defined civil about hydro power building

Upload: septian-anggoro

Post on 07-Jul-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/18/2019 Defined Civil About Hydro Power Building

    1/26

    DEFINED CIVIL,MECHANICAL

    FEED MHPP Mamasa

    1 DEFINED CIVIL

    1.1 Hydrological data

    The hydrological data is the most important data in a hydropower

    project and all of the design depends on it. The data sets should have as

    many years of registries as possible. The longer the data period, the more

    accurate will be the results.

    In ideal conditions there are two main data sets that must be

    obtained before the design phase of the project:• Daily ows: Used to compute the ow duration curve !D"# from which

    the project$s design ow is derived.

    • %a&imum ood ows: Used to predict the ma&imum ood ow for a

    given return period.

    Usually the hydrological data is obtained from a gauging station.

    'owever, in mini or micro hydropower projects, as they are located in

    remote areas and have small catchment areas watershed#, often no

    gauging stations are available. In the absence of hydrological data at the

    site, two procedures should be considered:

    • (dapting data from the nearest watershed with similar hydrological

    characteristics where a gauging station has been established and long

    term hydrological data is available. The watershed with the gauging

    station considered should have similar average annual temperature

    and rainfall, geology, and land cover

    • The second procedure is to measure the river ows during various

    seasons and speci)cally during low ow seasons. The more the

    measurements the more reliable the data will be.

    *. Daily !lows

    PT.ARYAGUNA INTI RANU *

  • 8/18/2019 Defined Civil About Hydro Power Building

    2/26

    To adapt a data set from a selected gauging station to the

    watershed of the project the procedure is based on transposition

    method that uses the ratio between the areas of the watersheds. Thus,

    being

    (gs + (rea of the watershed of the selected gauging station

    gs + !low measurement of the selected gauging station

    (p + (rea of the watershed of the project

    p + "alculated ow for the watershed of the project

    This method is widely used and can produce results that can be

    considered accurate. There are however other methods. !or further

    references the boo- %icro 'ydro Design %anual/ from (dam 'arvey

    should be consulted. Depending on the aim of the project and site

    conditions local measurements should also be carried out. If the aim of the

    project is to optimi0e it according to the available ows, then daily ows

    are needed in order to get data that will allow to calibrate the ow

    duration curve obtained from the transposition method. 'owever, if the

    aim of the project is to guarantee a constant supply of energy to a smallcommunity, then the main hydrological input will be the minimum ow

    and the project should be designed for that. The local measurements of

    minimum ow should be carried out during the low ow season.

    There are several methods to measure the ows at a site. !or

    further information on this subject the boo- 1%icro 'ydro Design %anual/

    from (dam 'arvey should be consulted.

    2. %a&imum ood ows

    2

  • 8/18/2019 Defined Civil About Hydro Power Building

    3/26

    The availability of ma&imum ood ows measurements is lower

    than of daily ows and this is often the case in remote areas li-e the

    ones where usually mini or micro hydro projects are implemented. To

    come up with an estimation of the ma&imum ood ow, the nearest

    gauged river data should be used to estimate the ood factor. The ratio

    of the ma&imum ood value recorded by least daily ow measured for

    various years can be computed and the average of such ratios can be

    used as ood factor. !low and ood ow data ma-e a time series which

    means they can undergo through a fre3uency analysis. This will allow to

    determine the recurrence interval of the hydrologic event of a given

    magnitude &. The average interval of time within which the magnitude y

    of the event will be e3ualled or e&ceeded once is -nown as return

    period, and is designated by T. If a hydrologic event e3ual to or greater

    than & occurs once in T years, the probability 4 56 is e3ual to * in T

    cases, or

    This means that a return period will be the average time interval in

    which a given ood ow is e3ual or e&ceeded. !or e&ample, if the ood

    ow at a river station, for a *77 years return period, is 277 m8 9s, this

    means that on average there will be at that river station a ood with a

    ow of 277 m8 9s or more at every *77 years. Thus the concept of return

    period can be used as a ris- management procedure. The higher the

    return period of the adopted design ood ow, the lower the ris- of a ood

    with a higher ow than the design one, and hence the lower the ris- of

    damaging the hydraulic structures at the inta-e area. In order to compute

    the ows for a given or several return periods statistical methods have to

    be applied to the ow data series so that the fre3uency analysis can be

    computed. The most common methods are the following statistical

    distributions:

