheme were operated. Minimum frequency was 48.44 Hz and initial rate of
change of frequency is -0.675 Hz/Sec
3.4.4 TMNP (Thermal Maximum Night Peak)
System was simulated with Load and Generation balance of 1904 MW and after 2 seconds
20% Generation (380 MW) was removed from the system. Two stages of the Load
Shedding Scheme were operated. Minimum frequency was 47.89 Hz and initial rate of
change of frequency is -0.802 Hz/Sec.
Figure 3.5: Frequency response of the System at HMNP condition
Page 17 of 60
Figure 3.6: Frequency response of the System at TMNP condition
3.4.5 HMOP (Hydro Maximum Off Peak)
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
20% Generation (190 MW) was removed from the system. Two stages of the Load
Shedding Scheme were operated. Minimum frequency was 47.90 Hz and initial rate of
change of frequency is -0.92 Hz/Sec.
Figure 3.7: Frequency response of the System at HMOP condition
Page 18 of 60
3.4.6 TMOP (Thermal Maximum Off Peak)
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
20% Generation (190 MW) was removed from the system. Two stages of the Load
Shedding Scheme were operated. Minimum frequency was 47.98 Hz and initial rate of
change of frequency is -0.82 Hz/Sec.
Summarizing the simulation results,
Table 3.2 – Rate of Change of Frequency for different system conditions
No. System Condition df/dt ( Hz/Sec)
1 HMDP -0.734
2 TMDP -0.676
3 HMNP -0.675
4 TMNP -0.802
5 HMOP -0.920
6 TMOP -0.820
After analyzing the simulation results, it was identified that HMOP scenario has the
highest Rate of change of frequency decline thus lowest system inertia. So HMOP is
selected as the best initial System condition for Load Shedding studies. Details of this
initial system conditions for the dynamic simulation are shown in the load flow diagram
attached in the appendix A and dispatch scenario is given in the appendix B.
Figure 3.8: Frequency response of the System at TMOP condition
Page 19 of 60
Chapter 4
PROPOSED LOAD SHEDDING SCHEME
4.1 Formulating a Load Shedding Scheme
Following factors are considered when analyzing existing load shedding schemes and
designing of the proposed load shedding schemes for the Sri Lankan network.
These include:
a) Maximum anticipated overload
b) Number of load-shedding steps
c) Time delay
d) Size of the load shed at each step
e) Frequency settings
4.2 Maximum anticipated overload
Load Shedding Scheme should be able to shed a load equal to the maximum anticipated
overload. Logically, there is no reason to limit load-shedding to any percentage of loads.
Indeed, it is desirable to shed 100% of load, preserving interconnections and keeping
generating units on line and synchronized, than to allow the system to collapse with
customers still connected. Even if 100% of the load is shed, service can be restored rapidly.
But if the system collapses, a prolonged outage would result. For this reason, it is
necessary to evaluate the cost of the load-shedding scheme in light of the probability that
an overload of a given severity can occur [1].
CEB Policy on Power System Operations, maximum loading on a generator is less than
20% of the total gross generation. CEB is following single outage criterion which is
mentioned in section 3.2.3.
In the existing scheme 50% of the load will reject after operation of all the stages, but due
to maximum loading on a generator is less than 20% of the total gross generation and
single outage criterion, Maximum anticipated overload will be 20% of the total load. But
Page 20 of 60
when consider n-2 outage criterion it is better to use value in-between 20% to 50%. This
value will be fine-tuned during identifying of step sizes of each load shedding stage.
4.3 Number of load-shedding steps
The basic and simplest load shedding scheme is one in which the predetermined
percentage of the load is shed at once when a group of relays senses a frequency drop.
Even though this scheme will arrest any anticipated frequency decline, it will often
disconnect far more customers than necessary. As per reliability concern it is not an
acceptable method. An improvement then would be to use two groups of relays, one
operating at a lower frequency than the other, and each shedding half the predetermined
load. The higher-set relays would trip first, halting the frequency decline as long as the
overload was half or less of the worst-case value. For more severe overload, the frequency
would continue to drop, although at a slower rate, until the second group of relays to shed
the other half of the expendable load.
The number of load shedding steps can be increased virtually without limit [13]. More the
number of steps, the system can shed load in small increments until the decline stops which
enable almost no excess load need be shed. But such a scheme may be difficult to
coordinate since there are so many steps.
Most utilities use between two and five load-shedding steps, with three being the most
common [1]. In existing Load Shedding scheme use six steps where the last step is purely
base on rate of change of frequency. So this scheme can be accepted since five steps Load
Shedding schemes are accepted universally.
4.4 Time Delay
Time delays of the existing Load Shedding Scheme are 0.1sec, 0.5sec, 1sec and 1.5
seconds respectively from Stage I to IV. Stage V is an instantaneous stage. The important
rule for Load Shedding Scheme is to use minimum possible time delays and lesser the
delay, the more easily the scheme can cope with severe system disturbance [1].
Page 21 of 60
So simulations were carried out using PSS®E software to improve the time delay settings.
For these simulations rate of change of frequency function is disabled since it is not
possible to obtain time delay values if load shed from this instantaneous function.
As per the section 3.4, CEB network is more viable to collapse during HMOP conditions
especially during 00:00 hrs to 05:00 hrs of the day due to low system inertia Constant. So
simulation was done with the similar load condition.
4.4.1 Simulation 1
Figure 4.1: Frequency response of the System for Simulation 1
Above simulation results were obtained with existing Frequency settings. System was
simulated with Load and Generation balance of 950 MW and after 2 seconds Norochcholai
Power Plant was removed from the system rejecting 190 MW, this is equal to the 20% of
the generation that time. Four stages of the Load Shedding Scheme were operated rejecting
251.12 MW of the loads. Minimum frequency was 47.90 Hz and Frequency stabilized at
50.59 Hz.
Page 22 of 60
4.4.2 Simulation 2
Figure 4.2: Frequency response of the System for Simulation 2
Above simulation results were obtained by changing the time delay to 0.5 sec for all the
stages except stage I (Time delay = 0.1 sec). System was simulated with Load and
Generation balance of 950 MW and after 2 seconds Norochcholai Power Plant was
removed from the system rejecting 190 MW, this is equal to the 20% of the generation that
time. Three stages of the Load Shedding Scheme were operated rejecting 201.2 MW of the
loads. Minimum frequency was 48.09 Hz.
When comparing Simulation 1 & 2, in Simulation 2 only three stages were operated which
reduced rejecting loads by 49.92 MW and also increased the system frequency by 0.19 Hz.
So from the above study it can be identified that reducing the time delay will make system
more reliable.
Before carryout the next Simulation, it should be identified the maximum time required to
trip a feeder from Load Shedding Scheme. Following factors should be consider when
selecting the maximum time value,
a) Operating time of the Load Shedding relay.
Page 23 of 60
b) Operating time of the Interposing auxiliary devises
c) Operating time 33 kV Circuit Breaker
a) Operating time of the Load Shedding relay.
Operating time of the Load Shedding relay can be estimated as 40 ms because most of the
frequency relays in CEB network are numerical type and these relays will operate below
20 ms. Please refer appendix C.
b) Operating time of the Interposing auxiliary devises
As per the below specifications CEB is recommending to use minimum interposing
auxiliary relays in-between relay and the circuit breaker trip coil, so 20 ms time delay is
sufficient for this factor.
“Relay contacts shall be suitable for making and breaking the maximum currents which
they may be required to control in normal service but where contacts of the protective
relays are unable to deal directly with the tripping currents, approved auxiliary contacts,
relays or auxiliary switches shall be provided. In such cases the number of auxiliary
contacts or tripping relays operating in tandem shall be kept to the minimum in order to
achieve fast fault clearance times. Separate contacts shall be provided for alarm and
tripping functions. Relay contacts shall make firmly without bounce and the whole of the
relay mechanisms shall be as far as possible unaffected by vibration, shock and bump or
external magnetic fields. [6]”
c) Operating time of the 33 kV Circuit Breaker
33 kV Circuit Breaker will trip within 3 cycle after trip signal received to the trip coil, so
operating time of the Circuit Breaker can be considered as 60 ms. Please refer appendix D.
Minimum Time delay = Operating time of the Load Shedding relay + Operating time of
the Interposing auxiliary devises + Operating time 33 kV Circuit Breaker
= 40 ms + 20 ms + 60 ms
Page 24 of 60
= 120 ms
Pickup (PU) and Operated (OP) frequency values of each stage of existing Load Shedding
Scheme with the above time value and rate of change of frequency of -0.85 Hz/sec can be
found in Figure 4.3.
Figure 4.3: Pickup and operated time of each stage of existing scheme
From Figure 4.3, it can be identified that Stage III & IV will pick up before operation of
Stage II, Stage V will pick up before operation of Stage III & IV and also Stage V will
operate before operation of stage IV. So to overcome above complications new time setting
is identified as 150 ms and this setting is proposed to Stage II to V. Stage I is not changed
since it is the initial stage of the Load Shedding Scheme.
Pickup (PU) and Operated (OP) frequency values of each stage of proposed Load
Shedding Scheme with the new time settings and rate of change of frequency of -0.85
Hz/sec can be found in Figure 4.4.
Page 25 of 60
Figure 4.4: Pickup and operated time of each stage of new scheme
With the use of new time delay to all the stages except stage I (Time delay = 0.1 sec)
4.4.3 Simulation 3
Figure 4.5: Frequency response of the System for Simulation 3
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
Norochcholai Power Plant was removed from the system rejecting 190 MW, this is equal
Page 26 of 60
to the 20% of the generation that time. Three stages of the Load Shedding Scheme were
operated rejecting 167.15 MW of the loads. Minimum frequency was 48.17 Hz.
When comparing Simulation 1 & 3, in Simulation 3 only three stages were operated which
reduced rejecting loads by 83.97 MW and also increased the system frequency by 0.27 Hz.
Frequency Stabilized at 49.75 Hz. So from the above study it can be found best time delay
value for proposed Load Shedding Scheme.
Table 4.1: Proposed Load Shedding Scheme with new delay time settings.
