design and testing of crbrp insulated horizontal and vertical pipe … · 2005. 5. 3. · vertical...

40
DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE CLAMPS L. P. Pollono and R. M. Meilo Westinghouse Advanced Reactors Division Madison, Pennsylvania -DISCLAIMER • This book was Dreca'ci at an account of work sponsored by an agency o! trie United Siasss Government. Neither the United States Government nor any agency -hereof. nor any ot iheir employees, makes any warranty, tj'P'ess o' implied, or assume any legal liability or responsibility for the accuracy, coupletertess, ot uw'ulneu at any infaimation, ar<Daraiui, oroduct, or process divided, or recresenls lhai l u use vwuitl not infringe privately owned righu. Reference herein 10 any scecitic commeft^i product. cocMi. or service by trade name, iradeinark, manufatlu'er, DT othcviiiM!, <Sotr, not rwcesiafily ajnstitute o> imply hs endariemeni, recammendatian, ar favo'ing by ih«> united States Governrmni or any agency lhe*eof. The vievn and opiniarn of author^ eipreued herein do not necessarily state of relleci ihose of the United States Government or any ayency thereof. 6123A-669A-{S1498) mSTRlBUTIQH OF THIS DOCUMENT IS UNLIMITED 1

Upload: others

Post on 07-Sep-2021

19 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE CLAMPS

L. P. Pollono and R. M. Meilo

Westinghouse Advanced Reactors Division

Madison, Pennsylvania

-DISCLAIMER •

This book was Dreca'ci at an account of work sponsored by an agency o! trie United Siasss Government.Neither the United States Government nor any agency -hereof. nor any ot iheir employees, makes anywarranty, tj'P'ess o' implied, or assume any legal liability or responsibility for the accuracy,coupletertess, ot uw'ulneu at any infaimation, ar<Daraiui, oroduct, or process d iv ided, orrecresenls lhai l u use vwuitl not infringe privately owned righu. Reference herein 10 any sceciticcommeft^i product. cocMi . or service by trade name, iradeinark, manufatlu'er, DT othcviiiM!, <Sotr,not rwcesiafily ajnstitute o> imply hs endariemeni, recammendatian, ar favo'ing by ih«> unitedStates Governrmni or any agency lhe*eof. The vievn and opiniarn of author^ eipreued herein do notnecessarily state of relleci ihose of the United States Government or any ayency thereof.

6123A-669A-{S1498) mSTRlBUTIQH OF THIS DOCUMENT IS UNLIMITED 1

Page 2: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

ABSTRACT

The Clinch River Breeder Reactor Plant (CRBRP) Primary Heat Transportsystem piping may be characterized as large-diameter, th in-wal l piping whichtransports l i qu id sodium at high temperatures. The piping i s arranged inaccord with the elevated loop concept, consisting of large horizontal inplane,expansion loops and long, ver t i ca l runs of p ip ing. These characterist ics andthe postulated thermal t ransient and seismic loads, which are imposed on thepiping, d ic ta te pipe clamp designs that are substantial ly d i f fe rent fromstandard "o f f the shelf11 pipe clamp designs. These designs include featuresto mit igate thermal transient temperature gradients and to accommodate pipethermal expansion. In addi t ion, the clamp has to be designed to minimize pipestresses that resul t fran clamping loads.

This paper w i l l describe the design features of the CRBRP horizontal andvert ical pipe clamps for the large sodium p ip ing, the various test programsused to ve r i f y the clamp designs, and the resul ts of th is tes t i ng .

I . INTRODUCTION

The Clinch River Breeder Reactor Plant Primary Heat Transport Systempiping is characterized by large-diameter, 0.914 m and 0^607 m^ andthin-wal led, 12^7 mm, piping which transportsThigh temperature, 546°C l iqu idsodium. This piping is arranged in accord with the elevated loop conceptconsisting qf Targe horizontal i n p l a n e , e x p a n s ^runs of p ip ing ; The loops connect between equipment nozzles. In addi t ion,the pi pi ng iriust wi thstand r api d thermal trans i ents and hi gh sei sm i c 1 oads(1)* . These design features and loadings, which may be imposed on the p ip ing,have di ctated specialized design features fOTV;the JCRBRP pipe clamps forsupporting thei horizontal runs and the" long ve r t i ca l runs of pipe.: Theessential features of the CRBRP clamp that supports horizontal runs of pipeclamp include sp l i t r ing outer steel bands held together by a system ofBe l lev i l le springs and s p l i t r ing inner bands made up of canned load-bearinginsulat ion.

The essential features of the support fo r vert ical runs of piping includea stepped inner r ing or t rans i t ion section which is part of the pipe boundary,a s p l i t r ing outer band and a s p l i t r ing inner band made up of cannedload-bearing insulat ion. The two outer steel bands are bolted together toform a very s t i f f assembly.

The primary purpose of the test ing programsdeveloped fo r the clamps wasto demonstrate structural adequacy of the clamps with part icular anphasis onthe structural in tegr i t y of the canned, load-bearing insu la t ion, undercombined deadweight and seismic loading conditions at expected temperatures.

•Numbers in parentheses refer to references l i s ted at the end of the paper.

6123A-669A-(S1498)

Page 3: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

Overall, the testing performed on the damps included the following:

(a)(b)(c)(d)

Mechanical and Thermal EvaluationStructural Integrity TestsTemperature Distribution and Thermal CyclingClamp Stiffness Tests

(e) Pipe Clamp Friction and Stiffness Tests

The mechanical and thermal characterization test of a prototypical0.607 m horizontal pipe clamp was performed to obtain clamping force and heatloss data to qualify the clamp load carrying capability. The pipe clamp heatloss and clamping force data obtained for various pipe temperatures provideduseful information to support final design of the pipe clamp configuration.

