design and construction of a bridge deck using frp as … · a research project was undertaken to...
TRANSCRIPT
Università degli Studi di Napoli “Federico II”
Corso di laurea in Ingegneria Civile
Tesi
DDEESSIIGGNN AANNDD CCOONNSSTTRRUUCCTTIIOONN OOFF AA BBRRIIDDGGEE DDEECCKK UUSSIINNGG FFRRPP AASS MMIILLDD AANNDD
PPOOSSTT--TTEENNSSIIOONNEEDD RREEIINNFFOORRCCEEMMEENNTT
Relatore: Ch.mo Prof. Ing. G. Manfredi
Correlatore: Ch.mo Prof. Ing. A. Nanni
Candidato: Raffaello Fico
Matr. 37/1991
Anno Accademico 2003-2004
BRIDGE DECK CONSTRUCTION WITH
INTERNAL FRP REINFORCEMENT
VALIDATION OF FRP COMPOSITE TECHNOLOGY
THROUGH FIELD TESTING
Construction of
Southview Bridge Deck
Prepared for:
University of Naples
April-October, 2004
iii
ABSTRACT
A research project was undertaken to evaluate the use of post-
tensioned FRP for bridge-deck construction.
The type of structure selected for this project is a four-span continuous
concrete slab having GFRP bars for top and bottom mats and CFRP
reinforcement for internal post-tensioning of the bridge deck. This
bridge is located in Rolla, Missouri (Southview Drive on Carter
Creek). One lane of the bridge was already built using a conventional
four-cell steel reinforced concrete box culvert. One lane and sidewalk
needed to be added. This additional lane was constructed using FRP
bars as internal reinforcement.
The combination of prestressed and non-prestressed FRP
reinforcement resulted in an economical solution for a deck system
with low deflection and high shear strength at a minimum deck
thickness.
This study includes the design of the FRP portion of the bridge using
existing codes when appropriate, the validation of the FRP technology
through a pre-construction investigation conducted on two specimens
representing a deck strip, construction and field evaluation through
load testing of the bridge.
The results showed how FRP, in the form of GFRP as passive and
CFRP bars as active internal reinforcement, could be a feasible
solution replacing the steel reinforcement of concrete slab bridges, and
specifically the enhanced shear capacity of the slab due to the CFRP
prestressing.
iv
ACKNOWLEDGMENTS
The first and greatest thanksgiving is referred to my parents, who gave
me the possibility to achieve this wonderful experience; thanks to my
best friends, Stefano, Giuseppe, Annalisa.
I wish to sincerely express thankfulness to Dr. Gaetano Manfredi and
Dr. Andrea Prota, who trusted in my capabilities and gave me the
great opportunity to live a so exciting adventure.
I want to express sincere appreciation to Dr. Antonio Nanni for his
guidance. His advice has been a very important factor that enabled me
to accomplish this research and gives me excitement for the future.
Sincere appreciation is also extended to Dr. Nestore Galati, for his
review of this thesis; I bothered him many times and he never hinted
any sign of nuisance.
This thesis was also a pleasing walking along which I met some
extraordinary people:
Andrea, who spent many hours teaching and helping me setting up
machines and tools in the ERL Lab, besides he was been my favourite
friend in Rolla, living with him whole weeks was like being in a funny
sit-com.
Bill, whose help and support was so selfless and helpful for my
activity, and Kathie, my American mamma.
Jason, whose skills were incredible and so needful for this project; he
helped me in the most difficult moments, behind a rough person there
was a large hearted, honest and lovely friend. He made this project a
special adventure that I will always remember with pride and joy; and
v
Abbie, whose kindness and effectiveness were simply amazing for
me. They are the best guide for my little buddy, Logan.
Thank you to my first Italian fan, Nina, who supported me in the
worst moments of my academical life.
Special appreciation goes to Umberto, who spurred me to accept the
proposal to go to USA for this thesis.
A hearty thank you to the brothers and sisters who upheld me during
my American stay: Fausta, Anna, Mario, Anita, Mariagrazia, Elia,
Anna Valentina, Dario, Marco, Davide, Carmine, Nico, Elena.
A brief but proud recall to the friends that sheared with me the most
intense periods of my “long” academical experience: Giuseppe
Malgeri, Giuseppe Carmignano and Graziano.
…Yet this thesis is dedicated to the person that watched over me more
than everyone: ciao Nonna, grazie …
vi
TABLE OF CONTENTS
ABSTRACT...............................................................................................iii
ACKNOWLEDGMENTS......................................................................... iv
1 INTRODUCTION ............................................................................. 15
1.1 BACKGROUND ................................................................................... 15
1.2 RESEARCH OBJECTIVES................................................................... 16
1.3 DESCRIPTION OF THE PROJECT...................................................... 16
1.4 THESIS OUTLINE................................................................................ 17
2 LITERATURE REVIEW.................................................................. 19
2.1 GENERAL............................................................................................. 19
2.2 INTRODUCTION ................................................................................. 20
2.3 RELATED LITERATURE REVIEW .................................................... 21
2.3.1 Non-Prestressed FRP Reinforced Bridge Decks.......................... 21
2.3.1.1 Bridge Street Bridge, Michigan........................................... 21
2.3.2 Prestressed FRP Reinforced Bridge Decks.................................. 25
2.3.2.1 Evaluation of Frp Prestressed Panels/Slabs for I-225/Parker
Road Project......................................................................................... 25
2.3.3 Research works on Shear Behavior of Prestressed FRP............... 31
2.3.3.1 S.Y. Park and A.E. Naaman (1999)..................................... 32
2.3.3.2 P.A. Whitehead and T.J. Ibell (Jan. 2004) ........................... 34
2.3.3.3 P. A. Whitehead and T. J. Ibell (Feb. 2004)......................... 35
3 EXPERIMENTAL PROGRAM 39
3.1 SPECIMENS LAYOUT......................................................................... 39
3.2 MATERIAL PROPERTIES................................................................... 40
3.3 SPECIMENS DESIGN .......................................................................... 42
3.4 SPECIMENS PREPARATION.............................................................. 45
3.5 TEST SETUP......................................................................................... 50
vii
3.6 TEST RESULTS AND DISCUSSION................................................... 56
3.6.1 Failure Modes............................................................................. 56
3.6.2 Discussion of Test Results .......................................................... 58
3.7 CONCLUSIONS.................................................................................... 61
4 SOUTHVIEW BRIDGE DESIGN................................................... 62
4.1 INTRODUCTION ................................................................................. 62
4.2 ASSUMPTIONS.................................................................................... 63
4.3 STRUCTURAL ANALYSIS ................................................................. 64
4.3.1 Load Combinations .................................................................... 64
4.3.2 Design Truck and Design Lanes ................................................. 64
4.3.3 Deck Analysis ............................................................................ 66
4.3.4 Flexural and Shear Analysis ....................................................... 66
4.3.5 Summary of the Analysis............................................................ 73
4.3.6 Deflections ................................................................................. 75
4.4 DESIGN ................................................................................................ 76
4.4.1 Assumptions............................................................................... 76
4.4.2 Slab Design ................................................................................ 78
4.4.2.1 Flexural Design................................................................... 78
4.4.2.2 Shear Design....................................................................... 80
4.4.2.3 Temperature and Shrinkage Reinforcement......................... 84
4.4.3 Serviceability.............................................................................. 86
4.4.3.1 Crack Width ....................................................................... 86
4.4.3.2 Long-Term Deflections....................................................... 88
4.4.3.3 Slab Creep Rupture and Fatigue .......................................... 89
4.5 LOAD RATING .................................................................................... 89
4.6 SOUTHVIEW BRIDGE DRAWINGS................................................... 92
5 SOUTHVIEW BRIDGE DECK INSTALLATION......................... 95
5.1 INTRODUCTION ................................................................................. 95
5.2 PRE-CONSTRUCTION MEETINGS.................................................... 95
5.3 SUBSTRUCTURE CONSTRUCTION.................................................. 97
viii
5.3.1 Footing and Floor Construction .................................................. 97
5.3.2 Abutments Construction ........................................................... 102
5.3.3 Walls Construction ................................................................... 104
5.4 SLAB CONSTRUCTION .....................................................................107
5.4.1 Bill of Material ......................................................................... 107
5.4.2 Outline of tasks......................................................................... 110
5.4.3 Investigation of the Slab Construction ...................................... 111
5.4.4 Post-tension of the Slab ............................................................ 121
6 CONCLUSIONS.............................................................................. 127
APPENDICES A. MORE DATA RELATED TO SECTION 2……………………………...134
B. LOAD RATING DETAILED CALCULATIONS……………………….155
C. MATERIAL AND CONSTRUCTION SPECIFICATIONS……………..166
ix
LIST OF TABLES
Table 1 - Mechanical Properties of FRP Bars ................................... 42
Table 2 – Comparison Experimental Theoretical Results ................. 58
Table 3 – Parameters for Girder Analysis ......................................... 67
Table 4 - Moment and Shear per Unit Strip (Live and Dead Load). 74
Table 5 - Material Properties .......................................................... 77
Table 6 - Slab Geometrical Properties and Internal FRP
Reinforcement ........................................................................... 80
Table 7 - Steel and GFRP Flexural Design of the Deck (No Prestress
Used) ......................................................................................... 81
Table 8 - Maximum Shear and Moment due to Live Load.............. 91
Table 9 - Rating Factor for the New Slab (Bending Moment)......... 91
Table 10 - Rating Factor for the New Slab (Shear) ......................... 92
Table 11 - Bill of FRP Material .................................................... 107
x
LIST OF FIGURES
Fig. 1 - Views of the Former Bridge ............................................... 17
Fig. 2 - Cross Section of the Bridge after the Expansion................. 17
Fig. 3 - Cross-sectional Details of Structure B (dim. in SI units) .... 22
Fig. 4 - Erection of DT Girders at the Bridge Site........................... 23
Fig. 5 - Installed DT Girders with External CFCC Post-tensioning
Strands....................................................................................... 23
Fig. 6 - Structure B Completed and Ready for Traffic .................... 24
Fig. 7 - I-225/Parker Road Bridge under Construction.................... 25
Fig. 8 - Installation of Precast Panels.............................................. 26
Fig. 9 - Precast Panels Supported on Two Box Girders .................. 26
Fig. 10 - Top Reinforcement........................................................... 27
Fig. 11 - Cast-in-Place Portion of the Deck .................................... 28
Fig. 12 - Panel and Anchorage Details............................................ 29
Fig. 13 - Construction of the Panels................................................ 30
Fig. 14 - Cross-sectional dimensions and helical reinforcement
shapes for................................................................................... 37
Fig. 15 - Reinforcement Layout (all dimensions in mm)................. 40
Fig. 16 - CFRP Tendons Trace (all dimensions in mm) ................... 40
Fig. 17 - Cage Detail ...................................................................... 45
Fig. 18 - Strain Gages Detail .......................................................... 46
Fig. 19 - Reinforcement Cages ....................................................... 46
Fig. 20 - Specimen Curing.............................................................. 47
Fig. 21 - Specimens after Removal of the Formwork...................... 47
Fig. 22 - Prestressing System.......................................................... 48
Fig. 23 - Steel Wedge Anchorage System....................................... 49
Fig. 24 - Drilling of CFRP Bar after Grout Curing ......................... 49
xi
Fig. 25 - Static Scheme for the Flexural Specimen ......................... 50
Fig. 26 - Hyperstatic Scheme.......................................................... 51
Fig. 27 - Flexural Plot..................................................................... 52
Fig. 28 - Static Scheme for the Shear Specimen ............................. 52
Fig. 29 Shear Plot ............................................................................ 53
Fig. 30 - Steel Plate Detail.............................................................. 54
Fig. 31 - Test Setup (all dimensions in mm) ..................................... 55
Fig. 32 - Shear cracks on the Flexure Specimen ............................. 56
Fig. 33 - Concrete Crushing in the Compressive Zone.................... 57
Fig. 34 - CFRP Bars Rupture Due to Kinking................................. 57
Fig. 35 - Failure in the Shear Specimen .......................................... 58
Fig. 36 - Mmeasured Vs. Mtheoretical....................................................... 59
Fig. 37 – Load deflection Diagram for the Longer Span................... 60
Fig. 38 – Comparison Between Experimental and ............................ 61
Fig. 39 - Bridge T0530 ................................................................... 62
Fig. 40 - View of the Existing Bridge ............................................. 63
Fig. 41 - Truck Load on the New Deck........................................... 65
Fig. 42 - Loading Conditions .......................................................... 66
Fig. 43 - Design Truck on the Girder .............................................. 67
Fig. 44 - Design Truck: Possible Loading Conditions..................... 68
Fig. 45 - Design Lane: Possible Loading Conditions ...................... 68
Fig. 46 - Unfactored Bending Moment Diagrams Due to Live Load
.................................................................................................. 69
Fig. 47 - Unfactored Bending Moment Diagrams Due to Dead Load
.................................................................................................. 70
Fig. 48 - Unfactored Shear Diagrams Due to Live Load ................. 71
Fig. 49 - Unfactored Shear Diagrams Due to Dead Load ................ 71
Fig. 50 - Unfactored Moment and Shear Diagrams......................... 73
xii
Fig. 51 - Bending Moment Envelopes (kN-m/m)............................ 74
Fig. 52 - Bridge Deflection Analysis (Live Load)........................... 75
Fig. 53 - Bridge Deflection Analysis (Dead Load).......................... 75
Fig. 54 - Strength Reduction Factor................................................ 79
Fig. 55 - Flexural Capacities of the Bridge ..................................... 79
Fig. 56 - Rationale for Proposed Shear Strength ............................. 83
Fig. 57 - Bridge Internal FRP Reinforcement: Section at Mid-Span85
Fig. 58 - CFRP Prestressing Tendons ............................................. 85
Fig. 59 - Stress and Strain at Service .............................................. 88
Fig. 60 - Wetting of the Basement and Digging of the Weed.......... 98
Fig. 61 - Work Area after the Water Filling.................................... 99
Fig. 62 - Devices to Remove or Avoid the Water ........................... 99
Fig. 63 - Footing Formwork ......................................................... 100
Fig. 64 - Pouring of the Footing.................................................... 100
Fig. 65 - Slump Test and Concrete Cylinders Casting .................. 101
Fig. 66 - Footing after Pouring ..................................................... 101
Fig. 67 - Floor Reinforcement ...................................................... 101
Fig. 68 - Water Overflowing and Casting of the Floor.................. 102
Fig. 69 - Laying of Abutments Reinforcement and Formwork...... 103
Fig. 70 - Use of the Steel Ties Gun............................................... 103
Fig. 71 - Casting of the New Abutments....................................... 103
Fig. 72 - Reinforcement and Formwork of the First Wall ............. 104
Fig. 73 - First Wall ....................................................................... 104
Fig. 74 - GFRP Anchoring Detail ................................................. 105
Fig. 75 - Laying of the GFRP Rebars ........................................... 105
Fig. 76 - Making of the Notch ...................................................... 106
Fig. 77 - Central Wall ................................................................... 106
Fig. 78 - Completion of the Prefatory Part of Southview Project .. 106
xiii
Fig. 79 - Formwork Hangers Details............................................. 111
Fig. 80 - Laying of the Formwork................................................. 112
Fig. 81 - Gluing and Placing of Styrofoam ................................... 112
Fig. 82 - Neoprene Pads and Plastic Chairs Details ...................... 113
Fig. 83 - Laying of Bottom Layer of GFRP Rebars ...................... 113
Fig. 84-The RTI Team with (from down on the left) Mr. Cochran, 114
Fig. 85 - Barrier Design................................................................ 114
Fig. 86 - Top GFRP Layer ............................................................ 115
Fig. 87 - Board Detail ................................................................... 116
Fig. 88 - Wooden Board (the wire indicates the position of the
tendons) ................................................................................... 116
Fig. 89 - Slab Section ................................................................... 117
Fig. 90 - Plastic Ducts Detail ........................................................ 117
Fig. 91 - T Connectors Detail ....................................................... 118
Fig. 92 - Attaching of a Strain Gage ............................................. 118
Fig. 93 - Strain Gages Scheme...................................................... 119
Fig. 94 - Pouring Fragments ......................................................... 119
Fig. 95 - Concrete Cylinders Execution and Slab Leveling.......... 120
Fig. 96 - Poured FRP Bridge Deck ............................................... 120
Fig. 97 - Pulling Machine Before and After the Optimizations ..... 121
Fig. 98 - New Pulling Machine Ready for the Use........................ 122
Fig. 99 - Load Cell and External Chuck Detail ............................. 122
Fig. 100 - Hammer Detail and Use on the Site.............................. 123
Fig. 101 - Orange Box .................................................................. 123
Fig. 102 - Wedges Insertion and Cutting of the Tendon................ 124
Fig. 103 - First Set of Pulled Tendons .......................................... 124
Fig. 104 - Grout Injection and Slots Locking................................ 125
Fig. 105 - Cutting of the Slab Edge .............................................. 126
xiv
Fig. 106 - Southview Bridge-Deck Completed ............................. 126
15
1 INTRODUCTION
1.1 Background
Reinforced and prestressed concrete (PC and RC) structures are facing
a worldwide problem, which is the corrosion of the steel as a result of
aging and aggressive environments. Steel corrosion leads to member
degradation, endangers structural integrity and may even cause
catastrophic failures. Research has been carried out in an effort to find
the solution for this problem. The recent advancements in the field of
material science have resulted in the development of new products
that can be used in many areas of civil engineering where
conventional materials have failed to provide satisfactory service life.