Stage Load to be
Remarks Tripping Criteria Tripped (%)
I 5 5% Load on only freq. based 48.75 Hz + t=100 ms
II 5 5% Load on only freq. based 48.50 Hz + t=150 ms
III 10
7% Load on only freq. based
48.25 Hz + t=150 ms OR
3% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
IV 10
7% Load on only freq. based
48.00 Hz + t=150 ms OR
3% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
V 10
6% Load on only freq. based
47.50 Hz + t=150 ms OR
4% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
VI 10 10% Load on df/dt based 49 Hz AND df/ft =
0.85 z/Sec
4.5 Size of the load shed at each step
The size of the load-shedding steps should be related to expect percentage overloads [14].
After the study of the system configuration reveals that there is relatively high probability
of losing certain generating units and transmission lines. So load shedding blocks should
be sized accordingly.
Since Sri Lankan network is large, there are many possible events causing only a small
percentage overload in itself. In this case, a number of overload situations may be lumped
together and handled in one step. On the other hand, it may be sufficient to shed a
Page 27 of 60
percentage of the overload in a few equal steps. In existing scheme 5% and 10% of step
sizes were used and by simulation using Power System Simulator (PSS®E) software
analyzed any future improvement is needed.
If we considered Simulation No. 3 with the proposed new time settings, System frequency
was stabled at 49.75 Hz even after operation of the load shedding stage three. This 49.75
Hz value is inside the system normal frequency range of 50.5 Hz to 49.5 Hz [2].
Stabilizing System frequency at 49.5 Hz will also accepted since it is in the normal
operating frequency range. So simulation done with reducing stage 3 step size from 10% to
5%. For these simulations also rate of change of frequency function is disabled and it will
be analyzed later.
4.5.1 Simulation 4
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
Norochcholai Power Plant was removed from the system rejecting 190 MW, this is equal
to the 20% of the generation that time. Three stages of the Load Shedding Scheme were
operated rejecting 121.14 MW of the loads. Minimum frequency was 48.17 Hz and rate of
change of frequency (df/dt) is -0.765 Hz/Sec. Frequency stabilized at 49.56 Hz.
Figure 4.6: Frequency response of the System for Simulation 4
Page 28 of 60
When comparing Simulation 1 & 4, in Simulation 4 only three stages were operated which
reduced rejecting loads by 129.98 MW and also increased the system frequency by 0.27
Hz. Frequency Stabilized at 49.56 Hz. So from the above study it can be found best step
size for Stage 3 of proposed Load Shedding Scheme.
When system disturbance occurs with n-1 stability criteria as per the proposed scheme only
up to stage 3 will operate. Next Simulation will be done when simultaneous two
disturbances occurred at same time in the system.
4.5.2 Simulation 5
Figure 4.7: Frequency response of the System for Simulation 5
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
Norochcholai Power Plant and Victoria Power Plant was removed from the system
rejecting 240 MW, this is equal to the 25% of the generation that time. Four stages of the
Load Shedding Scheme were operated rejecting 204.74 MW of the loads. Minimum
frequency was 47.95 Hz and Frequency Stabilized at 49.80 Hz.
System frequency was stabled at 49.80 Hz even after operation of the load shedding stage
four. This 49.80 Hz value is inside the system normal frequency range of 50.5 Hz to 49.5
Page 29 of 60
Hz [2]. Stabilizing System frequency at 49.5 Hz will also accepted since it is in the normal
operating frequency range. So simulation done with reducing stage 4 step size from 10% to
6%. For these simulations also rate of change of frequency function is disabled and it will
be analyzed later.
4.5.3 Simulation 6
Figure 4.8: Frequency response of the System for Simulation 6
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
Norochcholai Power Plant and Victoria Power Plant was removed from the system
rejecting 240 MW, this is equal to the 25% of the generation that time. Four stages of the
Load Shedding Scheme were operated rejecting 167.81 MW of the loads. Minimum
frequency was 47.97 Hz and Frequency Stabilized at 49.50 Hz.
When comparing Simulation 5 & 6, in Simulation 6 reduced rejecting loads by 36.93 MW
and Frequency Stabilized at 49.50 Hz. So from above study it can be found the best step
size for Stage 4 in the proposed Load Shedding Scheme.
Page 30 of 60
In the existing Load Shedding scheme 20% of the load will be rejected based on the rate of
change of frequency (dt/dt). So simulation was carried with dt/dt setting to identify system
response for this step size.
4.5.4. Simulation 7
Figure 4.9: Frequency response of the System for Simulation 7
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
Norochcholai Power Plant was removed from the system rejecting 190 MW, this is equal
to the 20% of the generation that time. df/dt Scheme was operated rejecting 181.81 MW of
the loads. Minimum frequency was 48.85 Hz and rate of change of frequency (df/dt) is -
0.92 Hz/Sec. Frequency stabilized at 49.85 Hz.
System frequency was stabled at 49.85 Hz even after operation of the df/dt stage. This
49.85 Hz value is inside the system normal frequency range of 50.5 Hz to 49.5 Hz [2].
Stabilizing System frequency at 49.5 Hz will also accepted since it is in the normal
operating frequency range. So simulation done with reducing df/dt stage step size from
20% to 12%.
Page 31 of 60
4.5.5. Simulation 8
Figure 4.10: Frequency response of the System for Simulation 8
System was simulated with Load and Generation balance of 950 MW and after 2 seconds
Norochcholai Power Plant was removed from the system rejecting 190 MW, this is equal
to the 20% of the generation that time. Stage I of the Load Shedding Scheme and df/dt
stages were operated rejecting 139.52 MW of the loads (107.7 MW from df/dt stage and
31.82 MW from Stage I). Minimum frequency was 48.48 Hz and rate of change of
frequency (df/dt) is -0.92 Hz/Sec. Frequency stabilized at 49.6 Hz.
When comparing Simulation 7 & above simulation , 107.70 MW reject in above
simulation, so df/dt stage reduced rejecting loads by 74.11 MW and Frequency Stabilized
at 49.6 Hz. So from the above study it can be found best step size for df/dt step size for
proposed Load Shedding Scheme.
So maximum anticipated overload can be identified 41% of the total system load.
Page 32 of 60
4.6 Frequency settings
The determination of the frequency settings is depends on the system’s normal operating
frequency range. The frequency of the first step should be below the normal operating
frequency band of the system. Further first level should be set at below a certain value
which the system could be recovered by system operator or system could be operated
continuously for shorter period. Generally during very low off peak conditions system
experiences 2-3 % sudden generation loss mainly due to tripping of wind plants. System
frequency drops to around 49 Hz for the above said generation losses. By considering the
above facts it was decided to remain in the existing initial frequency setting of 48.75 Hz
[11]. Since existing frequency settings are in the steps of 0.25 Hz there is no point of
changing frequency settings.
4.7. Proposed Load Shedding Scheme
After analyzing the simulation results new load shedding scheme can be proposed as
shown in Table 4.2,
Table 4.2: Proposed Load Shedding Scheme with new step size.
Stage Load to be
Remarks Tripping Criteria Tripped (%)
I 5 5% Load on only freq. based 48.75 Hz + t=100 ms
II 5 5% Load on only freq. based 48.50 Hz + t=150 ms
III 5
5% Load on only freq. based
48.25 Hz + t=150 ms OR
0% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
IV 6
6% Load on only freq. based
48.00 Hz + t=150 ms OR
0% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
V 10
8% Load on only freq. based
47.50 Hz + t=150 ms OR
2% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
VI 10
10% Load on df/dt based
49 Hz AND df/ft =
0.85 Hz/Sec
Page 33 of 60
Table 4.2 can be future simplify as shown in Table 4.3,
Table 4.3: Proposed New Load Shedding Scheme
Stage Load to be
Remarks Tripping Criteria Tripped (%)
I 5 5% Load on only freq. based 48.75 Hz + t=100 ms
II 5 5% Load on only freq. based 48.50 Hz + t=150 ms
III 5 5% Load on only freq. based 48.25 Hz + t=150 ms
IV 6 6% Load on only freq. based 48.00 Hz + t=150 ms
V 10
8% Load on only freq. based
47.50 Hz + t=150 ms OR
2% Load on only freq. based
49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
VI 10
10% Load on df/dt based
49 Hz AND df/ft =
0.85 Hz/Sec
Page 34 of 60
Chapter 5
ISLANDING OPERATION
5.1. Possible Islanding Operation
Due to limitations in Sri Lankan Network configuration following line tripping will
separate the system into two parts.
1. Tripping of 132 kV New Laxapana – Balangoda Line 1 and 2.
2. Tripping of 132 kV Pannipitiya – Matugama Line and Pannipitiya – Horana Line.
But even though there are capable Frequency controlling machines in these Islanded areas,
these systems always fails due to unbalance of Generation and Loads.
5.2. Tripping of 132 kV New Laxapana – Balangoda Line 1 and 2
Figure 5.1: Network Configuration of the Island
When this incident happens following Grid Substations are separated from the main
network.