Structural testing of the horizontal and vertical pipe clamps was carriedout to demonstrate the structural integrity of the clamps when subjecjted toconditions cf physical assembly, temperatures, and loadingswhich closelysimulated operating conditions for thje clamps. The test article and testset-ups were designed to apply design deadweight and vibratory loads while theclamp was at expected operating temperatures;

Temperature distribution and thermal cycling tests were conducted on bothtypes of clamps^ The purposes of these tests were to determine actual surfacetemperatures for both clamps, to verify that the clamp connection springs andbolting temperatures were below design limits, and to determine the reactionof the clamps (movement and spring preload) to temperature swings while underapplied deadloads.

In order to complete seismic analysis of the CRBRP piping loops, thestiffness of the clamp, which includes the effect'of the clamp/pipeinteraction, had to be determined, testing of the CRBRP prototypical clampwas carried but to determine the clamp/pipe stiffness. In these tests, theclamp was assembled on a straight length of pipe (approximately 2 m in length)and placed in a standard MTS test machine. The clamp/pipe stiffnesses werethen calculated from the load-deflections curves derived from these tests.

The horizontal tensile stiffness and the rotational friction of the pipeclamp were investigated during tests performed on a 0.607 m pipe clamp mountedon a 2 meter length i»f pipe. The purpose of these tests was to estimatehorizontal tensile clamp stiffnesses and the amount of overturning load neededto produce slipping of the clamp on the pipe as a function of clamp preload.

II. DESIGN FEATURES

Horizontal Pipe ClampThe design of the horizontal pipe clamp assembly used on CRBRP piping is

shown in Figures 1 and 2. The pipe clamp assembly con-ists essentially ofthree major parts; the split ring outer bands, the split ring inner bands, andthe spring loading system (1, 2).

6123A-669A-(S1498)

Page 4: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

The spl i t ring outer bands are weldments made up of low chrcmium-molybdenum carbon steel 12.7 mm thick and 152, 203, and 304 mm wide.Reinforced pads to accommodate the spring loaded closure bolts are provided atthe top and bottom of each half. Paired attachment ears are provided on eachhalf of the outer segments to accommodate pipe hanger and pipe snubberattachment hardware. The two halves are designed so that at cold pipeassembly, there is a 7.87 mm gap at the top and at the bottom of the matingfaces. This gap is provided to assure that the clamp w i l l f i t t ight ly on thepipe throughout al l conditions of pipe temperatures.

The two halves of the inner bands are made up of load-bearing insulationblocks completely encased within a .635 mm thick stainless steel containerwhich is 38.1 mm high and approximately 50 mm wider than the clamp band. Eachhalf of the inner bands contain 12 blocks of Marinite XL load-bearinginsulation (3) butted edge-to-edge and machined to conform to the curvature ofsteel containers. The containers are cold spun to a "channel" form so thatthe open end of the "channel" form faces toward the outer bands. Thecontainer is closed by spot welding a l i d to the containers.

The two insulation band halves are designed so that at cold assembly a6.36 mm gap exists at the top and the bottom of the mating halves. The gapnot only ensures positive contact with the pipe wall , but also provides a pathfor sodium aerosols in the event of a sodium leak. This provides for asensitive sodium leakage detection system. In order to fac i l i ta te clampassembly, the inner insulation bands are loosely captured to the outer clampbands through a system of pins and cl ips.

At assembly the two halves of the clamp are held together by a system ofBellevi l le spring washers and bolts located at the top and at the bottom ofthe clamp assembly. A predetermined preload is exerted on the clamp halves bythe Bellevil le springs. Thespring-bolt attachment assembly for the clamp wasrequired tGi accommodate the diametral thennalgrowiS of the pipe. Bel levi l lesprings were selected because of their n6h-l|near lbad-deflectioncharacteristics. Throughout the /ful1 temperature range at which the CRBRPpiping is operating; the increase in preload due to thermal expansion of thepipe i s less than 10%.

A typical support arrangement used on the horizontal runs of the CRBRPpiping is shown in Figure 3> In this case, vertical hangers and a horizontalsnubber are attached to the clamp ears. Other combinations of hangers andsnubbers are also usedv including application of supports along the clampsp l i t l ine. Although the CRBRP clamps weredesigned to minimize an^effects on the CRBRP piping, the stresses induced in the pipe wall by theclamp loads aresignif icant. A detailed discussion on the evaluation of cl ampeffects on CRBRP piping w i l l be presented in another paper in this session(4). Details of the testing carried out to verify the clamp structural andfunctional adequacy are described in subsequent sections of this paper.

6123A-669A-(S1498)

Page 5: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

Vertical Pipe ClampThe elevated loop concept of the CRBRP piping is characterized by long

vertical runs of pipe within guard vessels which can require support along thevertical run to minimize stress. For this application a non-integral verticalclamp assembly (5) was developed, as shown in Figures 4 and 5.

The vertical pipe clamp consists of three major components; the outersupport ring, the steel sheathed load-bearing insulation inner bands, and thepipe transition section which includes an axial support ledge. The outersupport ring is made up of two Type 304 stainless steel semi-circular ringswhich are bolted together to form a very stiff circular ring. The insidesurface of the ring is machined to a "channel" shape to receive and capturethe canned load-bearing insulation. Attachment lugs for snubbers and hangersare welded to the outer surface of the ring.

The inner bands are made up of two semi-circular metal sheathedload-bearing insulation bands similar to the inner bands for the horizontalclamps. The bearing area for the canned Marinite XL insulation bands wassized to limit compressive stress to less than 4.14 MPa.

The axially concentric pipe section consists of a stepped 304 stainlesssteel ring fprging which when instal1ed in the piping system forms an integralpart of the piping pressure boundary. The ends of the pipe transition sectionare sized to conform to the pipe dimensions for diameter and wall thickness(.609 m dia. and 12.7 mm wall). The transition section is .432 m long arid isgradually tapered to its midsection to form a support ledge 15.8 ffsit wide whichbears upon the canned insulation bands.

At assembly^ the inner load-bearing insulation bands are captured betweenthe outer ring and the pipe transition section- The pipje weight and forcesare reacted through the canned insulation bands to the outer ring as acompressive load. The design permits a maximum clearance of .63 mm betweenthe inner ring and the inner bands at CRBRP plant operating temperature.

