DEMOLITION OF STRUCTURES A Seminar on

Upload: abhinav-rawat

Post on 28-Jul-2015

82 views

Category:

Engineering


1 download

TRANSCRIPT

Page 1: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

DEMOLITION OF STRUCTURES

A Seminar on

Page 2: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

INDEX

I. IntroductionII. HistoryIII. ObjectivesIV. Steps before DemolitionV. Demolition sequenceVI. Methods of Demolition

Page 3: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

I. INTRODUCTION

Demolition is bringing down the building and other structures safely.

The demolition of structure with the help of explosives is called as implosion.

The main objective for demolition may be the age of the structure.

Methods of demolition depends upon the type of structure, height and surrounding structures.

Page 4: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Demolition of a building

Page 5: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

II. HISTORY Historians generally agree that the first true

"explosive" was black powder, which was developed around the 13th century. 

The first recorded use of black powder for demolition purposes appears to have occurred in the early 1600s, when quarries in Hungary began using it for rock blasting.

Black powder was put to use in the tin mines of England, and Switzerland adopted blasting technology for road construction.

Throughout the 1930s, structural explosive demolition was overseen by engineers working directly for large dynamite manufacturers.

Page 6: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

III. OBJECTIVES

Prevention damaging the neighbourhood environment. Repair of damaged structures. Construction of other structure at that previously

constructed site. Provides safety for the occupants in the building.

Page 7: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

IV. STEPS BEFORE DEMOLITION

1. Surveying

2. Removal of hazardous materials

3. Preparation of plan

4. Safety measures

Page 8: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

1. Surveying:

The building survey should cover following: The construction materials.  The existing use and, if possible, the past uses of the building prior

to demolition.  Adjoining pedestrian and vehicular traffic conditions.  The sensitivity of neighbourhood with respect to noise, dust,

vibration and traffic impact.  Available site area to allow on-site sorting of building debris.

Page 9: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

2. Removal of hazardous materials:

Asbestos Containing Material In the case when asbestos

containing material are discovered, specialist contractor shall be employed to remove such asbestos containing material. The asbestos waste should be handled, stored and disposed of as chemical waste in accordance with the Waste Disposal Regulation.

Soil Contamination Material In the case when possible soil

contamination material is present, specialist shall be employed to prepare soil contamination test proposal and submit such proposal to the Environmental Protection Department for comment.

Asbestos Material

Soil Contamination

Page 10: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

3. Preparation of plan:

A plan showing location of the building to be demolished, sections of the slopes with ground level contours and detailed topography, ground removal and backfilling, distances of adjacent structures from the building to be demolished.

A layout plan of all floors of the building to be demolished, with adequate sections.

A plan showing the procedure for the demolition of the building.

A plan showing the proposed shoring and temporary support to be provided to the building to be demolished.

In the case when powered mechanical plants and equipment are used, a plan showing the route of movement of powered mechanical plants and equipment.

Page 11: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
Page 12: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
Page 13: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

4. Safety measures:

Training and Communication: Demolition workers, including

plant or equipment operators, shall go through proper job safety training and be informed of the potential hazards by attending training sessions as well as on-the-job training.

Equipment Maintenance:  All equipment shall be tested

and examined before use. They shall be properly stored and maintained. The equipment shall be inspected daily and results of the inspection shall be recorded accordingly.

Page 14: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Electrical Safety A properly connected power source from a local electric utility

supplier or a mobile electricity generator shall be utilized in demolition sites.

Fire All flammable goods shall be removed from site unless they

are necessary for the works involved. Any remaining flammable goods shall be stored in proper storage facilities. All furniture, timber, doors, etc. shall be removed before any welding work is performed. Fire fighting appliances shall be provided and maintained in working conditions.

Page 15: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Safety Management

Page 16: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

V. DEMOLITION SEQUENCE All cantilevered structures, verandas and features

attached to the external walls shall first be demolished prior to demolition of main building.

When demolishing the roof structure, all lift machine rooms and water tanks at high level shall be demolished in “top down” sequence to the main roof level.

Floor beams shall be demolished in the order of cantilevered beams, secondary beams and then main beams.

Columns and load bearing walls shall be demolished after removal of beams on top.

If site conditions permit, the first floor slab directly above the ground floor may be demolished by machine standing on ground.

Page 17: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Demolition of the floor slabs shall begin at mid span and work towards the supporting beams.

Page 18: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Floor beams shall be demolished in the order of cantilevered beams, secondary beams and then main beams.

Wire and winch shall be used to secure the cross beam to other structural members.

The concrete is first broken away at both ends near its column supports to expose the reinforcement.