I. Balangoda GSS
II. Deniyaya GSS
Page 35 of 60
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 130 102 177 157 20 40 20 -5 641 29.31045659
2-Mar Wednesday Night 19:30 127 95 176 150 18 28 20 -134 480 21.94854783
3-Mar Thursday Night 19:30 115 89 162 152 19 48 11 -38 558 25.51518686
4-Mar Friday Night 19:30 126 97 168 157 19 59 -39 -18 569 26.01817441
5-Mar Saturday Night 19:00 124 99 168 140 18 55 22 -90 536 24.50921175
6-Mar Sunday Night 19:30 129 94 175 152 17 65 20 -37 615 28.12157691
7-Mar Monday Night 19:30 126 102 172 32 18 91 17 -134 424 19.38788392
8-Mar Tuesday Night 19:00 113 100 170 107 13 50 8 -50 511 23.36605821
9-Mar Wednesday Night 19:30 112 104 180 165 20 82 48 -19 692 31.64248979
10-Mar Thursday Night 19:30 114 105 180 162 50 84 49 -10 734 33.56298773
11-Mar Friday Night 19:00 110 102 171 159 17 85 -45 -8 591 27.02414952
12-Mar Saturday Night 19:30 108 99 175 158 19 81 42 -10 672 30.72796697
13-Mar Sunday Night 19:30 102 96 140 149 15 63 -37 -8 520 23.77759349
14-Mar Monday Night 19:00 110 101 167 147 18 74 20 -5 632 28.89892131
15-Mar Tuesday Night 19:00 105 92 160 135 19 73 31 -5 610 27.89294621
16-Mar Wednesday Night 19:30 111 99 174 140 18 58 38 13 651 29.767718
17-Mar Thursday Night 19:00 105 92 164 133 17 77 39 -45 582 26.61261425
18-Mar Friday Night 19:30 110 100 175 153 20 80 43 -12 669 30.59078854
19-Mar Saturday Night 19:30 95 94 169 144 17 75 -11 -28 555 25.37800843
20-Mar Sunday Night 19:30 95 92 150 138 17 32 -12 -22 490 22.40580925
21-Mar Monday Night 19:30 92 84 151 134 19 83 -10 -53 500 22.86307066
22-Mar Tuesday Night 19:30 107 86 190 149 22 60 -12 -20 582 26.61261425
23-Mar Wednesday Night 19:30 112 93 160 160 18 68 -50 -115 446 20.39385903
24-Mar Thursday Night 19:30 106 98 171 150 17 70 5 -38 579 26.47543582
25-Mar Friday Night 19:30 110 98 138 148 16 72 10 -89 503 23.00024908
26-Mar Saturday Night 19:00 113 98 173 150 18 75 10 -120 517 23.64041506
27-Mar Sunday Night 19:30 109 93 168 150 17 76 50 -110 553 25.28655615
28-Mar Monday Night 19:30 116 93 190 156 18 70 62 -95 610 27.89294621
29-Mar Tuesday Night 19:00 114 98 167 140 17 61 30 -55 572 26.15535283
30-Mar Wednesday Night 19:30 113 98 179 158 19 41 32 -38 602 27.52713707
31-Mar Thursday Night 19:30 119 102 178 165 18 59 50 -25 666 30.45361012
Max. 33.56299 MW
TimeDate Day Zone
III. Embilipitiya GSS
IV. Galle GSS
V. Hambantota GSS
VI. Matara GSS
VII. Ratnapura GSS
Load Study had been carried out to find the total load of the above Grid Substations.
Off Peak, Day Peak and Night Peak data have been analyzed and find out that Night Peak
load is always higher than off peak and Day peak. So following tables will include Night
Peak load analysis only.
Balangoda GSS
Table 5.1: Night Peak load analysis of Balangoda GSS
Page 36 of 60
1G 1F 2G 2F 3 4 5 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 23 23 21 26 42 21 156 7.133278046
2-Mar Wednesday Night 19:30 39 79 48 64 75 36 341 15.59261419
3-Mar Thursday Night 19:30 41 70 48 73 69 38 339 15.50116191
4-Mar Friday Night 19:30 36 66 42 70 32 34 280 12.80331957
5-Mar Saturday Night 19:00 40 72 49 58 70 35 324 14.81526979
6-Mar Sunday Night 19:30 42 71 52 82 73 39 359 16.41568473
7-Mar Monday Night 19:30 38 70 50 73 70 39 340 15.54688805
8-Mar Tuesday Night 19:00 41 65 53 73 77 37 346 15.8212449
9-Mar Wednesday Night 19:30 40 72 46 76 76 40 350 16.00414946
10-Mar Thursday Night 19:30 40 71 53 80 76 40 360 16.46141088
11-Mar Friday Night 19:00 40 71 51 75 74 40 351 16.0498756
12-Mar Saturday Night 19:30 41 72 53 77 75 40 358 16.36995859
13-Mar Sunday Night 19:30 38 67 42 73 69 34 323 14.76954365
14-Mar Monday Night 19:00 40 61 50 83 75 38 347 15.86697104
15-Mar Tuesday Night 19:00 41 65 46 73 74 29 328 14.99817435
16-Mar Wednesday Night 19:30 39 67 48 53 75 36 318 14.54091294
17-Mar Thursday Night 19:00 40 67 51 69 74 37 338 15.45543577
18-Mar Friday Night 19:30 42 68 48 78 77 36 349 15.95842332
19-Mar Saturday Night 19:30 38 65 39 64 69 36 311 14.22082995
20-Mar Sunday Night 19:30 36 70 42 53 66 28 295 13.48921169
21-Mar Monday Night 19:30 42 69 54 66 81 31 343 15.68406647
22-Mar Tuesday Night 19:30 42 66 54 70 80 37 349 15.95842332
23-Mar Wednesday Night 19:30 40 67 54 69 86 36 352 16.09560174
24-Mar Thursday Night 19:30 42 66 52 70 76 38 344 15.72979261
25-Mar Friday Night 19:30 43 65 54 79 79 40 360 16.46141088
26-Mar Saturday Night 19:00 39 66 51 67 71 38 332 15.18107892
27-Mar Sunday Night 19:30 41 67 47 75 72 31 333 15.22680506
28-Mar Monday Night 19:30 40 66 48 75 76 37 342 15.63834033
29-Mar Tuesday Night 19:00 35 51 45 43 73 39 286 13.07767642
30-Mar Wednesday Night 19:30 41 53 48 65 80 34 321 14.67809136
31-Mar Thursday Night 19:30 42 99 54 69 78 41 383 17.51311213
Max. 17.51311 MW
TimeDate Day Zone
Deniyaya GSS
Embilipitiya GSS
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 55 66 65 44 102 332 15.18107892
2-Mar Wednesday Night 19:30 55 69 69 44 95 332 15.18107892
3-Mar Thursday Night 19:30 55 65 63 42 89 314 14.35800837
4-Mar Friday Night 19:30 57 69 67 41 97 331 15.13535278
5-Mar Saturday Night 19:00 55 66 65 45 99 330 15.08962664
6-Mar Sunday Night 19:30 60 70 65 92 94 381 17.42165984
7-Mar Monday Night 19:30 56 70 65 56 102 349 15.95842332
8-Mar Tuesday Night 19:00 56 66 66 52 100 340 15.54688805
9-Mar Wednesday Night 19:30 60 70 129 52 104 415 18.97634865
10-Mar Thursday Night 19:30 60 66 126 52 105 409 18.7019918
11-Mar Friday Night 19:00 56 65 119 48 102 390 17.83319511
12-Mar Saturday Night 19:30 57 68 125 41 99 390 17.83319511
13-Mar Sunday Night 19:30 56 69 120 42 96 383 17.51311213
14-Mar Monday Night 19:00 55 66 120 48 101 390 17.83319511
15-Mar Tuesday Night 19:00 55 65 120 48 92 380 17.3759337
16-Mar Wednesday Night 19:30 72 68 119 47 99 405 18.51908723
17-Mar Thursday Night 19:00 70 60 115 28 92 365 16.69004158
18-Mar Friday Night 19:30 75 70 124 54 100 423 19.34215778
19-Mar Saturday Night 19:30 66 62 115 42 94 379 17.33020756
20-Mar Sunday Night 19:30 89 60 121 43 92 405 18.51908723
21-Mar Monday Night 19:30 89 62 150 45 84 430 19.66224077
22-Mar Tuesday Night 19:30 10 60 145 86 301 13.76356854
23-Mar Wednesday Night 19:30 51 60 120 43 93 367 16.78149386
24-Mar Thursday Night 19:30 50 60 120 36 98 364 16.64431544
25-Mar Friday Night 19:30 50 50 95 34 98 327 14.95244821
26-Mar Saturday Night 19:00 56 60 72 43 98 329 15.04390049
27-Mar Sunday Night 19:30 55 60 79 93 287 13.12340256
28-Mar Monday Night 19:30 40 55 117 41 93 346 15.8212449
29-Mar Tuesday Night 19:00 56 59 121 58 98 392 17.9246474
30-Mar Wednesday Night 19:30 60 60 129 97 98 444 20.30240675
31-Mar Thursday Night 19:30 63 62 134 99 102 460 21.03402501
Max. 21.03402501 MW
TimeDate Day Zone
Table 5.2: Night Peak load analysis of Deniyaya GSS
Table 5.3: Night Peak load analysis of Embilipitiya GSS
Page 37 of 60
Galle GSS
Hambantota GSS
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 177 21 10 138 346 15.8212449
2-Mar Wednesday Night 19:30 176 58 8 107 349 15.95842332
3-Mar Thursday Night 19:30 162 17 136 315 14.40373452
4-Mar Friday Night 19:30 168 56 104 328 14.99817435
5-Mar Saturday Night 19:00 168 54 103 325 14.86099593
6-Mar Sunday Night 19:30 175 58 104 337 15.40970962
7-Mar Monday Night 19:30 172 59 108 339 15.50116191
8-Mar Tuesday Night 19:00 170 18 144 332 15.18107892
9-Mar Wednesday Night 19:30 180 15 98 293 13.39775941
10-Mar Thursday Night 19:30 180 18 97 295 13.48921169
11-Mar Friday Night 19:00 171 15 90 276 12.620415
12-Mar Saturday Night 19:30 175 20 92 287 13.12340256
13-Mar Sunday Night 19:30 140 56 54 250 11.43153533
14-Mar Monday Night 19:00 167 52 54 273 12.48323658
15-Mar Tuesday Night 19:00 160 48 52 260 11.88879674
16-Mar Wednesday Night 19:30 174 12 76 262 11.98024903
17-Mar Thursday Night 19:00 164 12 10 70 256 11.70589218
18-Mar Friday Night 19:30 175 4 76 255 11.66016604
19-Mar Saturday Night 19:30 169 12 68 249 11.38580919