Fiber Reinforced Polymers (FRP) have been proposed for use in lieu
of steel for reinforcement and prestressing tendons in concrete
structures. The promise of FRP materials lies in their high-strength,
lightweight and non-corrosive, non-conducting, and non-magnetic
properties. In addition, FRP manufacturing offers a unique
opportunity for the development of shapes and forms that would be
difficult or impossible with conventional steel materials. They can be
manufactured as reinforcing bars and tendons for RC and PC
structures, sheets and laminates for external strengthening of beams,
slabs and masonry walls, wraps and shells for confinement of
columns, etc.
The interest in the use of FRP composites in prestressed concrete is
mainly based on durability issues. Corrosion of prestressing steel
16
tendons caused serious deterioration of infrastructure. Properties like
high tensile strength and high resistance to corrosion would appear to
make FRP composites good candidates for prestressing tendons.
1.2 Research Objectives
The objectives of the project at the University of Missouri Rolla were
as follows:
1. Evaluate the feasibility, behavior, and effectiveness of the new deck
system, showing how FRP, in the form of GFRP as passive and CFRP
bars as active internal reinforcement, could be an excellent solution
replacing the steel.
2. Provide analytical data in support of the enhanced shear capacity of
the concrete slab due to the CFRP prestressing.
1.3 Description of the project
The City of Rolla in Missouri has made available a bridge (Southview
Drive on Carter Creek) to demonstrate the use of FRP bars and
tendons in new constructions. One lane of the bridge was already
constructed using conventional four-cell steel reinforced concrete
(RC) box culvert. It consists of a steel RC slab about 25 cm (10 in)
thick, as depicted in Fig. 1. The slab deck is continuous over three
intermediate reinforced concrete vertical walls, and the overall length
of the bridge is roughly 12 m (40 ft). The new deck was built on three
conventional RC walls as for the existing structure. The expansion
phase included the removal of the curb from the existing RC deck to
allow extending the overall width of the bridge from 3.9 m (12.8 ft) to
17
11.9 m (39 ft). The curb-to-curb width of the resulting bridge is 9.1 m
(30 ft). The two additions consist of a FRP prestressed/reinforced
concrete deck and a steel RC deck as shown in Fig. 2. The
construction of the bridge started on July 2004 and finished on
October 2004.
Fig. 1 - Views of the Former Bridge
WEARING SURFACE5 cm ASPHALT
EXISTING DECKCURB FROM
REMOVE EXISTING
BARRIER WALLCONCRETE
REINFORCED
SIDEWALK (1.5m)NEW CONCRETE
CONCRETE DECKREINFORCED
STEEL
FRP REINFORCED CONCRETE DECK EXISTING REINFORCED CONCRETE
4.3 m1.5 m
12 m2 m3.9 m6 m
Fig. 2 - Cross Section of the Bridge After the Expansion
1.4 Thesis outline
This thesis consists of six sections:
• Section one gives a brief introduction of the background of FRP
applications in civil engineering and introduces the objectives
of the research.
• Section two contains informations on existing prestressing and
non-prestressing FRP bridge decks, so that they can be
compared with the new deck system that is the subject of this
18
thesis. It also gives a summary of the main research works on
shear behavior of prestressed FRP.
• Section three presents the pre-construction investigations
conducted on two specimens representing a deck strip 457 mm
(18 in) wide and 7 m (23 ft) long, fabricated and tested. The
specimens were constructed by the contractor peculiar for the
project allowing for his familiarization with the use of non-
conventional materials. The testing of the specimens as
continuous slabs over three supports allowed the validation of
the design calculations in terms of flexure and shear capacities.
• Section four focuses on Southview Brigde design, providing the
structural analysis of the new FRP concrete bridge deck based
on the AASHTO HS20-44 design truck and providing
calculations for its design using a combination of non-
traditional corrosion-resistant composites materials.
• Section five details the installation of Southview bridge deck,
focusing on the post-tensioning of the slab, the most
considerable and crucial part of the project.
• Section six gives a brief summary of the steps developed in the
previous sections and deepens the results of the research work
and installation of the bridge-deck.
19
2 LITERATURE REVIEW
2.1 General
There are only about fifty bridges in the world with Fiber Reinforced
Polymer superstructure as reported by the U.S. Department of
Transportation Federal Highway Administration1 as of July 2002.
The use of FRP bridge decks has been a direct result of technology
transfer initiatives taken by the defense industry in late 1980’s and
early 1990’s. In fact, many of the manufacturers of FRP bridge decks
were directly or indirectly related to the aerospace composites
industry. Furthermore, in recent years many state transportation
departments in partnership with the Federal Highway Administration
(FHWA) are introducing these new materials to bridge structures with
the intention of gaining design and construction experience and long-
term performance data on FRP, thus FRP deck systems are emerging
as a viable alternative to conventional systems, namely reinforced-
concrete slabs. Moreover the research on prestressing with FRP
tendons is getting attention mainly due to the fact that nearly half of
the nation’s bridges are reported to be in serious disrepair or
functionally obsolete.
The use of such systems to replace existing, deteriorated bridge deck
systems offers both economic benefits and improved performance.
The economic advantages are possible for a number of reasons: since
such composite systems are lighter, considerable savings are realized
20
by reduced transportation costs (several deck systems can be
transported on one truck); erection costs will be less as relatively light
cranes can be used to install the decks; and construction time is
reduced, which eliminates long traffic delays. Due to the high
resistance of FRP deck systems to environmental effects and corrosion
attack, the long term performance is also expected to be improved
significantly, leading to lower maintenance and longer service life. In
addition to economic advantages, FRP deck systems offer structural
advantages as well. For example, higher live loads can be resisted by
supporting steel stringers, as the dead load applied by the FRP deck
system is about one fifth of a conventional reinforced-concrete deck.
2.2 Introduction
The proposed literature review refers to different topics related to the
concrete bridge decks using FRP reinforcement:
• Non-prestressed FRP reinforced bridge decks.
• Prestressed FRP reinforced bridge decks.
• Research works on shear behavior of prestressed FRP.
In this section, some of the main existing internal FRP bridge decks
have been presented, so that they can be compared with the new deck
system that is the subject of this thesis.
Other existing samples are in Appendix A.
21
2.3 Related Literature Review
2.3.1 Non-Prestressed FRP Reinforced Bridge Decks
2.3.1.1 Bridge Street Bridge, Michigan
The Bridge Street Bridge in Southfield, Michigan, is the first vehicular
concrete bridge ever built in the United States that uses CFRP material
as the principal structural reinforcement. The project consists of two
parallel bridges - Structures A and B – over the Rouge River in the
City of Southfield. Both structures use three skewed spans, each over
62 m (204 ft) long, to carry vehicular traffic. Structure A consists of a
new substructure as well as a new superstructure, and incorporates
five equally spaced conventional AASHTO Type III girders in each of
its three spans. Its cast-in-place concrete deck slab is placed
continuously across the three spans. Structure B consists of four
special precast, prestressed double-tee (DT) girders in each of the
three spans configured as simply supported spans. Each DT girder is
structurally reinforced polymer (CFRP) LeadlineTM tendons and post-
tensioned carbon fiber composite cable (CFCC)TM strands in both
longitudinal and transverse directions. The non-prestressed
reinforcement in the girders and deck structure consists of CFCC
strands manufactured in bent configurations, straight CFCC
reinforcing bars, CFRP NEFMACTM grid reinforcement, and stainless
steel reinforcing bars for stirrups.
The bridge cross section (see Fig. 3) consists of four precast DT
sections and a minimum 75 mm (3 in.) thick non-continuous deck
slab.
22
Fig. 3 - Cross-sectional Details of Structure B (dim. in SI units)
The composite topping is reinforced with NEFMAC grids. The
composite section is also reinforced with four externally draped 40
mm (1.57 in.) diameter unbonded CFCC post-tensioning strands.
The unique construction method was based on a process developed
and tested previously at LTU. The transportation of the 12 girders
from the precast plant in Windsor, Ontario, to the bridge site in
Southfield, Michigan, required a special barging arrangement. The
girders were erected using two large capacity cranes at opposite ends
of the bridge.
Fig. 4 shows the erection of a DT girder for the south span, and Fig. 5
shows the installed girders with external post-tensioning strands in
place.
23
Fig. 4 - Erection of DT Girders at the Bridge Site
Fig. 5 - Installed DT Girders with External CFCC Post-tensioning Strands
The Bridge Street Bridge Deployment Project has served as an
extraordinarily successful example of technology transfer from
research and development to serviceable structure.
The bridge exhibits innovation not only in the material itself, but also
in the variety of prestressing methods implemented – pretensioning
and post-tensioning, internal and external.
This project recently won PCI’s Harry H. Edwards Industry
Advancement Award in the recent PCI Design Awards Program (see
Fig. 6).
24
Fig. 6 - Structure B Completed and Ready for Traffic
25
2.3.2 Prestressed FRP Reinforced Bridge Decks
2.3.2.1 Evaluation of Frp Prestressed Panels/Slabs for I-225/Parker Road Project
Under the Innovative Bridge Research and Construction (IBRC)
program of the Federal Highway Administration (FHWA), in 2001 the
Colorado Department of Transportation (CDOT) has introduced fiber
reinforced polymeric (FRP) reinforcement in a bridge project at I-
225/Parker Road. Precast prestressed concrete panels were used as
stay-in-place forms for a bridge deck. The bridge during construction
is shown in Fig. 7.
Fig. 7 - I-225/Parker Road Bridge under Construction
Some of these panels were prestressed with CFRP tendons and the rest
with regular seven-wire steel strands. The primary objective of this
project was to demonstrate the feasibility of using CFRP tendons in
place of seven wire steel strand for prestressed concrete panels.
26
It was the first time CFRP bars were used in such fashion. The precast
panels were supported on two cast-in-place, post-tensioned concrete
box girders (Fig. 8 and Fig. 9). A topping slab was added to the panels
to form a composite bridge deck to carry the traffic.
Fig. 8 - Installation of Precast Panels
Fig. 9 - Precast Panels Supported on Two Box Girders
Furthermore, the applicability of current AASHTO provisions to
CFRP prestressed panels was investigated. In addition to the
experimental investigation, a new rational design methodology for
27
bridge decks was proposed and investigated (Borlin 2001) in this
project. Most highway bridges in the United States have slab-on-
girder decks, in which steel or precast concrete girders support a
reinforced concrete slab. The two components are tied together with
shear connectors to allow for composite action. The main
reinforcement in the deck slabs is placed perpendicular to the direction
of traffic. For these decks, both the AASHTO Standard Specifications
for Highway Bridges (AASHTO 1996) and the conventional method
in the AASHTO LRFD Bridge Design Specifications (AASHTO
1998), resulted in two dense reinforcement mats, one in the top of the
slab and one in the bottom (Fig. 10 and Fig. 11).
Fig. 10 - Top Reinforcement
28
Fig. 11 - Cast-in-Place Portion of the Deck
Pullout tests conducted in this study showed that Leadline CFRP
prestressing tendons and C-BAR glass fiber reinforced polymeric
(GFRP) reinforcing bars had higher bond strengths than seven-wire
steel strand and regular steel reinforcing bars, respectively.
Load tests were first performed on two panels, one prestressed and
reinforced with FRP and the other prestressed and reinforced with
steel. Both panels were designed to barely satisfy the AASHTO
specifications. An additional panel that was prestressed and reinforced
with FRP and brought from the I-225/Parker Road project was tested
as well. This panel was conservatively designed with a significant
reserve capacity compared to the first two. Load tests were also
performed on steel and FRP prestressed panels that had a 125 mm (5
in.) composite topping slab (see Fig. 12 and Fig. 13). All test results
showed the feasibility of using CFRP tendons for prestressing and
GFRP bars for temperature and distribution reinforcement in precast
bridge panel construction. The GFRP reinforcement was selected
29
according to the recommendation for temperature reinforcement in the
ACI 440H draft report.
Load distribution data were taken during the composite slab tests to
validate the adequacy of the Equivalent Width Strip method used in
AASHTO LRFD Specifications. The method was found to be
conservative for both steel and FRP reinforced composite slabs.
However, results showed that the steel reinforced slab better
distributed the loading in the transverse direction than the FRP
reinforced slab. This suggests that the recommendation for
temperature reinforcement in the ACI 440H draft report may not be
adequate for distribution reinforcement.
Fig. 12 - Panel and Anchorage Details
30
Fig. 13 - Construction of the Panels
31
2.3.3 Research works on Shear Behavior of Prestressed FRP
The majority of research on concrete structures using FRP
reinforcement has been on members that are not critical in shear tests.
At present, the shear behaviour of prestressed concrete members using
FRP reinforcement is not well understood. Unlike flexural behavior,
shear behaviour is quite complex itself, even in ordinary reinforced or
prestressed concrete members.
Structures are usually conservatively designed, and rely on plasticity
theory for safety. This ensures that, if a set of internal forces exists
which is in equilibrium with the applied load, and since it is known
that steel is ductile, the lower bound (or ‘Safe Load’) theorem can be
used to assert that the structure is safe.
When advanced composites are used, however, the theoretical
justification is much less sound; many of the basic assumptions no
longer hold. Composites are generally less stiff than steel so, when the
concrete cracks, a composite is carrying less force than steel would be.
Cracks will, thus, be wider, so there will be less concrete–concrete
interaction across the crack; there will thus be less ‘aggregate
interlock’. Composites also delaminate when placed across shear
cracks, so ‘dowel action’ will be lower and there are problems caused
by the bends in the bars.
Finally, and most importantly, although composites have high strain
capacities, they do not behave plasticly, so the Safe Load theorem
cannot be used to hide the lack of knowledge about the deflections.
