RailCorp Version 1.0 Page 1 of 11
Waratah PPTV Test Crew CourseDelivery & Assessment Strategy
Section 1 Course Outline:
CourseCode &Title:
Code:WT 10
Title:Waratah Pre Production Test Vehicle (PPTV) Test Crew Course
Aim or PurposeStatement:
This course aims to equip Participants with the required knowledge and skills to drive thePPTV while under initial test conditions (limited eTIS)
LearningOutcomes:
At the completion of this Course, the participants will be able to:Drivers
Apply power to move the train
Apply brakes to stop the train
Identify the location and function of components and equipment on the PPTV which varyfrom Millennium
Carry out train preparation procedures on PPTV
Respond to fault and alarm indications
Locate Emergency coupler and related cocks
Understand the roles and responsibilities of Train Captain and crew while working onand around the PPTV.
Guards
Perform Guard functions on a moving train
Identify the location and function of components and equipment on the PPTV which varyfrom Millennium, OSCar or HRC
Carry out train preparation procedures on PPTV
Respond to fault and alarm indications
Understand the roles and responsibilities of Train Captain and crew while working onand around the PPTV
Enabling Objectives for PPTV Training are:Drivers
Apply power to move the train Operate driver controls to gain traction in the correct direction smoothly
Apply sufficient traction for safe operation and to suit environmentApply brakes to stop the train
Operate driver controls to bring the train to a halt smoothly
Apply sufficient braking for safe operation and to suit environmentIdentify the location and function of components and equipment on the PPTV which vary fromMillennium
Identify location and function of underfloor components and equipment on the PPTVthat vary by location or function to the Millennium
Describe underfloor components and equipment on the PPTV that vary by locationor function to the Millennium
Identify and describe cab components and equipment in the PPTV Cab that vary bylocation or function to the Millennium
Carry out train preparation procedures on PPTV Navigate and identify alerts and alarms using eTIS
Carry out Driver tasks to check a PPTV is ready for serviceCarry out Driver tasks to prepare a Dead PPTV for Towing
Understand preparatory tasks for a towed Waratah A Set
Understand preparatory tasks when an Waratah A Set is to tow a trainRespond to fault and alarm indications
Identify and report eTIS alerts and alarms
Identify Analogue indications of faults
State fault or alarms correctly to the Train CaptainLocate Emergency coupler and related cocks
Locate emergency coupler
Locate cocks used with the emergency couplerUnderstand the roles and responsibilities of Train Captain and crew while working on and
around the PPTV. Demonstrate appreciation of the role and responsibility of the Train Captain
Demonstrate working effectively with the Train Captain
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
2/11
RailCorp Version 1.0 Page 2 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
GuardsPerform Guard functions on a moving train
Monitor eTIS
Operate Park BrakeIdentify the location and function of components and equipment on the PPTV which vary fromMillennium
Identify location and function of underfloor components and equipment on the PPTVthat vary by location or function to the Millennium
Describe underfloor components and equipment on the PPTV that vary by locationor function to the Millennium
Identify and describe cab components and equipment in the PPTV Cab that vary bylocation or function to the Millennium
Carry out train preparation procedures on PPTV
Navigate and identify alerts and alarms using eTIS
Carry out Driver tasks to check a PPTV is ready for serviceCarry out Driver tasks to prepare a Dead PPTV for Towing
Understand preparatory tasks for a towed Waratah A Set
Understand preparatory tasks when an Waratah A Set is to tow a trainRespond to fault and alarm indications
Identify and report eTIS alerts and alarms
State fault or alarms correctly to the Train CaptainLocate Emergency coupler and related cocks
Locate emergency coupler
Locate cocks used with the emergency couplerUnderstand the roles and responsibilities of Train Captain and crew while working on andaround the PPTV.
Demonstrate appreciation of the role and responsibility of the Train Captain
Demonstrate working effectively with the Train Captain
Nominal Duration: 2 Days
Prerequisites: Applicable?
YES
Participants must be current, qualified Train Drivers and Guards and/or TrainControl personnel, experienced in train testing on Millennium (MILL), Oscar(OSCAR) or Hunter Rail Car (HRC) as examples, and nominated by RailCorp.All Participants must complete a Site Induction for the relevant site where thetraining is to be conducted.