20-Mar Sunday Night 19:30 150 16 70 236 10.79136935
21-Mar Monday Night 19:30 151 13 77 241 11.02000006
22-Mar Tuesday Night 19:30 190 12 96 298 13.62639011
23-Mar Wednesday Night 19:30 160 16 97 273 12.48323658
24-Mar Thursday Night 19:30 171 12 99 282 12.89477185
25-Mar Friday Night 19:30 138 44 82 264 12.07170131
26-Mar Saturday Night 19:00 173 52 104 329 15.04390049
27-Mar Sunday Night 19:30 168 10 24 202 9.236680547
28-Mar Monday Night 19:30 190 63 41 294 13.44348555
29-Mar Tuesday Night 19:00 167 64 40 271 12.3917843
30-Mar Wednesday Night 19:30 179 62 46 287 13.12340256
31-Mar Thursday Night 19:30 178 64 44 286 13.07767642
Max. 15.95842332 MW
TimeDate Day Zone
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 65 75 85 285 105 110 220 75 1020 46.64066415
2-Mar Wednesday Night 19:30 65 72 87 280 105 105 220 80 1014 46.3663073
3-Mar Thursday Night 19:30 65 68 82 280 100 102 210 75 982 44.90307078
4-Mar Friday Night 19:30 65 72 85 285 100 102 225 78 1012 46.27485502
5-Mar Saturday Night 19:00 65 65 83 285 100 100 200 67 965 44.12572637
6-Mar Sunday Night 19:30 60 75 75 260 105 105 210 60 950 43.43983425
7-Mar Monday Night 19:30 60 65 85 285 90 100 200 65 950 43.43983425
8-Mar Tuesday Night 19:00 60 65 85 295 60 105 220 75 965 44.12572637
9-Mar Wednesday Night 19:30 60 72 90 275 100 102 220 45 964 44.08000023
10-Mar Thursday Night 19:30 70 75 90 295 100 100 220 75 1025 46.86929485
11-Mar Friday Night 19:00 60 65 80 295 100 100 210 70 980 44.81161849
12-Mar Saturday Night 19:30 65 70 85 290 100 110 220 65 1005 45.95477203
13-Mar Sunday Night 19:30 65 72 270 110 172 220 65 974 44.53726165
14-Mar Monday Night 19:00 70 70 85 295 100 105 220 78 1023 46.77784257
15-Mar Tuesday Night 19:00 65 75 80 290 100 95 220 75 1000 45.72614132
16-Mar Wednesday Night 19:30 65 68 80 270 90 98 195 58 924 42.25095458
17-Mar Thursday Night 19:00 65 75 90 270 100 95 210 70 975 44.58298779
18-Mar Friday Night 19:30 70 82 78 290 105 108 220 78 1031 47.1436517
19-Mar Saturday Night 19:30 60 75 72 270 98 95 195 60 925 42.29668072
20-Mar Sunday Night 19:30 60 78 75 260 100 100 205 65 943 43.11975126
21-Mar Monday Night 19:30 65 82 88 290 100 112 220 82 1039 47.50946083
22-Mar Tuesday Night 19:30 65 70 90 300 100 110 230 80 1045 47.78381768
23-Mar Wednesday Off Peak 3:00 45 25 45 160 55 55 120 40 545 24.92074702
23-Mar Wednesday Day 11:30 55 25 45 290 60 65 180 55 775 35.43775952
23-Mar Wednesday Night 19:30 70 70 75 290 25 100 230 82 942 43.07402512
24-Mar Thursday Night 19:30 65 70 85 290 10 102 230 80 932 42.61676371
25-Mar Friday Night 19:30 70 75 90 295 10 110 230 83 963 44.03427409
26-Mar Saturday Night 19:00 60 70 80 280 5 100 220 72 887 40.55908735
27-Mar Sunday Night 19:30 60 65 70 260 5 100 220 60 840 38.40995871
28-Mar Monday Night 19:30 65 75 88 390 5 110 220 81 1034 47.28083012
29-Mar Tuesday Night 19:00 60 62 78 238 5 90 204 75 812 37.12962675
30-Mar Wednesday Night 19:30 70 72 82 300 10 110 230 80 954 43.62273882
31-Mar Thursday Night 19:30 65 78 88 300 5 90 224 85 935 42.75394213
Max. 47.78382 MW
TimeDate Day Zone
Table 5.4: Night Peak load analysis of Galle GSS
Table 5.5: Night Peak load analysis of Hambantota GSS
Page 38 of 60
Matara GSS
Ratnapura GSS
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 425 280 110 185 130 200 228 106 1664 76.08829916
2-Mar Wednesday Night 19:30 420 235 105 175 122 200 208 102 1567 71.65286345
3-Mar Thursday Night 19:30 421 265 102 175 130 175 210 95 1573 71.9272203
4-Mar Friday Night 19:30 420 280 102 185 128 205 225 104 1649 75.40240704
5-Mar Saturday Night 19:00 426 275 100 170 130 185 209 98 1593 72.84174312
6-Mar Sunday Night 19:30 426 280 105 180 128 190 225 107 1641 75.03659791
7-Mar Monday Night 19:30 426 280 100 175 130 195 225 105 1636 74.8079672
8-Mar Tuesday Night 19:00 420 275 105 175 136 180 228 105 1624 74.2592535
9-Mar Wednesday Night 19:30 421 280 102 178 135 205 228 106 1655 75.67676388
10-Mar Thursday Night 19:30 419 290 100 180 45 205 230 105 1574 71.97294644
11-Mar Friday Night 19:00 422 275 100 170 135 178 212 97 1589 72.65883856
12-Mar Saturday Night 19:30 422 285 110 180 132 195 228 105 1657 75.76821617
13-Mar Sunday Night 19:30 422 275 172 175 125 190 25 105 1489 68.08622443
14-Mar Monday Night 19:00 423 280 105 170 140 185 230 104 1637 74.85369334
15-Mar Tuesday Night 19:00 420 270 95 170 130 170 225 100 1580 72.24730329
16-Mar Wednesday Night 19:30 424 275 98 170 130 190 230 105 1622 74.16780122
17-Mar Thursday Night 19:00 423 270 95 168 130 165 221 104 1576 72.06439872
18-Mar Friday Night 19:30 419 285 108 180 135 188 237 105 1657 75.76821617
19-Mar Saturday Night 19:30 418 265 95 168 125 185 217 103 1576 72.06439872
20-Mar Sunday Night 19:30 422 275 100 165 128 175 222 101 1588 72.61311242
21-Mar Monday Night 19:30 420 290 112 180 140 205 240 108 1695 77.50580954
22-Mar Tuesday Night 19:30 422 280 110 180 138 210 230 108 1678 76.72846513
23-Mar Wednesday Night 19:30 420 265 100 170 140 200 215 108 1618 73.98489666
24-Mar Thursday Night 19:30 420 275 102 175 142 170 230 103 1617 73.93917051
25-Mar Friday Night 19:30 420 280 110 180 135 190 240 110 1665 76.1340253
26-Mar Saturday Night 19:00 422 280 100 175 135 185 223 102 1622 74.16780122
27-Mar Sunday Night 19:30 422 270 100 175 130 170 226 102 1595 72.93319541
28-Mar Monday Night 19:30 418 255 110 175 132 215 221 101 1627 74.39643193
29-Mar Tuesday Night 19:00 421 240 90 160 138 170 222 100 1541 70.46398377
30-Mar Wednesday Night 19:30 420 250 110 178 132 175 230 105 1600 73.16182611
31-Mar Thursday Night 19:30 421 255 90 180 140 200 250 105 1641 75.03659791
Max. 77.50581 MW
TimeDate Day Zone
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 153 51 -36 27 31 12 20 258 11.79734446
2-Mar Wednesday Night 19:30 158 50 -24 38 56 12 16 306 13.99219924
3-Mar Thursday Night 19:30 148 52 25 30 48 11 5 319 14.58663908
4-Mar Friday Night 19:30 140 49 -48 9 54 11 18 233 10.65419093
5-Mar Saturday Night 19:00 145 48 -38 24 48 12 -11 228 10.42556022
6-Mar Sunday Night 19:30 157 49 -27 28 55 12 12 286 13.07767642
7-Mar Monday Night 19:30 145 50 26 32 58 12 -8 315 14.40373452
8-Mar Tuesday Night 19:00 130 50 -24 30 22 11 13 232 10.60846479
9-Mar Wednesday Night 19:30 176 54 -20 36 64 12 22 344 15.72979261
10-Mar Thursday Night 19:30 164 55 -19 37 97 13 16 363 16.5985893
11-Mar Friday Night 19:00 159 54 -15 34 65 11 21 329 15.04390049
12-Mar Saturday Night 19:30 155 50 -49 31 -96 10 17 118 5.395684676
13-Mar Sunday Night 19:30 43 44 -52 10 36 10 8 99 4.526887991
14-Mar Monday Night 19:00 77 58 -43 22 89 12 9 224 10.24265566
15-Mar Tuesday Night 19:00 73 55 -30 28 58 12 8 204 9.328132829
16-Mar Wednesday Night 19:30 86 22 -26 30 62 12 12 198 9.053775981
17-Mar Thursday Night 19:00 35 51 -25 66 74 12 5 218 9.968298808
18-Mar Friday Night 19:30 35 52 -19 77 98 12 17 272 12.43751044
19-Mar Saturday Night 19:30 33 45 -17 75 66 12 16 230 10.5170125
20-Mar Sunday Night 19:30 30 45 -61 73 36 10 -2 131 5.990124513
21-Mar Monday Night 19:30 31 69 -173 -45 67 11 -20 -60 -2.74356848
22-Mar Tuesday Night 19:30 72 53 -81 61 45 12 -27 135 6.173029078
23-Mar Wednesday Night 19:30 64 49 -173 -33 39 11 -73 -116 -5.30423239
24-Mar Thursday Night 19:30 68 54 -71 48 30 12 -16 125 5.715767665
25-Mar Friday Night 19:30 67 51 -199 -28 43 11 -73 -128 -5.85294609
26-Mar Saturday Night 19:00 69 52 -151 22 42 11 -73 -28 -1.28033196
27-Mar Sunday Night 19:30 65 52 -52 62 49 11 -62 125 5.715767665
28-Mar Monday Night 19:30 63 50 -30 -33 35 10 -73 22 1.005975109
29-Mar Tuesday Night 19:00 69 54 -206 -38 35 11 -74 -149 -6.81319506
30-Mar Wednesday Night 19:30 68 58 -75 69 45 12 -44 133 6.081576796
31-Mar Thursday Night 19:30 68 65 -58 69 56 12 11 223 10.19692951
Max. 16.59859 MW
TimeDate Day Zone
Table 5.6: Night Peak load analysis of Matara GSS
Table 5.7: Night Peak load analysis of Ratnapura GSS
Page 39 of 60
There are three Generating Plants in this island.