The vertical clamp was designed to accommodate a maximum horizontal loadof 59,000 N and a vertical load of 49,000 N and to minimize the thermaltransient stresses in the piping wall. Testing of this design has beencarried out to verify structural and functional integrity which will bedescribed later in the paper.

III. TESTING PROGRAM

Mechanical and Thermal Eva]uationThe initial test carried out for the CRBRP pipe clamps was a mechanical

and thermal characterization test of a prototypic 0.607 m diameter by 0.152 mwidth, horizontal pipe clamp. The test was performed at the WestinghouseAdvanced Reactors Division. A prototypic horizontal pipe clamp assembly wasmounted on a 2 m section of 0.607 m diameter by 9.5 mm wall stainless steelpipe which was instrumented with heaters on the inside pipe surface andthermocouples and strain gages on the pipe and clamp to measure temperature

6123A-669A-(S1498)

Page 6: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

profiles and strains for various clamping forces and temperatures. The testassembly was insulated with 0.253 m of insulation and suspended from a teststructure frame. The test arrangement was as i l lustrated in Figure 6.

The objective of the test was to provide pipe clamp temperature andclamping force data for various pipe temperatures to support f inal design ofthe pipe clamp configuration.

The test program included cold tests and low temperature cyclic tests.For the cold tests, dimensional and strain characterizations of the clampassembly and the pipe section were recorded in i t ia l l y and at incremental clampbolt torque values.

The clamp dimensional characteristics that were recorded for the coldtests are illustrated by Figure 7, As shown, these measurements include thegap width between the two clamp halves and the spring lengths of theBellevil le washer assemblies. These data along with resultant springcompression and change in gap width values are shown in Table 1 as a functionof the clamp bolt torques. A torque value of 33.9 N-m was taken as thebaseline condition. The average spring compression and change in clamp gapwidths are plotted as a function of bolt torque in Figure 8.

The pipe section characterization included in i t ia l measurements of thepipe outside diameter at three locations along the length for twocircumferential orientations at each location. Pipe wall thickness was alsorecorded at the same points. These measurements are i l lustrated and tabulatedin Figure 9. Outside diameter measurements of the pipe section were alsorecorded as a function of clamp bolt torque during the cold tests. These ODmeasurements were made at several circumferential and axial locations as shownin Figure 10. The data from these torque tests along with the calculatedchange in OD are tabulated in Table 2.

For the strain characterization, six gages were installed on the clampassembly and twelve gages were installed on the pipe section as shown onFigure 11. The strain readings were taken as a function of clamp bolt torquefor each gage. As an example of these results^ Figure 12 shows the axialstrain pattern of the pipe as a function Of clamp bolt torque.

For the thermal cycling tests, heaters, /insulation and thermocouples wereinstalled on the test section. The pipe clamp assembly' was torqued to 234.6N-ni and dimensional, strain and temperature jdata were recorded at ambient,66OCj 149OC, 232OC, 316OC, and 399OC incrementsi after al l owing thetemperature to stabilize at each plateau, the rate of temperature change was380c per hour. The test assembly was ail 1 owj»d to cool to ambi ent after thein i t i a l test and two additional temperature cycles were performed with datarecorded at ambient and 399°C. A summary of the reduced data (averagetemperatures, spring compressions and gaps) for the cyclic tests are presentedin Table 3.

In summary, the above testing provided the mechanical and thermalcharacterization of the CRBRP horizontal clamp. The pipe clamp springcompression and the change in clamp gap/showed linear relationships to

6123A-669A-(S1498)

Page 7: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

torque. Temperatures of the clamp and the spring assembly did not exceeddesign values. Upon completion of the tests, visual inspection of the clamprevealed no damage to any of the pipe clamp components from the cold or hottorque tests. The dimensional changes and strain changes resulting from thecyclic tests were acceptably small.

Structural Integrity TestingStructural tests for the CRBRP horizontal and vertical pipe clamps were

performed at the Westinghouse Electric Advanced Energy Systems Division. Thepurpose of this pipe clamp testing program was to demonstrate the structuraladequacy of both the horizontal and vertical pipe clamps when subjected toconditions of physical assembly, temperature and loadings which closelysimulated CRBRP plant conditions. Particular attention was given to thestructural adequacy of the load-bearing insulation, "Marinite XL".

The general features of the horizontal clamp test r ig are shown inFigure 13. The test r i g was constructed of square structural tubing which wasmounted to a steel bed plate. Theirig was i f i t ted with[ mounting pads that wereused as attachment points for the snubbers and constant load hangers. Thepipe clamp was mounted on a section of stainless steel pipe .607 m indiameter by12.7 mm wall by 1.82 m long.

Vertical connection from the pipe clamp to the test r i g was provided byconstant load hangers while the horizontal connection from the pipe clamp tothe test r i g was provided by a snubber in series with a load ce l l . Load cellsand turnbuckles located at both ends of the pipe section and connecting withthe bed plate were provided to exert a downward pull on the clamp simulatingdeadweight of the piping. Three dynamic thrusters were connected to both endsof the pipe section through a structural beam. The thrusters were used toexert dynamic loads on the clamp^ The pipe was insulated in a configurationsimilar to the CRBRP plant piping and was trace heated on the inner surface toach ieve the pi pe sur face des i gn tern per ature of 546 90. Thermocou pi es,straining gages, load cells and accelerometers were used to measure testconditions and responses.

The general features of the vertical pipe clamp test r i g are shown inFigure 14. The test stand was constructed of structural steel elements andutilized portions of the building structural steel framing.

The vertical clamp assembly inner transition section, which actuallyforms part of the piping boundary, was welded to two sections of pipe .607m diameter x 12.7 mm wall and 1.29 m long forming one continuous pipe section2.89 m long. The pipe section was suspended vert ical ly within the test frameand supported by means of a constant load hanger, trapeze and connecting rodsattached to the clamp outer ring assembly. A load cell and turnbucklearrangement connecting the lower end of the pipe and the bed plate was used toexert and measure the downward load on the clamp section. The test frame wasdesigned to accommodate two horizontal snubbers (at a 90° angle) and twothrusters which were connected to both ends of the pipe.