Taken together, these results mean that care must be taken about
producing design guidelines for shear in compositely reinforced
structures.
32
There is clearly much work to be done in this field—a model is
required which satisfies all three of the basic principles of structural
mechanics—equilibrium, compatibility and the material stress–strain
behaviour [C.J. Burgoyne, August 2001].
Here a summary of the main research works on this topic is given.
2.3.3.1 S.Y. Park and A.E. Naaman (1999)
The authors conducted an experimental program on two series of tests
(two sets of beams). The first series comprised nine prestressed
concrete beams fabricated without stirrups. Five beams were
prestressed using CFRP tendons and, for comparison, four beams
were prestressed using conventional steel tendons.
The main objective of this first series of tests was to experimentally
confirm the shear-tendon rupture failure mode in prestressed concrete
beams with FRP tendons and to compare it with other failure modes in
prestressed concrete beams with steel tendons.
The second series of the experimental program comprised seven FRP
prestressed concrete beams and one non-prestressed concrete beam
shear reinforced with steel stirrups (seven beams) or steel fibers (one
beam). The test parameters were the pretensioning ratio, the shear
span-to-depth ratio, shear reinforcement ratio, the use of steel fibers,
the compressive strength of concrete, and the type of reinforcement.
The main goal of the second series was to evaluate the parameters
affecting the shear strength and ductility of concrete beams
prestressed with FRP tendons.
On the basis of this experimental investigation, the following
conclusions were drawn:
33
1. The shear-tendon rupture failure is a unique mode of failure,
which, unless properly designed for, is likely to occur in
concrete beams prestressed with FRP tendons. This premature
failure is due to tendon rupture by dowel shear at the shear-
cracking plane. It is attributed to the poor resistance of FRP
tendons in the transverse direction and their brittle behavior.
2. The ultimate shear resisting capacity of beams prestressed with
FRP tendons was about 15 percent less than that of beams
prestressed with steel tendons, regardless of their shear failure
mode.
3. The shear-tendon rupture failure occurred at the flexural-shear-
cracking plane in beams with FRP tendons, even when the
effective prestress ratio was low (about 40 %) and the required
amount of steel stirrups was provided according to the ACI
Code.
4. Adding steel fibers is a possible way to improve the shear
resistance of concrete beams prestressed with FRP tendons by
avoiding or delaying shear-tendon rupture failure.
5. Differences in the properties of FRP and steel tendons appear to
have no significant effect on the initial portion of load-
deflection response of prestressed concrete beams subjected to a
center point loading with a shear span-to-depth ratio of 2.5.
6. The ultimate shear displacement and crack width of prestressed
beams that failed by shear-tendon rupture were about one-third
and one-half, respectively, of those of similar beams with steel
tendons.
7. The following observations were made for beams prestressed
with FRP tendons:
34
• Increasing the shear span-to-dept ratio from 1.5 to 3.5 led to a
decrease in shear resistance but an increase in shear ductility
(displacement).
• Adding stirrups in sufficient quantity changes the failure mode
from shear-tension to shear-tendon rupture in beams with a low
effective prestress ratio of about 40 percent.
• Increasing the compressive strength of concrete slightly
increases the shear strength and considerably increases the
corresponding deflection.
2.3.3.2 P.A. Whitehead and T.J. Ibell (Jan. 2004)
The authors developed a model incorporating force equilibrium and
compatibility of strains so that the elastic properties of FRP could be
included rationally.
Fifteen specimens from the experimental program and four case-study
specimens (all of which failed in shear) were used to assess the
accuracy of predictions from the most prevalent codes and design
guides currently in use in the UK and the US, namely BS8110 (1997),
BD44 (1995), EC2 (1992) and ACI-440.1R-03 (2003). ACI-440.1R-03
is specifically intended for FRP-reinforced concrete. However,
predictions obtained using modified versions of the other three
standard codes were also provided. These modifications were termed
the Strain Approach and the Sheffield Approach (Guadagnini et al.,
2001).
The following conclusions were drawn:
1. The analytical shear predictions developed by the authors
predicted the experimental results with a better accuracy when
compared to the existing building codes.
35
2. Using either the Strain or Sheffield modification suggestions in
tandem with BS8110, BD44 and EC2 results in reasonable predictions
for all the reinforced (AFRP and GFRP) specimen capacities. ACI-
440.1R-03 provides more conservative predictions for the FRP-
reinforced specimens.
3. The presence of prestress was found to be significant in
increasing shear capacity of such specimens, due to the significant
crack-closing influence of the prestress. The unfactored code
evaluations are more conservative for the prestressed specimens,
implying that the presence of prestress aids the FRP-reinforced
concrete beams to a greater extent than it does steel-reinforced
concrete.
2.3.3.3 P. A. Whitehead and T. J. Ibell (Feb. 2004)
A novel FRP shear reinforcement strategy, in which both the concrete
and FRP are employed to maximum advantage was conceived by the
authors.
They presented the findings of research conducted into the shear
behaviour of FRP-reinforced and -prestressed concrete beams
containing continuous FRP helical transverse reinforcement. Twelve
tests were conducted on ordinarily-reinforced beams and fifteen on
FRP-prestressed concrete beams.
Tests on FRP-reinforced concrete beams were indeed conducted
initially, thereby allowing rapid assessment of the influence of various
shear reinforcement strategies which could later be investigated under
prestressed conditions. Accordingly, the more effective forms of shear
reinforcement were taken forward and re-examined under prestressed
conditions while the non-responsive forms were discarded. Further, in
36
order to make direct comparison between FRP-reinforced and -
prestressed beams, the effective depth was kept the same for both sets
of tests.
Ibell and Burgoyne suggested that geometry and bond (including the
locality of bond) are of paramount importance in the performance of
FRP shear reinforcement. Therefore, to examine these aspects, the
following FRP shear reinforcement strategies were employed within
the FRP-reinforced and -prestressed rectangular concrete beams:
1. Circular helix, fully-bonded or entirely unbonded, placed along
the top of the beam within the flexural compression zone. See
Fig. 14-a.
2. Circular helix, fully-bonded or entirely unbonded, angled in the
shear zones, following the lines of principal compression. See
Fig. 14-b.
3. Continuous rectangular draped helix, fully-bonded,
intermittently-bonded or entirely unbonded, placed over the full
depth of the section. See Fig. 14-c.
4. Two interlocking rectangular draped helices, entirely unbonded,
placed over the full depth of the section. See Fig. 14-d.
37
Fig. 14 - Cross-sectional dimensions and helical reinforcement shapes for
(a) Specimens containing a circular helix placed along the top of the beam,
(b) Specimens containing a circular helix angled in the shear zone,
(c) Specimens containing a continuous draped rectangular helix, and
(d) A specimen containing two interlocking rectangular helices
The following conclusions were made on shear behavior:
• The presence of prestress was significant in increasing shear
capacity of such specimens.
• When used to resist shear, fully-unbonded circular and
rectangular helices had to be spaced at a closer pitch in
comparison with fully-bonded or intermittently-bonded
rectangular helices to provide a similar increase in failure
capacity. The fully-unbonded rectangular helices appeared to
38
have been about 50% as effective as fully- or intermittently-
bonded rectangular helices in resisting shear.
• Of the arrangements considered, the best technically seemed to
involve the use of a fully-bonded circular helix and a fully-
bonded rectangular helix in the constant-moment region,
coupled with an intermittently-bonded rectangular helix in the
shear zones. This configuration led to considerable
deformability and ductility and produced high shear capacity
and genuine plastic-based ductility during shear collapse.
• FRP reinforcement need not simply be treated as a direct
substitute for steel reinforcement, but that rather its inherent
advantages should be exploited using rational design
approaches.
39
3 EXPERIMENTAL PROGRAM
This section presents the pre-construction investigations conducted on
two specimens representing a deck strip 457 mm (18 in.) wide, 254
mm (10 in.) deep and 7 m (23 ft) long, fabricated and tested. The
specimens were constructed by the contractor peculiar for the project
allowing for his familiarization with the use of non-conventional
materials. The testing of the specimens as continuous slabs over three
supports allowed the validation of the design calculations in terms of
flexure and shear capacities.
3.1 Specimens Layout
Two specimens having the same geometry and amount of
reinforcement were built and tested, one to investigate the flexural
behaviour, the other one the shear behaviour. The specimens were
reinforced using 3 f19 (6/8 in) GFPR bars as top and bottom mat and
2 f9 (3/8 in) CFRP bars as prestressed tendons. The position of the
prestressed tendons was varied along the slab in order to match the
moment demand. In addition, in order to reproduce the actual field
conditions also f13 (4/8 in) GFRP bars spaced 305 mm (12 in) on
center were placed in the transversal direction as temperature and
shrinkage reinforcement. Fig. 15 shows a detailed layout of the
reinforcement, while Fig. 16 shows the position of the CFRP tendons.
40
φ19 GFRP Bars
Temperature ans Shrinkage Reinforcement: φ13 GFRP Bars410 mm Long, 305 mm on Center
φ9 CFRP BarsPRESTRESSING TENDONS
PLASTIC TIES
CHAIRS
38
φ19 GFRP BarsSpaced 152 mm on Center
457
178
38
254
Fig. 15 - Reinforcement Layout (all dimensions in mm)
13706101370127 178178127
178
305 76268668612712717876
76
7010
1067
914 3685 1829 609
152
Supports
Tendon Trace
Fig. 16 - CFRP Tendons Trace (all dimensions in mm)
3.2 Material Properties
Tests were performed to characterize the mechanical properties of the
materials used in this investigation.
The designed concrete compressive strength was equal to 41.4 MPa
(6000 psi). Water to cement ratio for the concrete mixture was 0.45.
The components in the concrete mixture were proportioned as follow
by weight: 19% portland cement, 40% crushed limestone, 33% sand,
and 8% water.
41
The actual compressive strength of the concrete was checked on three
100 x 200 mm (4 x 8 in) cylinders per slab. The cylinders were tested
in compliance with ASTM C39/C39M. The average compressive
strength at the time of the test was found equal to 48.6 MPa (7040 psi)
and 45.4 MPa (6585 psi) for the flexural and shear specimens,
respectively.
The compressive strength of the high performance cementitious grout
was determined on three cylinders 100 x 200 mm (4 x 8 in) and it was
found to be 21.7 MPa (3150 psi) after one day, 36.5 MPa (5300 psi)
after three days, 49.3 MPa (7150 psi) after seven days, and 58.9 MPa
(8550 psi) after 28 days. In addition, splitting tensile tests in
compliance with ASTM C496 were performed on the same type of
cylinders (three repetitions). The splitting tensile strength was found
to be 1.5 MPa (218 psi) after one day, 2.8 MPa (406 psi) after three
days, 3.58 MPa (520 psi) after 7 days, and 5.59 MPa (810 psi) after 28
days.
Tensile tests were performed on FRP bars to determine their
mechanical properties which are related to fiber content. The average
tensile strength, ultimate strain and modulus of elasticity obtained
from the testing of the specimens (ASTM D3039) are presented in
Table 1.
42
Table 1 - Mechanical Properties of FRP Bars
Bar Type
Nominal Diameter of
the Bar mm (in)
Average Max. Strain
%
Average Max. Stress
MPa (ksi)
Average Elastic Modulus GPa (ksi)
GFRP Bar 12.7 (0.5) 1.68 689.5 (100.0) 40.80 (5920)
GFRP Bar 19.1 (0.75) 1.52 620.5 (90.0) 40.80 (5920)
CFRP Bar 9.5 (0.375) 1.67 2124.2 (308.1) 142.7 (20702)
3.3 Specimens Design
The theoretical moment and shear capacities have been computed
according to ACI 440.1R-03 provisions. As an alternative method to
compute the shear capacity of the specimens the equation developed
by Tureyen A. K. and Frosh R. J. and now under consideration for
adoption by ACI Committee 440, was used.
According to the ACI 440.1R-03 the nominal flexural capacity of an
FRP reinforced concrete member can be computed as follows:
1 1( ) ( )2 2n f fu fp fup pc cM A f d A f dβ β
= − + − (3.1)
where:
fA = area of FRP reinforcement
fuf = design tensile strength of FRP, considering reductions for
service environment
d = distance from extreme compression fiber to centroid of tension
reinforcement
1β = factor depending on the concrete strength, 'cf , equal to 0.75 for
'cf = 41.4 MPa (6000 psi)
43
c = distance from extreme compression fiber to the neutral axis
The second term symbols represent the same factors but referred to
the prestressed reinforcement.
The theoretical moment capacity is 97.9 kN-m (72.2 kip-ft), while
without the post-tension reinforcement this value becomes 76.0 kN-m
(55 kip-ft).
According to the ACI 440.1R-03 the concrete shear capacity Vc,f of
flexural members using FRP as main reinforcement can be evaluated
as shown below. The proposed equation accounts for the axial
stiffness of the FRP reinforcement (AfEf) as compared to that of the
steel reinforcement (AsEs).
,
f fc f c
s s
A EV V
A E=
(3.2)
Vc being the nominal shear strength provided by concrete with steel
flexural reinforcement, for members with effective prestress force not
less than 40 percent of the tensile strength of flexural reinforcement,
according to ACI 318R-99:
'(0.6 700 )u pc c p
u
V dV f bd
M= + (3.3)
where: '
cf = specified compressive strength of concrete
uV = factored shear force at section
pd = distance from extreme compression fiber to centroid of
prestressed reinforcement (but needs not to be less than 0.80h for
circular sections and prestressed members)
uM = factored moment at section
44
b = web width
When assuming the CE (environmental reduction factor) equal to 1,
the theoretical shear capacity will be 69.8 kN (15.7 kip).
According to Tureyen A. K. and Frosh R. J. the shear capacity can be
derived from the following equation:
= `, 5c f cV f bc (3.4)
where c is the position of the neutral axis at the service conditions, b
is the width of the specimens and `cf the compressive strength of the
concrete. The shear capacity computed according to this approach is
97.4 kN (21.9 kip).
Indeed using the neutral axis at the service conditions may not be
correct when the member is approaching its flexural capacity; hence,
assuming c corresponding to the ultimate conditions of the section,
the shear capacity will be 54.7 kN (12.3 kip).
The prestressing was primarily used to increase the shear capacity of
the slabs rather than the flexural one. In fact, the shear capacity of the
slabs without any prestressing load would have been 30.7 kN (6.9 kip)
and 33.8 kN (7.6 kip) using the ACI and the Tureyen A. K. and Frosh
R. J., respectively, versus 69.8 kN and 97.4 kN with post-tensioned
reinforcement, respectively. Hence, according to ACI, the post-tension
led to an increase in flexure of ~29%, while the shear is more than
doubled.
45
3.4 Specimens Preparation
The specimens were built in the way to reproduce the same
characteristics of the bridge deck that would be constructed in the
field.
The CFRP tendons were housed inside a plastic duct, in order to allow
the post-tensioning operations. Plastic T joints were used to connect
the duct housing the tendons with the duct going out of the specimen
to inject the grout.
Plastic chairs and ties were used to lay the bars and the tendons in
order to have a completely “steel free” structure, in compliance with
the requirements of the Southview bridge project. Fig. 17 shows the
cage details of both specimens.
Fig. 17 - Cage Detail
A total of 21 Electrical Strain Gages (ESG) were used to monitor the
strain at the most critical sections. They were placed on each GFRP
bar (see Fig. 18) and on the compressive face of the slab. Furthermore
Fig. 19 shows the two specimens ready for pouring.
