delay, disruption and acceleration michael j.r. kremer contract management in international...
TRANSCRIPT
Delay, Disruption and Delay, Disruption and AccelerationAcceleration
Michael J.R. Kremer
Contract Management in Contract Management in International ConstructionInternational Construction
Beijing, April 28, 2009Beijing, April 28, 2009
Delay, Disruption and Acceleration · April 2009 2
1. Introduction1. Introduction
Time is of essence in basically every construction project
Yet, delays of some sort are general rule, rather than the exception
Consequence: claims for extension of time, issue of acceleration
Therefore, closer look to: What are the obligations as to time in general? When and how does acceleration become relevant?
Delay, Disruption and Acceleration · April 2009 3
2. Contractor‘s obligations as to time2. Contractor‘s obligations as to time
Modern construction contracts typically foresee three separate, but inter-related express obligations:
First obligation: Contractor to complete works by certain date or within specified period; possibly with stage or sectional completion obligation
Second obligation: Contractor to progress the works regularly and diligently
Third obligation: Contractor to prepare and work to an accepted program (work schedule)
Delay, Disruption and Acceleration · April 2009 4
2.1 2.1 First obligation: specific date/periodFirst obligation: specific date/period
In case of “period for completion”, identification of “commencement date” as well as periods crucial
e.g.: x months from the “Commencement Date” clarification of “days” and “weeks”
If no date or period foreseen: obligation to complete “by a reasonable time”
Standard form contracts regularly provide for express obligation
Delay, Disruption and Acceleration · April 2009 5
2.1 2.1 First obligation: specific date/period (cont’d)First obligation: specific date/period (cont’d)
Effect of specific date of completion typically no qualification as of the essence clauses for extension of time or liquidated damages
prevent such interpretation Specific date of completion of little assistance in
management of the project Employer wants to take action early to avoid late
completion stage or sectional completion obligations and
liquidated damages give only limited recourse
Delay, Disruption and Acceleration · April 2009 6
2.2 2.2 Second obligation: “progress regularly”Second obligation: “progress regularly”
If specific date for completion agreed, no “implied” second obligation
Contractor has right to plan, execute and progress the works
severe evidential difficulties for Employer Therefore: express obligation (regularly included
in standard form contracts)
Delay, Disruption and Acceleration · April 2009 7
2.2 2.2 Second obligation: “progress regularly” (cont’d)Second obligation: “progress regularly” (cont’d)
Effect of express obligation to proceed regularly and diligently
“Proceed continuously, industriously and efficiently with appropriate resources so as to progress steadily towards completion substantially in accordance with the contract.”
Contractor may not slow down even if ahead in time schedule
Employer may have remedy of damages, even if completed in time, if Employer can show “loss”
Delay, Disruption and Acceleration · April 2009 8
2.3 2.3 Third obligation: programThird obligation: program
“program/work schedule” no legal term Requires basic information of activities or operation
with a list of dates for commencement and completion of respective activities
Types of programs: Bar Chart Network Program Line of
Balance
Delay, Disruption and Acceleration · April 2009 9
2.3 2.3 Third obligation: program (cont’d)Third obligation: program (cont’d)
Potential roles of the program: Monitor role:
- milestone program- progress program- prediction program
Dynamic role- management program- compensation program
Delay, Disruption and Acceleration · April 2009 10
3. Employer‘s obligations as to time3. Employer‘s obligations as to time
Completion of obligations specified in the contract e.g. supply information, provide material, execution
of certain pre-condition works, permits, appointment of engineer etc.
- at times specified in program- or reasonable times with regard to execution of works
Typically no obligation to comply with approved program, rather obligation not to hinder Contractor
implied obligation not to hinder implied obligation to cooperate
Delay, Disruption and Acceleration · April 2009 11
4. Acceleration4. Acceleration
What does the term mean? What is the benchmark? Basically, tow situations relating to the overall
works: Contractor is required to finish earlier than the
contractual date- variation of the contract, i.e. constructive order/change order- constructive acceleration
Contractor is likely to complete later than the contractual completion date
- acceleration to reduce delays
Delay, Disruption and Acceleration · April 2009 12
4.1 Constructive acceleration4.1 Constructive acceleration
typical example for constructive acceleration claim:
Equipment procured by Employer from a third-party is delivered late. Contractor’s words are delayed. Contractor applies for Extension of Time (EOT). Interim assessment of the Engineer denies EOT; final review still pending. Employer presses Contractor to increase resources to make up for the delay.