The pipe section was insulated and trace heated internally to achieve apipe temperature of 398°F. Care was taken to avoid contact between the

6123A-669A-(S1498)

Page 8: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

heater rods and the clamp assemblytransition section. Thermocouples, straingages, load cells and accelerometers were installed on theclamp arid pipesections to measure arid record test conditions arid responses.

The test setup for both clamps was designed to simulate CRBRP operatingplant conditions. The pipe section diameter, wall thickness and material wereidentical to the CRBRP sodium large piping system. The constant load hangersand attachment hardware for the CRBRP and the snubbers were conventionaldesigns. The insulation thickness and general design reflect the CRBRPinsulation design.

Loadings used in the testing for deadweight and seismic conditions weretaken equal to or exceed the design loadings for each clamp. The testsequence fo r each clamp consisted of the following steps;

(1) Application of deadweight vertical load

(2) Heatup of the pipe to the operating temperature

(3) Dynamic application of 50 cycles of the Operating Basis Earthquake(OBE) design load.

(4) Dynamic application of 10 cycles of the Safe Shutdown Earthquake(SSE) design load which was 2.0 times the OBE load.

(5) Shutdown and visually inspect the clamps.

The OBE (seismic) design loads were applied through the pipe ends via thethrusters. The input driving force to the thrusters was applied as a complexwave form which was made up of various frequency-load combinations astabulated in Table 4. For frequency-load values the input was generated byapplying sinusoidally the input force (20% of the design SSE load) required,one"channel at a time, and recording the input voltage necessary to generatethis force. Upon completion of al l individual inputs, a summation of al linput frequencies was i"putted to the system as a complex wave form.Increasing the amplitude of the 20% input ijy 2.5 times generated the OBEdesign loads, and increasing the input amplitude by 5.0 times generated theSSE design loads.

At the completion of the thermal and dynamic tests the clamps weredisassembled from the test stand and visually examined for damage or fa i lure.

For the horizontal clamp visual examination did not show any evidence ofdamage to the outer clamp bands other than some discoloration of the metal.No cracks or breaks occurred at any of the clamp welds. The canned insulationshowed some slight effects; A localized depression of approximately .80 mmdeep was seen at the extreme end of the band. The cause for this indentationwas the "digging in" of the ends of the outer band as a result of the preloadon the spring plates. The only other effect observed was the fai lure of a fewspot welds along the edges of the bands. These observations concerning theinsulation bands did not affect the adequacy of the clamp;

6123A-669A-(S1498) 8

Page 9: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

For the vertical clamp visual examination of the outer ring and the innerpipe transition section did not show any effects other than some surfacediscoloration. No cracks or breaks occurred at any of the welds in thesemetal parts. Examination of the inner canned load-bearing insulation bandsindicated a raised area on the load-bearing side of approximately 1.5 mm highby approximately .24 m long located approximately at the midpoint of theband. This raised section was observed on both bands. The probable cause forthis effect was the strong "rocking" motion of the test pipe during thedynamic load tests. None of the spot welds on the band were broken.

Temperature Distribution and Thermal CyclingThermalcycling and temperature distribution tests were conducted on both

the horizontal and the vertical pipe clamps. The purpose of these tests wasto investigate the following points of interest: (1) the actual surfacetemperature of both clamps, (e.g., the spring plate temperature of thehorizontal clamp) and (2) the reaction of the horizontal clamp to temperatureswings whi 1 e under pipe desi gn 1 oads .

Both c 1 amps were set up in their-.respective test ri gs as discussed in aprevious section of the paper. The location of thermocouples and strain gagesare shown in Figure 15 for the horizontal clamp and in Figure 16 for^thevertical, clamp. A static Toad of 39^000% was exerted on the horizontalclamp, and a static load of48,800 N was exerted on the vertical clamp throughthe turnbuckles attached to the clamps.

For the horizontal clamp, the temperatureof the pipe was increased to204°C at the rate of 5°C per hour and held constant until the;temperatureson the clamp body stabilized. The temperature was then increased in steps to412PC and finally to the design temperature of 546°F at the rate of 5°Cper hour. The pipe temperature was then reduced to ambient by means of forceddraft through the inside surface of the pipe. These three temperatureplateaus, which simulated sodium fill temperature, hot functional testtemperature and operating temperature, were repeated ten times.

For the vertical clamp the temperature of the pipe was increased to204°C at the rate of 5°C per hour and the clamp temperature allowed tostabilize. The temperature was then increased to the design temperature.-of412°C and cooled to ambient. This temperature cycle was applied ten timesas with the case for the horizontal clamp test. Throughout the temperaturetest, visual inspection was performed and strain gage and temperature readingswere monitored and recorded.

The clamp surface temperature obtained from the tests was in closeagreement with predicted temperature. Average temperatures as recorded by thethermocouples are given in Tables 5 and 6 for the horizontal and verticalclamps, respectively; Thermal growth of the pipe was shared equally by eachset of springs on the horizontal clamp. Stress levels as measured by thestrain gages were in general agreement with predicted values. Visualexamination of both clamps after disassembly did not reveal any structuraldamage.

6123A-669A-(S1498)

Page 10: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

The only unexpected result of thermal cycling occurred during thermalcycling of the horizontal clamp. During the cool down phase of temperaturecycling i t was observed that the two clamp halves shifted around the pipe inthe direction of the load. The shift came in incremental steps and wasaccompanied by a "snapping" sound. The tendency of the clamp to shift wasstopped by the addition of a stop screw located on the top spring plate of theouter band, as shown in Figure 17.