Recertification Applicable?NO
Target Audience: Test Drivers, Test Guards, OSM/Principal personnel identified to support the testing of theWaratah A Set Pre Production Test Vehicle (PPTV).
InquiryRecommendations/Compliance issuesaddressed:
Applicable?
Yes/No
List any Inquiry recommendations or compliance issues identified that thisprogram/course/session addresses and provide an overview of how they areaddressed.
Reference to RiskRegister & KnownHazard Statements:
Applicable?
Yes/No
List any risks/ known hazards that were identified that thisprogram/course/session considers or addresses.
Safety Management
System (SMS)Reference
Applicable?
Yes/No
List any reference to relevant SMS System Requirement or Procedure. (Insert
Document name and number)
Reference torelevant Bus inessRules/ StandardOperatingProcedures:
Applicable?
YES
Under development.
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
3/11
RailCorp Version 1.0 Page 3 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
CourseStructureOverview:
2 Days training as follows:
Day 1
Train Familiarisation
Introduction with eTIS
- Navigate Driver screens
- Navigate Guard screens
Working with the Train Captain
- Roles and responsibilities- Responding to faults and alerts
- Actions during an emergency
TWPs/Minimum Standards
Scenario Based Assessment
Day 2
Cab Familiarisation
RailCorp Preparation Procedure
Operate Test Train:- Apply traction- Braking the train
- Cut out and Cut In
Practical Assessment
Delivery and Assessment Strategy
The course will be delivered and assessed using the test train whilst in the EDI Downermaintenance facility and on the first day of on track operations (day 2 of the course). Trainingwill be undertaken using two facilitators (EDI and RailCorp).
The crew will be trained together. The training can be delivered either on a train or in a classroom. The priority will be to train on a train and if not available then in a classroom.
Day 1 training will cover the technical information related to the operation of the train, workingwith the Train Captain and PPTV TWPs.
Day 2 is conducted on the train on the test track and will cover familiarisation to the cab, ,traction and stop. Also covered is an introduction to PPTV preparation.
Assessments occur on both days to close off each module of training
AssessmentStrategy Overview:
Applicable?
YES
The DEDIR and RailCorp Assessors will conduct assessment together. Wherethe area being assessed is related to the conduct of the duties as a Driver orGuard then the RailCorp Assessor as the Assessor. Where the area beingassessed is related to the technical aspects of the PPTV then the DEDIRAssessor will be the Assessor1 x Scenario based assessments on train familiarisation and working with theTrain Captain
1 x Practical assessments covering train traction and stop
ResourcesRequired:
1 x Downer EDI Facilitator or equivalent.
1 x RailCorp Principal Driver or equivalent. 1 x Facilitators Guide per Facilitator.
1 x Crew Record Book per Participant & Handouts
1 x DRAFT Waratah A SET Operator Manual per Participant./TWPs/MinimumStandards
5 x HRC Operator Manual.
5 x Millennium Operator Manual.
5 x OSCar Operator Manual.
10 x CER01640Rev-PPTV Minimum Standard
10 x Appendix A 100305 Minimum Standard v1.5
10 x CER01642Rev-CN01 PPTV Train Preparation
10 xCER01641 Rev-PPTV Train Working Procedures
Scenario Based Assessment Tool To be packaged by the Assessor to suit theclass size.
Quantity of plain paper.
1 x Scenario Based Assessment Marking Guide.
1 x Classroom set up for up to 15 Participants.
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
4/11
RailCorp Version 1.0 Page 4 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
5 x Desk Easels.
1 x Laptop with access to the web.
1 x Digital Projector.
1 x PPTV for Day 2 suitable operational condition and limited testing on board toallow the priority of operation being for training.
Test Track between two rails stations of approximately 10 to 15 minutes travelduration for Day 2 of the course.
Train Captain for Session 3, Day 1 and all of Day 2.
RailCorp/EDI Downer to adviseQualification Code& Title and/or anyother Certificatesissued:
Code: Qualification/Certificate to be issued:
Statement of Attendance
When to be issued:
Relevant TrainingPackage Code &Title:
Applicable?
