design & construction managed projects · 2021. 6. 9. · related to construction...
TRANSCRIPT
Design & Construction
ManagedProjects
Table of Contents
Table of ContentsDesign & ConstructionManaged Projects
PageUnderstanding the Monthly Report 3-6Executive Summary 7Program Cost Report by Schedule Phase 8Program Cost Report by Project 9
PROJECT NAME PROJECT NUMBER PROJECT MANAGER
Bidding and NegotiationsSullivan ES - Vestibule Security Window DC21-012.0124.1022 Ashmi Kesaria 10Temporary Building Relocation 2021-2022 DC21-006.0118.1021 James Caylor 11
ConstructionGlover ES - Extended Learning Repair DC21-004.0117.1014 Ashmi Kesaria 12Hunters Glen ES – ELC#2 Renovations DC20-012.0105.2823 Ashmi Kesaria 13
Report Date: 05/31/2021
Understanding the Monthly Report
Understanding the Monthly Report
Design & ConstructionManaged Projects
Schedule Phase Description:
Not Started- Design or construction activities have not begun
Pre-Design- Activities between Board Approval of architectural services (if applicable) and actual design work
Design-Programming and design through Construction Documents
Bidding and Negotiations-Includes bidding, award and negotiation process with the contractor for construction work
Construction-Construction work in progress
Close Out – Final inspection, submission and acceptance of required documents, and concluding payment
Move In- Occupancy is permitted though minor activities or corrections continue - this phase includes project closeout
Graphical representation of the total project budgets grouped by Phase
Report Date: 05/31/2021 3
Understanding the Monthly Report
Design & ConstructionManaged Projects
Column Headings:
Original Budget-Original budget funded through this report date
Budget Changes-Approved budget adjustments by FBISD
Current Budget-Current project budget through the report period
Commitments-Sum of all contracts, contract change orders, and purchase orders through the report period
Additional Commitments to Complete-Additional costs anticipated on the project
Projected Commitments-Commitments plus additional commitments to complete
Projected Over/Under-Current Budget minus the Projected Commitments - it represents savings or overruns in the project
Cost to Date-Sum of all contract invoices and general invoices entered through the report period
% Expended-Cost to Date divided by Current Budget
Graphical representation of the Budget/Costs status for the overall Program
Report Date: 05/31/2021 Understanding the Monthly Report 4
Understanding the Monthly Report
Design & ConstructionManaged Projects
Activity Description:Design - Duration from design development through construction administration
Bidding and Negotiations - Duration of procurement activities through negotiations with the contractor
Construction - Duration from construction through substantial completion
Move In - Duration for move in
Activity Bars:Baseline Bar - Projected dates at the start of the project
Actual Bar - Dates of actual performance
#: Number noted inside each bar indicates number of calendar days
Dates:1st Column - Activity START date2nd Column - Activity END date
Report Date: 05/31/2021 Understanding the Monthly Report 5
Understanding the Monthly Report
Design & ConstructionManaged Projects
Cost Description:
Architect & Engineering/Professional Services-A/E Design Fees, A/E Design Reimbursables, Surveying, Geotechnical, Material Testing & Inspection, Commissioning, TAB (Test and Balancing), Consulting Other, Haz-mat Consulting Services
Construction-Facility Construction in general and other associated costs such as Allowances and Construction Contingency
Furniture, Fixtures & Equipment-Costs for furniture, fixtures and equipment
Site Development-Permit & Site Fees related to construction
Administrative and Other Project Costs-Construction related costs outside of main Construction Contract with the General Contractor. It includes: Temporary Buildings & Services, Printing/Misc., Bid Advertising, Hazmat/Abatement, etc.