Clamp Stiffness TestsFor the CRBRP, the main heat transport piping system has been designed to

withstand dynamic loadings that result from seismic excitations. Stressesinduced in the piping by these dynamic loadings depend upon the pipingrestraints, because the response of the piping is a function of the physicalresponse of the restraints. Analysis results show that small changes in thepiping restraint characteristics may result in marked changes in the pipingresponse obtained from system dynamic analysis (6).

To determine the piping stresses that result from seismic excitations,elastic dynamic analyses are completed with the piping supports modeled aslinear springs with f i n i t e stiffness. The stiffness of the modeled spring isdependent on the stiffness of the clamp/pipe structure. The complexity of theclamp/pipe interaction for the CRBRP piping supports required that structuraltesting be completed to yeri fy clamp/pipe st i ffnes s char acteri sties obtainedfrom analyses in References 4 and 6.

For the clamp/pipe stiffness tests, a 0.607 m by 0.152 m wide clamp wasassembled on a straight length of pipe (approximately 2 m in length) andpiaced i n a standard MTS test machine. For the test setup, the ends of thepipe section were not restrained. Thus, no beam bending is introduced. Theloading and attachment to the test machine were through the load ears of theclamp. Figures 18 and 19 show the deformation of the pipe and entirepipe/clamp assembly as a functioln of applied load for a 22,250 N and 44,500 Npreloaded, 0.607 m clamp, respectively.: Under tensile load, significanthysteresis is present due to the preloaded BelleviTie springs.

The testing results presented in Figures 18 and 19 indicate that thecombined clamp/pipe stiffness for the CRBRP 0.607 m thin-band clamp isapproximately,

U) 3.15 x l07 N/m for compressive loads(2) 1.75 x 107 N/m for tensile loads

Thus, these tests confirm the expected directional stiffness effect andapproximately verified calculational stiffness values. Further, these testsshowed that the clainp distributed the support load into the pipe, and that thetensile clamp/pipe stiffrters decreased substantially i f the clamp springpreload was exceeded such that the clamp began to deform independently of thepipe cross section.

6123A-669A-(S1498) 10

Page 11: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

Pipe Friction and Stiffness TestsThe ab i l i t y of a f r ic t ion type pipe clamp, l ike the CRBRP horizontal pipe

clamp, t j function under seismic load without rotating depends on themagnitude of two opposing forces. One is the overturning force or momentexerted upon the clamp as a result of a misaligntnent between clamp and pipecenter l ine and ^ c e n t e r l ine of thesnubbere^ is theresisting f r ic t ion force or moment generated by the clamp preload force; Aslong as the clamp fr ic t ion forces are greater than thevert ical component ofhorizontal seismic force, the clamp wi l l not s l ip .

The purpose of the clamp/pipe f r ic t ion tests was twofold; f i r s t , todemonstrate that an overturning vertical load of 10,800 N (equivalent to thevertical component of the permissible seismic force offset 7°) could beresisted by the clamp f r ic t ion force, and secondly, to evaluate the effect ofhorizontal loading of the clamp on the f r ic t ion forces.

The test setup used for f r ic t ion tests is shown in Figure 20. Thepipe/clamD was mounted in a test f ixture made up of a section of pipe .607m in diameter pipe and approximately 2 m long. The test f ixture was designedso that deadweights could be suspended from one ear of the pipe clamp while apre-determined horizontal load could be applied to the same clamp ear.

To demonstrate resistance to s l ip under a 7° mismatch, the clamp wasmounted on the test fixture and the Belleville springs were preloaded to89,000 N. No horizontal load was applied to the clamp in this case. Avertical load was incrementally added to a load ear as shown in Figure 21until a load of 10,960 N was reached, which was the capacity of the test j i g .The clamp did not sl ip for this load. The 10,960 N load represented a 90,000N horizontal applied force offset 7° from the horizontal.

To demonstrate the effect of horizontal side loading on the clampfrict ion force, the clamp was set up with a horizontal tensile load applied atone load ear, as shown on Figure 22. In this case the preload on the clampears was reduced to 8900 N, and an approximately equal horizontal load wasimposed on the clamp ear. The reduced preload (and hence the horizontal loadbecause of the preload to horizontal load relation of the CRBRP clamp) wasconsidered because of the anticipated high f r ic t ion loads. Under these loadconditions a vertical load was incrementally applied until rotational clampslip was observed. Clamp s l ip was accompanied by an audible "pop" from thetest assembly. A vertical load of 10,300 N was required to produce arotational s l ip of the clamp on the pipe. The horizontal deflection of theload ear, D2, was recorded after the clamp had slipped and at several interimload levels. These deflections are listed in Table 7.

The same test was repeated without the horizontal tensile load, androtational clamp sl ip began to occur with a 7565 N vertical load. Table 8l ists the load ear deflections for the various vertical loads for this test.

In these tests the addition of horizontal loads to the clamp earincreased the resistance to rotational sl ip between the pipe clamp and thepipe when a vertical load was applied. Without the horizontal load the pipe

6123A-669A-(S1498)

Page 12: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

clamp slipped when a vertical load equal to 85% of the clamp preload wasapplied. By applying a horizontal load equal to the preload, the verticalload required to make the clamp slip increased to 116% of the preload.

To further verify pipe/clamp stiffness values for the 0.607 m horizontalclamp which was discussed in the previous section of this paper, the testsetup used for the fr ict ion test was used to determine the clamp horizontaltensile stiffness. The horizontal load was applied to the clamp ear, as shownin Figure 20, and the deflection of the ear was determined as a function ofthe horizontal load. Based on these deflection measurements, the horizontaltensile clamp stiffness was computed. The best estimate value for thestiffness of the 0.607 m clamp was 7.0 x 10' N/m. This value accounts forthe applied load being carried through the clamp into the pipe and reacted outat the pipe ends. This is considered to be a somewhat more representativemodel of tha expected pipe/clamp behavior than the tests described in theearlier section.

IV. SUMARY AND CONCLUSIONS

Extensive structural and thermal testing of prototypical horizontal andvertical clamps planned for use on the CRBRP large diameter heat transportsystem piping was completed.