NO
Code: Name of Training Package:
Name ofRTO/TrainingProvider:
RailCorp/EDI Downer to advise
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
5/11
RailCorp Version 1.0 Page 5 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
Course Outline:
Course Structure Overview PPTV Crew
SESSION NO & TOPICS TIMINGRESOURCESREQUIRED COMMENTS
DAY ONE (7 hours)Course Introduction
Introduction of key appointments
Explanation of the days training
10 mins Facilitator GuideDRAFT Waratah ASET OperatorManual
SESSION ONE: TRAIN FAMILIARISATION
On Train Learning In Classroom Learning
In Two Groups - One Group per End (groups Guard/Dr iver. System based discussion
whilst on train relating same/similar or differentbetween Millennium or HRC or OSCar and ASet
Commence at underfloor Introduce anddiscuss each system and present theirassessment of the comparison of the A Setto the Millennium while progressing to thecabin
In Cab Driver and Guard desk layout,eTIS, Cupboard 7 and 8 and side cupboardequipment.
Learning Activity
Dead Train Preparation and EMCoupler storage and related cocks
130minutes
Group activity based using Train OperatorManuals relevant to their experience and
Desk Easels.Group review of systems and cab layout, thenpresentation and discussion relating Millenniumor HRC or OSCar and A Set
Break into groups based on the train typethey have worked. Give each group anumber of systems and then have the grouppresent to the class their assessment of thecomparison of systems. Rotate through allsystems
Have the groups then review the cab layout.This may be supplemented by pictures andvideo as available.
Learning Activity
Dead Train Preparation and EMCoupler storage and related cocks
Resources Required Comments Resources Required Comments
PPTV or A Set Truide
ainFacilitator GChecklistsDRAFT Waratah A SET
OperatorManual/TWPs/other
anualsm
The Facilitator uses thechecklist to leaddiscussion and indicatecomponents and
equipment, Seeking fromthe Participants to identifysimilarities or differenceso the Millennium traintThe Facilitator has theParticipants follow thediscussion by referencingthe DRAFT Waratah A
ET Operator ManualS
ClassroomFacilitator GuideDesk Easels x 5DRAFT Waratah A SET
Operator ManualHRC Operator ManualsMillennium OperatorManuals
SCar Operator ManualsO
The use of the OperatorManuals provides anadditional opportunity forthe Participant to become
conversant with theManual. It also reinforcesthe importance ofreferencing the Manualwhen seeking information
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
6/11
RailCorp Version 1.0 Page 6 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
SESSION NO & TOPICS TIMINGRESOURCESREQUIRED COMMENTS
SESSION TWO: INTRODUCTION TO E-TIS
N igate Driver screens
Sign in
av
Train Certificate
tion of tractionDemonstraAuto brake
and stop in
rface
ystem interface
s
Communications
40 minutes
aratah AET Operator
Manual
tyof
ill providea basic introduction tothe system.
mode
s and alarmsFault alert
Alert list
Resets and system inte
Sign off
rd screensNavigate Gua
Sign In
Fault alerts and alarms
Alert list
Resets and s
Park brakes Nightsafe
Doors
Climate control
Lights
Surveillance statu
Fire detection
ClassroomFacilitator Guide
eTIS Web linkLCD projector andLaptop
RAFT WDS
The web based eTISprogram provides
navigation capabiliand representationdata functionality(speed and airressures can bep
imitated on commandby the Facilitator).