Project Contingency-Budget to be used as necessary for unanticipated project costs following approval from FBISD
Report Date: 05/31/2021 Understanding the Monthly Report 6
Executive SummaryDesign & ConstructionManaged Projects
Current Budget: $ 6,366,522 Projected Commitments: $ 6,366,522
Program Status*As of May 31, 2021, the Fort Bend Independent School District Design and Construction Department (FBISD D&C) currently has four capital projects. The activeprojects’ current budgets total $ 6,366,522 with 83% in Bidding and Negotiations and 17% in Construction. The active projects have expended $ 491,692representing approximately 8% of the current budget. The composition of the portfolio by phase of work is represented in the following table and charts:
Phase # Projects Current Budget
Bidding and Negotiations 2 $ 5,287,380
Construction 2 $ 1,079,142
TOTAL 5 $ 6,366,522
Report Date: 05/31/2021 Executive Summary 7
Program Cost Report By Project
Fort Bend Independent School District
Design and Construction Department
$0
$5,000,000
$10,000,000
$15,000,000
$20,000,000
$25,000,000
Current Budget Commitments Cost To date
COSTBUDGET COMMITMENTS
A B C=A+B K=J/CJI=C-HH=D+E+F+GGFED
Cost To
Date
%
Expended
Budget
Changes
Current
Budget
Original
Budget
Project Name Projected
Over/Under
Projected
Commitments
Estimate To
Complete
Pending
Commitments
Approved
Changes
Original
Commitments
$218,000 $0 $0 $218,000 Glover ES - Extended Learning Repair 0%$0 $218,000 $60,295 $0 $0 $157,705
$861,142 $491,692 $0 $861,142 Hunters Glen ES-Early Literacy Center #2 Renovations 57%$0 $861,142 $301,499 $0 $(58,781)$618,424
$20,000 $0 $0 $20,000 Sullivan ES - Vestibule Security Window 0%$0 $20,000 $20,000 $0 $0 $0
$5,267,380 $0 $0 $5,267,380 Temporary Building Relocation 2021-2022 0%$0 $5,267,380 $5,226,217 $0 $0 $41,163
Grand Totals: $6,366,522 $491,692 7.72%$0 $6,366,522 $0 $6,366,522 $5,608,011 $0 $(58,781)$817,292
Report Date: 5/31/2021 Program Cost Report By Project 8
Program Cost Report By Schedule PhaseFort Bend Independent School District
Design and Construction Department
$1,079,142Construction
$5,287,380B idding & Negotiations
Bidding & Negotiations $5,287,380
Construction $1,079,142
Total: $6,366,522
Value of Projects by Phase
Current Budget
COSTBUDGET COMMITMENTS
A B C=A+B I=C-HH=D+E+F+GGFED K=J/CJ
Description Budget
Changes
Current BudgetOriginal
Budget
%
Expended
Projected
Over/Under
Projected
Commitments
Estimate To
Complete
Pending
Commitments
Approved
Changes
Original
Commitments
Cost
To Date
Bidding & Negotiations $0 $5,287,380 $0 $5,287,380 0%$41,163 $0 $0 $5,246,217 $5,287,380 $0
Construction $491,692 $1,079,142 $0 $1,079,142 46%$776,128 $(58,781) $0 $361,794 $1,079,142 $0
Grand Totals: $491,692 $6,366,522 $0 $6,366,522 8%$0 $6,366,522 $5,608,011 $0 $(58,781)$817,292
Report Date: 5/31/2021 Program Cost Report By Schedule Phase 9
Project Summary
Sullivan ES - Vestibule Security Window
FBISD Design and Construction
Project Manager : Ashmi Kesaria
Architect/Engineer : N/A
Project Number : DC21-012.0124.1022
General Contractor : JR Thomas Group
SCHEDULE SUMMARY
Design - Baseline: -- --
Design - Actual: -- --
Bidding & Negotiations - Baseline: 5/15/2021 7/30/2021
Bidding & Negotiations - Actual: 5/15/2021 --
Construction - Baseline: 8/1/2021 9/30/2021
Construction - Actual: -- --
Move In - Baseline: -- --
Move In - Actual: -- --
May-21 Jun-21 Jul-21 Aug-21 Sep-21
76
20
60
COSTBUDGET COMMITMENTS
A B C=A+B K=J/CJI=C-HH=D+E+F+GGFED
Description Budget
Changes
Current
Budget
Original
Budget
%
Expended
Projected
Over/Under
Projected
Commitments
Estimate To
Complete
Pending
Commitments
Approved
Changes
Original
Commitments
Cost
To Date
$0 $0 $0 $0 Architect & Engineering/ Professional Services 0%$0 $0 $0 $0 $0 $0
$0 $20,000 $0 $20,000 Construction 0%$0 $20,000 $20,000 $0 $0 $0
$0 $0 $0 $0 Furniture, Fixtures & Equipment 0%$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 Site Development 0%$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 Administrative and Other Project Costs 0%$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 Project Contingency 0%$0 $0 $0 $0 $0 $0
$0 $20,000 $0 $20,000 0%Totals: $0 $20,000 $20,000 $0 $0 $0
SCOPE/COMMENTS PROJECT PHOTO BUDGET/COST STATUS
$20K
$0K $0K
Current Budget Commitments Cost To Date
SCOPE: This project consists of removing and relocating the existing security vestibule window, installing an additional security vestibule window, and modifying existing under-counter cabinets to allow for more visitors and parents to be served at the main lobby.