    • ormal

    • ;umbel

    • 4earson III

  • 8/18/2019 Defined Civil About Hydro Power Building

    4/26

    =ach distribution will produce di>erent results so the designer will

    have to ma-e a decision on which design ood ow to use based on all the

    computed ows he gets. !or further reference on this subject please chec-

    the boo- 1'andboo- of (pplied 'ydrology/ from ?an Te "how. Typically the

    return period to adopt for the design of a hydropower scheme will depend

    on the ris- of human and material losses in its surroundings if the design

    ood ow is e&ceeded. (s micro hydro schemes are often located in

    remote areas, thus the ris- is low, the recommended return period for the

    design of ood structures is *77 years. (s these methods are estimations,

    during visits to the site the engineers should loo- in the area for mar-s of

    former oods and also as- the local residents about former oods. (fter

    getting an appro&imate cross section, the corresponding water level

    during the ood considered, and the river$s longitudinal slope at this

    stretch, the ood ow for that cross section can be computed. The

    computed value should then be compared with the estimated values. It

    has to be noted that given that oods with higher return periods are not

    fre3uent it will be di@cult to )nd mar-s of those oods, thus the identi)ed

    ood levels will li-ely correspond to ood ows with return periods of

    about * to A years. This should be ta-en into account when comparing

    these in situ estimation values with the ood ow values obtained from

    the statistical methods. If there are any hydrological studies for other

    projects in the area they should also be used. (s stated earlier, the more

    hydrological data that can be gathered and used, the more accurate will

    be the results.

    1.2 Topographic survey

    B

  • 8/18/2019 Defined Civil About Hydro Power Building

    5/26

    Topography of the project area should be obtained. It should include

    the areas predicted for the following structures: weir and inta-e, canal,

    forebay, penstoc- and powerhouse. (reas around this structures should

    also be included so that during the development of the project the

    designer can also have available information when designing for e&ample

    the ushing channel for the gravel trap or settling basin. It has to be noted

    that the area around the inta-e and weir should be detailed so that there

    is enough information for computing ood levels upstream and

    downstream of the weir section.

    1.3 Design Procedure

    The design template spreadsheet %'44 %amasa contains the

    following sheets:

    • Ceir stilling basin

    • Cater levels U9E D9E

    • Inta-e

    • Inta-e "anal

    • ;ravel trap

    • Eide Epillway

    • (pproach canal

    • Eettling Fasin

    • Eettling Fasin + !lushing pipe

    • 'eadrace "anal

    • !orebay

    • !orebay + !lushing pipe

    • 4enstoc- design

    • 'ead losses calculation

    • 4ower calculations

    A

  • 8/18/2019 Defined Civil About Hydro Power Building

    6/26

    • (nchor bloc-s

    • Ceir Etability

    1.4 Execution of the design process

    1.4.1Hydro desi !

    The design process should be carried out accordingly to the

    following instructions:

    * Inta-e:

    • Eet the design discharge d#.The inta-e design discharge din#

    will then be *.2 d. This is for safety and to account for the seepage

    losses on the canal, from the inta-e to the forebay. The din will be

    the ow value used for the design of the upstream structures li-e

    the canals.

    • "hoose the position of the inta-e and set the river bed level F

  • 8/18/2019 Defined Civil About Hydro Power Building

    7/26

    • !rom the governing e3uation of ow through submerged inta-es,

    the di>erence between the water levels upstream and downstream

    the inta-e, h# re3uired to allow the design flow to pass through

    the inta-e ori)ce is computed. ote that the downstream water

    level will be based on the inta-e canal geometry or other structures

    such as gravel trap#. Thus, the design and calculation process will be

    iterative.