46
Fig. 18 - Strain Gages Detail
Fig. 19 - Reinforcement Cages
The prestressing of the tendons was executed 28 days after the
pouring of the concrete. Fig. 20 and Fig. 21 show the specimens while
curing and after the removal of the formwork.
47
Fig. 20 - Specimen Curing
Fig. 21 - Specimens after Removal of the Formwork
The CFRP bars were prestressed by applying a force of 98 kN (22 kip)
using hydraulic jacks at both ends. This level of prestressing
corresponds to 65% of the ultimate capacity of the CFRP bars. Such
pre-stressing level was chosen in order to respect, after the initial
strain losses (supposed to be 35% of the initial strain of prestress
reinforcement), the creep rupture limits dictated for GFRP bars
according to ACI 440.1R-03 (0.20 times the ultimate guaranteed
48
tensile strength for prestress CFRP reinforcement), as underlined in
the next section.
Initially the prestressing load was applied only to one end of the slab
causing the breaking of the FRP tendons due to the high eccentricity
of the active reinforcement and to the friction between ductwork and
tendons. This problem was solved by applying the prestressing load in
steps of 31 kN (7 kip) from both ends by mean of two hydraulic jacks
(See Fig. 22). The prestressing load was monitored using two load
cells, one for each end of the slab, while the strain was measured
using two electrical strain gages attached on the bar. This solution was
suitable because the increased losses after the release of the tendons
induced by the new pre-stressing system (30%) were less than the
ones assumed for design (35%).
Anchorage System
CFRP Tendon
Steel Frame
Steel PlateSteel Plates Hydraulic Jack
Anchorage SystemsLoad Cell
End of the Slab
a) System Detail b) Field Assembly
Fig. 22 - Prestressing System
The steel wedge anchorage system used to anchor the CFRP bar and
to react against the hydraulic jack was a resin-free three part system
developed at the University of Waterloo, Canada. It included an outer
steel cylinder, a four-piece wedge and an inner sleeve (see Fig. 23).
The inner sleeve was made out of copper/steel and it was deformable.
The four-piece wedge was placed evenly around the inner sleeve and
49
inserted into the outer steel cylinder. The anchorage system was later
secured by tapping the inner sleeve and four-piece wedge into the
outer steel cylinder with a hammer.
Fig. 23 - Steel Wedge Anchorage System
The prestressing of the CFRP bars was followed by their grouting
using a high performance cementitious grout. The cementitious grout
was allowed to cure for seven days after which the anchoring of the
tendons was removed by drilling the CFRP bar inside the barrel (see
Fig. 24). The strain in the slab was monitored during and for 48 hours
after the cutting of the anchoring system: during this time no loss of
compressive strain in the specimens was recorded.
Fig. 24 - Drilling of CFRP Bar after Grout Curing
Outer steel cylinder
Four-piece Wedge
Inner sleeve
CFRP BarOuter steel cylinder
Four-piece Wedge
Inner sleeve
CFRP Bar
50
3.5 Test Setup
Each slab was tested as a continuous member on three supports,
comprising of a 3.6 m (12 ft) and 1.8 m (6 ft) spans. The positions of
the two loading points were chosen such to force flexural and shear
failure for the flexural and shear specimens, respectively.
They were placed at the mid-span for the flexural specimen:
Fig. 25 - Static Scheme for the Flexural Specimen
Given: 1 3.6 (12 )L m ft= Length of the first span
2 1.8 (6 )L m ft= Length of the second span
1 165 (37 )P kN kip= First live load
2 100 (23 )P kN kip= Second live load (higher than the theoretic value)
Solving the hyperstatic scheme (see Fig. 26) it’s possible to derive the
flexural moment acting on the central support (assigned as hyperstatic
unknown):
51
ϕϕ
Fig. 26 - Hyperstatic Scheme
φBL = φB
R
2 21 1 2 2
1 2
( * * )3 *16
P L P LML L
+= −
+ (3.5)
Hence the reactions of each support can be derived: 1
11
13.22P MR kip
L= − = (3.6)
1 22
1 2
462 2P PM MR kip
L L= + + + = (3.7)
23
2
0.82P MR kip
L= − = (3.8)
Finally the equation of flexural moment and its plot (see Fig. 27)
depending on z can be derived:
1 1( ) *M z R z= (3.9) when 10;2L
z ∈
2 1 1( ) ( ) *( )M z M z P z x= − − (3.10) when 1
1;2L
z L ∈
3 2 2 1( ) ( ) *( )M z M z R z L= + − (3.11) when 2
1 1;2Lz L L ∈ +
4 3 2( ) ( ) *[ ( )]tM z M z P z L y= − − − (3.12) when 2
1 ;2 tL
z L L ∈ +
52
0 2 4 6 8 10 12 14 16 18100
50
0
50
100
Axes of Structure [ft]
Mom
ent [
kip*
ft]
64.125
78.938−
M z( )−
180 z
Fig. 27 - Flexural Plot
max ( ) 86.9 * ( 64.1 * )M z kN m kip ft− = − −
max ( ) 107 * (78.9 * )M z kN m kip ft+ =
Regarding the shear test, the loading points were placed 0.9 m (3 ft)
away from the central support and the distance was determined by
performing the following calculations (See Fig. 28):
Fig. 28 - Static Scheme for the Shear Specimen
According to the same procedure used to solve the flexural scheme,
and given:
53
1 222 (50 )P kN kip= First live load
2 222 (50 )P kN kip= Second live load
the shear equations depending on z and the corresponding plot (see
Fig. 29) where derived: 1 1V R= (3.13) when 0;2.7z m∈
2 1 1V V P= − (3.14) when 12.7 ;z m L∈
3 2 2V V R= + (3.15) when 1 1; 0.9z L L m∈ +
4 3 2V V P= − (3.16) when 1 0.9 ; tz L m L∈ +
0 2 4 6 8 10 12 14 16 1840
20
0
20
40
60
Axes of Structure [ft]
Shea
r [ki
p]
44.531
39.063−
V z( )−
180 z
Fig. 29 Shear Plot
max ( ) 198 ( 44.5 )V z kN kip− = − −
max ( ) 173.5 (39 )V z kN kip+ =
The load was applied in cycles of loading and unloading. An initial
cycle for a low load was performed on each specimen to verify that
both the mechanical and electronic equipment was working properly.
54
Loads were applied to 102 x 457 x 25 mm (4 x 18 x 1 in) steel plates
resisting on the slab in order to prevent that the structure could touch
the edge of the support in the case of large deflections (see Fig. 30).
The flexural specimen (See Fig. 31 –a) was instrumented using three
load cells: two of them were placed under the loading points while the
third one was placed under one of the supports in order to determine
the end reaction and therefore the actual distribution of moments in
the slab.
Fig. 30 - Steel Plate Detail
The loads were applied by means of 30 ton (66 kip) hydraulic jacks
reacting against a steel frame. The loading rate was the same for the
two spans until reaching 85 kN (19 kip). After that, the load in the
shorter span was kept constant while the one in the longer one was
increased up to failure. This solution was adopted in order to avoid
shear failure at the central support. Linear Variable Displacement
Transducers (LVDTs) were positioned at the loading points (two for
each loading point) and at the supports in order to record maximum
displacements and support settlements. The strain gages were placed
on each GFRP bar at the location of the loading points and of the
55
central support. In addition, at the same locations, an additional strain
gage was attached on the compressive face of the slab in order to have
an additional backup point while determining the experimental
moment-curvature response of the slab.
For the shear specimen, the number of load cells was reduced to two.
The loads were applied to 102 x 457 x 25 mm (4 x 18 x 1 in) steel
plates using a 100 ton (220 kip) hydraulic jack (see Fig. 31 –b). Two
additional LVDTs were inserted in order to measure also the
maximum displacement which, in this case, was not at the loading
points.
1829
P P =19 kips
1829
LEGEND: LVDT'S
LOAD CELLS
610914
CONCRETE STRAIN GAGES
GFRP STRAIN GAGES
914
Load Cell 3
30 ton Hydraulic Jack
Load Cell 2
1 2
914
Load Cell 1
SUPPORTS
30 ton Hydraulic Jack
a) Test Setup to Determine the Flexural Capacity
1849
P
914
LEGEND: LVDT'S
LOAD CELLS
610914
CONCRETE STRAIN GAGES
GFRP STRAIN GAGES
914
Load Cell 2
Load Cell 1
100 ton Hydraulic Jack
914
SUPPORTS
914
b) Test Setup to Determine the Shear Capacity
Fig. 31 - Test Setup (all dimensions in mm)
56
3.6 Test Results and Discussion
3.6.1 Failure Modes
For the “flexural” specimen, the first flexural crack was observed on
the longer span when the load was approximately 66 kN (15 kip) on
both spans. As the loads were increased, some of the cracks started to
extend diagonally to form shear cracks (see Fig. 32).
Fig. 32 - Shear Cracks on the Flexure Specimen
The maximum forces, 163 kN (37 kip) and 100 kN (23 kip) on long
and short spans, respectively, represented the maximum load
determining concrete crushing on the top of the longer span,
indicating brittle flexural failure (see Fig. 33).
Shear Crack
57
Fig. 33 - Concrete Crushing in the Compressive Zone
This was immediately followed by a sudden shear failure which also
caused the rupture of the CFRP bars due to kinking (see Fig. 34).
Fig. 34 - CFRP Bars Rupture Due to Kinking
About the “shear” specimen, the first crack was observed at a load
approximately of 89 kN (20 kip) in correspondence of the central
support where the moment was maximum (see Fig. 35). As the load
was increased, the newly formed cracks between the central support
and the loading point on the central span started to extend diagonally
58
to form a shear crack. The failure of the specimen occurred for an
applied load equal to 273 kN (61 kip) due to diagonal tension shear.
Fig. 35 - Failure in the Shear Specimen
3.6.2 Discussion of Test Results
Table 2 compares the experimental results with the theoretical
moment and shear capacities of the slabs computed according to ACI
440 provisions and to the equation developed by Tureyen A. K. and
Frosh R. J. Table 2 – Comparison Experimental Theoretical Results
Experimental Theoretical
Specimen Maximum Bending Moment
kN-m (kip-ft)
Maximum Shear Force
kN (kip)
Moment Capacity
kN-m (kip-ft)
Shear Capacity(1) kN (kip)
Shear Capacity (2) kN (kip)
Shear Capacity(3) kN (kip)
Flexure 101.87 (73.7) 99.7 (22.4) Shear 70.2 (51.8) 142.3 (32.0)
97.9 (72.2)
69.8 (15.7) 97.4 (21.9) 54.7 (12.3)
(1) Computed according to ACI 440 provisions (2) Computed according to Tureyen A. K. and Frosh R. J. (3) Computed with a modified Tureyen A. K. and Frosh R. J. considering c at ultimate
From Table 2 it can be observed that for the flexural specimen the
experimental shear results largely overcame the theoretical shear
capacities of the specimen when calculated according to ACI 440. For
the same specimen the Tureyen A. K. and Frosh R. J. approach
Shear Crack
Central Support
59
overestimated the shear capacity when using the neutral axis at the
service conditions. By removing such assumption and taking c
corresponding to the ultimate conditions of the section, a more
conservative approach can be attained as shown in the last column of
Table 2.
The shear specimen presented a shear capacity larger than the
theoretical, demonstrating again the safe approach of ACI 440. For
this specimen the maximum theoretical bending moment determined
from the Tureyen A. K. and Frosh R. J. approach was only half of the
ultimate moment capacity experimented in the test.
Fig. 36 shows the different trend of measured moment compared to
the theoretical one derived solving the hyperstatic sheme (worked out
in the Test Setup), both related to the central support reaction, R2.
0
10
20
30
40
50
60
70
0 10 20 30 40 50 60 70 80 90
Central Support Reaction [kip]
Mom
ent [
kip-
ft]
M measuredM theoretical
Fig. 36 - Mmeasured Vs. Mtheoretical
60
Fig. 37 shows the load deflection diagram. The change of slope in the
diagram corresponds to the cracking of the specimen.
0
20
40
60
80
100
120
140
160
180
0 10 20 30 40 50 60 70Displacement at the Loading Point [mm]
App
lied
Load
[ kN
]
Fig. 37 – Load deflection Diagram for the Longer Span
of the Flexural Specimen
The same change can be observed, for the same specimen at the same
location, in the diagram of Fig. 38, which shows a comparison
between the experimental and the theoretical moment curvature
diagrams for the “flexure” specimen. The experimental diagram was
determined on the longer span in correspondence of the maximum
bending moment. Compared with the experimental curve, the
theoretical moment curvature diagram showed a lower slope leading
to overestimate the deflection of the bridge.
61
0
20
40
60
80
100
120
140
160
0 5000 10000 15000 20000 25000 30000 35000 40000
Curvature x106 [1/m]
Mom
ent [
kN-m
]
ExperimentalTheoretical
Theoretical Cracking Moment
Theoretical Ultimate Moment
Fig. 38 – Comparison Between Experimental and
Theoretical Moment-Curvature Diagrams
3.7 Conclusions
On the basis of the experimental investigation, it can be concluded
that GFRP bars as passive and CFRP bars as active internal
reinforcement could represent a feasible solution replacing the steel
reinforcement of concrete slab bridges. The prestressing material is
mostly needed for shear purpose rather than for flexure.
According to ACI 440, the shear capacity increases from 30.7 kN (6.9
kip) with mild reinforcement to 69.8 kN (15.7 kip) adding the post-
tensioned reinforcement, while the flexural capacity increases from
76.0 kN-m (55 kip-ft) to 97.9 kN-m (72.2 kip-ft).
Finally, the tools provided by ACI 440 provide a safe design at both
service and ultimate conditions.
62
4 SOUTHVIEW BRIDGE DESIGN
4.1 Introduction
In the following section, the analytical procedures used in the
widening of the Southview Bridge, located in Rolla, Phelps County,
MO, are summarized. The expansion phase included the removal of
the existing curb from the existing reinforced concrete deck to allow
the construction of two new structures adjacent to the original deck in
order to extend the width of the bridge from 3.9 m (13 ft) to 11.9 m
(39 ft). The curb-to-curb width of the resulting bridge is 9.1 m (30 ft).
The two new structures consist of a FRP prestressed/reinforced
concrete deck and a steel reinforced concrete deck as shown in Fig.
39.
WEARING SURFACE5 cm ASPHALT
EXISTING DECKCURB FROM
REMOVE EXISTING
BARRIER WALLCONCRETE
REINFORCED
SIDEWALK (1.5m)NEW CONCRETE
CONCRETE DECKREINFORCED
STEEL
FRP REINFORCED CONCRETE DECK EXISTING REINFORCED CONCRETE
4.3 m1.5 m
12 m2 m3.9 m6 m
FRP REINFORCEDCONCRETE
BARRIER WALL
Fig. 39 - Bridge T0530
The new structure is a box culvert. It consists of a steel reinforced
concrete slab about 25.4 cm (10 in.) thick, as depicted in Fig. 40. The
slab deck is continuous over three intermediate reinforced concrete
vertical walls, and the overall length of the bridge is roughly 12 m (40
ft). The new deck was built on conventional reinforced concrete (RC)
walls. The number of walls is identical to the existing number.
63
Fig. 40 - View of the Existing Bridge
The objective of this section is to provide the structural analysis of the
new FRP concrete bridge deck based on the AASHTO HS20-44
design truck (a detailed analysis is presented in APPENDIX B), and
provide calculations for its design using a combination of non-
traditional corrosion-resistant composites materials.
