Deep Water Installation of Steel Catenary Risers

Subsea Asia

3rd October, 2012

Kuala Lumpur, Malaysia

Grant Milne

Page 2: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Safety Moment – Abseiling for SCR Installation

• Used On Erha. SCR receptacles located above the waterline

• High standard of procedures

• Early involvement of the abseiling supervisor in the project

• Use of in-house abseiling

2Page 2-Oct-12

• Use of in-house abseiling department as well as subcontractors.

Page 3: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Agenda

Introduction

SCR Configurations

SCR Welding

Deepwater SCR Installation

SCR Hook-up

3Page 2-Oct-12

SCR Hook-up

BC-10 Experience

Page 4: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Introduction to Steel Catenary Risers

• Steel Catenary Risers:

– Economically attractive

– Large diameters

– High resistance to internal and external pressure

– Simple and robust installation methods

– Attractive for deepwater use

4Page 2-Oct-12

– Attractive for deepwater use

• Sensitive to dynamics and more vulnerable to fatigue when they are light in water

• Challenges:

– Increasing top tensions due to larger diameters and deeper water

– Increase of fatigue due to harsher environments, and increasing top tensions

Page 5: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Agenda

Introduction

SCR Configurations

SCR Welding

Deepwater SCR Installation

SCR Hook-up

5Page 2-Oct-12 5Page 2-Oct-12

SCR Hook-up

BC-10 Experience

Page 6: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Configurations For Minimised Fatigue

• Three configurations to choose from are:

– Free hanging SCR

– Lazy wave SCR

– Buoyancy supported riser

• Influenced by:

– Water depth

– Environmental conditions

6Page 2-Oct-12

– Environmental conditions

– Installation method

– SCR size and design

– Top tension

– Fatigue allowances

– Type of production platform

Page 7: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Configurations – Free Hanging SCR

• Simple and easy installation

• Often installed VIV strakes

• Economically attractive

• Can be subject to high fatigue damage at top end and TDP

7Page 2-Oct-12

and TDP

• Sometimes need hold-back anchors:

Page 8: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Configurations – Lazy Wave SCR

• Addition of buoyancy modules

• Decreased top tension

• TDP is further away from production facility

• Lower Stress and Fatigue at the Top End and TDP by

8Page 2-Oct-12

• Lower Stress and Fatigue at the Top End and TDP by factors of between 2 and 5

• Completed for BC-10, 2009

Page 9: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Configurations – Buoyancy Supported Risers

• De-couple FPSO motions from risers

• Effectively decreased top tension at FPSO or floating structure

• Easier SCR installation program:

9Page 2-Oct-12

program:– De-coupled from FPSO

– Completed without FPSO in field

• Suited to ultra deep water

• Guara Lula project – Brazil 2013/2014

Page 10: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Agenda

Introduction

SCR Configurations

SCR Welding

Deepwater SCR Installation

SCR Hook-up

10Page 2-Oct-12 10Page 2-Oct-12

SCR Hook-up

BC-10 Experience

Page 11: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Welding for Improved Fatigue Performance

• Fatigue performance of weld is critical

• Close control of pipe end tolerances and joint misalignment

• High integrity weld procedures

• Flush grinding of weld caps for better fatigue performance

• Reel lay installation – onshore fabrication and testing

11Page 2-Oct-12

Page 12: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Welding – Installation of Mechanically Lined Clad Pipe for Reel Lay

• Subsea7 has developed a methodology for the installation of mechanically lined pipe by reel lay.

• Qualification gained from DNV and the method will be used on Guara-Lula, 2013 for the SCR installation

• Methodology adopts reeling on the lined pipe in a flooded condition with back pressure to mitigate any wrinkling of the CRA liner due to plastic bending

12Page 2-Oct-12

the CRA liner due to plastic bending

• Method offers significant economic advantages due to the reduced cost from using metallurically clad pipe which has been previously reeled

Page 13: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Fabrication – Prefabrication Onshore

• Vigra spool base in Norway

• Maximum stalk length of 1520m

• 1000m fabrication shed

13Page 2-Oct-12

Page 14: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Fabrication – Prefabrication Onshore

• Pipeline stalks are fabricated first and then spooled onto reel lay vessel; Seven Navica

14Page 2-Oct-12

• SCRs can also be installed by offshore fabrication in S-Lay and J-Lay

Page 15: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Agenda

Introduction

SCR Configurations

SCR Fabrication

Deepwater SCR Installation

SCR Hook-up

15Page 2-Oct-12 15Page 2-Oct-12

SCR Hook-up

BC-10 Experience

Page 16: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Deepwater Installation Spread – Seven Borealis

Seven Borealis• Size: 182m x 46m

• J-Lay: 937Te, 24”

• S-Lay: 600Te, 46”

• Crane: 5000Te

16Page 2-Oct-12

• 15° gimble capacity allows vessel to fully weathervane in order to minimise motions and SCR fatigue.