    2 Inta-e "anal:

    • Eet the %anning coe@cient accordingly to the surface material of

    the canal.• Eet slope of the vertical canal walls m# to 0ero. Eet a slope for the

    canal. "ompute goal see- by setting dif to 0ero by changing h. If

    the water depth in the canal is not at least A cm higher than the

    height of the inta-e ori)ce then set a new slope and do goal see-

    again. Gepeat the process as many times as necessary until the

    water depth in the canal is at least A cm higher than the height of

    the inta-e ori)ce. This is to assure the ori)ce is submerged.• "hec- if the ma&imum si0e of particles to be transported in the

    canal is higher than the minimum si0e of particles to be settled in

    the gravel trap. If not increase the slope and chec- if the

    submergence condition of the ori)ce is still veri)ed.

    8 Inta-e:

    • The water level downstream of the inta-e, hD9E, ori)ce is now the

    level set previously in the inta-e canal. !rom this level it is

    calculated the water level upstream the inta-e, hU9E. which will set

    the normal water level, Cerent canal widths.

    B Ceir Etilling basin:

    • Eet the ma&imum ood discharge ma& ood# and the normal ood

    discharge norm ood# accordingly to the values obtained from ahydrological study.

    J

  • 8/18/2019 Defined Civil About Hydro Power Building

    8/26

    • Eet the length of the weir crest,

  • 8/18/2019 Defined Civil About Hydro Power Building

    9/26

    • ;o to the line 1Giver regime downstream/. If the critical depth is

    greater than the uniform depth hcLhu# then the river regime is

    supercritical and no hydraulic jump will occur. In this case go to step

    55. If hcM Mhu# then the regime in the river for ood conditions is

    subcritical hence there will be a hydraulic jump downstream the

    weir and a stilling basin must be provided.

    • Eet the depth of stilling basin bed level from downstream bed level,

    , to 0ero. This means that for the calculations of the hydraulic jump

    it is considered that the bed level of the stilling basin is the same as

    that of the river in the section immediately downstream.• !or the calculation of the hydraulic jump, the )rst step is to consider

    that between the weir crest and the bottom of the weir the total

    energy of the ow will remain constant because rapidly varied ow

    will occur. The water depth at the end of the weir is computed in

    accordance to this principle. !or this in the table named 1=nergy

    conservation at weir/ the cell dif =, using goal see-, must be set to

    0ero by changing D* which is the water depth at the end of the weir.• (fter the calculation of D* all of the calculations of the hydraulic

    jump are automatic and the designer can go directly to chec- if the

    water level at the river, TC

  • 8/18/2019 Defined Civil About Hydro Power Building

    10/26

    • Gepeat the iterative process at the table 1=nergy conservation at

    weir/ and chec- again the condition TC< TC

  • 8/18/2019 Defined Civil About Hydro Power Building

    11/26

    • Eet the safety factor, E!. This is an oversi0ing factor for the design of

    the gravel trap and its main purpose is to account for the turbulence

    in the ow which will decrease the e@ciency of the settling process.

    In comparison to a settling basin a gravel trap is usually a smaller

    structure in length because the settling velocity of particles is

    higher, thus they need a shorter distance from the beginning of

    structure to settle. (s a result of this, for the same volume of

    particles to store between ushing, a gravel trap will need a bigger

    collection depth. 'owever this value should be -ept in a reasonable

    range to prevent an e&cess of e&cavation. Increasing the safety

    factor is a way to solve this problem because as the si0e of the

    gravel trap increases the collection depth decreases.

    • "hec- if the ratio

  • 8/18/2019 Defined Civil About Hydro Power Building

    12/26

    • Eet the river carrying load of gravel. This -ind of data is very rare, so

    usually depending on the characteristics of the river the designer

    can assume a value between 7.A and 2.7 -g9m8 . & Eet the ushing

    time. In ideal conditions this time should be e3ual to the ushing

    fre3uency of the settling basin in order to ma-e easier and simpler

    the operation of the scheme. 'owever this is not always possible

    because it would lead to a high collection depth. It has also to be

    noted that the design ushing fre3uency is for ood season which

    means that during the remaining year when the river carrying load

    is much lower the ushing fre3uency will decrease.

    • Eet the density of gravel. Usually the value of 2H77 -g9m8 is

    considered.

    • !rom the previous inputs the dimensions and depths of the gravel

    trap are de)ned. The settling depth is considered e3ual to the depth

    of the ow in the inta-e canal. The freeboard is considered to be the

    same used in the inta-e canal 7.87 m#.

