department of collegiate and technical...
TRANSCRIPT
Department of Collegiate and Technical Education
Introduction to Estimation (Unit 1)
Course outcome
Estimation & Costing( V Semester)
Civil Engineering
Civil Engineering – 15CE53T
Table of Content
➢ Introduction
➢ Purpose Of Estimation
➢ Types Of Estimates
➢ Deduction & Measurement Rules
➢BOQ, Schedule Of Rates & Lead Statement
➢ Test - MCQ
Civil Engineering – 15CE53T
Introduction
ESTIMATION:
An estimate is the anticipated or probable cost of work and is
usually prepared before the construction is taken up.
Civil Engineering – 15CE53T
Purpose of Estimation
•It gives an idea of the cost of the work, i.e whether the project could
be taken or not.
•To get administration approvals in case of govt projects.
•It gives an idea of time required for the completion of the work.
•It is required to invite the tenders and quotations and to arrange
contract.
•It is also required to control the expenditure during the execution of
work.
•Estimate decides whether the proposed plan matches the funds
available or not.
Civil Engineering – 15CE53T
Data Required For Estimation
Civil Engineering – 15CE53T
DATA Required
DRWAINGS
RATESSPECIFICATIONS
Types Of Estimates
Civil Engineering – 15CE53T
•Preliminary estimate / approximate/ rough estimate
•Plinth area estimate
•Cube rate estimate
•Approximate quantity method estimate
• Detailed estimate / item rate estimate
•Revised estimate
•Supplementary estimate
•Supplementary & revised estimate
•Annual repair and maintenance estimate
❖Preliminary estimate / approximate/ rough
estimate
Civil Engineering – 15CE53T
This is prepared at the beginning of the project, with a little
information available with similar project reference.
❖Plinth area estimate
Plinth area estimate = plinth area x rate
= ( Floor area + wall area) x rate
❖Cube rate estimate
Civil Engineering – 15CE53T
Cube rate estimate = cubical content x rate
= ( L x b x d) x rate.
❖Approximate quantity method estimate
Approximate quantity method estimate = total length of the
wall x rate per meter.
❖Detailed estimate / item rate estimate
Civil Engineering – 15CE53T
It consists of working out each and every items of work and
their cost . it is prepared in two stages.
•Details of measurements and calculation of quantities
•Abstract of estimate form.
❖Details of measurements and calculation of
quantities
Civil Engineering – 15CE53T
The complete work is divided into various items and each
quantity is calculated and entered into format as shown :
❖Abstract of estimate form
Civil Engineering – 15CE53T
The cost of each item of work is calculated from already
computed quantity .. the rates are taken from s r or from rate
analysis.
•3 % to 5% is added for contingencies
( unforeseen expenditures)
•1.5 % to 3% for work charged establishment
❖ Revised estimate
Civil Engineering – 15CE53T
It is done under any one of the following circumstances:
•When the original estimate exceeds or likely to exceed by
more than 5%.
•In case where there is a structural alterations
•When the sanctioned amount is more than the actual
requirement.
• While a work is in progress, if additional works are incurred ,
for such supplementary work sanctioned amount may shortfall
, then there is a need of supplementary estimate
❖ Supplementary estimate
❖ Supplementary and revised estimate
Civil Engineering – 15CE53T
When it is necessary to increase the volume of the work , then
revise estimate may be done for the increased volume of work.
❖Annual repair and maintenance estimate
•It is prepared to maintain the structure or work in safe
condition,
•It includes repair works of buildings, roads, bridges and
culverts.
❖ Units of measurements for different items of works
Civil Engineering – 15CE53T
•For single units – no’s ( eg: doors, windows, truss etc..)
•For linear measurements – running metre (eg: cornice, hand
rail, band concrete)
•For surface measurements involve area – square meters (m2)
(eg: plastering, white washing painting)
•For cubical contents – cubic metre( eg: earth work, cement
concrete, masonry etc
❖ Deduction of openings in different items of work
and measurement as per BIS-2000
Civil Engineering – 15CE53T
Plastering:
Rules for measurements:
•Plastering on roofs, ceilings and walls shall be measured
separately.
•Removing plaster by scraping shall be measured separately in
m2
•Plastering at a height greater than 10 m above ground/datum level
shall be measured separately in stages of 5-m height.
•All plastering shall be measured in square meters unless
otherwise described.
❖ Rules for Deduction
Civil Engineering – 15CE53T
➢No deduction shall be made for openings not exceeding 0.5 m2 each and no
addition shall be made for reveals, jambs, soffits, sills, etc, of these openings
➢Deductions for openings exceeding 0.5 m2 but not exceeding 3 m2 each shall
be made as follows and no addition shall be made for reveals: jambs, soffits,
sills, etc, of these openings:
➢When both faces of wall are plastered with same plaster, deduction shall be
made for one face only
➢When width of door frame is equal to thickness of wall or is projecting
beyond thickness of wall, full deduction for opening shall be made from each
plastered face of the wall.
➢In case of openings of area above 3 m2 each, deduction shall be made for
opening on each face but jambs., soffits and sills shall be
➢ measured.
❖ Bill Of Quantities
Civil Engineering – 15CE53T
A bill of is a document used in tendering in the construction
industry in which materials, parts, labors ( and their cost) are
itemized to complete a given project
❖ Schedule of rates
S r is a list of rates of various items of works. To facilitates the
preparation of estimates.
•It is maintained by p w d in the form of printed book.
•It contains all the rates like, materials, labor wages, transportation
charges etc..
❖ Lead statement
Civil Engineering – 15CE53T
Lead statement: the distance between the source of availability of
material and construction site is known as "lead " and is expected
in km.
Mr. Madhu
Senior Lecturer,
Department of Civil Engineering,
G.P.T Raichur