Suited for the installation of the biggest SCRs in ultra-deepwater environments

Page 17: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Deep Water Installation Spread – Sapura 3000

Sapura 3000

• Size: 151m x 38m

• J-lay: 400Te, 20”

• S-lay: 240Te, 60”

• Crane: 3000 sTe

17Page 2-Oct-12

• Crane: 3000 sTe

Class leading heavy lift and pipelay vessel operating in

water depths of up to 3000m

Page 18: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Deepwater Installation Spread – Seven Oceans

Seven Oceans

• Size: 157m x 28m

• Reel Lay: 3500Te

• Pipe Size: 6”-16”

• Crane: 350Te

18Page 2-Oct-12

• Crane: 350Te

Efficient reel lay vessel with SCR experience

Page 19: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Deepwater Installation Spread

Seven Seas

• Construction and flex-lay vessel with J-lay capabilities through the moonpool

• Top tension: 400Te

19Page 2-Oct-12

Page 20: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Deepwater Installation Spread – Weather Mitigation

• J-Lay: 15° gimble to allow 360° heading changes

• Larger vessels: smaller motions

• Reel lay: small installation window needed due to quick lay speeds

• Moonpool lay decreases vessel motions seen by SCR.

20Page 2-Oct-12

Page 21: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Agenda

Introduction

SCR Configurations

SCR Welding

Deepwater SCR Installation

SCR Hook-up

21Page 2-Oct-12 21Page 2-Oct-12

SCR Hook-up

BC-10 Experience

Page 22: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Hook-up – SCR Wet Store

• De-couple SCR fabrication and installation with FPSO delivery

• Tight corridors

• Additional vessel to recover and transfer SCR to FPSO

• Pull-in head and laydown

22Page 2-Oct-12

• Pull-in head and laydowntool installation

Page 23: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Hook-up – Direct Transfer

• From pipelay vessel to FPSO

• Historically preferred method

• Deploy SCR on A&R winch from pipelay vessel and handover subsea to FPSO pull-in wire

23Page 2-Oct-12

Page 24: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

SCR Hook-up – Riser Pull-in Equipment (RPE)

• Located on FPSO to complete final pull-in of SCR

• Up to 450Te has been completed, 600Te in the future

• Slides between riser receptacles

24Page 2-Oct-12

receptacles

• De-mobilised off FPSO after hook-up.

Page 25: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Agenda

Introduction

SCR Configurations

SCR Welding

Deepwater SCR Installation

SCR Hook-up

25Page 2-Oct-12 25Page 2-Oct-12

SCR Hook-up

BC-10 Experience

Page 26: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Shell BC-10 Overview

• Brazil – Campos Basin– Harsh environmental conditions

• 1190-1940m WD

• 2009

• Reel lay – Seven Oceans– Ubu spool base

26Page 2-Oct-12

• Lazy Wave SCR– Improved fatigue life

– Reduced top tension and reduced loads on FPSO turret

– FPSO motions affect the SCR less.

• 3 SCR’s were wet stored and 2 were directly transferred.

Page 27: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Shell BC-10 – Buoyancy Modules

• Installed after the initiation of the PLET.

• Installed under lay spread on Seven Oceans.

• Half shells of buoyancy were heavy and large.

• Operation completed without

27Page 2-Oct-12

• Operation completed without incident.

• Fatigue performance for SCR are very good.

Page 28: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Shell BC-10 – Flexjoint Weld

• SCR hung off in worktable.

• Flexjoint lifted into lay spread by vessel crane.

• Flexjoint section manually welded onto SCR.

• J-lay methodology

28Page 2-Oct-12

• J-lay methodology

Page 29: Deep Water Installation of Steel CatenaryRisers - Subsea UK of scrs... · Deep Water Installation of Steel CatenaryRisers ... Deepwater Installation Spread –Seven Borealis ... –

Conclusion

• Selection of the best SCR configuration

– Lazy Wave for decreased top tension and lower fatigue

– Free hanging for simplicity

– Buoyancy supported riser for ultra deep water

• Selection of a vessel to minimise installation fatigue loads

– Reel lay for minimal installation time

– J-lay for high top tension and 360° heading changes

29Page 2-Oct-12

– J-lay for high top tension and 360° heading changes

– S-lay

• Wet-store or direct transfer

– De-couple installation schedule from FPSO delivery

• Pull-in and landing of SCR into receptacle on floating structure