4.2 Assumptions
The following assumptions are made:
a) Nominal properties for FRP reinforcing material are taken from
the manufacturer published data and considered as initial
guaranteed values to be further reduced to take into account the
environmental reduction factors as given in ACI 440.1R-03
(ACI 440 in the followings);
b) Load configurations are consistent with AASHTO
Specifications;
c) Design carried out according to ACI 440; and
d) Effects due to the skew are neglected.
64
4.3 Structural Analysis
4.3.1 Load Combinations
For the structural analysis of the bridge the definitions of the design
truck and design lane are necessary. This will be addressed in the next
paragraph.
Ultimate values of bending moment and shear force are obtained (in
the following Summary of the Analysis) by multiplying their nominal
values by the dead and live load factors and by the impact factor
according to AASHTO Specifications as shown in Eq. (4.1):
[ ]1.3 1.67( )u d D L Iω β= + + (4.1)
where D is the dead load, L is the live load, βd=1.0 as per AASHTO T
able 3.22.1A, and I is the live load impact calculated as follows: 50 50 0.37 0.30125 10 125
IL
= = = >+ +
(4.2)
and L=3.0 m (10 ft) represents the span length from center to center of
support. The impact factor should not be larger than 0.30, and
therefore the latter value is assumed for the design.
4.3.2 Design Truck and Design Lanes
The analysis of the bridge is carried out for an HS20-44 design truck
load having geometrical characteristics and weight properties shown
in Fig. 41.
65
36 k
N HS20
Variable
4.3 m-9.1 mSpacing
1.8
m
Parapet
30.5
cm
Cle
aran
ce
4.3 m
Parapet
142
kN
142
kN
Fig. 41 - Truck Load on the New Deck
Two loading conditions are required to be checked as depicted in Fig.
42. The HS20-44 design truck load (Fig. 42-a) has a front axle load of
35.6 kN (8.0 kips), second axle load, located 4.3 m (14.0 ft) behind the
drive axle, of 142.3 kN (32.0 kips), and rear axle load also of 142.3 kN
(32.0 kips). The rear axle load is positioned at a variable distance,
ranging between 4.3 m (14.0 ft) and 9.1 m (30.0 ft). Given the specific
bridge geometry, the worst loading scenario is obtained for the
minimum spacing of 4.3 m (14.0 ft) between the two rear axles. The
design lane loading condition consists of a load of 9.3 kN/m (640
lbs/ft), uniformly distributed in the longitudinal direction with
concentrated loads so placed on the span as to produce maximum
stress. The concentrated load and uniform load are considered to be
applied over a 3.0 m (10ft) width on a line normal to the center line of
the lane. The intensity of the concentrated load is represented in Fig.
42-b for both bending moments and shear forces. This load shall be
placed in such positions within the design lane as to produce the
maximum stress in the member.
66
142 kN
4.3 m TO 9.1 m4.3 m
36 kN 142 kN
a) Design Truck (HS20-44)
116 kN FOR SHEAR80 kN FOR MOMENT
9.3 kN/m OVER A 3 m WIDTHTRANSVERSELY UNIFORMLY DISTRIBUTED
b) Design Lane
Fig. 42 - Loading Conditions
4.3.3 Deck Analysis
The deck slab is considered to be a one-way slab system. The width of
the slab, E, to be used in the analysis is provided by AASHTO
(Section 3.24.3.2) as follows: 4 0.06 4 0.06(10 ) 1.4 ( 4.6 )E S ft m ft= + = + = = (4.2)
where S represents the slab length assumed equal to 3.0 m (10 ft).
4.3.4 Flexural and Shear Analysis
Fig. 43 shows a lateral view of the bridge deck when an HS20-44
design truck moves from the right to the left as the value of x1
increases from 0 to L, where L represents the total bridge length.
67
Fig. 43 - Design Truck on the Girder
The values of Pi (i=a,b,c) represent the wheel load as defined by
AASHTO (~18, 71 and 71 kN, namely 4, 16 and 16 kips,
respectively).
Table 3 summarizes values reported in Fig. 43 and reports parameters
used in the calculation of the moment and shear due to dead load. The
analysis and design are carried out for a unit-width strip (~30 cm, 12
in) of slab deck.
Table 3 – Parameters for Girder Analysis
First Span Length, L1 2.89 m (9.49 ft) Second Span Length, L2 3.38 m (11.10 ft) Third Span Length, L3 3.30 m (10.82 ft) Fourth Span Length, L4 2.85 m (9.35 ft) First Load, Pa 17.8 kN (4 kip) Second Load, Pb 71.2 kN (16 kip) Third Load, Pc 71.2 kN (16 kip) Concrete Unit Weight, γc 24 kN/m3 (150 p/f3) Asphalt Unit Weight, γa 17.3 kN/m3 (108 p/f3) Slab Unit-Width, b 30.5 cm (12 in) Slab Height, h 25.4 cm (10 in) Asphalt Thickness, t 15.2 cm (6 in)
As the design truck moves from the right to the left side of the bridge,
fourteen different loading conditions are defined, as shown in Fig. 44.
68
Fig. 44 - Design Truck: Possible Loading Conditions
Three more loading conditions related to the design lane will be
analyzed as reported in Fig. 45. The first loading condition is related
to the maximum positive moment, the second one to the maximum
negative moment, and the third one to the maximum shear.
Fig. 45 - Design Lane: Possible Loading Conditions
69
Fig. 46 shows the moment diagram as the design truck moves on the
bridge following the fourteen loading phases highlighted in Fig. 44.
Fig. 47 shows the moment diagram due to the slab and asphalt layer
self-load. Both diagrams are drawn for a ~30 cm (12 in) strip-width.
0 1.67 3.33 5 6.67 8.33 10 11.67 13.33 1540
30
20
10
0
10
20
30
Axes of the Bridge [m]
Mom
ent [
kN-m
/m]
Fig. 46 - Unfactored Bending Moment Diagrams Due to Live Load
70
0 10 20 30 402
1
0
1
2
Axes of the Bridge [ft]
Mom
ent [
k-ft
/ft]
Fig. 47 - Unfactored Bending Moment Diagrams Due to Dead Load
Ultimate values are obtained by taking into account the maximum
positive and negative moment from Fig. 46 with the load factors
summarized in Eq.(4.1), and by adding the corresponding moment due
to the dead load (Fig. 47) with the load factors taken from the same
equation.
The same diagrams can be drawn for shear as reported in Fig. 48 and
Fig. 49 for live and dead load, respectively, and for a ~30 cm (12 in)
wide unit-strip.
71
0 5 10 1515
10.63
6.25
1.88
2.5
6.88
11.25
15.63
20
Axes of the Bridge [m]
Shea
r For
ce [k
N]
Fig. 48 - Unfactored Shear Diagrams Due to Live Load
0 10 20 30 401.5
1
0.5
0
0.5
1
1.5
Axes of the Bridge [ft]
Shea
r [ki
ps/ft
]
Fig. 49 - Unfactored Shear Diagrams Due to Dead Load
It has to be underlined that both moment and shear diagrams due to
the dead load have been calculated using a simplified structure where
the distances between supports were assumed to be equal to 3.0 m (10
ft).
72
Similarly, moment and shear diagram related to the design lane
loading condition can be found as depicted in Fig. 50 for the three
structures shown in Fig. 45. The design has been performed for a ~30
cm (12 in) unit strip.
0 5 10 15 20 25 30 35 40 455
4
3
2
1
0
1
2
Axes of the Bridge [ft]
Mom
ent [
k-ft/
ft]
Maximum Positive Moment
0 5 10 15 20 25 30 35 40 454
3
2
1
0
1
2
3
4
Axes of the Bridge [ft]
Mom
ent [
k-ft/
ft]
Maximum Negative Moment
73
0 5 10 15 20 25 30 35 40 453
2.5
2
1.5
1
0.5
0
0.5
1
Axes of the Bridge [ft]
Shea
r [ki
ps/ft
]
Maximum Shear
Fig. 50 - Unfactored Moment and Shear Diagrams
Due to Design Lane Analysis
4.3.5 Summary of the Analysis
Bending moments and shear forces are summarized in Table 4.
Columns (1) and (3) represent the factored coefficient to be applied to
dead and live load, respectively. Columns (2) and (4) show both
unfactored dead and live load moment and shear, respectively, as
taken from the previous figures.
74
Table 4 - Moment and Shear per Unit Strip (Live and Dead Load)
Since the design truck analysis produces the highest stresses on the
slab, only moment and shear related to this analysis will be
considered.
Fig. 51 shows the envelope of the bending moment diagram obtained
when the truck travels on the bridge following all the loading
conditions summarized in Fig. 44.
Fig. 51 - Bending Moment Envelopes (kN-m/m)
Dead Load Live Load Ultimate Loading Conditions
Moment and Shear (1) (2) (3) (4) (5)=(1)(2)+(3)(4)
M+ [kN-m/m]
6.27 (1.38 k-ft/ft)
29.69 (6.55 k-ft/ft)
92.09 (20.3 k-ft/ft)
M- [kN-m/m]
8.69 (1.92 k-ft/ft)
23.52 (5.19 k-ft/ft)
77.56 (17.1 k-ft/ft) Design Truck
Shear [kN /m]
4.92 (1.09 kip/ft)
15.42 (3.40 kip/ft)
160.53 (11.0 kip/ft)
M+ [kN-m/m]
6.27 (1.38 k-ft/ft)
18.21 (4.01 k-ft/ft)
59.41 (13.1 k-ft/ft)
M- [kN-m/m]
8.69 (1.92 k-ft/ft)
17.29 (3.81 k-ft/ft)
59.88 (13.2 k-ft/ft)
Design Lane
Shear [kN /m]
(1.3)
4.92 (1.09 kip/ft)
(1.3)(1.67)(1.3)
12.47 (2.75 kip/ft)
134.25 (9.2 kip/ft)
75
4.3.6 Deflections
The worst loading condition scenario for calculating the slab deck
deflections is reported in Fig. 52. Two concentrated loads simulating
the truck wheels are applied at mid-span of the second and fourth
span. For this analysis, the span lengths have been assumed equal to
30 m (10 ft). To further simplify the analysis, the fourth span of Fig.
52-a could be separately analyzed as depicted in Fig. 52-b. Only the
latter approach is presented here, and the obtained results need to be
considered as an upper bound limit.
a)
b)
∆ LL
PP
P
Fig. 52 - Bridge Deflection Analysis (Live Load)
The deflection due to the dead load (as depicted in Fig. 53) needs to
be added to the live load deflections of Fig. 52.
∆ DL
ωd
l Fig. 53 - Bridge Deflection Analysis (Dead Load)
76
The two settlements can be written as follows: 3
4
8384
0.0065
LLs s
dDL
s s
PE I
E Iω
∆ =
∆ =
l
l (4.3)
where P= 1.3* 71.2 kN (1.3*16 kips) is the wheel load increased by
the impact factor, ωd ~2.6 kN/m (0.179 k/ft) represents the dead load of
the bridge, and Es and Is are the modulus of elasticity of the concrete
and the moment of inertia of the cross-section of the slab,
respectively. The value of the moment of inertia will change
depending on whether the cross-section can be considered cracked or
uncracked.
4.4 Design
4.4.1 Assumptions
The design of the internal FRP reinforcement is carried out according
to the principles of ACI 440. The properties of concrete, steel and FRP
bars used in the design are summarized in Table 5. The reported FRP
properties are guaranteed values.
77
Table 5 - Material Properties
Concrete Compressive
Strength f`c (MPa)
FRP Internal
Reinforcement Type
FRP Bar Size
FRP Tensile Strength f*
fu (MPa)
FRP Tensile Strain ε*
fu
FRP Modulus
of Elasticity Ef (GPa)
f9 (#3) 758 (110 ksi) 0.018 40.8
(5,920 ksi)
f13 (#4) 689 (100 ksi) 0.017 40.8
(5,920 ksi) f19 (#6) 621
(90 ksi) 0.015 40.8 (5,920 ksi)
GFRP
f22 (#7) 586 (85 ksi) 0.014 40.8
(5,920 ksi)
41.4 (6,000 psi)
CFRP f19 (#3) 2068 (300 ksi) 0.017 124.1
(18,000 ksi)
Material properties of the FRP reinforcement reported by
manufacturers, such as the ultimate tensile strength, typically do not
consider long-term exposure to environmental conditions, and should
be considered as initial properties. FRP properties to be used in all
design equations are given as follows (ACI 440): *
*
fu E fu
fu E fu
f C f
Cε ε
=
= (4.4)
where ffu and εfu are the FRP design tensile strength and ultimate strain
considering the environmental reduction factor (CE) as given in Table
7.1 (ACI 440), and f*fu and ε*
fu represent the FRP guaranteed tensile
strength and ultimate strain as reported by the manufacturer (see Table
5). The FRP design modulus of elasticity is the average value as
reported by the manufacturer.
78
4.4.2 Slab Design
4.4.2.1 Flexural Design
The flexural design of a FRP reinforced concrete member is similar to
the design of a steel reinforced concrete member. The main difference
is that both concrete crushing and FRP rupture are potential
mechanisms of failure. As an FRP reinforced concrete member is
usually less ductile than the correspondent steel reinforced concrete
member, the strength reduction factor, φ, needs to be revisited
according to Eq. (4.5) (ACI 440):
0.50
1.420.70 1.4
f fb
ffb f fb
fb
f fb
if
if
if
ρ ρ
ρφ ρ ρ ρ
ρ
ρ ρ
≤= < < ≥
(4.5)
where ρf is the FRP reinforcement ratio and ρfb represents the FRP
reinforcement ratio producing balanced failure condition.
Fig. 54 shows the trend of the strength reduction factor as a function
of both concrete compressive strength and the number of GFRP bars
used.
79
2000 4000 6000 80000.4
0.5
0.6
0.7
0.8
#[email protected]"f`c (psi)
Phi F
acto
r as p
er A
CI 4
40
F19@15 cm 19@12 cm [email protected] cm F
Fig. 54 - Strength Reduction Factor
By increasing the concrete compressive strength, the value of the φ
factor changes from 0.7 to 0.5 as the failure mode moves from
concrete crushing to FRP rupture.
Fig. 55 shows the nominal and factored flexural capacities of the
bridge deck as a function of the concrete compressive strength and the
number of FRP bars installed (same legend of Fig. 54).
2000 4000 6000 800020
30
40
50
60
#[email protected]"f'c [psi]
Mn
[k-ft
/ft]
2000 4000 6000 8000
15
20
25
30
35
#[email protected]"f'c [psi]
phiM
n [k
-ft/f
t]
a) Nominal b) Factored Fig. 55 - Flexural Capacities of the Bridge
Table 6 summarizes the properties and the flexural capacity of the
bridge deck corresponding to a cross section with a f19 (#6) Aslan
80
100 GFRP as mild reinforcement at ~15 cm (6 in) center-to-center.
Prestressing FRP tendons made out of f9 (#3) Aslan 200 CFRP bars
are installed at ~23 cm (9 in) center-to-center and post-tensioned after
the concrete deck is cured. Calculations are carried out for a ~30 cm
(12 in) unit strip.
Table 6 - Slab Geometrical Properties and Internal FRP Reinforcement
Overall Height
of the Slab,
h
Area of Tension GFRP Reinforcement,
Af
GFRP Effective Depth,
d
Area of Prestressed
CFRP Tendons,
Ap
CFRP Effective Depth,
dp
Flexural Capacity
φMn
[cm] [cm2/m] [cm] [cm2/m] [cm] [kN-m/m] 25.4
(10 in) 19.39
(0.916 in2/ft) 20.6
(8.125 in) 2.13
(0.101 in2/ft) 17.8
(7.0 in) 92.8
(20.5 k-ft/ft)
The above flexural capacity is related to both positive and negative
moment regions, and it is larger than the required demand previously
shown in Table 4.