Delay, Disruption and Acceleration · April 2009 13
4.1 Constructive acceleration (cont’d)4.1 Constructive acceleration (cont’d)
Contractor‘s stark choice: Continue in hope to prove EOT or “accept” to be in
default temporarily and take steps to mitigate Nature of problem: contract’s EOT procedures
and contractor’s “temporary default” Conclusion: Constructive acceleration claim
presents significant legal difficulties; claim for disruption may be possible with fewer legal difficulties
Delay, Disruption and Acceleration · April 2009 14
4.2 4.2 Acceleration to reduce delaysAcceleration to reduce delays
The issue of right or obligation to reduce the effect of qualifying delays may arise in three ways:
- Contractor’s may have right to choose how to deal with a qualifying delay and whether to accelerate or not and to recovery on the basis of this right;
- Contractor may be entitled to EOT and any associated loss only to the extent that he has mitigated the effect of the delays;
- Contractor may be under an obligation to progress the works including an express obligation to mitigate delays and the failure to do so prevents remedies of EOT/associated losses.
Delay, Disruption and Acceleration · April 2009 15
4.2 4.2 Acceleration to reduce delays (cont’d)Acceleration to reduce delays (cont’d)
Mitigation of delay by acceleration? Contractor reacts to the qualifying delay
- most contracts provide for EOT provisions and express terms for agreement for acceleration
- generally no right of contractor to accelerate and recover costs (except if “constructive order”)
- “reasonabless”-argument Contractor does not react to the qualifying delay
- Generally no obligation where EOT provisions apply Mitigation by managing delay?
obligation to re-plan recourses and activities obligation to progress “regularly & diligently” includes
managing of effects of delay
Delay, Disruption and Acceleration · April 2009 16
4.3 Obligation to accelerate?4.3 Obligation to accelerate?
Differentiation by reason for delay: Delay not caused by Contractor, i.e. entitled to EOT
- no obligation; only by means of separate agreement Delay caused by Contractor:
- in principle no obligation (discretion of contractor in regard of his own culpable delay)
- contract may provide power to order Contractor to adopt acceleration measures
“Indirect” obligation Contractor must weigh costs of acceleration, chance of
recovery against liquidated damages potentially levied against him
Delay, Disruption and Acceleration · April 2009 17
4.4 Entitlement to acceleration4.4 Entitlement to acceleration
Contractor may perceive commercial advantage to accelerate; generally only bound by completion date
Generally no obligation of the Employer to co-operate
Exception: entitlement of acceleration provided in the contract and bound to program
Delay, Disruption and Acceleration · April 2009 18
5. Conclusion5. Conclusion
Time is of the essence in construction projects The effort of planning, negotiating and drafting
does not end at providing sophisticated terms for the event of delays by
finding a realistic completion date, incorporating EOT provisions and delay related
liquidated damages Instead, the same though and sophistication
should be put in addressing delays in terms of acceleration, rather than only dealing with them in terms of EOT and liquidated damages.
Clifford Chance, Königsallee 59, 40215 Düsseldorf, Germany
© Clifford Chance 2009
Clifford Chance Partnerschaftsgesellschaft von Rechtsanwälten, Wirtschaftsprüfern, Steuerberatern und Solicitors · Sitz: Frankfurt am Main · AG Frankfurt am Main PR 1000
www.cliffordchance.com
Delay, Disruption and Delay, Disruption and AccelerationAcceleration
#960898
ContractContract Management in Management in International ConstructionInternational Construction
Beijing, April 28, 2009Beijing, April 28, 2009