I. Samanalawewa PS (Frequency Controlling Generator)
II. ACE Embilipitiya PS
III. ACE Matara PS
Table 5.8: Generation Capacity of the Island
Generation Plant Capacity / MW
Samanalawewa PS 2 x 60 120
ACE Embilipitiya PS 100 100
ACE Matara PS 4 x 5 20
Total Generation 240
Table 5.9: Load Demand of the Island
Grid Substation Demand / MW
Balangoda GSS 33.56
Deniyaya GSS 17.51
Embilipitiya GSS 21.03
Galle GSS 47.78
Hambantota GSS 15.96
Matara GSS 77.51
Ratnapura GSS 16.60
Total Demand 229.95
As per the analysis 10 MW generations is excess in this island, but analysis revealed that
islanding operation fails at all the time when New Laxapana – Balangoda Line 1 and 2
trips. When considering typical plant dispatch, ACE Embilipitiya plant is dispatching 97
MW, Samanalawewa Generator 1 and 2 is dispatching 20 MW and 40 MW or wise versa.
Then total generation in this island becomes 177 MW. So normal plant dispatch condition
there is a generation deficiency of 53 MW for this island and it receives via New Laxapana
– Balangoda Line 1 and 2.
Page 40 of 60
Figure 5.2: Load Flow diagram of Balangoda 132 kV Busbar.
So with the proposed load shedding scheme simulate the system with above estimated
Generation and load condition.
Table 5.10: Load Shedded capacity of each GSS
Grid Substation Load Shedded / MW
Balangoda GSS Not Assigned
Deniyaya GSS Not Assigned
Embilipitiya GSS Not Assigned
Galle GSS 7.5
Stage 1 4
Stage 4 3.5
Hambantota GSS Not Assigned
Matara GSS 23
Stage 1 14.5
Stage 4 8.5
Ratnapura GSS Not Assigned
Total Shedded Load 30.5
Page 41 of 60
Deficit = (53 – 30.5) = 22.5 MW
Figure 5.3: Frequency response of the System
From above simulation results it can be identified that minimum frequency of the island
goes below 47 Hz for 2.5 seconds, where Generators will trip from Under Frequency Trip
Setting.
Table 5.11: Under Frequency Trip Settings
Generation Plant Under Frequency Trip Setting
Frequency Time Delay
Samanalawewa PS 47 Hz 0 Sec
ACE Embilipitiya PS 47 Hz 2.1 Sec
ACE Matara PS 47 Hz 0.24 Sec
So this Island operation is unstable even though simulation shows as stable since all the
above generators will trip from their Under Frequency Trip Setting. (There is no facility to
simulate the system with Under Frequency Trip Settings of the generators by using
available software license)
Finally, Simulate was carried out with more Loads added to the Load Shedding stages,
Page 42 of 60
Table 5.12: Load Shedded capacity of each GSS after modification
Grid Substation Load Shedded / MW
Balangoda GSS 13.5
Stage 1 4.5
Stage 2 5
Stage 3 4
Deniyaya GSS 7.5
Stage 3 7.5
Embilipitiya GSS 8
Stage 1 1
Stage 2 7
Galle GSS 16.5
Stage 1 5
Stage 2 3
Stage 3 8.5
Hambantota GSS Not Assigned
Matara GSS 20.25
Stage 1 14.5
Stage 4 5.75
Ratnapura GSS Not Assigned
Total Shedded Load 65.75
Deficit = (53 – 65.75) = -12.75 MW
Page 43 of 60
Figure 5.4: Frequency response of the System after modification of Load Shedding
Feeders.
Figure 5.5: Voltage response of the Busbars
Since the frequency stabilized at 49.25 Hz and bus voltages are within acceptable limits
(0.9 Pu – 1.1 Pu [2]) after Load Shedding operation, Samanalawewa Generator can keep
this system alive, which makes this Islanding Operation Successful.
Page 44 of 60
Let’s also consider New Laxapana – Balangoda line loading when Load Shedding operates
up to stage 4 due to system disturbance outside the island. So under typical plant dispatch
condition 65.75 MW generation will be available more than loads in this island and will be
flow into the New Laxapana busbar via New Laxapana – Balangoda line. This is equal to
290 A. Since single line can carry 420 A hence both lines can carry 840 A, this island will
operate perfectly also in above stated condition.
Finally it can be identified that Islanding Operation is possible with Samanalawewa
Frequency controlling machine after the Load Shedding Feeders of the following Grid
Substation are arranged such a way that it will shed equal or more than below proposed
MW values in each Load Shedding stage.
Table 5.13: Proposed Load Shedded capacity of each GSS in the island
Grid Substation Existing Load Shedding
Amount / MW
Proposed Load Shedding
Amount / MW
Balangoda GSS - 13.5
Stage 1 - 4.5
Stage 2 - 5
Stage 3 - 4
Deniyaya GSS - 7.5
Stage 3 - 7.5
Embilipitiya GSS - 8
Stage 1 - 1
Stage 2 - 7
Galle GSS 7.5 16.5
Stage 1 4 5
Stage 2 - 3
Stage 3 3.5 8.5
Hambantota GSS - -
Matara GSS 23 20.25
Stage 1 14.5 14.5
Stage 4 8.5 5.75
Ratnapura GSS - -
Total Shedded Load 30.5 65.75
It is necessary to reduce above increased MW value (35.25 MW) from the rest of the
network to maintain the total load shedding step size of each stage equal.
Page 45 of 60
5.3. Tripping of 132 kV Pannipitiya – Matugama Line and Pannipitiya – Horana
Line.
Figure 5.6: Network Configuration of the Island
When this incident happens following Grid Substations are separated from the main
network.
I. Ambalandoga GSS
II. Horana GSS
III. Matugama GSS
IV. Panadura GS
Page 46 of 60
Load Study had been carried out to find the total load of the above Grid Substations.
Off Peak, Day Peak and Night Peak data have been analyzed and find out that Night Peak
load is always higher than off peak and Day peak. So following tables will include Night
Peak load analysis only.
Ambalangoda GSS
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 89 193 51 333 15.226805
2-Mar Wednesday Night 19:30 84 184 48 316 14.449461
3-Mar Thursday Night 19:30 89 194 53 336 15.363983
4-Mar Friday Night 19:30 85 184 49 318 14.540913
5-Mar Saturday Night 19:00 83 180 49 312 14.266556
6-Mar Sunday Night 19:30 87 187 52 326 14.906722
7-Mar Monday Night 19:30 82 174 47 303 13.855021
8-Mar Tuesday Night 19:00 83 186 52 321 14.678091
9-Mar Wednesday Night 19:30 85 194 54 333 15.226805
10-Mar Thursday Night 19:30 89 199 53 341 15.592614
11-Mar Friday Night 19:00 85 185 51 321 14.678091
12-Mar Saturday Night 19:30 88 189 0 52 329 15.0439
13-Mar Sunday Night 19:30 87 191 51 329 15.0439
14-Mar Monday Night 19:00 110 189 15 314 14.358008
15-Mar Tuesday Night 19:00 82 188 49 319 14.586639
16-Mar Wednesday Night 19:30 70 176 42 288 13.169129
17-Mar Thursday Night 19:00 79 172 40 291 13.306307
18-Mar Friday Night 19:30 86 198 49 333 15.226805
19-Mar Saturday Night 19:30 85 184 45 314 14.358008
20-Mar Sunday Night 19:30 86 188 46 320 14.632365
21-Mar Monday Night 19:30 78 181 59 318 14.540913
22-Mar Tuesday Night 19:30 80 192 61 333 15.226805
23-Mar Wednesday Night 19:30 76 298 57 431 19.707967
24-Mar Thursday Night 19:30 82 270 60 412 18.83917
25-Mar Friday Night 19:30 81 301 58 440 20.119502
26-Mar Saturday Night 19:00 80 296 131 507 23.183154
27-Mar Sunday Night 19:30 78 285 132 495 22.63444
28-Mar Monday Night 19:30 78 299 132 509 23.274606
29-Mar Tuesday Night 19:00 64 276 122 462 21.125477
30-Mar Wednesday Night 19:30 78 293 133 504 23.045975
31-Mar Thursday Night 19:30 79 302 137 518 23.686141
Max. 23.6861 MW
Date Day Zone Time
Table 5.14: Night Peak load analysis of Ambalangoda GSS
Page 47 of 60
1 2 3 4 5 6 7 8 9 10 Total Total
A A A A A A A A A A A MW
1-Mar Tuesday Night 19:30 33 68 22 183 73 60 93 186 121 151 990 45.26888
2-Mar Wednesday Night 19:30 32 91 23 190 76 59 93 192 128 159 1043 47.69237
3-Mar Thursday Night 19:30 31 82 23 185 75 62 92 201 125 151 1027 46.96075
4-Mar Friday Night 19:30 6 78 32 174 64 57 84 178 112 145 930 42.52531
5-Mar Saturday Night 19:00 94 51 20 109 70 50 71 165 115 142 887 40.55909
6-Mar Sunday Night 19:30 95 73 23 119 75 55 87 188 123 153 991 45.31461
7-Mar Monday Night 19:30 93 70 21 108 71 48 72 173 111 140 907 41.47361
8-Mar Tuesday Night 19:00 94 114 21 107 72 52 84 171 115 151 981 44.85734
9-Mar Wednesday Night 19:30 101 90 23 119 79 61 91 204 124 155 1047 47.87527
10-Mar Thursday Night 19:30 99 94 23 123 77 55 94 191 127 156 1039 47.50946
11-Mar Friday Night 19:00 94 92 21 111 72 52 90 186 119 151 988 45.17743
12-Mar Saturday Night 19:30 98 79 23 120 75 55 91 196 124 153 1014 46.36631
13-Mar Sunday Night 19:30 96 64 23 117 72 54 89 191 122 150 978 44.72017
14-Mar Monday Night 19:00 95 71 22 121 71 66 87 194 103 173 1003 45.86332
15-Mar Tuesday Night 19:00 98 92 22 113 71 60 90 188 121 154 1009 46.13768