Post-test visual examination of the clamp parts after structural testingshowed no effects aside from minor indentations at a few locations to thesheathing covering the load-bearing insulation.

D.tring the thermal testing, the temperature distributions obtained atvariout locations on the clamp were in agreement with expected values. Thetemperature- cycling tests did reveal a tendency of the horizontal clamp toshift in the direction of the applied load. However, the addition of a stoppin on the clamp limited this shif t .

The fr ict ion tests on the horizontal clamps showed that the pre-loadedclamp will resist rotational slipping on the pipe.

The pipe/clamp stiffness testing showed that the pipe/clamp f lex ib i l i t yis significant and must be considered in the dynamic or seismic analysis ofthe piping.

In a l l , the testing completed verified the adequacy of horizontal andvertical insulated pipe clamps for their planned use on the high temperature,thin-wall CRBRP sodium piping.

ACKNOWLEDGEMENTS

This paper i s based on work performed under U.S. Department of EnergyContract EY-76-C-15-2395 with Westinghouse E lec t r ic Corporation, Advanced'Reactors Div is ion. The authors wish to express t h e i r appreciation of the

6123A-669A-(S1498) 12

Page 13: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

technical contributions made by Dr. R. H. Mallett and Mr. G. M. Hulbert andthe testing organizations at Westinghouse's Advanced Reactors and AdvancedEnergy Systems Divisions. A special word of thanks is due to JaniceHockenbery for her efforts in preparing the manuscript.

REFERENCES

1. L» P. Poliono and R. M. Mello, "Design Considerations for CRBRP HeatTransport System Piping Operating at Elevated Temperatures", ASMEPaper 79-NE-5.

2. L. P. Pollono, "Pipe Support", U. S. Patent 4134563, January 1979.

3. "Marinite XL Specification Data11, Bulletin IND-3221, Johns-Manvilie,Inc..Denver, Colorado, April 1978.

4. Gerald L. Jones, "An Evaluation of Clamp Effects on High TemperaturePiping Systems with Insulated Pipe Clamp", to be presented at theASME Century II Emerging Technology Conference, San Francisco,California; August 1980.

5. L. P. Pollono and R. M. Mello, "Pipe Support for use in a NuclearSystem", U .S . Patent 4046169, September 1977.

6. R. M. Mello and L. P. Pollono, "Evaluation of the Influence ofSeismic Restraint Characteristics on Breeder Reactor Pi ping Systems",in Piping Restrained Effects on Piping Integrity, PVP-37, pp. 63-77,American Society of Mechanical Engineers, New York, 1979.

6123A-669A-(S1498) 13

Page 14: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

SBj-SEd-ii-Ji:

Table 1 Dimensional Changes for Clamp SpringDuring Preloading (Cold Test)(See Figure 7 for Dimensions)

3 ^ ^ j | ^ jjjjjj feasurenenl Point (refe- to Figure 10)

1 Z 3 4 5 6 7 8 9 10 II 12 13 14 IS 16

61-039 61.Pad 61.054 61.838 61.046 61.082 61.^H T T ^ 5 "TS 0 ~~8

61.026

itt .113 61.0

6L.130 60.989-.666

61.016 61.02* 61.072.043 ^030 T55J

61.018 61.034 i 61.079 61.153 60.968

61.168 ._.~3S79" T l

61.024 61.039 61.084 61.161.04fi

61.1

61.083 61.10 0

61.016 61.173

61.156 60.836 60.IS3 60.978 61.021u 0 0 0 Q

60.985 61.029 61.143 61.084 61.034-.061 .533 -.620 -.541 ' ,.8K

61.0

60.998 fii.123 61.067-.(541 - . o 5 S

61.116 61.057 6K;

60J950 60.950 60.-.089 -.*» ~

61.064.056

60.578 61.115 61.039

61.051'

Table 2 Pipe Section O.D. Characterization(Average Values of^ Three Tests)

i4

Page No.

Page 15: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

•**"*%£*

Table 3 Clamp Thermal and Mechanical BehaviorDuring Temperature Cyclic Tests

(a ) Horizontal Clamp

Frequency (Hz.)

5.84

5.86

8.95

11.16

16.53

28.35

Force (N)

17,410

440333

7,830

675235

(b) Vertical Clamp

Frequency faz. )5.645.666.07

10.8017.7718.8319.9424.3024.8426.09

Force (N)

7,760

998

734

1,010

910

1,057

2,163

1,781

1,165

607

Table 4 Frequency-Load Content of Input DrivingForce (201 of the Design SSE Load)

15

Page No,

Page 16: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

Table 5 Temperature Behavior of Horizontal PipeClamp During Thermal Cycling Tests(For TC Location, See Figure 15)

Table 6 Temperature Behavior of Vertical PfrieClamp During Thermal Cycling Tests(For TC Location, see Figure 16)

16

Page No.

8Q14-3

Page 17: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

TABLE 7

CLAMP SLIP TEST RESULTS (wi th side load)

8900 N PRELOAD

HORIZONTAL LOADN ;:."..• •

8900890089008900890089008900

VERTICAL LOAD

2,7504,8096,1836,8687^5578,92810,300

Dl*cm

-•0038-.0044-•0051-.0025

D2*cm

-.0038-^0076-ioii4-;0152-^0203-.0305-^0635

slip occurred

VERTICAL LOAD REMOVED

8900 0 -.0025 -.0559

*See Figure 20 for location of D l , D2 measurement

6123A-669A-(S1498) j 1 7

Page 18: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

TABLE 8

CLAMP SLIP ̂ EST RESULTS (no side load)

8900 N PRELOAD

HORIZONTAL LOAD. .'YY^RY:

000000

VERTICAL LOAD-.": :YN,;V Y

2,7504,8096,133

7,5578,928

Dl*cm

-.0013-.0019-.0025-10025-.0025-;0025

D2*cm

-,0051-10089-ioii4-•6127

slip occurred

*See Figure 20 for location of Dl, D2 measurement.