The prestress strain in the tendons is equal to 65% of their ultimate
strain. All CFRP losses are assumed to be 30% of the initial
prestressing strain.
4.4.2.2 Shear Design
The shear capacity of FRP reinforced concrete sections is calculated
following the principles of ACI 440. Particularly, the concrete
contribution to the shear capacity, Vc,f, can be expressed as follows:
,f f
c f cs s
A EV V
A E= (4.6)
81
where the ratio (AfEf/AsEs) takes into account the axial stiffness of the
FRP reinforcement as compared to that of steel reinforcement, and Vc
is given as follows (ACI 318-99):
'(0.6 700 )u pc c p
u
V dV f bd
M= + (4.7)
As reported in Eq. (4.6) can be found by determining the area of steel
reinforcement required to match the factored FRP flexural capacity,
φMn. Table 7 summarizes the steel and GFRP design and the assumed
value of As.
Table 7 - Steel and GFRP Flexural Design of the Deck (No Prestress Used)
Description Steel Design GFRP Design Deck Slab, h 25.4 cm (10 in) 25.4 (10 in) Deck Width, b 30.5 cm (12 in) 30.5 (12 in) Effective Depth, d 20.6 cm (8.125 in) 20.6 (8.125 in)
Reinforcement Area f13@25cm=11.2cm2/m (#4@10”=0.528 in2/ft)
f19@11cm=25.3 cm2/m (#[email protected]”=1.195 in2/ft)
Factored Flexural Capacity,φMn
94.3 kN-m/m (20.8 k-ft/ft)
93.0 kN-m/m (20.5 k-ft/ft)
The concrete contribution to the shear capacity of the member yields:
11.0(7 /12)0.6 6000 700 (12)(7) 379.4 / ( 26.0 / )17.1cV kN m kips ft = + = =
(4.8)
and from Eq. (4.6):
,(1.195)(5,920) 26.0 175 / ( 12.0 / )
(0.528)(29,000)c fV kN m kips ft= = = (4.9)
Finally, the factored shear capacity is φVn=φVc,f=0.85*175=148.9
kN/m (=10.2 kips/ft). This value is slightly smaller than the shear
demand Vu=160.5 kN/m (=11.0 kips/ft, see Table 4). The value can be
82
accepted because the analysis has been performed on the centerline of
the support, while it is allowed to evaluate both Vu and Mu at a cross
section flush with the vertical wall representing the support. In this
case, Vu will not change substantially, while Mu will have an
appreciable lower value. Therefore (while keeping Vudp/Mu<1), Vc
expressed by Eq. (4.8) will increase.
Consistent with section 3 it is to be noted that the prestressing force is
most needed for shear purpose rather than flexure. In fact, if the
prestressing action was not considered, the concrete contribution to
the shear capacity would have been Vc=220.4 kN/m (=15.1 kips/ft),
and the final factored shear capacity of the bridge would have been
equal to φVn=86.09 kN/m << 148.9 kN/m (φVn=5.9 kips/ft << 10.2
kips/ft); therefore the post-tensioning allowed to increase the shear
capacity of the slab more than 40%.
As an alternative approach to the shear capacity of the bridge deck,
the following equation (Tureyen A. K. and Frosh R. J., 2003), now
under consideration for adoption by ACI Committee 440, could be
used:
`, 5c f cV f bc= (4.10)
where c is the position of the neutral axis at service. This approach is
justified by the parametric analysis laid out in the next Fig. 56.
83
Fig. 56 - Rationale for Proposed Shear Strength
The values of c can be determinate using the approach shown in
paragraph 4.4.3.1 afterwards:
5 6000 12 3.295= 68.10kN(=15.31 kip)cV = ⋅ ⋅ ⋅ (4.11)
Finally, the factored shear capacity is φVn=φVc,f=0.85(213.2) =189.9
kN/m (0.85(14.61)=13.01 kip/ft) larger than Vu=160.5 kN/m (11.0
kip/ft).
84
4.4.2.3 Temperature and Shrinkage Reinforcement
GFRP reinforcement perpendicular to the main flexural reinforcement
is required to control both crack width and shrinkage of the concrete.
The equation adopted by ACI 440 can be written as follows:
,60,0000.0018 0.0036s
f tsfu f
Ef E
ρ = ≤ (4.12)
where ffu (psi) is defined in Eq.(4.4), and Es an Ef are the elastic
moduli of steel and GFRP, respectively. The area of GFRP
reinforcement deemed necessary for temperature and shrinkage can be
expressed as follows:
, ,f ts f tsA bhρ= (4.13)
and it is subdivided in two layers, each close to one of the concrete
surfaces. In the previous equation, b and h represent unit width and
height of the cross-section, respectively (b=30.5 cm, 12 in, and
h=25.4 cm, 10 in).
It is suggested to use a f13 (#4) Aslan 100 GFRP bar spaced at ~30
cm (12 in) center-to-center, as depicted in Fig. 57 representing a cross
sectional view of the bridge deck.
Fig. 58 shows a longitudinal view of the prestressing CFRP tendons.
85
F
F
19 ASLAN 100 GFRP AT 15 cm ON CENTERS (G1)
9 ASLAN 200 CFRP (C1)PRESTRESSING TENDONSSPACED 23 cm ON CENTERS
TEMP. & SHRINK.13 ASLAN 100 GFRP
AT 30 cm ON CENTERS
19 ASLAN 100 GFRPAT 15 cm ON CENTERS
(G2)
(G3) AND (G4)
9 ASLAN 100 GFRPCHAIRS (G5)
FF
F
Fig. 57 - Bridge Internal FRP Reinforcement: Section at Mid-Span
Fig. 58 - CFRP Prestressing Tendons
a) Longitudinal View
F9 ASLAN 200 CFRPPRESTRESSING TENDONSSPACED 23 cm ON CENTERS
A
A
b) Detail
86
4.4.3 Serviceability
Unlike steel reinforced concrete sections, members reinforced with
FRP bars have relatively small stiffness after cracking. Therefore,
serviceability requirements like crack width and long-term deflection
need to be specifically tailored for composite structures as highlighted
in ACI 440. In the following two sections, both crack width and long-
term deflection checks will be presented.
4.4.3.1 Crack Width
The service moment per unit strip of slab deck can be calculated
starting from the data of Table 4 as follows:
1.3 1.381 (1.3)(6.549) 44 / ( 9.9 / )s DL LLM M M kN m m k ft ft= + = + = − = − (4.14)
where MDL and MLL represent moment due to dead and live load,
respectively.
Crack width of FRP reinforced flexural members can be expressed as
suggested by ACI 440 as follows:
32200b f c
f
w k f d AE
β= (4.15)
where β is the ratio of the distance from the neutral axis to extreme
tension fibre to the distance from the neutral axis to the center of
tensile reinforcement, kb is a bond-dependant coefficient equal to 1.2,
ff represents the stress at service in the FRP, dc is the thickness of the
concrete cover measured from extreme tension fiber to the center of
the bar, A is the effective tension area of concrete defined as the area
87
of concrete having the same centroid as that of tensile reinforcement,
divided by the number of bars (N=2), and Ef is the modulus of
elasticity of FRP. The above mentioned terms, can be written as
follows:
1
1
2c
c
h cd c
d h dd bAN
ββ
β−
=−
= −
=
(4.16)
Assuming a cracked concrete cross-section at service as shown in Fig.
59, the stress in the GFRP, ff =Ef ef, can be calculated by solving the
following system of equations:
c c p p p f f f pi
c c p p p p f f f s pi
pc
p
c f
1 E bc A E A E N21 h c h hE bc A E d A E d M M2 2 3 2 2
c d c
c d c
ε ε ε
ε ε ε
εε
ε ε
− − =
− + − + − = − = − = −
(4.17)
where Mpi and Npi represent the axial load and the bending moment to
the centroid of the section, induced by the post-tensioning of the
CFRP bars.
By solving Eq. (4.17) and finding the unknown fε , the following
value for the stress in the GFRP can be evaluated as follows, after :
f f ff E 13.58MPa( 1.97 ksi)ε= = = (4.18)
88
Fig. 59 - Stress and Strain at Service
The crack width calculated with Eq. (4.15) yields w=0.086mm
(0.0034 in) which is smaller than the allowed values suggested by ACI
440 and equal to 0.51mm (0.02 in).
4.4.3.2 Long-Term Deflections
Based on the conservative deflection analysis carried out on Section
B.3.3, the long-term deflection can be calculated as suggested by ACI
440 as follows:
( 0.2 )LL DL LLλ∆ = ∆ + ∆ + ∆ (4.19)
where λ=1.2 represents the multiplier for additional long-term
deflection as recommended in ACI 440. Assuming the concrete cross-
section uncracked because of the presence of the prestressing tendons,
both concrete modulus of elasticity and moment of inertia can be
expressed as follows: '
3
57000
12
cE f
bhI
=
= (4.20)
where b~30 cm (=12 in) for dead load analysis, and b=E=1.4 m (4.6
ft) for live load analysis. Eq. (4.19) yields to ∆=1.30 mm (0.051 in)
89
smaller than the suggested AASHTO value of l/800=3.81mm (0.15
in).
4.4.3.3 Slab Creep Rupture and Fatigue
To avoid creep rupture of the FRP reinforcement under sustained
loads, the stress level in the FRP bar should be limited to the value
suggested in ACI 440. Specifically, when GFRP reinforcement is
used, the stress limit has been set to be equal to 0.20 ffu ~87 MPa (12.6
ksi). The stress at service in the FRP can be found as:
(9.9)(12) 114.5 ( 16.6 )0.9430.916 8.125
3 3
sf
f
Mf MPa ksicA d
= = = = − −
(4.21)
Once again, because the bridge is mostly uncracked at service due to
the prestress, the above findings are conservatives, and the value
obtained from Eq. (4.21) can be considered acceptable.
4.5 Load Rating
Bridge load rating calculations provide a basis for determining the
safe load carrying capacity of a bridge. According to the Missouri
Department of Transportation (MoDOT), anytime a bridge is built,
rehabilitated, or reevaluated for any reason, inventory and operating
ratings are required using the Load Factor rating. All bridges should
be rated at two load levels, the maximum load level called the
Operating Rating and a lower load level called the Inventory Rating.
The Operating Rating is the maximum permissible load that should be
allowed on the bridge. Exceeding this level could damage the bridge.
90
The Inventory Rating is the load level the bridge can carry on a daily
basis without damaging the bridge.
The Operating Rating is based on the appropriate ultimate capacity
using current AASHTO specifications (AASHTO, 1996). The
Inventory Rating is taken as 60% of the Operating Rating.
The vehicle used for the live load calculations in the Load Factor
Method is the HS20 truck. If the stress levels produced by this vehicle
configuration are exceeded, load posting may be required.
The tables below show the Rating Factor and Load Rating for this
bridge. The method for determining the rating factor is that outlined
by AASHTO in the Manual for Condition Evaluation of Bridges
(AASHTO, 1994). Equation (4.22) was used:
( )1
2 1C A DRF
A L I−
=+
(4.22)
where: RF is the Rating Factor, C is the capacity of the member, D is
the dead load effect on the member, L is the live load effect on the
member, I is the impact factor to be used with the live load effect, A1
is the factor for dead loads, and A2 is the factor for live loads. Since
the load factor method is being used, A1 is taken as 1.3 and A2 varies
depending on the desired rating level. For Inventory rating, A2 = 2.17,
and for Operating Rating, A2 = 1.3.
To determine the rating (RT) of the bridge Equation (4.23) was used:
( )RT RF W= (4.23)
In the above equation, W is the weight of the nominal truck used to
determine the live load effect.
91
For the Southview Bridge, the Load Rating was calculated for a
number of different trucks, HS20, H20, 3S2, and MO5. The different
ratings are used for different purposes by the bridge owner. For each
of the different loading conditions, the maximum shear and maximum
moment were calculated. Impact factors are also taken into account
for Load Ratings. This value is 30% for the Southview Bridge. The
shear and moment values for the deck are shown in below in Table 8.
Table 8 - Maximum Shear and Moment due to Live Load
Truck Maximum Shear (kN)
Maximum Moment (kN-m)
Maximum Shear with
Impact (kN)
Maximum Moment
with Impact (kN-m)
HS20 15.1 (3.40 kips)
9.06 (6.55 k-ft)
19.66 (4.42 kips)
11.78 (8.52 k-ft)
MO5 14.7 (3.30 kips)
6.47 (4.68 k-ft)
19.66 (4.29 kips)
8.41 (6.08 k-ft)
H20 12.7 (2.86 kips)
5.93 (4.29 k-ft)
14.55 (3.72 kips)
7.70 (5.57 k-ft)
3S2 13.0 (2.93 kips)
5.89 (4.26 k-ft)
16.95 (3.81 kips)
7.66 (5.54 k-ft)
Table 9 below gives the results of the Load Rating pertaining to
moment and Table 10 shows the results for shear. All calculations for
the load rating are located in APPENDIX B.
Table 9 - Rating Factor for the New Slab (Bending Moment)
Truck Rating Factor (RF)
Rating (RT) (Tons)
Rating Type
HS20 1.793 64.5 Operating HS20 1.074 38.7 Inventory MO5 2.482 89.4 Operating H20 2.330 46.6 Posting 3S2 2.345 85.9 Posting
92
Table 10 - Rating Factor for the New Slab (Shear)
Truck Rating Factor (RF)
Rating (RT) (Tons)
Rating Type
HS20 2.152 77.5 Operating HS20 1.289 46.4 Inventory MO5 2.217 81.2 Operating H20 2.202 44.0 Posting 3S2 2.148 78.7 Posting
Since the factors RF are greater than 1 then the bridge does not need
to be load posted. In addition, from Table 9 and Table 10 the
maximum operating and inventory load can be found as 64.5T and
38.7T respectively.
4.6 Southview Bridge Drawings
The following drawings show the main characteristics of the
Southview bridge deck, consistent with the previously tested
specimens and with the design presented in this section.
Drawing 1 and Drawing 2 show a plan strip view with the transverse
and longitudinal section of the deck, respectively. Drawing 3 details
profile, section, top and bottom view of the slab; FRP reinforcement
details at the midspan and at the supports are also shown.