As the level of eTIS isunknown and mayexpand during testing,the session w
SESSION THREE: WORKING WITH THE PT up)TRAIN CA AIN (In 1 Gro
Introduction to the Tr
Responsibilities of theain Captain
Train Captain
o iolea
train in an emergency
80 minutes
cilitator Guidesk Easels x 2
rain Captain
participating in the
Lear ng1 scenar
- Fault on thePPTV
Division of Responsibilities Reporting faults
W rking with the Train Captain Scenard discussions
Working through faults
Working together when evacuating the
Train CaptainlassroomC
FaeD
Facilitated learningwith the T
session
ni Activity io
SESSION FOUR: PPTV TWPs/Minimum Standards (In 1 Group)
Group Discussion Led by the PrincipalDr ver covering:
CER01640Rev-PPTV Minimum Stand
i
ard
Appendix A 100305 Minimum Standardv1.5
Engineering Report CER01641 Rev-PPTV Train Working Procedures
60 minutes Training RoomFacilitator GuideSet of TWPS perParticipant
edto allow
the Principal Driver todiscuss the MOS andTWPs with theParticipants
This is an informationonly session providin the training
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
7/11
RailCorp Version 1.0 Page 7 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
SESSION NO & TOPICS TIMINGRESOURCESREQUIRED COMMENTS
ASSESSMENT
Scenario Based Assessment on trainfamiliarisation and working with the Train
Captain.
The Participants are put into Groups of 2as a crew (Driver and Guard)
c t
evid rmay1. Give them a new scenario to work
nt orthe group against a
nario to draw evidence ofcompetence
120minutes nt which
nario/s
es.
ssessment MarkingGuide
The Assessor maymoderate the
responses if required.
Each Group is given a scenario and 15minutes to develop their solution and 5minutes for each to present their solutionper person (Driver/Guard Action)
Facilitator to check their response againsta marking guide and rotate each group
When all of the groups have presentedtheir solutions the Assessor will walkthrough the marking guide notations and
indi ate sufficiency of responsesWhere a group has not provided sufficien
ence in their response the Assesso:
through and represeestion2. Orally qu
new sce
Assessment Toolper Participa
ncludes sceiand paper to writedown their
sponsreA
The Participants aregiven time to develop
their solutions.Once they have donethis, the responsesare handed in to theAssessor.Each crew group isthen called back intothe classroom handedtheir responses backand allowed time topresent their solutionto the Assessor.
Wrap up days trainingBrief on Day 2
10 minutes
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
8/11
RailCorp Version 1.0 Page 8 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
SESSION NO & TOPICS TIMINGRESOURCESREQUIRED COMMENTS
DAY TWO (7 hours)
Introduction to the days training 10 minutes Facilitator Guide
SESSION FIVE: CAB FAMILIARISATION
Reconfirm Cab Layout and all requiredequipment are on board.
Daily Briefing to occur during this period.
60 minutes Facilitator Guide -ChecklistsDRAFT Waratah ASET OperatorManualPPTV at stationTest Track
If more than 5 + 5Participant then thishas to be run as 2 x30 minute sessionsand the groups splitinto 2 with the Guardsfamil at one end andDriver famil at the
other
SESSION SIX: PPTV PREPARATION
Issue:
CER01642Rev-CN01 PPTV TrainPreparation
Discuss:
The procedures seeking comparison tothe train type the participant has operated.
Explain:
That the participants will be trained in theprocedures as crews when rostered to thePPTV and;
Assessed when ready
25 minutes Facilitator GuideCER01642Rev-CN01 PPTV TrainPreparationDRAFT Waratah ASET OperatorManualPPTV at stationTest Track
This is a discussionsession to introduce theprocedure and explainwhen the training andassessment will occur
NOTE: Participants willbe assessed in PPTVPreparation at the startof each night the train is
tested until all areassessed.
SESSION SEVEN: OPERATE TRAIN (In Pairs of a Driver + Guard each end of the train)
DRIVER
Power against Brake test
Apply traction
Braking the train
Cut out
GUARD Observe speed and ride characteristics of
train
Respond if speed and ride characteristicsremain dangerous
Cut out
NoteAt the end of the train run, the in charge crewcut out and the new crew complete a handover and then are trained in traction andbraking back to the original station
160minutes
Facilitator Guide -ChecklistDRAFT Waratah ASET OperatorManualPPTV
Test Track
Assessment DuringLearningComplete procedure inlog book whencompleted learning
5 X 15 minutes percrew per run pluspreparation each end ofthe run
If more that 5 x 5Participants thenoperate andassessment to becombined andcontrolled byFacilitators andAssessors
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
9/11
RailCorp Version 1.0 Page 9 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
SESSION NO & TOPICS TIMINGRESOURCESREQUIRED COMMENTS
ASSESSMENT (In Pairs Driver + Guard)
Power against Brake Test
Apply traction and stop
Work with the Train Captain
Cut out
125minutes
Assessment Toolper Participant
PPTVTest Track
5 X 15 minutes percrew per run plus a
handover at eachend of the run
END OF COURSE PROCEDURES
Course Evaluation 10 minutes
Wrap up of the course 10 minutes
Units of Competency: Appl icable? No
Approval Section 1: Course Outlineby Course Committee Members
By signing below, the Course Committee members acknowledge they have read and agreed with Section 1 of theDelivery & Assessment Strategy prior to the development of curriculum material.
