department of transport
DESCRIPTION
Department of Transport. Select Committee on Finance Public Hearings on Division of Revenue Bill 2009/10 3 March 2009. Contents of presentation. Additional allocations: List of additional allocations MTEF Overview: Budgets per Programme Breakdown of major budgets - PowerPoint PPT PresentationTRANSCRIPT
Department of Transport
Select Committee on Finance
Public Hearings on Division of Revenue Bill 2009/10
3 March 2009
Contents of presentation
• Additional allocations:• List of additional allocations
• MTEF Overview:
• Budgets per Programme • Breakdown of major budgets • Growth in major capital budgets • Other budgets and major projects
• Conditional Grants:• Bus subsidies• Gautrain• Other Grants: Roads, overload control & rural
transport• Public Transport Infrastructure and Systems (PTIS)
2
Additional allocations
Details (R’000) 2009/10 2010/11 2011/12
SANRAL 70,047 298,928 1,062,807
PTIS: SANRAL 6,559 0 0
SARCC 98,177 338,381 818,752
Compensation of employees SARCC 71,357 75,867 78,832
PTIS: SARCC 14,758 0 0
Bus operations and fuel costs 483,094 624,289 720,163
PTIS Grants to Local Government 93,177 325,275 416,638
Gautrain Rapid Rail Link 325,480 23,134 0
Taxi operations 200,000 100,000 50,000
Railway Safety Regulator 3,000 5,000 5,000
Compensation of employees 5,401 5,095 5,271
Capital 1,854 3,572 4,576
Reduction in transfers to Departmental Agencies (1,103) (683) (722)
Efficiency saving (18,337) (19,099) (6,450)
Reduction in goods and services (5% per year) (30,609) (29,821) (31,284)
Total 1,322,855 1,749,938 3,123,583
3
Budgets per Programme
Table 33.1: Transport
R thousand
2008/09 2009/10 2010/11 2011/12
Adjusted
Appropri-ation
Medium-term estimates
MTEF Baseline
1. Administration 245,165 231,023 230,753 235,291
2. Transport Policy and Economic Regulation
47,211 51,592 52,083 54,766
3. Transport Regulation and Accident and Incident Investigation
432,563 195,580 207,997 224,190
4. Integrated Planning and Inter-sphere Co-ordination
8,767,012 8,855,424 11,908,301 13,444,044
5. Transport Logistics and Corridor Development
35,076 31,809 38,992 40,288
6. Public Transport 12,277,229 14,191,689 12,953,416 13,829,382
7. Public Entity Oversight and Border Operations and Control
2,688,584 177,712 88,755 92,980
Total 24,492,840 23,734,829 25,480,297 27,920,941 4
Breakdown of major budgetsDetails R’000 2008/09 2009/10 2010/11 2011/12
SARCC 4,917,290 6,567,635 7,688,206 8,607,979
SARCC – Shosholoza Meyl 500,000 450,000 400,000 424,000
Bus subsidies 2,984,131 3,531,909 3,863,033 4,153,232
SANRAL 4,072,974 5,594,986 6,964,501 8,128,314
Taxi 571,567 751,561 624,409 605,303
PTIS (2010 Soccer World Cup) 3,480,000 3,089,494 4,789,775 5,149,008
Gautrain 3,265,993 2,832,691 340,660 0
Disaster Fund Grant - Provincial roads
1,035,473 0 0 0
RAF 2,500,000 0 0 0
Other 1,165,412 916,553 809,713 853,105
Total 24,492,840 23,734,829 25,480,297 27,920,941
% Growth 48.05% -3.09% 7.35% 9.58%
5
Breakdown of major budgets (Continued – excl. once off allocations in 08/09)
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
Rail 5,417,290 7,017,635 8,088,206 9,031,979
Bus 2,984,131 3,531,909 3,863,033 4,153,232
Roads 4,072,974 5,594,986 6,964,501 8,128,314
PTIS 3,480,000 3,089,494 4,789,775 5,149,008
Gautrain 3,265,993 2,832,691 340,660 0
2008/09 2009/10 2010/11 2011/12
• Allocations for rail operations and capital remain the largest single budget item.
