dependent demand lumpy mrp detailed schedule for raw materials & components used in the end...
TRANSCRIPT
•Dependent demand•lumpy
MRP
DETAILED SCHEDULE FOR RAW MATERIALS
&
COMPONENTS
USED IN THE END PRODUCTS
MASTER SCHEDULE
FOR END ITEMS
TIME
Avg.rate ofdemand
Inv.LEVEL
TIME
Inv.LEVEL
t1t2 t3 t4 t5 t6
Ordering Lead Time:(for purchased parts)
Initiation of purchase requisition
Receipt of item from vendor(off shelf / fabricate)
Manufacturing Lead Time:
Place order Item deliveredProcess part through sequence of machines as given on route sheet (operation + non-productive times)
C1 C2 C3 Cn
P1 P2 P3 PN
BASIC RAW MATERIAL
COMPONENTS
PRODUCTS
Gross & Net requirements report
Capacity vsLoad report
Shop floorPlanningreport
Production OrderStatus & exceptionsreport
ServiceParts
requirements
Salesforecasts
Customerorders
Inventorytransactions
MasterProductionschedule
Engg.changes
InventoryRecord
file
MRPPROCESSOR
Bill ofMaterials
file
OUT PUTREPORTS
…
DEMANDOften excluded from MPS, since it does not include end product demand.
Demand for individual component Parts (for repair and service)
Firms customer orders
Forecasted demand
Week no 6 7 8 9 10
Product P1 50 100
Product P2 70 80 25
Etc.
C1 C2 C3 C4 C5 C6
S1 S2
P1
(1) (2)
(1) (4) (1) (2) (2) (1)
Level 0(product)
Level 1(sub-assemblies)
Level 2(raw materials)
OrderingLead time
ManufacturingLead time
Purchasingrecords
ProcessRoutesheets
C1 C2 C3 C4 C5 C6
S1 S2
P1
(1) (2)
(1) (4) (1) (2) (2) (1)C4 C6 C7 C2 C8
S3 S4
P2
(1) (1)
(1) (4) (2) (2) (1)
M4
PRODUCT STRUCTURE FOR PRODUCTS P1 & P2Initial inventory status for M4
Assembly Manufacturing Ordering
P1 = 1
P2 = 1
S2 = 1
S3 = 1
C4 = 2 M4 = 3
Lead times (in weeks)
PLANNED ORDER RELEASES
NET REQUIREMENTS
90ON HAND
40SCHEDULED RECEIPTS
GROSS REQUIREMENTS
ITEM RAW MATERIAL M4
654321PERIOD
50
EVOLUTION OF MRP
Manufacturing ResourcePlanning
• Links up the closed loop MRP system with the financial systems of the company
(Links functions-Capacity planning-Inventory management-Shop floor control-MRP)
Improved computational efficiency of computers
Unrealistic M/c schedules, ignoring plant capacities
Not only plans priorities but provides feedback to executing the priority plan
AN IMPROVED ORDERING METHOD
PRIORITY PLANNING
CLOSED LOOP MRP
MRP II