16-Mar Wednesday Night 19:30 49 67 13 93 56 50 78 183 107 147 843 38.54714
17-Mar Thursday Night 19:00 84 62 22 98 66 58 55 173 116 147 881 40.28473
18-Mar Friday Night 19:30 99 82 25 120 76 56 95 195 123 153 1024 46.82357
19-Mar Saturday Night 19:30 95 84 27 116 72 47 89 182 123 152 987 45.1317
20-Mar Sunday Night 19:30 93 55 24 112 67 47 80 169 118 149 914 41.79369
21-Mar Monday Night 19:30 90 66 22 111 76 55 94 200 125 156 995 45.49751
22-Mar Tuesday Night 19:30 100 71 23 122 78 61 95 206 126 156 1038 47.46373
23-Mar Wednesday Night 19:30 21 83 24 119 77 55 87 210 122 159 957 43.75992
24-Mar Thursday Night 19:30 101 85 22 122 78 58 98 197 127 158 1046 47.82954
25-Mar Friday Night 19:30 103 90 23 121 76 56 97 205 129 158 1058 48.37826
26-Mar Saturday Night 19:00 98 81 23 43 74 56 89 183 124 158 929 42.47959
27-Mar Sunday Night 19:30 96 84 23 43 77 58 92 181 125 151 930 42.52531
28-Mar Monday Night 19:30 93 37 22 36 75 61 96 194 119 159 892 40.78772
29-Mar Tuesday Night 19:00 98 81 22 43 71 62 97 193 129 158 954 43.62274
30-Mar Wednesday Night 19:30 92 53 19 39 73 39 78 175 121 150 839 38.36423
31-Mar Thursday Night 19:30 102 91 22 44 76 64 97 203 124 155 978 44.72017
Max 48.3783 MW
Date Day Zone Time
Horana GSS
1 2 3 4 5 6 7 8 Total Total
A A A A A A A A A MW
1-Mar Tuesday Night 19:30 10 121 259 140 100 41 426 71 1168 53.40813
2-Mar Wednesday Night 19:30 10 121 253 137 92 39 405 71 1128 51.57909
3-Mar Thursday Night 19:30 10 112 241 132 83 41 335 70 1024 46.82357
4-Mar Friday Night 19:30 10 119 229 138 72 34 432 71 1105 50.52739
5-Mar Saturday Night 19:00 9 91 217 82 78 30 437 70 1014 46.36631
6-Mar Sunday Night 19:30 6 126 195 108 75 38 429 73 1050 48.01245
7-Mar Monday Night 19:30 10 130 223 108 69 19 420 68 1047 47.87527
8-Mar Tuesday Night 19:00 8 120 259 142 83 38 432 69 1151 52.63079
9-Mar Wednesday Night 19:30 9 13 278 151 95 43 432 74 1095 50.07012
10-Mar Thursday Night 19:30 10 118 263 142 85 43 441 75 1177 53.81967
11-Mar Friday Night 19:00 8 64 278 140 89 41 430 71 1121 51.25900
12-Mar Saturday Night 19:30 8 135 258 141 89 41 438 73 1183 54.09403
13-Mar Sunday Night 19:30 6 119 221 118 81 40 437 72 1094 50.02440
14-Mar Monday Night 19:00 9 123 270 146 93 43 424 71 1179 53.91112
15-Mar Tuesday Night 19:00 10 128 262 150 91 42 419 75 1177 53.81967
16-Mar Wednesday Night 19:30 7 131 249 138 86 35 427 74 1147 52.44788
17-Mar Thursday Night 19:00 7 126 245 116 84 42 415 73 1108 50.66456
18-Mar Friday Night 19:30 7 139 255 145 90 43 430 74 1183 54.09403
19-Mar Saturday Night 19:30 4 140 208 132 84 42 421 74 1105 50.52739
20-Mar Sunday Night 19:30 0 126 196 123 78 39 431 76 1069 48.88125
21-Mar Monday Night 19:30 6 136 274 148 91 40 437 78 1210 55.32863
22-Mar Tuesday Night 19:30 8 127 278 151 91 43 439 76 1213 55.46581
23-Mar Wednesday Night 19:30 6 123 274 147 91 33 429 67 1170 53.49959
24-Mar Thursday Night 19:30 6 117 280 151 94 42 430 74 1194 54.59701
25-Mar Friday Night 19:30 8 128 271 153 90 43 438 73 1204 55.05427
26-Mar Saturday Night 19:00 8 127 254 144 91 42 439 71 1176 53.77394
27-Mar Sunday Night 19:30 6 122 217 127 88 44 445 71 1120 51.21328
28-Mar Monday Night 19:30 9 126 269 162 92 44 316 70 1088 49.75004
29-Mar Tuesday Night 19:00 9 120 274 150 96 43 320 73 1085 49.61286
30-Mar Wednesday Night 19:30 8 107 262 108 91 43 321 72 1012 46.27486
31-Mar Thursday Night 19:30 8 127 270 149 91 48 320 70 1083 49.52141
Max 55.4658 MW
Date Day Zone Time
Mathugama
Table 5.15: Night Peak load analysis of Horana GSS
Table 5.16: Night Peak load analysis of Mathugama GSS
Page 48 of 60
After this incident Panadura GSS has no feeding, so its load study is not done.
There are two Generating Plants in this island.
I. Kukule PS (Frequency Controlling Generator)
II. ACE Horana PS
Table 5.17: Generation Capacity of the Island
Generation Plant Capacity / MW
Kukule PS 2 x 35 70
ACE Horana PS 4 x 5 20
Total Generation 90
Table 5.18: Load Demand of the Island
Grid Substation Demand / MW
Ambalangoda GSS 23.69
Horana GSS 55.47
Mathugama GSS 47.38
Total Demand 126.54
As per the analysis 36 MW generations deficiency is in this island, so with proposed load
shedding scheme simulate the system for above Generation and load condition.
Table 5.19: Load Shedded capacity of each GSS
Grid Substation Load Shedded / MW
Ambalangoda GSS 3
Stage 1 3
Horana GSS 8
Stage 3 2
Stage 4 6
Mathugama GSS 15
Stage 1 4
Stage 2 4
Stage 3 7
Total Shedded Load 26
Page 49 of 60
Deficit = (36 – 26) = 10 MW
Figure 5.7: Frequency response of the System
It can be identified that this System is unstable.
Then simulate with more Loads added to the Load Shedding stages and also priority given
to Stage 1 and 2.
Table 5.20: Load Shedded capacity of each GSS after modification
Grid Substation Load Shedded / MW
Ambalangoda GSS 4
Stage 1 4
Horana GSS 20
Stage 1 14
Stage 2 6
Mathugama GSS 26
Stage 1 14
Stage 2 4
Stage 3 8
Total Shedded Load 50
Page 50 of 60
Deficit = (36 – 50) = -14 MW
Figure 5.8: Frequency response of the System after modification of Load Shedding
Feeders.
Since the frequency stabilized at 49.90 Hz and bus voltages are within acceptable limits
(0.9 Pu – 1.1 Pu [2]) after Load Shedding operation, Kukule Generator can keep this island
alive and which makes this Islanding Operation Successful.
Let’s also consider Pannipitiya – Matugama Line, Pannipitiya – Horana Line and Horana
- Matugama Line loading when Load Shedding operates up to stage 3 due to system
disturbance outside the island. So under typical plant dispatch condition 61 MW generation
will be available more than loads in this island and will be flow into the Pannipitiya busbar
via above mentioned lines (In Panadura GSS 11 MW rejects from Load Shedding). This is
equal to 267 A. Since single line can carry 630 A [10] and hence total of 1260 A, this
island will operate perfectly also in above stated condition.
Finally it can be identified that Islanding Operation is possible with Kukule Frequency
controlling after the Load Shedding Feeders of the following Grid Substation are
rearranged such a way that it will shed equal or more than below proposed MW values in
each Load Shedding stage.
Page 51 of 60
Table 5.21: Proposed Load Shedded capacity of each GSS in the island
Grid Substation Existing Load Shedding
Amount / MW
Proposed Load Shedding
Amount / MW
Ambalangoda GSS 3 4
Stage 1 3 4
Horana GSS 8 20
Stage 1 - 14
Stage 2 - 6
Stage 3 2 -
Stage 4 6 -
Mathugama GSS 15 26
Stage 1 4 14
Stage 2 4 4
Stage 3 7 8
Total Shedded Load 26 50
It is necessary to reduce above increased MW value (24 MW) from the rest of the network
to maintain the total load shedding step size of each stage equal.
Page 52 of 60
Chapter 6
CONCLUSION & RECOMMENDATION
Load shedding schemes have been deployed almost universally in the power systems to
provide the fastest possible remedial action in the event of severe generation – demand
mismatch. The under frequency load shedding scheme must be modified to adapt the
changes in the power system such as commissioning of large generators, increase in
demand and changing the operating conditions. This dissertation discussed about designing
of new under frequency load shedding scheme align with the development of Sri Lankan
power system.
In Chapter 4, whole Sri Lankan power system has been modeled using the PSS®E
software and Existing Load Shedding scheme was simulated using this model. Then
improve the Load shedding scheme settings step by step to reduce the rejecting loads from
the Load shedding scheme while maintaining the stability of the system. After analyzing
simulation 1 to 8, Proposed Load Shedding scheme is shown in Table 6.1.
Table 6.1: Proposed New Load Shedding Scheme
Stage Load to be
Remarks Tripping Criteria Tripped (%)
I 5 5% Load on only freq. based 48.75 Hz + t=100 ms
II 5 5% Load on only freq. based 48.50 Hz + t=150 ms
III 5 5% Load on only freq. based 48.25 Hz + t=150 ms
IV 6 6% Load on only freq. based 48.00 Hz + t=150 ms
V 10
8% Load on only freq. based 47.50 Hz + t=150 ms
OR
2% Load on only freq. based 49 Hz AND df/ft =
+ df/dt based 0.85 Hz/Sec
VI 10
10% Load on df/dt based
49 Hz AND df/ft =
0.85 Hz/Sec
Load reduction from Load Shedding tripping after implementing the above scheme and be
found on Table 6.2.
