department of social development
DESCRIPTION
Department of Social Development. AN INTEGRATED EARLY CHILDHOOD DEVELOPMENT PROGRAMME OF ACTION FOR– MOVING AHEAD 2013 -2018. PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 11 JUNE 2013. OUTLINE OF THE PRESENTATION. Purpose of the Presentation Background - PowerPoint PPT PresentationTRANSCRIPT
Department of Social Development
AN INTEGRATED EARLY CHILDHOOD DEVELOPMENT PROGRAMME OF ACTION
FOR– MOVING AHEAD 2013 -2018.
PORTFOLIO COMMITTEE ON SOCIAL DEVELOPMENT 11 JUNE 2013
1
OUTLINE OF THE PRESENTATION
• Purpose of the Presentation
• Background
• An Integrated ECD Programme of Action- Moving Ahead 2013-2018.
• Conclusion
• Recommendations
2
PURPOSE OF THE PRESENTATION
• To make a presentation on An Integrated ECD Programme of Action - Moving Ahead 2013-2018 to the Portfolio Committee on Social Development.
3
BACKGROUND• The Department of Social Development, in collaboration with the ECD Sector
launched an awareness campaign to promote ECD in local communities. The purpose of the campaign is to promote Early Childhood Development in South Africa and to ensure that all South Africans commit themselves in supporting the implementation of Early Childhood Development services in the country.
• As part of concurrent review processes of ECD, Department of Performance Monitoring and Evaluation in the Presidency (DPME) and the Inter-Departmental Steering Committee on Early Childhood Development commissioned a Diagnostic Review of the prevailing Early Childhood Development (ECD) paradigm, current services, human resources, funding and impact. This was the first evaluation under the emerging National Evaluation System led by DPME.
• There were three National activities which impacted on ECD services in South Africa from 2011/2012. These included The Review of the National Integrated Plan for Early Childhood Development, the ECD Diagnostic Review and the ECD Conference Action Plan. The aim of the above was to review ECD services provisioning, coordination and implementation for children, birth to four years in South Africa.
• The above processes were merged into a zero draft “An Integrated ECD Programme of Action-Moving Ahead 2013-2018 ”(Document attached).
Merging of the ECD Action Plan, NIPECD and the Improvement Plan
AN INTEGRATED ECD PROGRAMME OF ACTION -
MOVING AHEAD 2013-2018
The time frames are as follows:•Short Term: April 2013 – March 2014;•Medium Term: April 2014 – March 2016; and•Long Term: April 2016 – March 2018.
6
1. LEGISLATION AND POLICY FRAMEWORK
OBJECTIVE TO PROVIDE ENABLING ENVIRONMENT FOR BUILDING STRONG
EARLY CHILDHOOD DEVELOPMENT INSTITUTIONS
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILITY TIMEFRAME BUDGET
1. An ECD policy developed
H Develop an integrated ECD Policy Cost and implement an integrated ECD Policy
DBE, DSD, DoH and DWCPD and DPME led by DSD
Short Term
2. To develop the National Integrated regulatory framework for ECD
M Conduct an audit on the applicable legislation Identify the gaps and challenges in the various legislation
DBE, DSD, DoH and DWCPD and DPME led by DSD
Medium Term
7
LEGISLATION AND POLICY FRAMEWORK…CONT…
OBJECTIVE TO PROVIDE ENABLING ENVIRONMENT FOR BUILDING STRONG
EARLY CHILDHOOD DEVELOPMENT INSTITUTIONS
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILITY TIME
FRAME
BUDGE
T3. Review all legislation, Regulations, Policy and municipal by-laws pertaining to Early Childhood Development.
M Alignment and harmonisation of the legislation, regulations, policies and municipal by –laws
DSD, DBE, DOHMunicipalitiesDPW, DCOG, DWCPD, NPC
Medium Term
4. Norms and standards for differentiated services, provisioning and funding for ECD reviewed and new norms and standards developed.