    K Eide spillway

    • The design discharge, d, is lin-ed to the spreadsheet of the inta-e

    • The minor ood discharge, minor ood, is computed considering

    that it is e3ual to *.*A d. This will be the ow used to design the

    spillway as it is considered to be an unfavorable situation for the

    design of the inta-e. This happens because a small e&cess to the

    design ow will produce a low head of water over the spillway crest

    leading to a higher length of the crest than in a major e&cess over

    the design ow where the head over the crest will be higher and

    re3uire a shorter crest length re3uired.

    • The height of the spillway crest is considered to be e3ual to the

    normal water depth in the canal, which mean that any e&cess of

    ow will be spilled.

    *2

  • 8/18/2019 Defined Civil About Hydro Power Building

    13/26

    • Eet the discharging coe@cient, ", accordingly to the pro)le of the

    weir crest to be used.

    Eet the safety factor, E!. This is to account for the appro&imationsconsidered in the design of the spillway. Usually it is used *.A but

    this value can go up to 2. The designer must have in mind that the

    higher the safety factor the higher the length of the crest.

    N (pproach canal

    • The %anning coe@cient is lin-ed to the to the inta-e canal sheet

    because it is assumed that all of the canals are built with the same

    material.

    • The ow is the design ow and is lin-ed to the inta-e sheet

    • Eet the slope of the canal. If possible ma-e it e3ual to the one of the

    inta-e canal this is for easy of construction#.

    • Eet the width of the canal. The approach canal will not have to

    convey ood ow since ood ows are spilled from the side spillway

    upstream#, but only the design ows and thus the canal can benarrowed. "hoose a width, b, which ma-es the height of the canal

    walls including the freeboard#, hwalls, about double its si0e.

    • Use goal see- to set the cell dif to 0ero by changing h. If the

    height of the canal walls including the freeboard#, hwalls, is not

    about two times the si0e of the width of the canal, b, change the

    width of the canal and repeat the goal see-.

    • "hec- if the ma&imum si0e of particles to be transported in thecanal is greater than the minimum si0e of particles that were settled

    in the gravel trap. This is to assure that there will not be settling of

    sediments before the settling basin. If this is not veri)ed increase

    the slope of the canal and repeat the previous steps.

    *7 Eettling Fasin

    • The settling basin is designed for the inta-e design discharge and

    this value is lin-ed to the inta-e sheet.

    *8

  • 8/18/2019 Defined Civil About Hydro Power Building

    14/26

    • Eet the minimum si0e of particles to be settled in the settling basin

    usually it is considered this si0e to be 7.2 mm#

    (ccording to the Gouse graph which is in the spreadsheet# set thefall velocity of the particles for the selected si0e.

    • Eet the width of the settling basin. This value should be 2 to A times

    the width of the approach canal.

    • Eet the safety factor, E!. This is an oversi0ing factor for the design of

    the settling basin and its main purpose is to account for the

    turbulence in the ow which will decrease the e@ciency of the

    settling process. Usually the safety factor, E!, ranges between * and

    2. & "hec- if the ratio

  • 8/18/2019 Defined Civil About Hydro Power Building

    15/26

    • Eet the ushing time. In ideal conditions this time should be e3ual to

    the ushing fre3uency of the gravel trap in order to ma-e easier and

    simpler the operation of the scheme. 'owever this is not always

    possible because the smaller dimensions of the gravel trap reduce

    its storage capacity, thus leading to higher ushing fre3uencies. It

    has also to be noted that the design ushing fre3uency is for ood

    season, when the river carries a high sediment load, which means

    that during the remaining year when the sediment load is much

    lower, the emptying fre3uency will decrease.

    Eet the density of sand. Usually the value of 2H77 -g9m8 isconsidered.

    • !rom the previous inputs the dimensions and depths of the settling

    basin are de)ned. The settling depth is considered e3ual to the

    depth of the ow in the approach canal. The freeboard is considered

    to be the same used in the approach canal 7.87 m#.

    • ote that if the collection tan- has sloped side walls the computed

    Dcollection is not the real depth to be used. In this case the designer

    should decide on the longitudinal slope of the settling basin bottom

    and then set the collection depths at the beginning and end of the

    settling9collection area in a way that the volume for sediment

    storage is at least e3ual to ?olsand.