Reinforcement shall be then cut to partially drop the beam and the brought down with wire.

Page 19: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Secure the column by wire and winch to existing structure.

Pre-weakening at the bottom of column:

1) Break away the concrete to expose the reinforcing bars.

2) Cut the reinforcing bars at the exterior half of the column. Cutting shall be performed immediately prior to pulling.

Pulling down the column in a controlled motion.

Page 20: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

VI. METHODS OF DEMOLITION:

A. Ball and craneB. DismantlingC. Pneumatic and hydraulic breakerD. Pressure burstingE. Explosives

Page 21: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

A. Ball and crane

This is one of the oldest and most commonly used methods for building demolition. A crane uses a wrecking ball, weighing up to 6120 kg, which is either dropped onto or swung into the element to be demolished.

The ball is made from forged steel, which means the steel is not cast into a mould in a molten state. It is formed under very high pressure while the steel is red hot (soft but not molten) to compress and to strengthen it.

Concrete members can be broken into small pieces, but secondary cutting of reinforcing may be necessary.

Wrecking ball at rest

Swinging the wrecking ball

Page 22: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
Page 23: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT
Page 24: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Advantages:1) To demolish roofs and other horizontal spans.

2) The wrecking balls are still used when demolition may not be possible due to local environmental issues or asbestos/lead building content.

1) It demands a great deal of skill from the crane operator.

2) The height of a building that can be demolished is limited by crane size and working room; however, buildings as high as 20 stories have been demolished.

3) The breakup process can cause considerable dust, vibration and noise which may be objectionable.

Advantages and Disadvantages of Ball and Crane method:

Advantages

Disadvantages

Page 25: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

B. Dismantling

Selective or complete demolition of concrete structures is possible by cutting elements and then removing them with a crane.

The cutting process may be by sawing, water jetting or thermal lance.

Because the surface of the cut concrete is smooth and relatively regular, these methods have particular application when the objective is partial demolition, for instance in the creation of openings in walls and slabs.

Dismantling a beam

Page 26: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Cutting with a water jet minimizes dust and eliminates vibration and fire hazards. An abrasive and water-catching system is required to clean up during the jetting process.

Hydro demolition uses  a high pressure supersonic water jet, that penetrates the pores and cracks of the concrete and  builds up an internal pressure.  When this pressure exceeds the tensile strength of the concrete, the concrete breaks.

The water jet can be used not only for cutting straight lines but also contours, a useful feature for cutting access manholes.

Water Jet cutting

Page 27: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

A thermal lance is created by packing a seamless mild steel tube with low carbon rods and passing oxygen through the tube.

While this method eliminates vibration and dust problems, it creates other hazards associated with smoke and fire danger.

Whether sawing, jetting or lancing is used to dismantle the structure or its components, each element must be safely lowered to the ground.

Thermal Lance Sawing method

Page 28: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

 1) Dismantlement of building components, specifically for re-use, recycling, and waste management.

2) Reducing disposal costs where waste collection, hauling or disposal is supported by the tax base.

3) Building components that are dismantled will need to be stored in a secure, dry location. This will protect them from water damage and theft.

1)  The amount of time and cost of labor are the main drawbacks.

2)  Harvesting materials from a structure can take weeks, whereas demolition may be completed in roughly a day.

3) Toxic waste such as asbestos sheets and lead paint have no resale value so they are discarded.

Advantages and Disadvantages of Dismantling method:

Advantages

Disadvantages

Page 29: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

C. Pneumatic and hydraulic breaker

 A common piece of equipment used for demolishing bridge decks, foundations and pavements is a hydraulically or pneumatically operated, boom-mounted breaker.

The advantages of a machine mounted breaker may include a telescoping boom for easy reach and, remote control operation and underwater demolition capabilities

Some of the smaller remote- controlled machines can be lifted through window openings and used inside a building to demolish floors and walls.

Productivity can vary greatly depending on hammer size, type of concrete, amount of reinforcing and working conditions.

Page 30: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Pneumatic hammer

A jackhammer is a pneumatic or electro-mechanical tool that combines a hammer directly with a chisel. Hand-held jackhammers are typically powered by compressed air, but some use electric motors.Electric powered tools come in a variety of sizes from about 12 lbs - 65 lbs. They require an external power source, but do not require a compressor.

Page 31: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Hydraulic breaker

A hydraulic jackhammer, typically much larger than portable ones, may be fitted to mechanical excavators or backhoes and is widely used for roadwork, quarrying and general demolition or construction groundwork.