H Develop Norms and Standards for differentiated services provisioning and funding for ECD.
DSD, DBE, DOHMunicipalitiesDPWDCOG DWCPD, NPC
Long
Term
8
LEGISLATION AND POLICY FRAMEWORK….CONT…
OBJECTIVE To provide enabling environment for building strong Early
Childhood Development institutions
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBI
LITY
TIME
FRAME
BUDGET
5. Amendment of Children’s Act on ECD
H Proposed amendments to legislation on ECD to be included in the Parliamentary legislative programmePromulgation and implementation of the agreed upon legislative amendments
DSD, DBE, DoH and DWCPD, NPC
Short Term
6. To develop an Integrated Strategy for the implementation of universal access for children birth to school going age.
M Desktop research on the concept on the universal access to ECD. Complete a cost analysis on the Integrated Strategy Conduct a consultative process on the universal access to ECD services and programmes. Obtain approval on the Integrated Strategy through various interdepartmental structures of government up to Cabinet and the three spheres of government. Effect appropriate legislation amendments.
DoH DBE DWCPD DPME DPWDCOG DCS National Treasury led by DSDNPC
Long Term
9
2. INSTITUTIONAL ARRANGEMENTS, COORDINATION
AND INTEGRATIONOBJECTIVE Setting up multi-sectoral integration and coordination
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBI
LITY
TIME
FRAME
BUDGET
7. Feasibility study conducted on options for inter sectoral management and coordination
H Research on the various options of an integrated governance structures such as an ECD Council, ECD Institute, ECD Agency, and integrated ECD Directorates/units in the Department of Health, Department of Women, Children and People with Disabilities, Correctional Services, COGTA Establish an inter sectoral management and coordination mechanism for ECD by April 2014
DSD, DBE DOH DWCPD, COGTA
Short Term
8.Interim management and coordination mechanism for ECD established
H Establish an Interim Management Committee on ECD
DSD, DoH DBE DWCPD DPME National Treasury
Short term
10
3. HUMAN RESOURCES, TRAINING AND CAPACITY
BUILDINGOBJECTIVE BUILDING HUMAN CAPITAL/DEVELOPMENT FOR THE ECD SECTOR IN SOUTH AFRICA
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBI
LITY
TIME
FRAME
BUDGET
9. Human Resource Development plan for the ECD Sector (Government and ECD service providers) developed and costed.
H Conduct Capacity audit Establish Posts for government departments Employ Staff by government departments
Led by DBE DOH, DSD DWCPD DPSA
Short Term
10. Improved quality of ECD services through provisioning skills and career pathing for people working with young children and service providers
M Profile levels and category of ECD practitioners and servicesContinued training of ECD Practitioners through the EPWP Review of qualifications Map learning pathways Review employment practices to improve working conditions Mentoring and coaching Facilitate the establishment of Board to regulate the sector
Led by DBE & DPWDOH, DSD, Treasury, DWCPD
Medium term
11
3. HUMAN RESOURCES, TRAINING AND CAPACITY
BUILDINGOBJECTIVE BUILDING HUMAN CAPITAL/DEVELOPMENT FOR THE ECD SECTOR IN
SOUTH AFRICA
OUTPUT PRIORI
TY
L/M/H
ACTIVITIES RESPONSIB
ILITY
TIME
FRAM
E
BUDGE
T
11.Revised National Qualifications Framework which includes career path developed to address gaps
H Revise the ECD qualifications Approved ECD qualifications Review ECD unit standards Implement teacher development Strategy for ECD grade R practitioners
DBE (lead) ETDP SETA responsible for managing ECD qualification
s,
DBE (lead), with DSD & DOH, DHET, DWCPD & Service Providers
Short Term
12
3. HUMAN RESOURCES, TRAINING AND CAPACITY
BUILDINGOBJECTIVE BUILDING HUMAN CAPITAL/DEVELOPMENT FOR THE ECD SECTOR IN
SOUTH AFRICA
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
12. Revise the ECD Training programmes for alignment to the comprehensive package and differentiated modalities for ECD Services and compliance to the inclusive policy on disabilities
M Revise learning programmes at all training institutions e.g. FET colleges in place by 1 April 2015
DBE (lead), DoH and DSD DHET, Universities, & CHE, ETDP SETA, Training organisations, DWCPD
Medium Term
13.Improved accredited provisioning of training for ECD practitioners
M Increased number of accredited training service providers
DBE (lead), Quality Assurance Bodies e.g. ETDP SETA and UMALUSI, CHE
Medium
Term
13
3. HUMAN RESOURCES, TRAINING AND CAPACITY
BUILDING
OBJECTIVE BUILDING HUMAN CAPITAL/DEVELOPMENT FOR THE ECD SECTOR IN
SOUTH AFRICA
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
14.Integrated professional registration system for ECD practitioners
H Integrated professional registration system for ECD practitioners working with children birth to pre-grade R in place by June 2015.