6123A-669A-(S1498) 18

Page 19: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

o

ill

SHEATE0 LOADBEARING IMSULATION

SECTION "A-A"

LOAD SPRING ASSY

OUTER CLAMP RING

ATTACHMENTPADS

SHEATHED LOADBEARING INSULATION

Figure 1 Horizontal Pipe Clamp Assembly

Page 20: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

20

'&t-iT. 6014-3-

Page 21: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

o

to

C

///J//////////J/// /////I///CONSTANT LOAD

HANGERS

HANGER ROD

ADJUSTMENT

HORIZONTAL PIPE CLAMP

\ iLARGE DIAMETER PIPE

I

I

[

!

L

Figure 3 Typical CRBRP Piping Restraint Assembly

Page 22: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

SNUBBERATTACHMENT

OUTER CLAMP RING

SNUBBER ATTACHMENT

HANGERATTACHMENT

-ADAPTOR

- SPHERICAL RODENDS

X -STEEL SHEATHED LOADBEARING INSULATION

Pf§ure 4 Vertical Pipe Clamp Assemblyi

22

Page No.

60'i 4-3

Page 23: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long
Page 24: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

INSTRUMENTTABLE

BLOWER

STRUCTURE

MBLY

PLAN VIEW

STRUCTURE -

AIR BLOWER

0.223 m INSULATION ONPIPE AND HINGEDEND COVERS

TUBULAR HEATERS ON PIPEINSIDE SURFACE

/•/./•//)/•.//-»/•/ / / r r r r / / /\rrnA

Figure 6 Test A^artgement for Mechani caland Thermal Evaluation Tests

24

Page-No.

5014 3

Page 25: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

9 WASHERS INPARALLEL TO KAKEA S E T t T W

"D"-DISTANCERD-1 CONVEX SIDE

ADJACENT TOLOAD WASHER

NUT

• "6SETSREQ.IN THIS DISTANCEFACE TO FACE &BACK TG BACKAS SHOWN (TYP)

NUT

LOADWASHER

Figure 7 'BeTTev.ilfe'- Spring Assembly andLocation of Measurements

25

Fade No.

60-J4-:

Page 26: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

.55

.50

.45

.40

SJ -35inu

.30

Ul

uca

CO

.25

.20

.15

.10

.05

.00

.050

.045

.040

.035

Ia§ .030

Ul

a

« 025

a

.020

.015

.010

.005

.000

nullsA&AVJ

25 IB.SB75100125150175200

-

-

f" • / /

' / '

?CWt.

JB,.(71.171.241414.378.443.546

f

/f

1

ZSFT-LB.5075100124150175200

1

HEIftBE

JOjno.023JI28.031JD344139..042

Y1

JJ/f

11N. = 2.540 cm1 FT-LB = 1.356 N-m

AVERAGE SPRING COMPRESSIONAND CHANGE IN CLAMP GAPVERSUS TOROUE, COLD TEST

-

V GAP CHANGE

O SPRING

1 1

COMPRESSION

I I I I I

0 20 40 60 80 100 120 140 160 180 200TORQUE (FT-LBS.)

Figure 8 Average Spring Compression and Changein Clamp Gap Versus Torque - Cold Test

6014-3

26

Parje No.

Page 27: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

10° SEAM WELD

1" = 2.54 cm

WALL THICKNESS

0° AND 180°

90° AND 270°

A

B

C

0:0.1

24.013

24.037

24.004

O C 2

23.973

23.923

24.043

T1

.39^^"*^^ .339

T2270° \ ^ ^

270° _^*$f

Figure 9 Outside Diameter Measurements-Unloaded Pipe Section

6014 3

27

' P a g e No,,

Page 28: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

10

SPRING ASSY BRACKET

0.25'

#6 T

i0.75"

t#3•

\

#5

I #4

#2 1• ~L

0.75"

T#1

-ATTACHMENTPAD

SECTION A A

SECTION B-BALL GAUGES 1 TRU 6"HOOP

1"= 2.54 cm

-F#10 ILU i#i2lLU #14LLLJ

#

#|16Cp

a #15

#13

!#17D #18 a

14

W-i

9QP

I HOOP D AXIAL

GAUGES: MICflO MEASURE-MENT CEA 09-125 UT-120

GAUGES 7,8,9,11,13HOOP

GAUGES 0,12,14,15,16,17.18-AXIAL

Figure 11 Strain Gage Locations on Pipe Section

Page 29: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

CLAMP ASSY.

o

z . °°o

270°

45°

13,14

U.3,411.&12

PIPE SECTION

1" = 2.54 cm

Figure 10 Measurement Points for PipeSection with Clamp Loading

Page 30: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

120

110 -

-10 -

-20 ~

-30 -

-40 -

-50 -

-60 -

-70

SEE FIGURE 11 FOR LOCATIONOF STRAIN GAGES

_ ,

_ ^ ^

PIPE AXIAL STRAIN > vVERSUS TORQUE, N

~ COLD TEST

1 FT-LB = 1.356 N-m

AXIAL STRAIN GAUGE NO. 10,12,14,15,16,17, & 18

I I I I I

/-is

j-n ^ / ^

v

j i25 50 75 100 125

TORQUE (FT-LBS)

150 175 200

Figure 12 Axial Strain in Pipe Section VersusTorque (Cl amp Preload) -Cold Test

30

6Q14 3

Page 31: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

01o

to

2 LOAD BEAMSUPPORT ASSY,

3THRUSTERSF0RSEISMIC INPUT

CONSTANT LOADHANGERS

SPHERICAL BEARINGROD ENDS

TEST STAND

ELECTRIC HEATERSEQUALLY SPACED ON1.0. OF PIPE

MECHANICAL SNUBBER

1 - 1

LOAD CELL TO READLOAD APPLIEDTHRU PIPE CLAMP

— 3 THRUSTER DRIVE RODS

SEISMIC LOAD SEAM

PIPE CLAMP ASSY

TEST STAND

MECHANICAL SNUBDER

TEST STAND FIXTURE

2C0NSTANI LOADHANGERS

2 HANGING RODS FORSEISMIC LOAD BEAM

(8) EIGHT 1" fHK LAYERSOFGERABLANKEIINSULATION

iifll-PULL DOWN LOAD B80D LB.TOTAL INCLUDING WEIGHTOF PIPE. CLAMP. INSULATIONETC.