2009/10
7,017,635
3,531,909
5,594,986
3,089,494
2,832,691
• The National contribution to the Gautrain Rapid Rail Link was introduced in 2006/07 at R3,241Bn, and declines to zero in 2011/12
• Allocations for infrastructure from the Public Transport Infrastructure and Systems Grant was introduced in 2005/06 at R241,7m, growing to R3,1bn in 2009/10.
• The budget for road infrastructure overtook that of bus subsidies from 2007/08 onwards.
R’000
Gautrain
PTIS Grant
6
Growth in major capital budgets
(R’000)
0
2,000,000
4,000,000
6,000,000
8,000,000
10,000,000
12,000,000
14,000,000
16,000,000
18,000,000
Gautrain 0 3,241,000 3,029,411 3,265,993 2,832,691 340,660 0
PTIS 241,710 697,020 1,780,000 3,480,000 3,089,494 4,789,775 5,149,008
Roads 565,333 833,952 1,429,350 1,806,944 2,841,470 4,065,177 5,062,566
Rail 688,300 1,029,598 1,696,078 2,367,686 3,831,791 4,813,273 5,566,768
2005/06 2006/07 2007/08 2008/09 2009/10 2010/11 2011/12
7
Breakdown of other budgets and major projects
Details R’000 200910 2010/11 2011/12
Compensation of Employees 212,798 208,867 221,272
P1: October Month & World Remembrance Day 26,362 36,575 37,515
P1: Conferences (AFI-RAN) 3,800 3,800 3,800
P1: Arrive Alive 14,250 0 0
P1: NLTIS, VPN, ECM, Recruitment 15,152 15,580 16,144
P1: Security, Skills development 8,740 8,740 8,740
P1: Centres of Development 8,178 8,669 9,189
P1: Comms: BEE, events, exhibitions, web & audio visual, branding 10,925 10,925 10,925
P1: Property management 14,884 16,372 17,356
P1: Other 45,236 49,166 45,897
P2: Transport Policy, Research and Economic Regulation 15,806 16,361 17,341
P2: Rail economic regulation 11,382 11,623 11,893
P3: eNaTIS 3,682 7,419 11,598
P3: Special Investigating Unit 21,235 22,439 23,785
P3: Rail Economic Regulator 4,257 4,498 4,768
P3: ICAO and IMO offices 7,365 7,785 8,251
P3: Watch Keeping services 27,109 28,644 30,363 8
Breakdown of other budgets and major projects (Continued)
Details R’000 200910 2010/11 2011/12
P3: Oil Pollution prevention services 48,805 51,572 54,666
P3: Maritime Security Coordination Centre 6,559 6,930 7,346
P3: Commissioner of Civil Aviation 4,742 5,011 5,312
P3: Maritime Rescue Coordination Centre (Transfer payment) 5,236 5,533 5,865
P3: International membership fees 5,114 5,420 5,745
P3: Road Transport Regulation projects 20,800 21,980 23,299
P3: Other and Administration 5,592 5,876 6,229
P4: Transport planning and infrastructure projects 12,096 12,371 13,164
P4: Rural transport and NMT projects 52,293 55,231 58,520
P4: Road infrastructure planning 2,829 2,449 5,252
P4: Sani Pass and Overload Control 44,416 48,688 52,399
P4: 2010 SWC Monitoring and Evaluation 23,750 0 0
P4: Other and Administration 4,389 4,619 4,897
P5: Transport Logistics and Corridor Development 19,475 26,593 27,151
P6: Bus contract model 4,750 0 0
P6: Project Implementation 2010 and beyond 23,750 7,600 7,600
P6: Other and Administration 11,092 11,501 12,191 9
Details R’000 2008/09 2009/10 2010/11
P7: Transfers to RTMC 83,603 0 0
P7: Transfers to RSR 37,260 35,634 37,475
P7: Transfers to Ports Economic Regulator 13,603 8,832 9,361
P7: Transfers to SAMSA 8,896 9,402 9,966
P7: Transfers to SACAA 7,781 8,223 8,716
P7: Performance Management System 950 950 1,007
P7: RAF restructuring 13,300 13,300 13,300
P7: Other and Administration 4,311 4,535 4,807
Total 916,553 809,713 853,105
Breakdown of other budgets and major projects (Continued)
10
Bus subsidies• Subsidy levels have been insufficient since 2005/06 to halt
the declining levels of service, escalation in costs and the growth in demand
• In order to improve operational and financial efficiency a more focussed approach to determining service priorities will need to be developed