COMMENTS: Contractor's proposal has been received and is under review.
Sullivan ES - Vestibule Security WindowReport Date: 5/31/2021 10
Project Summary
Temporary Building Relocation 2021-2022
FBISD Design and Construction
Project Manager : James Caylor
Architect/Engineer : MWA Architects
Project Number : DC21-006.0118.1021
General Contractor : JR Thomas Group
SCHEDULE SUMMARY
Design - Baseline: 3/15/2021 4/19/2021
Design - Actual: 3/15/2021 --
Bidding & Negotiations - Baseline: 4/20/2021 5/25/2021
Bidding & Negotiations - Actual: 4/20/2021 --
Construction - Baseline: 5/26/2021 8/4/2021
Construction - Actual: -- --
Move In - Baseline: -- --
Move In - Actual: -- --
Mar-21 Apr-21 May-21 Jun-21 Jul-21
35
81
35
45
70
COSTBUDGET COMMITMENTS
A B C=A+B K=J/CJI=C-HH=D+E+F+GGFED
Description Budget
Changes
Current
Budget
Original
Budget
%
Expended
Projected
Over/Under
Projected
Commitments
Estimate To
Complete
Pending
Commitments
Approved
Changes
Original
Commitments
Cost
To Date
$0 $170,500 $0 $170,500 Architect & Engineering/ Professional Services 0%$0 $170,500 $170,500 $0 $0 $0
$0 $3,134,880 $0 $3,134,880 Construction 0%$0 $3,134,880 $3,134,880 $0 $0 $0
$0 $795,000 $0 $795,000 Furniture, Fixtures & Equipment 0%$0 $795,000 $753,837 $0 $0 $41,163
$0 $75,000 $0 $75,000 Site Development 0%$0 $75,000 $75,000 $0 $0 $0
$0 $1,092,000 $0 $1,092,000 Administrative and Other Project Costs 0%$0 $1,092,000 $1,092,000 $0 $0 $0
$0 $0 $0 $0 Project Contingency 0%$0 $0 $0 $0 $0 $0
$0 $5,267,380 $0 $5,267,380 0%Totals: $0 $5,267,380 $5,226,217 $0 $0 $41,163
SCOPE/COMMENTS PROJECT PHOTO BUDGET/COST STATUS
$5,267K
$41K $0K
Current Budget Commitments Cost To Date
SCOPE: This project consists of the relocation of 12 classroom buildings within the
District and the connection of utilities for six purchased temporary classroom buildings
and four leased temporary classroom buildings.
COMMENTS: Contracts with Mobile Modular for the purchase and lease of the
temporary classroom buildings are in process. Architect purchase order has been
issued. Contractor's proposal is under review.