-BED PLATE

60"LGTYPE304SSItVELDEO PIPE

HORIZONTAL PIPECLAMP ASSY.

1" = 2.54 cm1 LB. = 4.4SN

Figure 13 Test Arrangement for Structural IhtegrityTesting of Horizontal Pipe;Clamp

Page 32: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

O

-Js.

TEST STAND

15"-5" LEVEL

to

FOHCE THRUSTERFOR SEISMIC INPUT

LOAD FIXTURE FORSEISMIC INPUT TP PIPE

8'-5" LEVEL

THRUSTER FORSEISMIC INPUT

ROOF TRUSS

COnStTANT LOADHANGER

TRAPEZE(ROTATED45° FOR CLARITY)

6 ELECTRIC HEATERS EQUALLYSPACED ON I.D. OF PIPE

8 LAYERS OF 1" THK. CERABLANKET INSULATION

VERTICAL PIPE CLAMP ASSY.

LOAD FIXTURE FORSEISMIC INPUT-TOPIPE

6 ELECTRICAL HEATERS NOTIN CONTACT WITH CLAMPADAPTOR

2 MECHANICAL SNUBBERS(ROTATED 4tf»FOR CLARITY)

LOAD CELL TO READ: LOAD APPLIED THRU PIPE CLAMP2 LENGTHS OF 24"O.D. * %'*WALL x4 '0" LG.TYPE 304 SST WELDED PIPE

PULL DOWN LOAD 11,000 LB. TOTALINCLUDING WEIGHT OF PIPE, CLAMP,INSULATION/ETC.

VERTICAL PIPECLAMP ASSY.

MECHANICAL SNUBBER

SECTION 8-8

LOAD CELL(TYPI

1LB.=4.46N1"= 2.54 cm

Figure 14 Test Arrangement for Structural IntegrityTesting of Vertical Pipe CTanip

Page 33: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

o

oCO CAJ

32 ON BOLT

A « I > B

THERMOCOUPLE =

25VIEW C-C

Figure 15 Thermocouple Location for ThermalTesting of Hortzontal Ptpe Glanip;

Page 34: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

ta

THERMOCOUPLE = •

SNUBBER

ANGERR00

Figure 16 Thermpcpyple Location fbr ThermalTesting of Vertical Pipe Clamp

— l

Page 35: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

DEADWEIGHT

SET SCREWAT TOP ONLY

Figure 17 Horizontal Pipe Clamp Design Change toPrevent SItppage

35

Page No.

8014 3

Page 36: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

0.3DISPLACEMENT (cm)

-0.2 -0.1 0 0.1

4.000

3,000

2,000

" 1,

_ MARINITEINSULATOR

3 °§1,000

| 2,000

-3,000

4,000

5,000

6,000

•7,000

•8,000

-9,000

10,000

5 = HALF OF PIPE OIA CHANGE

~ A = HALF OF PIN SPAN CHANGE

0.2 0.4

M.T.S. HYDRAULIC /- j - CYLINDER .

STIFFNESS (COMP.)

= _P_ 40.000 N

A .126 cm

K = 3.15 x 107 N/md.a

PIN DEFL. A

AVERAGEPIN DEFL.'

PINOEFL. (A)

STIFFNESS (TEN.)

K - I - 40QQN

A " .252 cm

K = J.58x107N/m(.9x10slb/in)

40.000

30,000

20,000

10,000 g

a.a

0-15 0.10 -0.OB 0 fl.05

DISPLACEMENT (INCHES) 6, A

0.10

LU

10,000

-20,000

•30,000

-40,000

0.15

Figure 18 Stiffness Test for Pipe/Cl ampwith 22,250 N Clamp Preload

36

Page No.

G014-3

Page 37: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

-0.3

DISPLACEMENT (cm)

•0.2 -0.1 0 0.1 0.2 0.3 0.4

> 14.000

12.000

10,000

too*

6.000

S 4.000

* 2,000

§ • ; • . • _

3 -••

S-2.000

I -4.000

6,000

8.000

10,000

-12,000

-14,000

-16,000

-18.000

5 = HALF OF PIPE DIA. CHANGE

- A = HALF UF PIN SPAN CHANGE

AVERAGEPINOEFL.

NUTS

. MARINITE-INSULATOR

-BELLEVILLEWASHERS

HYDRAULICM.T.S.CYLINDER

STIFFNESS (COMP.)

= f . 97.860 N

A .311 cm

K = 3.15 x 107 N/m- (1.8x105lb/in)

PINDEFL (A)

STIFFNESS (TEN.)

K _ t . 62.300 W~ A .318 cm

K = 1.96 xiO7 N/m '(1.1x105lb/in)

I I I

-riO -SO5 0 .05 .10

DISPLACEMENT (INCHES) 6, A

.15

Figure 19 Stiffness Test for Pipe/Glampwith 44,500 N Clamp" Preload

80.000

60,000

40,000

20,000

0 §©

20,000

40,000

-60,000

80,000

60'.4 3

37

Paqe No.

Page 38: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

CO

AR CLAMPED TOTEST RIG

1.83 m

Figure 20 Test Arrangement for Pipe ClampFriction/Stiffness Test

Page 39: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

Figure 21 Photograph of Test Arrangement for the Friction Test

39

Page Mo.

Page 40: DESIGN AND TESTING OF CRBRP INSULATED HORIZONTAL AND VERTICAL PIPE … · 2005. 5. 3. · Vertical Pipe Clamp The elevated loop concept of the CRBRP piping is characterized by long

c

HORIZONTALLOAOi

Figure 22 Clamp Friction Test Assembly (Section C-C)