Page 53 of 60
Table 6.2: Saved Load from Proposed New Load Shedding Scheme
Further, due to present network configuration after certain power System failures some
part of the system isolates from the main system and operates in islanding mode. This
islanding operation fails at all the times due to unbalance of the generation and load. This
dissertation also discussed in what way to overcome above situation by rearranging 33 kV
Load Shedding Feeders in the Sri Lankan network.
In Chapter 5, it was identified possible islanding operations and analyzed the stability of
them with proposed load shedding scheme. Finally rearrange the 33 kV load shedding
feeders in the Sri Lankan network to facilitate islanding operation by analyzing the
stability of the islands using simulation.
Finally it can be identified that Islanding Operation is possible with Samanalawewa and
Kukule Frequency controlling machines after the Load Shedding Feeders of the following
Grid Substation are arranged such a way that it will shed equal or more than Table 6.4
proposed MW values in each Load Shedding stage.
Load reduction with proposed Load Shedding feeder arrangement of each island can be
found on Table 6.3.
Table 6.3: Saved Load from proposed feeder arrangement in each island
Page 54 of 60
Table 6.4: Proposed Load Shedded capacity of each GSS in the islands
Grid Substation Proposed Load Shedding Amount / MW
Balangoda GSS 13.5
Stage 1 4.5
Stage 2 5
Stage 3 4
Deniyaya GSS 7.5
Stage 3 7.5
Embilipitiya GSS 8
Stage 1 1
Stage 2 7
Galle GSS 16.5
Stage 1 5
Stage 2 3
Stage 3 8.5
Matara GSS 20.25
Stage 1 14.5
Stage 4 5.75
Ambalangoda GSS 4
Stage 1 4
Horana GSS 20
Stage 1 14
Stage 2 6
Mathugama GSS 26
Stage 1 14
Stage 2 4
Stage 3 8
Finally it is recommended to analyze and revise the under frequency Load Shedding
scheme at least once in two years under consideration of continuous changes of the
characteristics of the Sri Lankan power system.
Page 55 of 60
Reference list
[1] Walter A. Elmore, “Protective Relaying Theory and Applications”, Marcel Deckker Inc publications, New York, 10016, pp 345-355.
[2] Ceylon Electricity Board, “CEB Policy on Power System Operations”, July 2009.
[3] Failure Details, Ceylon Electricity Board, 2011.
[4] Siemens Energy Inc., “PSS®E 32.0 Program Operation Manual”, Siemens Power
Technologies International, New York, USA, 2009.
[5] Ceylon Electricity Board, “Coal Fired Thermal Development Project West Coast -
CEB Transmission Connection Power System Analysis Studies”, 2009.
[6] Ceylon Electricity Board, “Bidding Document, Part B-Technical Specification”,
vol. 5, pp. 12-62, 2011.
[7] PUCSL, “Findings of the committee appointed to investigate the power system failures on 9th October 2009”, 2009.
[8] Alstom Grid, “Network Protection & Automation Guide”, Alstom Grid Worldwide Contact Centre, France, 2011.
[9] P.Kundur, “Power System Stability and Control”, McGraw-Hill, New York, 1994.
[10] Ceylon Electricity Board, “Long Term Transmission Development Plan 2011-
2020”, July 2011.
[11] D.D.P. Yasarathna, “Review the Existing Load Shedding Scheme used in Sri Lanka
power system and Design a new Load Shedding Scheme”, University of Moratuwa,
Sri Lanka, 2002
[12] Alejandro P. Ojeda, “A Load Shedding Scheme for Inverter Based Microgrids”, Massachusetts Institute of Technology, USA, 2011
Page 56 of 60
[13] R.L. Muttucumaru, “A new algorithm for load shedding in an industrial
cogeneration power plant”, Victoria University Of Technology, Australia, 1999.
[14] Poonam M. Joshi, “Load shedding algorithm using voltage and frequency data”,
The Graduate School of Clemson University, USA, 2007
[15] Yunfei Wang, “Advanced load shedding scheme for voltage collapse prevention”,
University of Alberta, Canada, 2011.
[16] Shahrzad Rostamirad, “Intelligent Load Shedding Scheme for Frequency Control
in Communities with Local Alternative Generation and Limited Main Grid
Support”, The University of British Columbia, 2009
[17] Haibo You, Vijay Vittal, Juhwan Jung, Chen-Ching Liu, Massoud Amin, Rambabu
Adapa,“An Intelligent Adaptive Load Shedding Scheme”,14th PSCC, June 2002
[18] Ding Xu, Adly A.Girgis, “Optimal Load Shedding Strategy in Power Systems with
Distributed Generation”, Clemson University, USA
[19] A.A. Mohd Zin, H.Mohd Hafiz, M.S Aziz, “A Review of Under Frequency Load Shedding Scheme on TNB System,” National Power & Energy Conference 2001
Proceedings), Malayia, pp 170-174, 2004.
[20] A. Gjukaj, G. Kabashi, G.Pula, N. Avdiu, B. Prebreza, “ Re-Design of Load
Shedding Schemes of the Kosovo Power System,” Worl Acadami of Science, Engineering and Technology 74, pp 262-266, 2011.
[21] Ceylon Electricity Board, “Statistical Digest 2011”.
1130POLPI-1
132.2
1170SAMAN-1
129.3
1210BOWAT-1
132.2
1770KIRIB-1
2220KOTMA-2
222.3
2230VICTO-2
224.4
2240RANDE-2
225.4
2250RANTE-2
225.4
32.7
32.6
3620BADUL-3
32.8
12.6
4252RANTE-G2
1790RATMA-1
132.4
1300KELAN-1
132.7
132.6
4760COL_F-11
10.9
4750COL_E-11
131.1
3500KOSGA-3
33.1
33.1
3670MATARA-3
132.0
33.3
132.0
3520NUWAR-3
33.3
1520NUWAR-1
130.7
1620BADUL-1
130.5
131.2
3540ORUWA-3
33.0
1670MATARA-1
125.8
132.3
1660EMBIL-1
1100LAX-1
132.0
131.3
3200UKUWE-3
3530THULH-3
33.0
32.7
217.2
2300KELAN-2
216.2
1540ORUWA-1
132.1
1530THULH-1
131.2
132.3
218.4
33.1
3860MADAM-3
132.6
225.3
1705NEWANU-1
133.5
1700ANURA-1
1850PANAD-1
132.4
1800MATUG-1
132.6
132.6
1240VAVUN-1
3240VAVUN-33
32.9
32.8
32.7
127.4
3400HAMBA-33
33.0
3660EMBIL-3
32.9
32.7
33.4
1160INGIN-1
127.0
3160INGIN-3
125.7
33.3
3700ANURA-3A
216.2
32.9
33.0
1710TRINC-1
33.0
132.1
32.9
32.9
131.8
32.7
3690HABAR-3
33.0
1740RATNAP-1
129.633.2
1595KHD -1
132.2
133.3
1600BOLAW-1
131.032.6
132.2
32.6
1840JPURA_1
132.4
3840JPURA_3
131.9
132.0
132.3
10.9
4435COL_A_11
3890DEHIW_3
33.0
3800MATUG-3
33.0
1810PUTTA-1
135.1
33.7
2.8
0.92.8
0.9
3.8
9.6
3.8
9.6
5.2
9.9
5.2
9.9
23.0
3.823.0
3.8
25.5
5.1
25.3
3.9
40.2
1.1
40.2
1.1
0.6
9.230.8
14.3
5.6
3.0
18.4
9.4
5.4
24.0
14.6
17.3
7.2
21.8
9.8
3.9
12.0 6.6
8.1
5.6
8.2
17.3
28.6
5.5
28.3
4.6
9.6
7.1
5.1
10.4
1.2
10.4
1.2
14.6
3.0
14.4
5.0
23.1
3.1
23.1
15.1
9.0