    ** Eettling basin + !lushing pipe

    • Eet the depth of ushing vertical distance between the bottom of

    the gravel trap and the end of the ushing pipe#. If there is no

    ushing pipe and the ushing system is a gate and downstream a

    ushing canal, then set this value to 0ero. & Eet the ori)ce

    coe@cient usually *.N#.

    • =3uation * accounts for the situation when the basin is full and its

    volume and the incoming ow will be totally ushed. =3uation 2

    accounts for the situation when the basin is already empty and only

    the incoming ow will be ushed.

    *A

  • 8/18/2019 Defined Civil About Hydro Power Building

    16/26

    • The diameter of the pipe is automatically computed. If h ush was

    set to 0ero then only e3uation * will have a result.

    If the ushing system to adopt has a pipe then its diameter will bed ushing. If the system is a gate and a downstream ushing canal

    then the gate will be si0ed based on the area of the ori)ce. !or this,

    set the width and the height will be automatically calculated.

    *2 'eadrace canal

    • The %anning coe@cient is lin-ed to the to the inta-e canal sheet

    because it is assumed that all of the canals are built with the same

    material.

    • The ow is the design discharge and is lin-ed to the inta-e sheet

    • Eet the slope of the canal. If possible ma-e it e3ual to the one of the

    inta-e canal this is for easy of construction#.

    • Eet the width of the canal. "hoose a width, b, which ma-e the height

    of the canal walls including the freeboard#, hwalls, about double its

    si0e.• Use goal see- to set the cell dif to 0ero by changing h. If the

    height of the canal walls including the freeboard#, hwalls, is not

    about two times the si0e of the width of the canal, b, change the

    width of the canal and repeat the goal see-.

    • "hec- if the ma&imum si0e of particles to be transported in the

    canal is greater than the minimum si0e of particles that were settled

    in the settling. This is to assure that the particles that failed to settlein the settling basin will not settle in the bed of the canal. If this is

    not veri)ed increase the slope of the canal and repeat the previous

    steps. ote that sometimes this will not be possible because of

    topography or location of forebay and in such cases the particles

    deposited along the headrace canal will have to be manually

    cleaned after the ood seasons.

    *8 4enstoc- design

    *H

  • 8/18/2019 Defined Civil About Hydro Power Building

    17/26

    • The design discharge of the penstoc- is the design discharge of the

    hydropower scheme. This cell is lin-ed to the inta-e sheet.

    Eet the length of the penstoc-,

  • 8/18/2019 Defined Civil About Hydro Power Building

    18/26

    • Eet the surge head factor. This will depend on the selected turbine.

    !or 4elton and "ross !low *7 27P, and for !rancis turbines 87 B7P.

    & "hec- the safety factor, E!. If the value is less than 8.A then

    increase the e>ective thic-ness, te>, until it the E! is at least 8.A.

    *B !orebay

    • The design discharge for power generation is lin-ed to the inta-e

    sheet and the diameter of the pipe and the velocity of the ow in

    the penstoc- lin-ed to the penstoc- design sheet.

    • Eet the width of the forebay. (s a thumb rule, to start the design, it

    can be assumed that the length of the forebay will be 2 to 2.A timesthis si0e. 'owever according to the re3uired volume of water above

    the penstoc- and to meet the site conditions the designer may have

    to change this ratio.

    • Eet the clearance of the penstoc- from the bottom of the forebay.

    This is to avoid that particles and sediments settled in the forebay

    get in the penstoc-. The minimum clearance is 7.87 m. 7.A7 m is a

    common and reasonable value to use.

    • The minimum submergence of the penstoc- is automatically

    calculated because it depends only on the diameter of the pipe and

    ow velocity.

    • !or the design of the forebay it is considered that it should be

    available to cope with the ow variations in the turbine during

    normal operation conditions# a bu>er volume e3uivalent to *A

    seconds of supply at the design ow. This is also automatically

    calculated as well as its corresponding depth of water.

    • Eet the discharger coe@cient of the spillway. This depends on the

    shape of the crest and spillway.