Name Title Signature Date
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
10/11
RailCorp Version 1.0
Date Issued 18/01/1200 Revised: 01/04/2010 C:\Documents and Settings\Paul James\Local Settings\Temporary Internet Files\OLK14A\Delivery_and_Assessment_Strategy_W
Section 2 Detailed Program/Course/Session Information:
A. Mapping of Units of Competency to Courses (i f Program) or Session (if Course):
B. Assessment Methods:
C. Qualifications & Technical Competencies of Trainers/Assessors:
A. Course & Mapping to Units of Competency B. Assessment Methods
CourseCode
Course or Session Title Unit Code(refer to
Section 1)
Full/PartialCompletion
of Unit
AssessedOn/Off the
job
A B C D E F G H
Train Familiarisation Off-the-job
Introduction to eTIS
Off-the-joband On theJob (OnPPTV)
Working with the Train Captain
Off-the-joband On theJob (OnPPTV)
Train Work Procedures (TWPs) (Not Assessed)
Cab Familiarisation andCommunications Equipment
Off-the-joband On theJob (OnPPTV)
RailCorp PreparationOn the Job
(On PPTV)
Operate Test TrainOn the Job(On PPTV)
Assessment Methods Key:
(customise methods accordingly)
A Writtentest
B Practicalobservation
C Questions D RolePlay
E ThirdPartyReport
-
8/12/2019 Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2)
11/11
RailCorp Version 1.0 Page 11 of 11
Date Issued 18/01/2010 Revised: 01/04/2010 Uncontrolled when printedC:\Documents and Settings\Paul James\Local Settings\Temporary Internet
Files\OLK14A\Delivery_and_Assessment_Strategy_Waratah PPTV v1 1 100407 (2).doc
D. Mapping of courses to Units of Competency: Applicable? No
Reasonable Adjustment:
Participants are experienced in train testing and adaption to new trains. The delivery sessions allow for abroad range of experience in terms of Diesel or electric as long as Drivers have single control andeTIS/TOS experience. Likewise for Guards who have had eTIS/TOS experience and similar dooroperational equipment.
Crews will be tested in accordance to their role.
Allowances will be made for the capability of the Test Train as the level of functionality is unknown andmay change during training and assessment
Recognition:
The course is designed for personnel who have no previous experience with the Waratah (A Set) train andspecifically designed for the test crew to the PPTV ONLY. As such there is no recognition available.
Record of Curriculum Materials:
Curriculum materials are located on the RCT G: server under __________ (insert pathway) according to the
Curriculum Development Procedure (QTMS-PR-39).
Evaluation/Review/Validation & Continuous Improvement:
The course package may need to be reviewed once RailCorp business rules for the Waratah (A Set) are issued.
RCT TrainingManagersendorsement(name & signature):
Date:
DAS History:
Version Date Changed Author of changes Descript ion of Changes
0.1 18 JAN 2010 G. Jones Initial development
0.2 19 JAN 2010 G Jones Feedback from EDI and SYDAC
0.3 24 FEB 2010 G. Jones Feedback from EDI and RailCorp
0.4 25 FEB 2010 G Jones Adjustment of delivery strategies
0.5 06 MAR 2010 G. Jones Feedback from EDI and RailCorp
0.6 26 MAR 2010 G. Jones Feedback from Test and Confirm Meetings
0.7 29 MAR 2010 G. Jones Feedback from RailCrop
1.0 01 APR 2010 G. Jones Feedback from Committee Meeting 31/03/2010