del rey project in las cruces
DESCRIPTION
The AARA funded Del Rey improvements make the Del Rey community safer from floods.TRANSCRIPT
![Page 1: Del Rey Project in Las Cruces](https://reader033.vdocuments.us/reader033/viewer/2022060202/559cf4011a28ab8c438b45c6/html5/thumbnails/1.jpg)
DEL REY BLVD/ SANDHILLDEL REY BLVD/ SANDHILLARROYO CROSSINGARROYO CROSSING
Bid AwardBid Award
City of Las CrucesCity of Las CrucesProject No. 09-10-429Project No. 09-10-429
![Page 2: Del Rey Project in Las Cruces](https://reader033.vdocuments.us/reader033/viewer/2022060202/559cf4011a28ab8c438b45c6/html5/thumbnails/2.jpg)
• The City received $2,000,000 in funding from the NMDOTas a result of the American Recovery and Reinvestment Act(ARRA) of 2009 and Statewide Transportation ImprovementProgram (STIP) to construct road improvements on Del ReyBlvd from Starburst Ridge to Settlers Pass.
• The Del Rey Blvd / Sandhill Arroyo Crossing project willinclude the following:– Widen the existing two lane section to a four lane section– Provide sidewalks and bike lanes– Install street lighting– Improve the roadway surface– Upgrade the existing city utilities with in the project limits– Install 15- 5’x10 concrete box culverts across the Sandhill Arroyo
BackgroundBackground
![Page 3: Del Rey Project in Las Cruces](https://reader033.vdocuments.us/reader033/viewer/2022060202/559cf4011a28ab8c438b45c6/html5/thumbnails/3.jpg)
DEL REY BLVD. / SANDHILL ARROYO CROSSINGN
EW
S
SANDHILL ARROYO
![Page 4: Del Rey Project in Las Cruces](https://reader033.vdocuments.us/reader033/viewer/2022060202/559cf4011a28ab8c438b45c6/html5/thumbnails/4.jpg)
DEL REY BLVD. TYPICAL STREET CROSS SECTION
![Page 5: Del Rey Project in Las Cruces](https://reader033.vdocuments.us/reader033/viewer/2022060202/559cf4011a28ab8c438b45c6/html5/thumbnails/5.jpg)
BackgroundBackground
•• Bids Received: 8Bids Received: 8
•• Engineers Base Bid + Add Alt. . . . . . .Engineers Base Bid + Add Alt. . . . . . . $2,596,167.50$2,596,167.50
•• Low Bid Base + Add Alt. . . . . . . . . . . Low Bid Base + Add Alt. . . . . . . . . . . $2,080,859.30$2,080,859.30–– Burn Construction, Inc.Burn Construction, Inc.–– 19.84% Below Engineers Estimate19.84% Below Engineers Estimate
•• Funding Source: ARRA, Flood Control and Utility FundsFunding Source: ARRA, Flood Control and Utility Funds
•• Contract Duration: 180 Working Days.Contract Duration: 180 Working Days.
![Page 6: Del Rey Project in Las Cruces](https://reader033.vdocuments.us/reader033/viewer/2022060202/559cf4011a28ab8c438b45c6/html5/thumbnails/6.jpg)
Council OptionsCouncil OptionsDel Rey Blvd / Sandhill Arroyo Crossing ProjectDel Rey Blvd / Sandhill Arroyo Crossing Project
• Option 1– Award contract to Burn Construction Company, Inc.– $2,080,859.30– $2,352,325.39 w/ Tax & Contingency
• Option 2– Reject and Re bid the project
• Option 3– Reject and Re scope the project
• Option 4– Reject and Abandon the project for a later date