 They are used in mines where there is an explosion risk since they lack any high-power electrical circuitry that might cause a triggering spark.

The jackhammer is connected with hydraulic hoses to a portable hydraulic power pack: either a petrol or diesel engine driving a hydraulic pump

Page 32: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

1) The hydraulic breakers have tremendous power output also means they are the most power efficient, getting the most work out of the available energy.

2) A properly used and maintained hydraulic machine can last for a long time.

3) Pneumatic breakers are simpler tools with fewer moving parts, requiring less maintenance.

1) They require power, fuel or battery for their work.2) They tend to be the most expensive types.3) They require an external power source.

Advantages and Disadvantages of Pressure Bursting method:

Advantages

Disadvantages

Page 33: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

D. Pressure bursting

Pressure bursting can be used in cases where relatively quiet, dust-free, controlled demolition is preferred.

Both mechanical and chemical pressure bursting split the concrete, either with a splitting machine operating on hydraulic pressure provided by a motor in the case of mechanical bursting, or through the insertion of an expansive slurry into a pre-determined pattern of boreholes in the case of chemical bursting.

The split concrete is then easily removed, either by hand or by crane.

Both methods work by applying lateral forces against the inside of holes drilled into the concrete.

Pressure bursting

Page 34: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

E. Explosives

Introduction In the controlled

demolition industry, building implosion is the strategic placing of explosive material and timing of its detonation so that a structure collapses on itself in a matter of seconds, minimizing the physical damage to its immediate surroundings.

Despite its terminology, building implosion also includes the controlled demolition of other structures, such as bridges, smokestacks, towers, and tunnels.

Numerous small explosives, strategically placed within the structure, are used to catalyze the collapse. Nitro-glycerine, dynamite, or other explosives are used to shatter reinforced concrete supports. 

RDX-based explosive compounds expand at a very high rate ofspeed, up to 27,000 feet per second (8,230 meters per second)

Page 35: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Building Implosion

Page 36: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Blasting methods employ rapidly expanding gases confined within a series of boreholes to produce controlled fractures which provide for easy concrete removal.

For the demolition of concrete structures it is usual to drill holes at a predetermined angle into the concrete to be removed.

Implosion is the strategic placing of explosive material and timing of its detonation so that a structure collapses on itself in a matter of seconds, minimizing the physical damage to its immediate surroundings.

The technique weakens or removes critical supports so that the building can no longer withstand the force of gravity and falls under its own weight.

Strategic implosion

Page 37: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Pre-blast Considerations

The design may include pre-weakening of the structure, the strategy in placement of the explosives and time delay so that the building will collapse in a safe manner.

Pre-weakening of the structure may include cutting out a portion of the shear walls and other structural elements.

A test blast may be conducted to verify the strength of the structural member and to fine tune the explosive design.

Protection of the adjacent properties and habitats is also an important consideration.

Page 38: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Pre-weakening of the structure may include cutting out a portion of the shear walls and other structural elements.

A test blast may be conducted to verify the strength of the structural member and to fine tune the explosive design.

Protection of the adjacent properties and habitats is also an important consideration.

Page 39: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Process of Implosion

Page 40: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Post-Demolition

Page 41: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Test Blast:

Before carrying out the actual blasting, a test blast, in ordered to ascertain the efficiency of explosive & detonators.

Page 42: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Wrapping of holes:

The wrapping of holes is done to ensure that due to explosion of charges the debris does not fly in air. For this purpose, the holes were covered with gunny bags and iron net after placement of explosive and detonators.

Page 43: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Ballasting:

Ballasting of Charges / Explosives work are carried out in a controlled manner such that there will be a time gap of 1/100 second between two successive blasts. The trigger of charges is done in such a control manner so that the noise pollution and air pollution should be minimum.

Falling of structure:

Once central support/column will be destroyed and adjoining columns will be weakened, due to its gravity the entire mass will come down on its footprints

Page 44: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

CONCLUSION It can be concluded that

demolishing/imploding the building structure will prove very useful, economical and quickest for reconstruction.

Leads to a safe and controlled demolition for the occupants and neighbourhood.

Development in techniques allows rapid demolition with no harm to the environment.

Page 45: DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

REFERENCES

http://www.implosionworld.com/history.html www.wikipedia.com http://archsd.gov.hk/media/11640/

demolition_e2004.pdf http://wiki.iricen.gov.in/doku/lib/exe/

fetch.php?media=m%E0%A4%BEr%E0%A5%8Dc_march_2013:achuta_rao.pdf

http://www.concreteconstruction.net/Images/Demolition%20of%20Concrete%20Structures_tcm45-341335.pdf