Implementation Plan: • Conditional Grant to Provinces introduced• Phased implementation in co-operation with Provinces• Negotiated performance based contracts for route operations• Formalisation of unscheduled Interim Contract services• Define operating areas that will not be served• Implementation of supporting infrastructure• Continued enforcement and monitoring of all contracted
Public Transport Operations
11
Finalise integrated road based networks
Develop KPI’s
Identify key role-players who are to be part of the operating entity
Engage with all parties to establish operating entity
Implement depots and vehicles if so decided
Recruit/develop admin capacity to manage the contracts
Contracting authorities will have to: Change in compensation method – based on fixed
kilometre
KPI’s
New national monitoring model
Fare levels as set by the authority
Fleet replacements to be based on requirements of the contracting authority
Contracting authority may purchase existing assets (eg depots) and contract compliant vehicles
Operators will have to accept:
Bus Subsidy Funding - Conditional Grant in DORA
Critical conditions:
Interim contracts to be converted to negotiated (kilometre based) contracts by September 2009
Alignment with IRPTN`
Bus subsidies: Interventions for achieving change 2009/10 onwards
12
Operators that accept will sign an negotiated contract that Operators that accept will sign an negotiated contract that includes:includes:
KPI’sKPI’s
Provision that the operator will be provided with an Provision that the operator will be provided with an opportunity to be party to a new integrated contract regime opportunity to be party to a new integrated contract regime for some or all of the services within the contract areafor some or all of the services within the contract area
Operators that do Operators that do notnot accept will continue on month-to- accept will continue on month-to-month basis and their contracts will be terminated as and month basis and their contracts will be terminated as and when requiredwhen required
Bus subsidies: Intervention conditions
13
0
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
R'000 3,241,000 3,029,411 3,265,993 2,507,211 340,660
2006/07 2007/08 2008/09 2009/10 2010/11
Gautrain
Allocations from 2006/07 to 2010/11
14
Gautrain
• Annual allocations are paid in terms of a payment schedule• Key and General Milestones have to be achieved before payment• The Provincial Support Team then checks whether Milestones have
indeed been achieved• The Milestones are certified by the Independent Certifier (IC)• The certified claim is submitted by the IC to the Gauteng Management
Agency to check claims for compliance• The GMA then sends the claim to the Department with a request for
payment from the DORA Grant• The Department satisfies itself that there has been compliance with the
DORA requirements and the conditions contained in the DORA Framework
Currently, indications are that Phase 1 of the Project, i.e. the section between OR Tambo International Airport and Sandton will be completed in September 2010, while the rest of the Project will be completed in September 2011.
15
Roads, Overload Control and Rural Transport Grants
0
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
45,000
Sani Pass 30,000 34,347 37,650 40,520
Overload control 8,796 10,069 11,036 11,879
Rural transport 8,900 9,800 10,400 11,100
2008/09 2009/10 2010/11 2011/12
R’000 These grants to be introduced in 2010 budget
16
Road Grants
• The grant was introduced to develop road infrastructure projects that promote regional integration, development and connectivity between neighbouring states
Construction of the Sani Pass:
• Phase 1 – Upgrade of P318 Sani Pass (km 0 to 13.6) - completion scheduled for April 2010.