    *K

  • 8/18/2019 Defined Civil About Hydro Power Building

    19/26

    • Eet the depth of water over the crest of the spillway. 'ave in mind

    that the higher the water depth the smaller will be the crest length

    of the spillway. The spillway is designed to spill all the design ow in

    case the powerhouse is shut down and no ow is going through the

    penstoc-.

    • Eet the freeboard for the spillway. This is a safety margin in case

    higher ows than the design ow arrive to the forebay. "onsider a

    value that is half the water depth over the weir crest. This will

    increase, if necessary, in A7P of the discharge capacity of the

    spillway.• The length of the spillway is automatically calculated using the

    previous input data and the weir e3uation. It has to be noted that

    this value must be smaller than the length of the forebay.

    • Eet the angle of the transition walls at the entrance of the penstoc-.

    This transition must be smooth so mild angles are recommended

    around 27P#. 'owever to )t site conditions the values can be

    adjusted.

    • !or the )nal placing of the forebay the designer has to set the

    normal water level C

  • 8/18/2019 Defined Civil About Hydro Power Building

    20/26

    • The input data for penstoc- and ow characteristics is lin-ed to

    other sheets.

    (ccording to the material of the penstoc- set the roughness, -. forsteel - *.A&*7 B m#. & Use goal see- to set the cell "olebroo-

    Chite, " C, to 0ero by changing the cell f. Cith this the continuous

    head loss is automatically calculated.

    • Eet the thic-ness of the trash rac- bars, t typically * to 2 cm#.

    • Eet the distance between bars, s this value will depend on the

    selected turbine and the speci)cations of the manufacturer. In a

    preliminary design consider this value around 2 or 8 cm. ote that

    the smaller the spacing between bars the more protected the

    turbine will be, but the head loss will increase as well as the

    clogging and the conse3uently the cleaning fre3uency#.

    • Eet the angle of the trash rac- with the hori0ontal, , typically it is

    used J2 degrees which is e3uivalent to a slope of *:8 ':?#.

    • Eet the cross section shape factor, V, accordingly to the shape of the

    bar cross section. & (fter all the mentioned inputs the head loss in

    the trash rac- is calculated

    • Eet the entrance factor, -e, factor accordingly to the shape of the

    transition between the forebay and the penstoc-. The head loss is

    calculated after this values is set.

    • !or the head loss in a bend, set the angle of the bend, W, and the

    bend factor, X use the table for bends on the right as reference#,the head loss is then computed. (dd as many bends as necessary. If

    the bend has two components hori0ontal and vertical# then

    calculate them separately accordingly to the bending angles.

    • !or the head loss due to contraction reduction of the pipe si0e at

    the joint between the penstoc- and the turbine# set the diameter of

    the smaller pipe, D2 usually this value depends on the dimensions

    of the turbine, but in a preliminary phase can be considered 7.B mfor low power !rancis turbines.

    27

  • 8/18/2019 Defined Civil About Hydro Power Building

    21/26

    • Eet the loss factor, -e. !or this type of transition -e 7.7A. The head

    loss is then calculated.

    (ll of the losses are resumed in point 8 and the total head loss iscalculated.

    • The net head, 'net is then calculated:'net 'gross htot.

    • (s stated earlier, if the head loss is too high repeat the calculations

    assuming a larger pipe diameter.

    *H Tailrace canal

    • The %anning coe@cient is lin-ed to the to the inta-e canal sheet

    because it is assumed that all of the canals are built with the same

    material.

    • The ow is the design discharge and is lin-ed to the 4enstoc- Design

    sheet.

    • Eet the slope of the canal. If the tailrace canal is stepped then set

    the slope to 0ero.

    • If the canal is made of steps then it is assumed that the ow will be

    critical, hence the water depth will be e3ual to the critical depth.

    • Eet the width of the canal. "hoose a width, b, which ma-e the height

    of the canal walls including the freeboard#, hwalls, about double its

    si0e.

    • If the canal has a slope then use goal see- to set the cell dif to

    0ero by changing h. If the height of the canal walls including the

    freeboard#, hwalls, is not about two times the si0e of the width of

    the canal, b, change the width of the canal and repeat the goal

    see-.