DBE (lead) DSD, DOH ETDP SETA DWCPD
Short Term
15.Develop a training programme for the ECD Sector on the changed ECD policy
L Training programme on the amended ECD policy implemented
DBE (lead) DSD DOH ETDP SETA DWCPD
Long term
14
4. CORE PACK OF COMPREHENSIVE ECD SERVICES
OBJECTIVE AN EXPANDED, STRENGTHENED AND COSTED COMPREHENSIVE
PACKAGE OF SERVICES FOR ECD.
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
16.Develop a comprehensive package of ECD services for children birth to school going age with roles and responsibilities of government departments and other stakeholders.
H Review the current package of services as described in the NIPECD for young children pertaining to ECD services. Describe a comprehensive package of services to ECD Develop and cost an implementation plan for ECD comprehensive package of services. Approval of comprehensive package of ECD services by April 2013
Implement the Comprehensive Package for ECD services
DSD (lead), DBE, DOHDWCPD, SALGA, DWA, DCSHome AffairsCOGTA
Short Term
15
4. CORE PACK OF COMPREHENSIVE ECD SERVICESOBJECTIVE AN EXPANDED, STRENGTHENED AND COSTED COMPREHENSIVE
PACKAGE OF SERVICES FOR ECD.
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
17.Develop mechanisms and service delivery model for a comprehensive package of ECD services for children birth to school going, ensuring government provisioning of the obligatory services
H Service delivery model developed
DSD (lead), DoH, DBE, DHA, DWCPD, Human Settlements,
Short Term
16
5. ECD INFRASTRUCTUREOBJECTIVE TO DEVELOP AN INTEGRATED INFRASTRUCTURE POLICY FOR ECD
OUTPUT PRIORI
TY
L/M/H
ACTIVITIES RESPONSIBIL
ITY
TIME
FRAME
BUD
GET
18. Audit of existing ECD infrastructure provisioning
H Produce an audit report by March 2014 with an Improvement Action Plan Identify models of good practice for differentiated ECD services
DSD (lead), COGTA, SALGAPublic Works, Human Settlements, NDA, DWCPD
Short Term
19. Develop an integrated infrastructure policy for ECD
H Identify all policies relating to infrastructure on ECD. Compile a list of all applicable policies relating to infrastructure for ECD. Identify the gaps and challenges in the various infrastructure policies. Alignment of the infrastructure policies.Model by-laws on infrastructure developed and circulated to all municipalities by November 2013 Proposed amendments to infrastructure policies on ECD to be included in the Parliamentary legislative programme. Promulgation and implementation of the agreed upon infrastructure policies amendments Develop a rural infrastructure rollout plan for ECD plan
DSD (lead), COGTA, SALGAPublic Works, Human Settlements, NDA, DWCPD
Short Term
17
OBJECTIVE AN EXPANDED, STRENGTHENED AND COSTED COMPREHENSIVE
PACKAGE OF SERVICES FOR ECD.