93
plastic ductwork
safety ductwork
SOUTHVIEW DRIVE BRIDGEFRP post-tensioned slab
19 ASLAN 100 GFRP (G1,G2)
13 ASLAN 100 GFRP(G3,G4)
A A
Plan Strip15
91
30
30
23
safety ductwork
1.5 m long bolsters
CHAIRS (G5)140 9 ASLAN 100 GFRP
AT 15 cm ON CENTERS
Section A-A40 19 ASLAN 100 GFRP (G1)
AT 30.5 cm ON CENTERS
SPACED 23 cm ON CENTERS
13 ASLAN 100 GFRP(G3,G4)
PRESTRESSING TENDONS26 9 ASLAN 200 CFRP (C1)
9 ASLAN 200 CFRP (C1)F
F
F
F
F
F
AT 15 cm ON CENTERS
F
40 19 ASLAN 100 GFRP (G1)F
Drawing 1 - Section A-A
Plan Strip
12.420.41 0.41
0.412.853.303.382.890.41
9 ASLAN 200 CFRP (C1)
622
F
F
F
F
F43 13 ASLAN 100 GFRP AT 30.5 cm ON CENTERS (G4)
622
43 13 ASLAN 100 GFRP AT 30.5 cm ON CENTERS (G3)
3019 ASLAN 100 GFRP(G1,G2)
1.5 m LONG BOLSTERS AT 60 cm
CHAIRS AT 3'140 9 ASLAN 100 GFRP (G5)
section B-B
25
BB
Drawing 2 - Section B-B
94
6.35
21.6421.64
6.31
13.23
0.41 0.41
0.410.41
Bottom chairs
UP CHAIRS (G5)
3.00
0.61
0.038
0.178
0.038
0.254
chairs detail
22.86
15.24
0.254
0.038
0.178
0.0380.038
0.177
1.22
0.254
section 2-2
Bottom chairsbottom chairs
13 GFRP (G4)
13 GFRP (G3)
n.8 19 GFRP (G1)
n.8 19 GFRP (G2)
n.5 9 CFRP (C1)
section 1-1
up chairs (G5) up chairs (G5)
safety ductwork
45.7245.72
safety ductwork
wal
l axis
wal
l axis
plastic ductwork
plastic ductwork
plastic ductwork
0.06
0.25
1.22
22.86
15.24
0.61
0.039
2
2
1
1
n.22 13 GFRP (G4)n.21 13 GFRP (G3)
n.6 19 GFRP (G2)n.4 9 CFRP (C1)
Bottom reinforcment plan Top reinforcement plann.6 19 GFRP (G1)n.4 9 CFRP (C1)
PLAN - 3 feet slab's strip
43 13 ASLAN 100 GFRP AT 30.5 cm ON CENTERS (G4)
(L=13.7 m)
(L=13.1 m)
(L=13.1 m)
DETAIL - FRP Reinforcement
9 ASLAN 200 CFRP PRESTRESSING TENDONS AT 23 cm ON CENTERS (C1)
wal
l axis
SECTION - deck's FRP reinforcement
19 ASLAN 100 GFRP AT 15 cm ON CENTERS (G2)
43 13 ASLAN 100 GFRP AT 30.5 cm ON CENTERS (G3)
19 ASLAN 100 GFRP AT 15 cm ON CENTERS (G1)
PROFILE - Southview Drive Bridge
2.853.303.382.89
12.42
F
F
F
F
F
F F
F F
F F
F
F
F
F
F
Fn.8 19 GFRP (G1)
13 GFRP (G3)F
F 13 GFRP (G4)
n.8 19 GFRP (G2)F
n.5 9 CFRP (C1)F Drawing 3 - Ultimate Design
95
5 SOUTHVIEW BRIDGE DECK INSTALLATION
5.1 Introduction
This section details the installation of Southview bridge deck,
conducted by Master Contractors LLC, overseen and documented by
the author as part of this thesis.
As outlined in the first section, the slab is 25 cm (10 in) thick, 12 m
(40 ft) long and 6 m (19.83 ft) wide. It is supported by three
intermediate reinforced concrete vertical walls. The three span lengths
are, from North to South, 2.89 m (9.49 ft), 3.38 m (11.10 ft) and 3.30
m (10.82 ft), respectively, on centers.
The material and construction specifications are detailed in Appendix
C.
5.2 Pre-construction Meetings
In order to ensure a successful completion of the project, extensive
planning and collaboration was required between the different entities
involved in the construction: the City of Rolla in charge of the
construction of walls and abutments expansion and of the post-
tensioning system which was optimized for the particular field
application as part of a cooperation between University of Missouri
Rolla (UMR) and the Rolla Technical Institute (RTI) in the person of
Mr. Max Vath.
A first meeting was held on Tuesday, July 27th, 2004 at the City of
Rolla. This meeting was attended by representatives of the City: the
96
engineer, David Brown and the foreman construction, Mr. Bill
Cochran; the contractor in charge of the construction of the slab, Mr.
Jason Cox from Master Contractors LLC, and Dr. Antonio Nanni and
the author from UMR.
The three main topics were discussed at this meeting concerning
issues of constructability, materials, and structural concerns.
• Constructability issues dealt with the schedule of construction
and access to the bridge deck during construction. The existing
lane of the bridge was the only access that could be used to
reach the construction site; therefore carefulness had to be paid
to the trucks that continuously passed on the bridge in order to
create a safe environment for the workers.
• Material issues dealt with quality assurance testing: the
University of Missouri-Rolla volunteered testing concrete
samples extracted during the pouring and the steel rebar.
• Structural issues dealt on the discussion of details such us
laying GFRP bars on the central wall in order to create a
connection between slab and walls, the walls had to have
different height due to the presence of Neoprene pads only on
two of the three walls, and the construction of the formwork
supporting the slab by the City of Rolla.
The second pre-construction meeting was held at the construction site
on Thursday, August 12th 2004. The meeting was attended by the
same people present at the first one, with the addition of one the
bridge deck designers, Dr. Nestore Galati from UMR.
The main topics pertained to concrete, formwork and barrier:
97
• Concrete issues dealt with quality and required characteristics
of concrete to be used for the construction of the deck. A high
slump value was determined to be necessary and it had to be
achieved with the addition of super-plasticizers in order to make
sure the matching of an adequate strength in a short period time.
The City of Rolla was in charge of providing the concrete.
• Formwork: In order to facilitate the post-tensioning a formwork
longer than the slab itself had to be built on both sides of the
bridge (see Fig. 87). This exceeding part of the formwork would
have been cut after the post-tensioning operations, thus not
affecting the construction of two more box cells, scheduled after
the installation of the deck.
• Barrier: During the construction of the walls it was also decided
to build the barrier on the “FRP side” of the bridge using GFRP
rebars instead of steel rebars.
Such decision would in-fact allow the comparison between the
durability of the FRP and the steel barrier to be built on the
opposite side of the bridge, as already discussed and shown
before.
5.3 Substructure Construction
5.3.1 Footing and Floor Construction
As highlighted before, the erection of the substructure and the
extension of the existing abutments and walls were performed by the
City of Rolla employees prior to the slab construction.
98
The 21st of July the works started with the removal of the guardrail,
the wetting of the basement and the digging of the weed on the “FRP
side”, as shown in Fig. 60.
Fig. 60 - Wetting of the Basement and Digging of the Weed
The following days, after the excavation of the bridge site and the
moving of soil, the suction of the water overflowing from the creek
was the main operation to deal with; indeed the area where the footing
had to be built (see Fig. 61) was often and very easily filled with water
either due to rain or to a mizzle. In order to remove the stagnant water
different devices were utilized, such as electric pumps or a pipe
allowing the water to flow from the creek getting over the basin to the
opposite side of the stream (see Fig. 62).
99
Fig. 61 - Work Area after the Water Filling
Fig. 62 - Devices to Remove or Avoid the Water
On July 27th, the formwork and the steel reinforcement for the footing
were placed (see Fig. 63), then the following day, after removing the
remaining water, the footing was poured (see Fig. 64). The concrete
slump was found to be 10 cm (4in).
100
Fig. 63 - Footing Formwork
Fig. 64 - Pouring of the Footing
Fig. 65 shows the Slump Test and the casting of concrete cylinders
used to determine the concrete strength. The footing was built by the
end of the working day (see Fig. 66).
101
Fig. 65 - Slump Test and Concrete Cylinders Casting
Fig. 66 - Footing after Pouring
On July 29th the floor reinforcement was placed, after filling the voids
between the footing beams with gravel (see Fig. 67).
Fig. 67 - Floor Reinforcement
102
As highlighted before several delays were caused by the bad weather
conditions. Fig. 68 shows the site conditions after a thunderstorm. The
casting of the floor was completed on the 3rd of August.
Fig. 68 - Water Overflowing and Casting of the Floor
5.3.2 Abutments Construction
The abutments construction started after replacing the former
abutments caps, since the existing ones were in very bad conditions.
Then, the formwork and the reinforcement of the abutments were
placed quickly (see Fig. 69). Fig. 70 shows the device used to tie the
steel reinforcement together.
August 5th the new abutments were cast (see Fig. 71).
103
Fig. 69 - Laying of Abutments Reinforcement and Formwork
Fig. 70 - Use of the Steel Ties Gun
Fig. 71 - Casting of the New Abutments
104
5.3.3 Walls Construction
Prior to the walls construction, during the curing of the new
abutments, the dowels for the walls were fixed on the existing floor;
thus the first wall reinforcement and formwork were placed (as shown
in Fig. 72).
The following Monday, August 9th, the first wall was cast (see Fig.
73).
Fig. 72 - Reinforcement and Formwork of the First Wall
Fig. 73 - First Wall
The second wall to be built was the one close to the other abutment. In
this way it was possible to reuse the first wall formwork. The central
105
wall formwork had to be lower than the others to allow the insertion
of the GFRP bars anchoring the slab to that wall.
The construction of the central wall was complicated by the lack of
room and the short distance between vertical steel rebars to which the
GFRP rebars had to be tied (see Fig. 74 and Fig. 75). In addition a
central groove on the top of the wall was made to strengthen the
connection between wall and slab (see Fig. 76).
The prefatory part of the project was completed on August the 12th
(see Fig. 77 and Fig. 78).
F
3.8
76.2
19.7
0.950.9538.1
n.40 9 ASLAN 100 GFRP
76.2
10.25.1
38.1
76.2
1.95.50
3.81.9
25.4
20.725.4
5.1
10.2
7.67.6
Fig. 74 - GFRP Anchoring Detail
Fig. 75 - Laying of the GFRP Rebars
106
Fig. 76 - Making of the Notch
Fig. 77 - Central Wall
Fig. 78 - Completion of the Prefatory Part of Southview Project
107
5.4 Slab Construction
Prior to the construction of the slab all the material needed was
computed. The bill of materials and equipment used for the
installation of the slab is reported in the following section.
5.4.1 Bill of Material
Table 11 summarizes the amount of FRP reinforcement needed.
Table 11 - Bill of FRP Material
No. Size Length Mark Location Fiber Type
Bending Sketches
26 f9 #3
16.15 m (53’-0”) C1 Deck Carbon
40 f19 #6
13.11 m (43’-0”) G1 Deck Glass
40 f19 #6
13.11 m (43’-0”) G2 Deck Glass
43 f13 #4
5.79 m (19’-0”) G3 Deck Glass
43 f13 #4
5.79 m (19’-0”) G4 Deck Glass
140 f9 #3
0.97 m (3’-2”) G5 Deck Glass
43 f19 #6
1.95 m (6’ -1”) G6 Barrier Glass
43 f13 #4
1.85 m (5’ -9”) G7 Barrier Glass
10 f13 #4
13.11 m (43’-0”) G8 Barrier Glass
40 f19 #6
1.70 m (5’ -7”) G9 Deck Glass
40 f9 #3
1.24 m (3’-9”) G10 Deck-Wall Glass
Moreover the following materials were used:
1. Neoprene pads: NEWLON 60 durometer molded neoprene
for load-bearing applications. Considering ~15x10 cm2 (6x4
108
in2) pads, 1.3 cm (1/2 in) thick, ~15 cm (6 in) from each other,
each wall needed 24 pads. Since only two of the three walls
needed the pads and accounting also for the two abutments, a
total of 96 pads were needed (~1.5 m2, about 2300 in2).
2. Styrofoam: ~6.6 m2 (71 ft2) of styrofoam were required to
place around the pads.
3. Chairs: ~1.5 m (5 ft) long bolsters at ~60 cm (2 ft) spaced
were deemed necessary to support the bottom longitudinal
GFRP bars, considering ~6 m (20 ft) of width and ~12 m (40
ft) of length of the slab, 4 sets of 20 chairs, namely 80 chairs
were ordered.
4. Ties: 5000 plastic zip ties were used to tie the bars and the
duct, in order to have a complete “steel free” structure.
5. Plastic duct: The bridge is ~13 m (43 ft) long, so a ~13.7 m
(45 ft) long duct was necessary for each tendon, plus three
~1.5 m (5 feet) long pieces of duct coming out from the deck
and inserted through a T connector to the previous duct in the
way to inject the grout. Hence the needed amount was about
~18 m (60 ft) of ~2.3 cm (9/10 in) diameter plastic duct for
each tendon for a total amount of ~400 m (1300 ft). Adding
thirteen ~13.7 m (45 ft) long safety duct (plus two ~1.5 m long
coming out pieces) plus a supply, the overall duct length was
~700m (2300 ft).
6. T connectors: 3 T connectors of ~2.5 cm (1 in) internal
diameter for each tendon trace were provided, so as to create a
straight duct with a 3rd piece coming out in the way to inject
the grout. 26 tendons request 78 T connectors, plus 26 T
109
connectors for the safety duct is 104 T connectors, with
supplies, hence 110 T connectors overall.
7. Injection grout: The Sikadur 300 PT is the grout for injection
that was used for the bridge. Every bag is about ½ cubic foot,
thus considering 39 per ~13.7 m (45 ft) long duct ~2.3 cm
(9/10 in) diameter with a f9 (#3) tendon inside, ~0.26 m3 (9.35
ft3) of grout was ordered, and namely 20 bags of Sikadur 300
PT were provided.
8. Concrete: The ~12*6*0.25 m3 (40*20*0.83 ft3) slab required
~21 m3 (750 ft3) of concrete, with supplies.
In addition the following tools were used to pull the CFRP tendons:
1. Stereophone packs: two ~37*25*25 cm3 (12*10*10 in3)
stereophone packs were assembled in order to house the
tendons, at the same time providing enough room to push the
wedges inside the chucks before cutting the post-tensioned
bars. More details will be itemized afterwards.
2. Chucks: Pulling 13 tendons per time, 2 chucks for each
tendon and two more after the two hydraulic jacks when the
load was applied were deemed needful. Therefore 28 chucks
were requested overall. Each chuck includes an outer steel
cylinder, a four-piece steel wedge and an inner copper sleeve
(The same type used for the specimens load test, see section
3).
3. Steel Plates: Each tendon needed two steel plates between the
edges of the slab and the pulling machine. Thus twentysix
~(10*10*1.3) cm3 (4*4*1/2 in3) steel plates were required. All
the steel plates had a 1.9 cm (0.75 in) inner hole, in order to
avoid excessive transversal movement of the tendons.
110
Additionally the following equipment was used for the prestressing
operations:
• 2 hydraulic jacks (40 tons), to pull the tendons from each side
of the slab.
• 2 load cells (~222 kN, i.e. 50 kips each), to monitor the applied
load.
• 1 injection pump, to inject the grout inside the duct.
• 4 wedges hammers to push the wedges inside the chucks.
• Orange box, an easily transportable system that records the
load, the strains and the deflections.
• Wooden Boards, to build a surface suitable for the post-
tensioning, given the skewness of the slab.
5.4.2 Outline of tasks
The installation of the deck proceeded based on the following tasks:
• Partial embedding of anchoring GFRP bars into the central wall,
already described before.
• Laying of neoprene pads on the two external walls and on the
abutments.
• Setting of the formwork.
• Installation of bottom chairs, bottom longitudinal and
transversal GFRP bars.
• Installation of top chairs, top longitudinal and transversal GFRP
bars.
• Placing of the GFRP reinforcement for the barrier.
• Placing of ductwork, T connectors and CFRP bars inside the
ductwork; setting of the safety ductwork.
111
• Pouring and curing of concrete.
• Post-tensioning of CFRP tendons.
• Injection of grout inside the ductwork.
• Cutting of the tendons outside of the slab after the curing of the
grout.
• Cutting of the edges of the slab.
5.4.3 Investigation of the Slab Construction
On August 13th the installation work started, but, given the lack of
some hangers (see details in Fig. 79 and Fig. 80), only on August 17th
the activities could restart.