3.6
3.6
2.222.9
2.1
0.0
0.0
0.0
6.7
11.4
13.9
4.5
10.0
4.7
0.0
1.9 0.0
1.9
0.0
0.0
0.0
0.0
104.2
34.6
103.5
42.8
104.2
34.6
103.5
42.8
2.8
0.2
2.8
0.2
2.6
1.4
0.1
16.7
3.4
64.5
46.1
64.5
46.1
0.0
43.9
43.9
6.1
3.1
3.3
17.3
10.9 17.3
10.9
34.6
21.8
7.8
2.6
1.2
0.4
0.0
0.0
21.5
3.621.5
3.6
0.0
0.5
0.0
0.0
40.6
40.1
0.0 0.0
0.0
0.4
1.8
11.1
6.9
0.4
1.8
23.0
12.6
5.4
7.6
19.5
75.9
27.7
76.1
75.9
27.7
76.1
27.1
22.3
1.9
9.6
9.6
0.7
13.3
1.2
13.2
2.3
1.3
0.2
1.3
0.2
2.5
4.5
48.0
44.2
48.1
48.0
44.2
48.1
43.0
20.6
0.0
0.0
23.4
18.9
30.0
5.430.0
5.4
27.3
17.8
0.2
89.2
6.1
89.1
6.689.2
6.1
89.1
6.6
77.1
13.777.1
13.7
9.5
54.9
28.9 54.9
28.9
6.8
0.0
12.0
20.0
26.2
14.8 46.9
19.4
67.0
12.8
20.6
11.3
11.3
6.7
6.2
3.6
1.2
6.3
6.3
2.8
12.6
4.6
19.0
8.4
16.7
19.5
6.7
19.0
2.3
19.2
0.3
18.4
10.7
9.2
5.3
9.2
5.3
1.0
000 30.8
14.8
8.1
8.1
8.2
0.0
16.4
1.6
16.4
1.6
8.3
7.3
0.2
7.3
0.2
23.0
53.8
23.0
51.8
23.0
53.8
23.0
51.8
22.2
30.5
30.5
4.9
4.1
2.9
8.4
1
23.1
8.2
L
37.0
17.0
H
1
1
2.2
1
2.9
1
20.6
10.0
1 25.0
7.0R
1
1 22.9
14.1
1 23.4
16.2
1
17.3
6.7
1
24.0
13.4
1
15.6
8.1
1
17.3
5.6
1
1 34.6
1 4.5
2.3
1 10.0
1 0.0
1
1 34.6
20.1
1
1
0.0
0.0
1
18.4
9.4
1
24.5
1
7.8
2.4
SW 0.0
1
1
1.2
1
0.0
1 12.6
4.3
23.2
8.2
L
2
37.3
17.0
H
2
25.0L
60.0
25.0L
2
24.0
3.0L
2 24.5
2.0L
1
1
2 40.0
26.0H
1
2
1
22.9
16.7
SW
19.7
1
23.0
11.5
1 22.9
11.0
1
7.5
4.5
SW
1
20.6
1
25.7
1
0.0
0.0
1
27.3
16.6
1
24.0
13.3
1
1
9.5
5.7
1 8.4
6.2
1
1
1 13.9
8.6
1 20.0
11.4
1
20.6
9.0
1 26.2
10.7
1
11.7
6.1
2
5.4R
1
1
30.0
5.4R
1
19.0
11.0SW
1
16.7
8.4
1
1
18.4
1
1 0.0
1 22.3
12.3
1
1.1
1 83.0
SW
10.4
0.033.0
4.5
33.0
6.7
5.6
0.0
3121WIMAL-3B
0.0
60.0
26.9
3780VALACH_3
33.0
131.4
1780VALACH_1
6.8
19.9
0.4
16.2
131.7
27.1
6.6
3.2
3560PANNI-3
30.0
1590SAPUGA-1
18.5
3830VEYAN-33
1250RANTE-1
26.5
75.3
26.5
26.0
11.6
26.0
11.4
18.9
15.7
4.5
26.0
11.6
26.0
15.7
3.3
0.3
2.2
22.9
1 1.6
1.0
25.9
11.7
14.1
25.9
13.2
8.6
3600BOLAW-3
1
1
10.0
1
SW 0.0
1.9
20.0
3.9
19.6
6.5
3.6
1.2
8.4
5.0L
16.0
25.7
18.8
9.3
1 10.0
0.0L
6.2
1
1
10.0
1
1
5.0
0.0R
1
14.5
10.1
4.1
1
129.7
132.5
3880AMBALA
32.8
9.6
6.0
4.8
3.0
4.8
1
9.6
5.8
1
15.6
15.0
7.5
1900PNNALA
11.2
0.9
1.6
14.7
9.1
1910ANIYA
3910ANIYA
15.6
10.0
16.2
1
16.2
10.0
131.7
32.9
1
19.5
10.0
SW
0.0
SW
0.0
20.6
6.7
6.1
6.7
1.6
0.0
11.1
7.9
6.5
3710TRINC-3
SW
1
2
0.0
0.0
0.0
0.0
0.7
3250RANTE-3
3630BALAN-3
0.0
L
0.0
33.3
23.8
10.4
2.3
9.1
3565PANNI-C
10.2
10.0
15.9
2.0
32.6133.3
7.3
2.5
1 7.3
2.3
32.8
1.1 1.1
0.6
13.0
131.4
14.1
5.014.1
5.0
3440KATUNA-3
32.7
1
12.7
9.7
0.0SW
0.0
1 0.0
0.0
3
3811CEMENT
32.8
16.2
131.1
11.2
6.8
6.8
86.5
30.7
86.5
30.7
87.2
14.5
87.2
14.5
8.2
1
1 10.0
0.0L
20.0
2580KOTUG-2
6.1
3.5
SW 0.0
1
219.2
32.6
18.9
216.1
32.9
11.4
4.5
14.1
1
1.3
13.9
7.8
1920SUB-C
132.7
4920SUB C-11
4.0
1
11.0
1760COL_F-1
8.0
33.2
8.0
4.4
11.0
1500KOSGA-1
15.1
22.2
13.7
3.5
13.6
5.0
10.4
8.2
23.0
3.9
22.7
2.0
23.0
3.9
19.8
1
190.0
1.0
000 174.3
29.1
4811PUTT COAL-2
19.8
1 0.0
0.0
43.0
1 15.6
11.2
52.9R
11.4
12.0
0.3
1651GALLE-2
10.9
43.5
0.0
0.0
0.0
0.0
16.7
29.3
32.8
1
5.7
3.2
3.3
1
1
1
1
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
4310SAPUG-P
11.0
1 48.0
32.0H
11.0
1
26.5
20.0H
2 35.5
20.0H 48.0
27.0 62.0
31.0
0.6
32.6
1
8.0
1.0
7.3
15.4
2.8
7.3
4.7
8.0
2560PANNI-2
132.2
2
60.0
19.4R
3
60.0
19.4R
2.8
1550KOLON-1 2
3.4
6.7
0.0
10.9
3302KELAN-3B
1650GALLE-1
2.4
9.2
20.6
4.6
20.6
4.6
1
2.5
3405HAMBA-33
1400HAMBA-1
127.6
4.0
3340BELIATT-3
126.7
1.1
1340BEATT-1
15.3
2.9
32.8
129.8
3.1
19.5
1150AMPA-1
3150AMPA-3
4251RANTE-G1
12.5
1120WIMAL-1
3120WIMAL-3
1110N-LAX-1
6.1
3.3
3650GALLE-3
129.5
3651GALLE-3B
6.7
129.3
1640DENIY-1
3640DENIY-3
3740RATNAP-3
1630BALAN-1
1140CANYO-1
132.0
1.4
1690HABAR-1
3245VAVUN-33
2.3
0.3
1200UKUWE-1
8.5
24.6
3770KIRIB-3
33.1
SW
130.6
0.0
5.6
132.8
131.1
22.7
2.0
2705NEWANU-2
3810PUTTA-3
0.0
4305KERAWALA-G
14.4
1680KURUN-1
3680KURUN-3
SW
75.3
32.8
1860MADAM-1
131.2
4810PUTT COAL-1
1580KOTUG-1
2830VEYAN-2
1830VEYAN-1
13.5
5.7
32.6
3701ANURA-3B
SW
2810PUTTALAM-PS
224.4
1.0
430
11.2
3581KOTU_NEW-3
3580KOTUG-3
32.6
3510SITHA-33
23.4
11.7
1440KATUNA-1
3900PANNAL
15.9
0.0
24.0
14.1
3590SAPUG-3A
33.0
4311SAPUG-P2
1310SAPUG-1P
1870K_NIYA-1
3870K-NIYA-3
SW 0
.0
3820ATURU-3
Present Transmission Network
0.9
1880AMBALA
10.8
1420HORANA_1
131.8
3420HORANA_3
132.2
1890DEHIW_1
20.6
1435COL_A_1
7.0
7.0
9.0
13.9
3301KELAN-3A
30.5
0.0
15.1
3850PANAD-3
12.3
3790RATMA-3A 1560
PANNI-1
10.9
0.0
0.2
1510SITHA-1
15.1
3550KOLON-3A
32.7
3551KOLON-3B
8.0
22.9
1750COL_E-1
2570BIYAG-2
2305KERAWALA_2
218.4
14.4
4306KERAWALA-S
0.9667
* 53.0
2.0
7.5
* 1
2.3
0.9667
1.0000 1.0166
* 53.0
2.0
40.7
7.5
* 1
2.3
6.3
6.3
40.7
1.0000
0.9833
3.2
17.3
4.1
* 2.8
0.7
1.0000
1.0000 0.9833
* 20.1
3.2
17.3
4.1
* 2.8
0.7
133.5
1.1000
1.0000 0.9833
* 54.6
21.5
34.3
35.1
* 2
0.4
1.0000 0.9833
* 54.6 21.5
34.3
35.1
* 2
0.4
10.6
1.0000
1.0000 1.083357.2
23.0
53.4
* 0.0
0.0
1.0000
1.0000 1.0833
* 23.0
57.2
23.0
53.4
* 0.0
0.0
* 23.0
4300GT 07
2222BARGE-2
3300KELANI-3
1.0000
1.0000 1.0493
* 48.0
44.2
48.0
41.7
* 0.0
0.0
1.0000
1.0000 1.0493
* 48.0
44.2
48.0
41.7
* 0
.0
0.0
4302KCCP ST
4301KCCP GT
4303AES GT
4304AES ST
1820ATURU-1
3570BIYAG-3
10.6
1.0000
* 20.1
3705NEWANU-3
1570BIYAG-1
1.1000
40.7
21.2
32.9
128.1
1.01661.0000
1.0
450
4430COL_I_11
19.3
1430COL_I_1
33.0
1410KUKULE-1
Bus - VOLTAGE (kV)Branch - MW/MvarEquipment - MW/Mvar
100.0%RATEA
1.050OV0.950UV
kV: <=60.000 <=120.000 <=200.000 >200.000
Page 58 of 60
Appendix B: Dispatch Scenario during HMOP Condition
Machine ID MW
O/LAX-I 1 24 O/LAX-II 2 24.5 N-LAX-1 1 23.1432 N-LAX-1 2 23.2156 WIMAL-1 1 25 WIMAL-1 2 0 POLPI-1 1 37 POLPI-1 2 37.3 CANYO-1 1 30 CANYO-1 2 0 SAMAN-1 1 60 SAMAN-1 2 0 UKUWE-1 1 18 UKUWE-1 2 0 BOWAT-1 1 11 KELAN-1 1 0 KUKULE-1 1 30 KUKULE-1 2 30 KHD -1 1 46 EMBIL-1 1 40 PUTTA-1 1 83 KOTMA-2 1 0 KOTMA-2 2 60 KOTMA-2 3 60 BARGE-2 1 60.4 VICTO-2 1 0 VICTO-2 2 60 VICTO-2 3 60 RANDE-2 1 0 RANDE-2 2 40 RANTE-G1 1 25 RANTE-G2 1 0 GT 07 1 0 KCCP GT 1 0 KCCP ST 1 0 AES GT 1 0 AES ST 1 0 KERAWALA-G 1 81.3 KERAWALA-G 2 50 KERAWALA-S 3 90 SAPUG-P 1 48 SAPUG-P2 1 26.5 SAPUG-P2 2 35.5 PUTT COAL-1 1 190
Total 952.1588