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
20. Amend and consolidate spatial norms and standards for ECD infrastructure
M Develop an integrated norms and standards for ECD infrastructure
DSD (lead) COGTA, SALGAPublic Works, Human Settlements, NDA, DWCPD, Municipalities
Medium Term
5. ECD INFRASTRUCTURE
18
6. FUNDING AND PARTNERSHIPS
OBJECTIVE AN ECD SECTOR FUNDING PLAN IS DEVELOPED INCLUDING
CONSIDERATION OF FUNDING MODELS FOR THE PROPOSED SET OF
COMPREHENSIVE ECD SERVICES, ENSURING THAT POOR AND
VULNERABLE CHILDREN, INCLUDING CHILDREN WITH DISABILITIES,
CAN ACCESS ECD SERVICES.
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
21. Identify and conduct research on all existing funding models
M Identify and conduct research on all existing funding models Compile a list of all applicable funding models relating to ECD. Identify the gaps and challenges in the various funding models for ECD services.
DSD (lead), DBE, DOHCOGTA, National Treasury, DWCPD
Short Term
Develop a comprehensive funding model with different funding options and mechanisms The new proposed funding model to be included in the Parliamentary legislative programme Implementation of the approved funding model
DSD (lead), DBE, DOHCOGTA, National Treasury, DWCPD
Medium Term
19
6. FUNDING AND PARTNERSHIPS
OBJECTIVE AN ECD SECTOR FUNDING PLAN IS DEVELOPED INCLUDING
CONSIDERATION OF FUNDING MODELS FOR THE PROPOSED SET OF
COMPREHENSIVE ECD SERVICES, ENSURING THAT POOR AND
VULNERABLE CHILDREN, INCLUDING CHILDREN WITH DISABILITIES,
CAN ACCESS ECD SERVICES.
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
21. Funding policy with differentiated modalities for ECD developed
H ECD funding policy with the cost-benefits of differentCosted ECD service models by November 2013
DSD (lead), National Treasury, DBE, DOH, DWCPD
Short Term
22. Funding norms and standards developed for every modality
H Bench marks available for norms and standards for all services available by May 2013Funding Norms and Standards available by June 2013
DSD (lead), DBE DOH, DWCPD
Short Term
20
6. FUNDING AND PARTNERSHIPS
OBJECTIVE AN ECD SECTOR FUNDING PLAN IS DEVELOPED INCLUDING
CONSIDERATION OF FUNDING MODELS FOR THE PROPOSED SET OF
COMPREHENSIVE ECD SERVICES, ENSURING THAT POOR AND
VULNERABLE CHILDREN, INCLUDING CHILDREN WITH DISABILITIES,
CAN ACCESS ECD SERVICES.
OUTPUT PRIORITY
L/M/H
ACTIVITIES RESPONSIBILIT
Y
TIME
FRAME
BUDGET
24. Develop an ECD Sector funding plan
Develop an ECD Sector Funding
plan
DSD (lead),
DBE DOH
DWCPD,
National
Treasury
25.Identify government and private donors to leverage resources for ECD services including children with disabilities.
H increase leverage and lobby for adequate financial and human resources for ECD from Government
Lead DSD, National Treasury, DWCPD and relevant stakeholders
Short Term
21
6. FUNDING AND PARTNERSHIPS
OBJECTIVE AN ECD SECTOR FUNDING PLAN IS DEVELOPED INCLUDING
CONSIDERATION OF FUNDING MODELS FOR THE PROPOSED SET OF
COMPREHENSIVE ECD SERVICES, ENSURING THAT POOR AND
VULNERABLE CHILDREN, INCLUDING CHILDREN WITH DISABILITIES,
CAN ACCESS ECD SERVICES.
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBI
LITY
TIME
FRAME
BUDGE
T26. Strengthening of the existing ECD donor forum for ECD services
H Identify private donors to leverage resources for ECDDevelop Memorandums of Understanding (MOUs) with Donors.