Fig. 79 - Formwork Hangers Details
112
Fig. 80 - Laying of the Formwork
After the installation of the formwork, on August the 18th the
following operation was the gluing of the Styrofoam on the two
abutments and on the two walls that didn’t have the GFRP anchoring
rebars (See Fig. 81).
Fig. 81 - Gluing and Placing of Styrofoam
Hence the Neoprene pads were placed in the room created in the
Styrofoam as shown in Fig. 82. The neoprene pads were used to avoid
113
restraining horizontally the slab and therefore to effectively post-
tension it.
Fig. 82 also shows the plastic chairs that supported the bottom layer of
GFRP mild reinforcement.
Fig. 82 - Neoprene Pads and Plastic Chairs Details
The placing of the FRP reinforcement was speed up thanks to the
presence of many students from RTI, leaded by Mr. Harold Martin,
who envisioned this as an opportunity to teach to his students new
technologies (see Fig. 83 and Fig. 84).
Fig. 83 - Laying of Bottom Layer of GFRP Rebars
114
Fig. 84-The RTI Team with (from down on the left) Mr. Cochran,
the Author and Mr. Cox
On August 21st the top layer was also laid after placing all the GFRP
top chairs. Furthermore, according to the design reported in Fig. 85,
also the GFRP rebars for the barrier were placed as shown in Fig. 86:
TEMP. & SHRINK.13 ASLAN 100 GFRP
AT 25 cm ON CENTERS3.8
20
AT 30.5 cm ON CENTERS
AT 25 cm ON CENTERSTEMP. & SHRINK.
(G8)
(G7)
(G6)
(G8)
Bridge Deck
F13 ASLAN 100 GFRP
19 ASLAN 100 GFRPF
F13 ASLAN 100 GFRPF
25.4
111.8
POST-TENSIONED FRP DECK
AT 30 cm ON CENTERS
SIDEWALK
Fig. 85 - Barrier Design
115
Fig. 86 - Top GFRP Layer
A wooden board was built to make the slab surface perpendicular to
the tendons. This operation was performed in order to ease the post-
tensioning phase. An alternative solution would have been to build a
skewed slab, but it would have implied the development of a more
sophisticated tool to pull the tendons. The position of the wooden
triangles was designed in order to have the two tendons full centering
each board. After the post-tensioning, the slab portion coming out of
the abutments had to be cut (see Fig. 87 and Fig. 88).
116
45.7
38.445.7
38.4
43.7
52.1
43.7
52.1
7.9 m
6.1 m
50°
45.7
38.4
45.7
38.4
38.4
45.7
38.4
45.7
38.4
45.7
38.4
38.4
45.7
45.7
38.445.7
38.4
45.7
Fig. 87 - Board Detail
Fig. 88 - Wooden Board (the wire indicates the position of the tendons)
On August 23rd the plastic ducts were placed and tied to the GFRP
rebars as prescribed in the design specifications. Thirteen additional
117
safety ducts were placed (as shown in Fig. 89 and Fig. 90), straight
and carefully tied to avoid their floating on the liquid concrete during
the pouring.
22.86
15.24
0.038
0.177
1.22
0.254
bottom chairs
13 GFRP (G4)
13 GFRP (G3)
n.8 19 GFRP (G1)
n.8 19 GFRP (G2)
n.5 9 CFRP (C1)
up chairs (G5)
45.72
safety ductwork
plastic ductwork
0.039
F
F
F
F
F Fig. 89 - Slab Section
Fig. 90 - Plastic Ducts Detail
T connectors were used on each end (see Fig. 91) in order to allow the
injection of the grout as specified in the construction specifications in
Appendix D.
118
Fig. 91 - T Connectors Detail
Strain gages were also attached on the GFRP bars (see Fig. 92) and
they were positioned as shown in Fig. 93.
Fig. 92 - Attaching of a Strain Gage
119
Strain Gages Scheme
GFRP Rebars
5th from the right edge
the right edge 17th from
5.00
1.67
Upper Layer
Lower Layer
Midspan
1st wall axis
2nd wall axis
0.611.83
Fig. 93 - Strain Gages Scheme
The bridge deck was poured by the City Workers on August 25th. The
pour began at 7.30 am and was finished at 9.30 am (see Fig. 94).
Fig. 94 - Pouring Fragments
In order to let the concrete filling all the voids inside the FRP cage, a
more liquid concrete was used (Slump Test = 9 cm, ~4.5 in.), with the
addition of super-plasticizers which increase the slump without
120
detrimental effects on the concrete strength. A total of 16 concrete
cylinders were also prepared (see Fig. 95). Fig. 96 shows the just
poured slab.
Fig. 95 - Concrete Cylinders Execution and Slab Leveling
Fig. 96 - Poured FRP Bridge Deck
121
5.4.4 Post-tension of the Slab
After a week of curing of the slab, on September 1st the CFRP tendons
were post-tensioned. The pulling was achieved by means of the
machine already used for the two test specimens. Modifications were
required afterward in order to decrease its weight and improving its
functionality. These improvements were accomplished with the help
of Mr. Max Vath, a Rolla Technical Institute instructor. Moreover,
some handles were joined to better and easily transport it from a
tendon to another (see Fig. 97).
Fig. 97 - Pulling Machine Before and After the Optimizations
Fig. 98 shows the modified pulling device. It comprises an open steel
box having enough room to push the wedges inside the chuck after
pulling the tendon, an hydraulic jack to apply the pulling force, a
round steel plate, a load cell to measure the load, a second plate and a
second chuck. Fig. 99 details the terminal part of the pulling machine.
122
Fig. 98 - New Pulling Machine Ready for the Use
Fig. 99 - Load Cell and External Chuck Detail
Before pulling the tendons, they were carefully cleaned from grout,
grease or dust; then the wedges were pushed inside the external chuck
in order to provide a grip, using a copper sleeve (shown in the 3rd
section). The tendons were pulled by means of two hydraulic jacks,
connected to two pumps using load steps of 13-22 kN (3-5 kip) per
side. Also the use of a single pump with two jacks connected in series
was considered, but it was found to be harmful for the tendons being
OPEN STEEL BOX
HYDRAULIC JACK
INNER CHUCK
STEEL PLATES
LOAD CELL
OUTER CHUCK
LOAD CELL WEDGES
BARREL
TENDON
123
the applied load not uniform along the tendon. A special two-parts
steel hammer was built to push the wedges into the barrel (see Fig.
100).
The applied load was measured using a data acquisition system
(Orange Box) connected to a computer allowing to monitor the
applied load in real time (see Fig. 101).
Fig. 100 - Hammer Detail and Use on the Site
Fig. 101 - Orange Box
After reaching the desired load of 62.3 kN (14 kips), corresponding to
the 45% of the maximum allowable load to avoid the breaking of the
124
tendons for the tight grip, the wedges were pushed inside the inner
chuck, so the jacks were released, engaging in such way the inner
chucks. At this point the pulling device could be removed by cutting
the FRP bar with an electric saw (see Fig. 102).
Fig. 102 - Wedges Insertion and Cutting of the Tendon
In 2 weeks the first half of the tendons was pulled. Some delays
occurred due to further changes of the pulling machine in order to
better suit the slab surface: it was not always possible to have a
surface perfectly perpendicular to the tendon.
Fig. 103 - First Set of Pulled Tendons
125
The injection of grout followed the pulling of the tendons and was
carried out with the use of a pump, after sealing the chucks to avoid
grout leaking (see Fig. 104).
Fig. 104 - Grout Injection and Slots Locking
After 4 days of curing the inner chucks were removed drilling the
tendons inside of those.
On October 7th the second set of tendons was pulled after a stop
intermission of two weeks for a scheduled load test that the contractor
had to carry out in Winsconsin, then the works could restart; thus the
grout was injected also in the safety duct.
Eventually the extra part of the slab added for the post-tension was cut
using a big cutter, as shown in Fig. 105. On October 15th the
Southview bridge-deck was completed (see Fig. 106).
126
Fig. 105 - Cutting of the Slab Edge
Fig. 106 - Southview Bridge-Deck Completed
127
6 CONCLUSIONS
The present thesis deals with a new technology, explored with the
literature review, validated experimentally and verified on the field; it
is part of a series of collaboration activities between the University of
Naples, “Federico II”, and the University of Missouri-Rolla, UMR.
The project developed is a further step in the study and use of FRP in
civil engineering; in fact, the use of FRP both for mild reinforcement
(Glass FRP) and for post-tensioned reinforcement (Carbon FRP) was
required for the construction of a bridge deck in the City of Rolla,
Missouri.
The objectives of the project at UMR were as follows:
1. Evaluate the feasibility, behavior, and effectiveness of the new deck
system, showing how FRP, in the form of GFRP as passive and CFRP
bars as active internal reinforcement, could be an excellent solution
replacing the steel.
2. Provide analytical data in support of the enhanced shear capacity of
the concrete slab due to the CFRP prestressing.
Informations on existing prestressing and non-prestressing FRP bridge
decks have been given in the section two, so that they can be
compared with the new deck system that is the subject of this thesis. A
summary of the main research works on shear behavior of prestressed
FRP was also given, showing the lack of research projects on the
specific topic of this thesis.
Section three dealt with pre-construction investigations that were
conducted on two specimens representing a deck strip 457 mm (18 in)
wide and 7 m (23 ft) long, with the same geometry and amount of
128
reinforcement. They were built and tested one to investigate the
flexural behaviour, the other one the shear behaviour. The two beams
were constructed by the contractor peculiar for the project also
allowing for his familiarization with the use of non-conventional
materials. Their testing as continuous slabs over three supports
allowed the validation of the design calculations in terms of flexure
and shear capacities.
The specimens were reinforced using 3 f19 (6/8 in) GFPR bars as top
and bottom mat and 2 f9 (3/8 in) CFRP bars as prestressed tendons.
The position of the prestressed tendons was varied along the slab in
order to match the moment demand. In addition, in order to reproduce
the actual field conditions also f13 (4/8 in) GFRP bars spaced 305
mm (12 in) on center were placed in the transversal direction as
temperature and shrinkage reinforcement.
The experimental results were compared with the theoretical moment
and shear capacities of the slabs computed according to ACI 440.1R-
03 provisions and to the equation developed by Tureyen A. K. and
Frosh R. J.
According to ACI 440, the shear capacity increased from 30.7 kN (6.9
kip) with mild reinforcement to 69.8 kN (15.7 kip) adding the post-
tensioned reinforcement, while the flexural capacity increased from
76.0 kN-m (55 kip-ft) to 97.9 kN-m (72.2 kip-ft), showing that the
prestressing material is mostly needed for shear purpose rather than
for flexure.
On the basis of the experimental investigation, it can be concluded
that GFRP bars as passive and CFRP bars as active internal
reinforcement could represent a feasible solution replacing the steel
reinforcement of concrete slab bridges.
129
The objective of section four has been to provide the structural
analysis of the new FRP concrete bridge deck based on the AASHTO
HS20-44 design truck and provide calculations for its design using a
combination of non-traditional corrosion-resistant composites
materials.
Two load configurations were considered, consistent with AASHTO
Specifications, the HS20-44 design truck and the design lane; the
concentrated load and uniform load were considered to be applied
over a 3.0 m (10ft) width on a line normal to the center line of the
lane. These loads were placed in such positions within the design lane
as to produce the maximum stress in the member.
Since the design truck analysis produced the highest stresses on the
slab, only moment and shear related to this analysis were considered.
The design of the internal FRP reinforcement was carried out
according to the principles of ACI 440.1R-03, using the same
percentage of reinforcement already used ant tested in the
experimental phase.
Consistent with section 3 it was noted that the prestressing force is
most needed for shear purpose rather than flexure. In fact, if the
prestressing action was not considered, the concrete contribution to
the shear capacity of the slab would have been Vc=220.4 N/m (=15.1
kips/ft), and the final factored shear capacity of the bridge would have
been equal to φVn=86.09 kN/m << Vu=148.9 kN/m (φVn=5.9 kips/ft
<< Vu=10.2 kips/ft), that is the shear capacity of the slab with post-
tensioning; therefore the post-tensioning allowed to increase the shear
capacity of the slab more than 40%.
130
Section five detailed the installation of Southview bridge deck,
focusing on the post-tensioning of the slab, the most considerable and
crucial part of the project.
The slab is 25 cm (10 in) thick, 12 m long (40 ft) long and 6 m (19.83
ft) wide. It is supported by three intermediate reinforced concrete
vertical walls. The three spans lengths are, from North to South, 2.89
m (9.49 ft), 3.38 m (11.10 ft) and 3.30 m (10.82 ft), respectively, on
centers.
The erection of the substructure started the 21st of July; the extension
of the existing abutments and walls was performed by the City of
Rolla employees prior to the slab construction.
On August 17th the installation of the deck started, after the partial
embedding of anchoring GFRP bars into the central wall, in order to
provide a fix central section, avoiding the total slipping of the
superstructure during the prestressing operations. Hence, after the
laying of formwork, the neoprene pads on the two external walls and
on the abutments were placed in order to allow the axial sliding of the
middle fixed slab.
The installation of bottom and top longitudinal and transversal GFRP
reinforcement was completed by the 21st of August, after which the
GFRP reinforcement for the barrier was also placed on the ”FRP
side”.
Wooden boards were positioned in order to ease the post-tensioning
operations, then the placing of the ductwork, the T connectors and the
CFRP tendons inside the ductwork was carried out by August 23rd.
Before pouring, some strain gages were also attached on the GFRP
bars of the slab, in order to allow checking the behavior of the slab in
service.
131
The bridge deck was poured by the City Workers on August 25th; after
a week of curing, on September 1st the CFRP tendons were post-
tensioned.
The pulling and releasing of the tendons were the newest and the most
critical parts of the project.
The pulling of the tendons was achieved by means of the machines
already used for the two test specimens, with two hydraulic jacks and
special chucks to provide the grip between the machine and the
tendons themselves, as detailed in the third section.
On September 15th, after some delays occurred due to further changes
of the pulling machine in order to better suit the slab surface, the first
half of the tendons had been pulled, hence the grout was injected
inside their ductwork.
The same procedure was carried out for the second half of the
tendons; hence all the tendons edges outside of the slab were cut after
the curing of the grout.
On October 15th the edges of the slab were also cut.
The main result of this project has been to show how FRP, in the form
of GFRP as passive and CFRP bars as active internal reinforcement,
could be a feasible solution replacing the steel reinforcement of
concrete slab bridges, and specifically the enhanced shear capacity of
the slab due to the CFRP prestressing.
Moreover, the following conclusions can be summarized:
• The real advantage in the use of FRP materials as reinforcement
of a bridge deck is seen through its increased durability, mainly
due to the absence of corrosion. To better show it, a barrier with
GFRP reinforcement was built on the new “FRP side”, in order
to have a comparison during time with the steel reinforced
132
concrete barrier on the opposite side, which was going to be
built after the FRP bridge deck installation.
• Utilizing FRP in the form of reinforcing bars allows for the use
of many steel-RC concrete practices. The fabrication and
installation details were nearly identical to the methods
regularly utilized for steel-reinforced slabs.
• The installation of the bridge highlighted the fact that having an
efficient system is as important as having the adequate
components. As well, for a new technology its learning curve
must be overcome before its applications can be conducted
proficiently.
• There was an increase in productivity using the FRP materials
in each stage of construction versus conventional steel. This is
directly associated with a labor savings. While this labor
savings does not offset the initial increase in material costs, it is
hoped that will become a factor in lowering the total life cycle
cost of the bridge.
• Further investigation must be done in this field in order to
improve and refine the techniques related to the post-tensioning
of bridge-decks using CRFP, its future development being
certainly hopeful and helpful.