design deliverable enhancement project ( ddep ) - update
DESCRIPTION
Design deliverable enhancement project ( ddep ) - update. In 2006, the MDOT / ACEC Design Technology Committee was formed. To-date, several DTC Forums have been held throughout Michigan. Nearly 150 MDOT and Consultant designers attended each Forum. - PowerPoint PPT PresentationTRANSCRIPT
In 2006, the MDOT / ACEC Design Technology Committee was formed.
To-date, several DTC Forums have been held throughout Michigan. Nearly 150 MDOT and Consultant designers attended each Forum. eProposal, PDF deliverables, GEOPAK, MicroStation and other
technology related issues.
In early 2007, the DTC presented MDOT / ACEC leadership with the DDEP concept.
DDEP Participants: Sponsors:
Mark Van Port Fleet, MDOT - Director of Highway Development
Brenda O’Brien, MDOT - Engineer of Construction and Technology Division
Tony Kratofil, MDOT Metro Region Engineer
Team Leaders: Dan Belcher, MDOT - Engineering Support Services
Robert Rayl, RS Engineering, LLC
DDEP Core / Tech Team:MDOTBrian Dollman-Jersey, Survey
Dave Geyer, Design
Harold Hovey, Design
Joel Ingle, Design
Tom Vandenberg, Design
Chuck Occhiuto, Bridge Design
Brad Wieferich, Engineer of Design
Rachelle VanDeventer, Lansing TSC
Mike Irwin, Jackson TSC Const.
Channing Page, Lansing TSC Const.
ACEC - ConsultantsBrad Lund, Wilcox
Nate Buning, URS Corp
Aaron Wekenman, Alfred Benesch
Tom Seresoroz, RS Engineering
Doug Parmerlee, URS Corp
Tony Migaldi, HNTB
Jeff Bartlett, SSI
MITA - ContractorsDoug Needham, MITA
Jim Doescher, Dan’s Excavating
Mike Malloure, C.A. Hull
DDEP Goal: Use current technology to……….
Produce deliverables to construction that will improve efficiency as well as reduce extras and overruns.
Improve the efficiency of developing design deliverables while reducing errors and omissions.
Conduct Focus Groups (12/07 – 2/08)
MDOT / Consultant Designers MDOT / Consultant Construction MDOT Experts MITA Contractors
Compile / Categorize 500+ Comments (2/08)
General Comments Received: Plans (97) – Reduce redundancy, reduce clutter, clearly show
details, show information once and correctly, maximize consistency, enhance necessary details, reduce number of typical cross sections, and provide design cross sections.
Technology (71) – Use current technology as much as possible and streamline the flow of data from survey through design to construction.
Quantities (63) – Minimize number of calculations, reduce errors, minimize manual handling of data.
Communication (50) – Improve access to information throughout development and delivery process.
Standards (47) – Use checklists, do not include special details in plans, minimize frequency of changes, and use standard specs as much as possible.
Field Operations (21) – Do not skimp on survey and geotechnical scopes of services.
MOT / Staging (18) – Improve the detail / consistency / constructability of MOT plans and provisions.
Bids / Ads / Let (13) – Provide as much information as possible at the time of bidding and do not include “boilerplate” information in each set of plans.
Utilities (13) - Accurately locate utilities, properly identify impacts, clear before construction, use the Miss Dig Design Ticket.
As-Builts (12) – MDOT / designers need them but contractors are not properly capable to produce them.
Technical Team Meetings to Develop Potential Enhancements (3/08 – 9/08)
Presentation to Core Team and Sponsors (10/08)
Acceptance of Proposed Enhancements (Pt 1) (10/08)
Technical Team Meetings (Ongoing)
Presentations to Stakeholders (10/08 – 9/09)
The following enhancements……… are not a final version. are subject to change. need input from stakeholders. need to be tested in the “real world” (Pilot Project). will be adjusted as needed based on input and
testing. will be finalized and presented in the future with
more in-depth supporting information.
Eliminate boilerplate information in plans and proposals. Include this information for each letting instead of for each project.
Provide as much digital information as possible at the time of bidding. Design cross sections Quantity spreadsheets Drawing files 3D digital terrain models Other
New sheet borders to be used for all sheets. Number sheets in PDF file. Formally integrate the use of MS Word and Excel in
the development of plan information in PDF format. Clarify information as much as possible.
Sheet includes: Sheet index Utility contacts List of all standard plans and special details
Sheet is now developed using MS Word with the sheet border as a watermark.
Sample Project Information Sheet
Reduce the number of typical cross sections.
Provide design cross sections as a deliverable at each phase of a project for applicable projects.
Sample Design Cross Section
MDOT will maintain a master note sheet in MS Word.
Designers will retrieve the master note sheet and delete notes that do not apply.
Project specific notes will be added to the end of the document.
Sample Note Sheet
Develop and maintain MS Excel Spreadsheets (Master and Working Files) that include all necessary layout, item and quantity information for the project.
Once the data has been reviewed…… Copy layout information to certain plan sheets. Create quantity sheets. Export *.csv file for SAPW / TrnsPort.
The goal is to create and review a master set of data then copy it to different locations. This will reduce errors due to manual manipulation.
Develop working files for each discipline or work group. Road (prime), Road (sub), Bridge (S01), Bridge (S02),
Traffic Signals, Electrical, Landscaping, etc. Each working file has a common format (tabs).
Input – Item and quantity listing broken down by Job No., Category No., Facility, DGN No., and Element ID. This information is either entered manually or automatically from GEOPAK.
Layout – Design variables, item usage and quantities required to construct certain elements. This information is either entered manually or automatically from GEOPAK.
Validation – Perform calculations to check quantities. Output – Export all item, quantity and break down data to Master
Project Spreadsheet.
Work Group A
Work Group B
Work Group C
Develop and maintain a Master Project Spreadsheet.
Collect and append output files from all disciplines and/or work groups.
Summary tabs use pivot tables to automatically sort and summarize all information by work type, pay item, facility, DGN No., Element ID, Job No., Category No., etc.
The total project quantity tab is automatically generated using a pivot table based on pay items.
Export tabs are used to copy all data as *.csv to SAPW /TrnsPort.
Discussion /Questions?