Lead DSD, National Treasury, DWCPD and relevant stakeholders
Short Term
22
7. RESEARCH, MONITORING AND EVALUATION
OBJECTIVE DEVELOP AN INTEGRATED MONITORING AND EVALUATION
FRAMEWORK FOR ECD.
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBI
LITY
TIME
FRAME
BUDGE
T27. Develop an Integrated Monitoring and Evaluation framework for ECD
M Review existing Monitoring and Evaluation frameworks and align them with the new integrated ECD Policy. Develop an integrated M&E framework aligned to the new ECD policy. Test the validity and reliability of the integrated Monitoring and Evaluation framework
DPME (lead), DSD, DOH, DBE DWCPD
Medium to Long term
23
8. COMMUNICATION AND AWARENESSOBJECTIVE COMMUNICATION STRATEGY IMPLEMENTED TO WIDEN KNOWLEDGE
AND AWARENESS OF IMPORTANCE OF ECD AND WHERE SUPPORT IS
AVAILABLE, IN PARTICULAR EARLY IDENTIFICATION, INTERVENTION
AND REFERRAL WHERE NECESSARY.
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBI
LITY
TIME
FRAME
BUDGE
T28. Develop an integrated inter-sectoral awareness raising and communication strategy.
H Provide public education and raise public awareness on the importance of Early Childhood Development to ensure that all young children have access to quality ECD programmes/services. Inform communities, parents and caregivers about the comprehensive Package of services for ECD and how to access the comprehensive Package of services for ECD. Make the community and all South Africans in general, aware and commit them in supporting the implementation of S.A Integrated Plan of Action for ECD. Inform communities about the training and opportunities in ECD through Expanded Public Works Programmes.
GCIS (lead), Department of Communicationand SABC, DSD, DWCPD, DBE, DoH Communications Sub-committee with representatives from all departments under the leadership of the GCIS
Short Term and on going
24
8. COMMUNICATION AND AWARENESSOBJECTIVE COMMUNICATION STRATEGY IMPLEMENTED TO WIDEN KNOWLEDGE
AND AWARENESS OF IMPORTANCE OF ECD AND WHERE SUPPORT IS
AVAILABLE, IN PARTICULAR EARLY IDENTIFICATION, INTERVENTION
AND REFERRAL WHERE NECESSARY.
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBI
LITY
TIME
FRAME
BUDGE
T29. Communication materials developed
M Communicate key messages through Media (radio, television, print media)
Communications Sub-committee with representatives from all departments under the leadership of the GCIS
Medium
term
30.Advocacy, Communications and Social Mobilisation Campaign implemented.
M Plan advocacy communication and social mobilisation Campaign
DSD (lead), DBE DOH GCIS, DWCPD
Medium
Term
25
8. COMMUNICATION AND AWARENESSOBJECTIVE COMMUNICATION STRATEGY IMPLEMENTED TO WIDEN KNOWLEDGE
AND AWARENESS OF IMPORTANCE OF ECD AND WHERE SUPPORT IS
AVAILABLE, IN PARTICULAR EARLY IDENTIFICATION, INTERVENTION
AND REFERRAL WHERE NECESSARY.
OUTPUT PRIORIT
Y L/M/H
ACTIVITIES RESPONSIBILI
TY
TIME
FRAME
BUDGE
T31. ECD Annual Awards held
H Preparations for the 10th ECD Annual awards
Communications sub-committee - GCIS
Short
Term
32. Roll out of the ICT Strategy for Children
M Roll out of ICT Strategy to ECD children in rural areas.
Department of Communications (lead) GCIS, DSD, DBE, DOH, DWCPD, COGTA, SALGA, DCS
Medium
Term
26
Conclusion
• This is an integrated programme of Action which requires the commitment of all governments departments, stakeholders and the broader ECD sector in realising the objectives of building a better future for the young children in SA.
27
RECOMMENDATION
• The Portfolio committee on Social Development take note of the presentation made on the integrated ECD Programme of Action - Moving Ahead
28
THANK YOU