Temporary Building Relocation 2021-2022Report Date: 5/31/2021 11
Project Summary
Glover ES - Extended Learning Repair
FBISD Design and Construction
Project Manager : Ashmi Kesaria
Architect/Engineer : PBK Architects
Project Number : DC21-004.0117.1014
General Contractor : E Contractors
SCHEDULE SUMMARY
Design - Baseline: 3/1/2021 4/15/2021
Design - Actual: 3/1/2021 4/15/2021
Bidding & Negotiations - Baseline: -- --
Bidding & Negotiations - Actual: -- --
Construction - Baseline: 4/16/2021 5/31/2021
Construction - Actual: 5/17/2021 --
Move In - Baseline: -- --
Move In - Actual: -- --
Mar-21 Apr-21 May-21 Jun-21
45
45
45
18
COSTBUDGET COMMITMENTS
A B C=A+B K=J/CJI=C-HH=D+E+F+GGFED
Description Budget
Changes
Current
Budget
Original
Budget
%
Expended
Projected
Over/Under
Projected
Commitments
Estimate To
Complete
Pending
Commitments
Approved
Changes
Original
Commitments
Cost
To Date
$0 $50,000 $0 $50,000 Architect & Engineering/ Professional Services 0%$0 $50,000 $28,770 $0 $0 $21,230
$0 $168,000 $0 $168,000 Construction 0%$0 $168,000 $31,525 $0 $0 $136,475
$0 $0 $0 $0 Furniture, Fixtures & Equipment 0%$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 Site Development 0%$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 Administrative and Other Project Costs 0%$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 Project Contingency 0%$0 $0 $0 $0 $0 $0
$0 $218,000 $0 $218,000 0%Totals: $0 $218,000 $60,295 $0 $0 $157,705
SCOPE/COMMENTS PROJECT PHOTO BUDGET/COST STATUS
$218K
$158K
$0K
Current Budget Commitments Cost To Date
SCOPE: This project consists of the repair and restoration of the exterior facade,
interior damages (including but not limited to flooring, furniture, fixtures, casework,
etc.) and building grounds damage to Extended Learning at Glover ES.
COMMENTS: The purchase orders and Notice To Proceed have been issued . Work is in
progress.
Glover ES - Extended Learning RepairReport Date: 5/31/2021 12
Project Summary
Hunters Glen ES-Early Literacy Center #2 Renovations
FBISD Design and Construction
Project Manager : Ashmi Kesaria
Architect/Engineer : PBK
Project Number : DC20-012.0105.2823
General Contractor : The Thomas Group
SCHEDULE SUMMARY
Design - Baseline: 3/24/2020 5/11/2020
Design - Actual: 5/1/2020 6/30/2020
Bidding & Negotiations - Baseline: 5/12/2020 5/15/2020
Bidding & Negotiations - Actual: 5/7/2020 6/24/2020
Construction - Baseline: 5/18/2020 7/17/2020
Construction - Actual: 6/30/2020 --
Move In - Baseline: 7/20/2020 7/31/2020
Move In - Actual: -- --
Mar-20 May-20 Jul-20 Sep-20 Nov-20 Jan-21 Mar-21 May-21
48
60
3
48
60
339
11
COSTBUDGET COMMITMENTS
A B C=A+B K=J/CJI=C-HH=D+E+F+GGFED
Description Budget
Changes
Current
Budget
Original
Budget
%
Expended
Projected
Over/Under
Projected
Commitments
Estimate To
Complete
Pending
Commitments
Approved
Changes
Original
Commitments
Cost
To Date
$41,032 $80,000 $0 $80,000 Architect & Engineering/ Professional Services 51%$0 $80,000 $36,000 $0 $0 $44,000
$450,660 $621,142 $0 $621,142 Construction 73%$0 $621,142 $105,499 $0 $(58,781)$574,424
$0 $100,000 $0 $100,000 Furniture, Fixtures & Equipment 0%$0 $100,000 $100,000 $0 $0 $0
$0 $60,000 $0 $60,000 Site Development 0%$0 $60,000 $60,000 $0 $0 $0
$0 $0 $0 $0 Administrative and Other Project Costs 0%$0 $0 $0 $0 $0 $0
$0 $0 $0 $0 Project Contingency 0%$0 $0 $0 $0 $0 $0
$491,692 $861,142 $0 $861,142 57%Totals: $0 $861,142 $301,499 $0 $(58,781)$618,424
SCOPE/COMMENTS PROJECT PHOTO BUDGET/COST STATUS
$861K
$560K$492K
Current Budget Commitments Cost To Date
SCOPE: This project consists of interior renovation work at Hunters Glen ES to
accommodate the Early Literacy Center #2 (ELC2).
COMMENTS: Way finding package finalization is under review . Additional paint
work under Bond 2018 scope has been completed. Outdoor Learning Experience submittal is under review for approval.
Hunters Glen ES-Early Literacy Center #2 RenovationsReport Date: 5/31/2021 13