department of collegiate and technical...

20
Department of Collegiate and Technical Education Introduction to Estimation (Unit 1) Course outcome Estimation & Costing( V Semester) Civil Engineering Civil Engineering 15CE53T

Upload: others

Post on 27-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

Department of Collegiate and Technical Education

Introduction to Estimation (Unit 1)

Course outcome

Estimation & Costing( V Semester)

Civil Engineering

Civil Engineering – 15CE53T

Page 2: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

Table of Content

➢ Introduction

➢ Purpose Of Estimation

➢ Types Of Estimates

➢ Deduction & Measurement Rules

➢BOQ, Schedule Of Rates & Lead Statement

➢ Test - MCQ

Civil Engineering – 15CE53T

Page 3: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

Introduction

ESTIMATION:

An estimate is the anticipated or probable cost of work and is

usually prepared before the construction is taken up.

Civil Engineering – 15CE53T

Page 4: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

Purpose of Estimation

•It gives an idea of the cost of the work, i.e whether the project could

be taken or not.

•To get administration approvals in case of govt projects.

•It gives an idea of time required for the completion of the work.

•It is required to invite the tenders and quotations and to arrange

contract.

•It is also required to control the expenditure during the execution of

work.

•Estimate decides whether the proposed plan matches the funds

available or not.

Civil Engineering – 15CE53T

Page 5: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

Data Required For Estimation

Civil Engineering – 15CE53T

DATA Required

DRWAINGS

RATESSPECIFICATIONS

Page 6: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

Types Of Estimates

Civil Engineering – 15CE53T

•Preliminary estimate / approximate/ rough estimate

•Plinth area estimate

•Cube rate estimate

•Approximate quantity method estimate

• Detailed estimate / item rate estimate

•Revised estimate

•Supplementary estimate

•Supplementary & revised estimate

•Annual repair and maintenance estimate

Page 7: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖Preliminary estimate / approximate/ rough

estimate

Civil Engineering – 15CE53T

This is prepared at the beginning of the project, with a little

information available with similar project reference.

❖Plinth area estimate

Plinth area estimate = plinth area x rate

= ( Floor area + wall area) x rate

Page 8: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖Cube rate estimate

Civil Engineering – 15CE53T

Cube rate estimate = cubical content x rate

= ( L x b x d) x rate.

❖Approximate quantity method estimate

Approximate quantity method estimate = total length of the

wall x rate per meter.

Page 9: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖Detailed estimate / item rate estimate

Civil Engineering – 15CE53T

It consists of working out each and every items of work and

their cost . it is prepared in two stages.

•Details of measurements and calculation of quantities

•Abstract of estimate form.

Page 10: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖Details of measurements and calculation of

quantities

Civil Engineering – 15CE53T

The complete work is divided into various items and each

quantity is calculated and entered into format as shown :

Page 11: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖Abstract of estimate form

Civil Engineering – 15CE53T

The cost of each item of work is calculated from already

computed quantity .. the rates are taken from s r or from rate

analysis.

•3 % to 5% is added for contingencies

( unforeseen expenditures)

•1.5 % to 3% for work charged establishment

Page 12: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖ Revised estimate

Civil Engineering – 15CE53T

It is done under any one of the following circumstances:

•When the original estimate exceeds or likely to exceed by

more than 5%.

•In case where there is a structural alterations

•When the sanctioned amount is more than the actual

requirement.

Page 13: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

• While a work is in progress, if additional works are incurred ,

for such supplementary work sanctioned amount may shortfall

, then there is a need of supplementary estimate

❖ Supplementary estimate

Page 14: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖ Supplementary and revised estimate

Civil Engineering – 15CE53T

When it is necessary to increase the volume of the work , then

revise estimate may be done for the increased volume of work.

❖Annual repair and maintenance estimate

•It is prepared to maintain the structure or work in safe

condition,

•It includes repair works of buildings, roads, bridges and

culverts.

Page 15: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖ Units of measurements for different items of works

Civil Engineering – 15CE53T

•For single units – no’s ( eg: doors, windows, truss etc..)

•For linear measurements – running metre (eg: cornice, hand

rail, band concrete)

•For surface measurements involve area – square meters (m2)

(eg: plastering, white washing painting)

•For cubical contents – cubic metre( eg: earth work, cement

concrete, masonry etc

Page 16: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖ Deduction of openings in different items of work

and measurement as per BIS-2000

Civil Engineering – 15CE53T

Plastering:

Rules for measurements:

•Plastering on roofs, ceilings and walls shall be measured

separately.

•Removing plaster by scraping shall be measured separately in

m2

•Plastering at a height greater than 10 m above ground/datum level

shall be measured separately in stages of 5-m height.

•All plastering shall be measured in square meters unless

otherwise described.

Page 17: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖ Rules for Deduction

Civil Engineering – 15CE53T

➢No deduction shall be made for openings not exceeding 0.5 m2 each and no

addition shall be made for reveals, jambs, soffits, sills, etc, of these openings

➢Deductions for openings exceeding 0.5 m2 but not exceeding 3 m2 each shall

be made as follows and no addition shall be made for reveals: jambs, soffits,

sills, etc, of these openings:

➢When both faces of wall are plastered with same plaster, deduction shall be

made for one face only

➢When width of door frame is equal to thickness of wall or is projecting

beyond thickness of wall, full deduction for opening shall be made from each

plastered face of the wall.

➢In case of openings of area above 3 m2 each, deduction shall be made for

opening on each face but jambs., soffits and sills shall be

➢ measured.

Page 18: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖ Bill Of Quantities

Civil Engineering – 15CE53T

A bill of is a document used in tendering in the construction

industry in which materials, parts, labors ( and their cost) are

itemized to complete a given project

❖ Schedule of rates

S r is a list of rates of various items of works. To facilitates the

preparation of estimates.

•It is maintained by p w d in the form of printed book.

•It contains all the rates like, materials, labor wages, transportation

charges etc..

Page 19: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

❖ Lead statement

Civil Engineering – 15CE53T

Lead statement: the distance between the source of availability of

material and construction site is known as "lead " and is expected

in km.

Page 20: Department of Collegiate and Technical Educationdte.karnataka.gov.in/Institutes/gptraichur/FileHandler/... · Test - MCQ Civil Engineering –15CE53T. Introduction ESTIMATION: An

Mr. Madhu

Senior Lecturer,

Department of Civil Engineering,

G.P.T Raichur