    • ote that for safety if the ow regime in the tailrace canal is

    supercritical the )rst A7 meters of the tailrace canal should always

    have the height of the vertical walls determined by the critical

    depth.*J Giver water level at tailrace

    2*

  • 8/18/2019 Defined Civil About Hydro Power Building

    22/26

    • De)ne a cross section on the river at the end of the tailrace.

    • Eet the %anning coe@cient accordingly to the river bed

    characteristics• 4ic- a point some meters upstream the selected cross section and

    other a few meter downstream and compute the longitudinal slope

    of the river. Input the value in cell Elope.

    • !rom the cross section pro)le get the slope from the river ban-s m

    left ban- and m right ban-#

    • Eet the width of the river canal on that cross section, b.

    • Gun goal see- by setting cell dif to 0ero by changing h. This will

    compute the uniform water depth for the appro&imate cross section

    of the river.

    • The computed river water level will be used to decide the location of

    the end of the tailrace canal.

    *K 4ower calculations

    • Eet the basic data inputs: density of water and gravity acceleration.

    • The design discharge and net head are lin-ed to respectively the

    penstoc- design and head loss calculations sheets.

    • Eet the e@ciency of the turbine. !or a preliminary phase of the

    study before the turbine manufacturer is selected and the

    characteristics of the turbine de)ned# use 7.KA for !rancis 7.JA for

    4elton turbines and 7.HA for "ross ow.

    1.4." #im$%i&ed s'r()'(ra% desi !

    The simpli)ed structural design includes two procedures: verifying

    the stability of the weir and of the anchor bloc-s.

    It has to be noted that anchor bloc-s should be placed at:

    • "onnections of the penstoc- to other structures !orebay#

    • =&pansion joints

    • Fends vertical in plan and9or pro)le#

    22

  • 8/18/2019 Defined Civil About Hydro Power Building

    23/26

    • "hanges in the diameter of the penstoc-

    * (nchor bloc-s

    • Input the basic data: density of water, speci)c weight of water,speci)c weight of concrete, speci)c weight of soil and soil friction

    angle. The soil friction angle, Y, should be obtained from samples at

    the site, however when this data is not available a value between 2A

    and 87 degrees can be assumed. The friction angle between soil and

    concrete is considered to be 298 of the soil friction angle.

    • Eet the dimensions of each of the anchor bloc-s. (dd as many

    columns corresponding to anchor bloc-s as necessary. The volume

    and weight of the anchor bloc-s are automatically computed.

    • Input the hydraulic data: set the water head in the penstoc- for

    each of the anchor bloc-s the surge head will be automatically

    computed accordingly to the type of turbine that was set in the

    sheet 14enstoc- Design/R set the upstream diameter of the

    penstoc-, D*, this can be understood as the diameter of the

    penstoc- that goes in the anchor bloc-#R set the plan and pro)le

    angles of the upstream penstoc- *h and *v#, set the downstream

    diameter of the penstoc-, D2, this can be understood as the

    diameter of the penstoc- that goes out of the anchor bloc-#R set the

    plan and profile angles of the downstream penstoc- 2h and 2v#.

    • (fter inputting the previous data all of the hydraulic forces are

    automatically computed using the =uler Theorem.

    • "hec- the safety factors for sliding and overturning. These factors

    must be at least e3ual to 8. ote also that the resultant force should

    be in the middle third of the base for stability against overturning. If

    these conditions are not veri)ed then go bac- to the dimensions of

    the anchor bloc-s and change them. Usually the solution will be to

    increase the anchor bloc- dimensions, and if this does not wor- or

    the )nal dimensions of the anchor bloc- are too big, then consider

    changing the alignment of the penstoc- in plan and9or pro)le#

    28

  • 8/18/2019 Defined Civil About Hydro Power Building

    24/26

    • !or the bearing capacity: set the depth of the base of the foundation

    this depth is measured in relation to the )nal ground level above

    the anchor bloc- foundation#. In accordance to the friction angle of

    the soil, Y, input the bearing capacity factors 3 and Z obtain

    these values from the table that is in the spreadsheet template on

    the right of the calculation for bearing capacity#.