• Phase 2 – Upgrade of sections 1 and 2 (km 14 to 25 and 25 to 33):• Environmental Impact Assessment Studies underway with record of
decision scheduled for announcement in September 2009• Engineering designs are underway and are at various stages of
completion by the joint venture consultant team
• Future road construction projects to be identified for inclusion in the Division of Revenue Act
17
• To achieve the objectives of the national overload control strategy, a 3-year grant has been developed in conjunction with National Treasury
• Grant funds are currently being used for upgrading the weighbridge infrastructure facilities in Mpumalanga and Limpopo
• In Mpumalanga, projects for the upgrade of weighbridge infrastructure were completed in October 2008:
• Kinross Traffic Control Centre• Ermelo Traffic Control Centre
• In Limpopo, the detailed design, planning and bill of quantities have been compiled, and construction works are set to begin in 2009/10 on:
• Rathoke Traffic Control Centre• Mooketsi Traffic Control Centre
• Future allocations:
Overload Control Grants
2009/10 Gauteng R4,8m Limpopo R4,8m
2010/11 Eastern Cape R5,1m Mpumalanga R5,1m18
Rural Transport Grants
Purpose :• To improve mobility and access in rural municipalities in support of
Integrated Development Plans
Reasons for not incorporating in equitable share:• This is a specific purpose grant mainly for the provision of rural transport
infrastructure and services. • This grant ensures that district municipalities are giving priority to the
following rural transport interventions:• infrastructure construction• maintenance, upgrading and rehabilitation• support rural development and• accelerated and shared growth initiatives in line with government
priorities• It is also used as vehicle for stimulating the use of labour intensive methods
in large infrastructure programmes / projects to create jobs and develop required skills in terms of the Expanded Public Works Programme
19
Rural Transport Grants
• Timeframes : MTEF Allocations – R8.9 million 2008/09,
– R9.8 million 2009/10
– R10.4 million 2010/11
– R11,1 million 2011/12.
• Details of Projects : 2008/09 Allocations:
DM PROJECT BUDGET
Chris Hani Intermodal Public Transport Facility
R 4,1m
Thabo Mofutsanyane Upgrading of Access Road to a Thusong Service Centre
R 2.0m
Dr Ruth S. Momphati Construction of 2No. Pedestrian Bridges
R 2.0m
Sekhukhune Development of a Pedestrian & Bicycle Paths Master Plan
R0.8m
20
Public Transport Infrastructure and Systems Grants
Contents:
• PTIS Background• Allocations• Conclusion
21
Background InformationBackground Information
The PTIS grant is aimed at improving transport infrastructure & systems for 2010 and beyond;
Total PTIS grant from 2005/06 to 2010/11 = R13.639bn Total Host Cities PTIS grant = R10.979bn which is 80% of
PTIS Grant Ongoing Monitoring and Evaluation of progress is in place,
with monthly reporting Five Host Cities currently receiving technical assistance
(Polokwane, Rustenburg, Mangaung, Mbombela and Tshwane)
22
PTIS Allocations per City and/or Entity
Allocations per City / Entity Budget Budget Totals
R'000 2009/10 2010/11 Period
Johannesburg 600,214 950,471 2,831,756
Tshwane 565,245 864,180 2,068,744
Ethekwini 376,926 529,699 1,690,934
Cape Town 291,912 527,270 1,602,025
SARCC 450,000 1,315,000
Nelson Mandela 147,079 323,058 1,029,871
Mangaung 82,168 183,551 586,166
Inter-city buses 500,000 500,000
SANRAL 200,000 430,000
Mbombela 60,833 135,893 424,910
Polokwane 66,146 147,161 420,914
Non Host Cities 66,695 152,880 414,134
Rustenburg 67,782 150,337 323,776
CBRTA 1,000
Total 2,975,000 4,464,500 13,639,230
23
Allocated (Rm)
2,069
1,691 1,6021,315
1,030
586 500 430 425 421 414 324
1
2,832
Johannesburg Tshwane Ethekwini Cape Town
SARCC Nelson Mandela Mangaung Inter-city buses
SANRAL Mbombela Polokwane Non Host Cities
Rustenburg CBRTA
Total R13,64 Billionfrom 2005/06 to 2010/11
PTIS Allocations per City and/or Entity
24
Thank you
25 25