    • "hec- the safety factor for the bearing capacity. This value must be

    e3ual or greater than 8. If not then change de dimensions of the

    anchor bloc- in a way that the ma&imum bearing load is reduced

    increase the length and width, and decrease the height#.2 Ceir

    • Eet the speci)c weights of water, soil, saturated soil, and weir. Eet

    also the friction angle of the soil,Y. The soil characteristics should be

    obtained from samples collected at the site, however if this data is

    not available values of *J - 9m8 for the speci)c weight of the soil,

    *N - 9m8 for the saturated speci)c weight of the soil, and between

    2A and 87 degrees for the friction angle should be considered.• (ccording to the shape of the weir divide its cross section in simple

    geometric )gures and input the areas of each one of them as well as

    the length of their base.

    • Eet the factor for calculating the hori0ontal coordinate of the center

    of gravity, ";factor, for each of the internal shapes of the weir.

    • Eet the depth for the high ood level hf#. This depth is measured

    from the point where the upstream weir apron intersects the ground

    level.

    • Eet the height between the turning point the point in the

    downstream e&tremity of the weir body that is in contact with the

    foundation# and the upstream river bed level.

    • (fter the previous input data all of the loads are automatically

    calculated.

    2B

  • 8/18/2019 Defined Civil About Hydro Power Building

    25/26

    • "hec- the safety factors for sliding and overturning. These factors

    must be at least e3ual to 8. ote also that the resultant force should

    be in the middle third of the base for stability against overturning. If

    these conditions are not veri)ed then go bac- to the dimensions of

    the weir and change them. If the problem is safety against sliding

    then increase the weight of the weir and increase the contact

    surface between the weir and the foundation soil. If the problem is

    in the safety against the overturning then increase the length of the

    weir, F, and particularly increase the length and cross section area

    of the upstream section of the weir by upstream section of the weir

    shall be understood the section of the weir upstream the crest#.

    • !or the bearing capacity: set the depth of the base of the foundation

    this depth is measured in relation to the )nal river bed level above

    the weir foundationR if the river slope is too high and the depth of

    the foundation cannot be considered the same upstream and

    downstream the use an average value#. In accordance to the friction

    angle of the soil, Y, input the bearing capacity factors 3 and Zobtain these values from the table that is in the spreadsheet

    template on the right of the calculation for bearing capacity#.

    • "hec- the safety factor for the bearing capacity. This value must be

    e3ual or greater than 8. If not then change de dimensions of the

    weir in a way that the ma&imum bearing load is reduced increase

    the length#.

    1.4.* G(ide%i!es +or $o er-o(se %ayo('

    The design of the powerhouse layout should ta-e into account the

    following:

    • The powerhouse should be safe from not only annual oods but also

    rare ood events. Discussions should be held with the local

    community members to ensure that ood waters have not reached

    the proposed powerhouse site within at least the past 27 years.

    2A

  • 8/18/2019 Defined Civil About Hydro Power Building

    26/26

    • if possible the powerhouse should be located on the ground level to

    minimi0e e&cavation wor-s.

    The proposed location should be accessible throughout the year.• The powerhouse should be located close to the community that it

    serves, provided that the penstoc- alignment and other parameters

    are feasible and economical. This will reduce the transmission line

    cost, and if agro processing units are also installed in the

    powerhouse, the community will not have to carry their grain for a

    long distance.

    • !or each turbine a plan area of *7 m & K m is re3uired.

    • The clear height of the building should be at least 8 m.

    • ( control room is re3uired. It should have an area that is enough to

    accommodate the control panels typical dimensions are * m width

    by 7.H m depth and re3uiring a minimum bac-space of 7.K m, also

    note that for each turbine are re3uired about 8 to B control panels#,

    and a des- for the operator as well as a storage area for documentsand operation manuals. The control room should also have a window

    that allows the operator a direct view to the machinery.

    • ( toilet room is re3uired.

    • There should be a clear spacing of at least * m around each item of

    e3uipment that has moving parts such as the generator, turbine

    and the belt drive#

    • (de3uate windows should be provided for lighting and ventilation.

    ote that the door and windows need to be located such that they

    do not obstruct access to the e3uipment. This re3uires coordinating

    the locations of the e3uipment, windows and the door.