deemed savings methodologies reid hart, pe associate director, technical research july 2009 –...
TRANSCRIPT
Deemed Savings Methodologies
Reid Hart, PE
Associate Director, Technical Research
July 2009 – Regional Technical Forum
2
Deemed Saving Methodologies
• Need for a New Deemed Method• Relevant Baseline Parameters• Approaches• Decision Framework Matrix• Expected Value Deemed Savings• Seeking Approval as Provisional Method
3
Need for a New Deemed Method• Current approaches
– Custom savings require pre-review and approval– Calculators work well with energy auditor– Deemed savings desired for contractor delivery
• Limits on deemed savings– Very few commercial HVAC items– Savings may be excessively conservative– Approval of deemed savings not always timely
• Desired Method– Covers range of conditions– Arrives at appropriate program-wide savings
4
Relevant Baseline Parameters
• Typically: Building Type & Vintage– Vintage not account for retrofit changes– Building types can be generalized
• Meta Parameters (Require Separate Savings)– Major climate zones– Heating fuel type
• Analyzed Baseline Parameter Variation– Internal loads: lighting; density– Envelope: glazing; perimeter/area ratio– Schedule– Measure specific parameters
5
Measure Specific Baseline Parameters
• Premium Ventilation Package as an exmple:– Economizer found changeover– Economizer maximum outside airflow– Minimum outside air setting (Example field data)
Ventilation Air Minimum Setpoint
0
1
2
3
4
5 10 15 20 25 40 55 100 More
Min OA%
Fre
qu
ency
Source: Ecotope EWEB study – 2001
6
Parameters for Premium VentilationParameter Sym Parameter variation
in baseline BEFORE
measure is installed
Internal Load L+ 1.8 LPD, 1.5 plug, 100 sf/person
LPD = 1.8 w/sf LPD; eQuest defaults
Density L- 1.0 w/sf LPD; eQuest defaults
Ventilation V+ 37.6 cfm/person
Minimum = 31 cfm/person (typical)
V- 22.6 cfm/person
Glazing G+ Low-e Argon, double pane
Type = Double pane, solar Bronze
G- Single Pane
Economizer E++ B, double stage
Changeover E+ C, single stage
= D or Snap Disk
E- Failed Economizer
Economizer M+ 80% Max OSA
Max OSA = 65% Max OSA
M- 50% Max OSA
7
Individual Baseline Parameter Impact on Savings
Savings with Various Baseline ParametersPortland, OR, Individual Changes
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
All = L+ L- E+ E- G+ G- M- M+ V+ V-
KW
h /
sq
uar
e fo
ot
Sav
ing
s
All
Heat
Cool
Fan
8
Parameter Sensitivity
Impact of Baseline on kWh/sf SavingsHeat Pump Heating
0
0.5
1
1.5
2
2.5
LPD/Density EconoChangeover
Glazing VentilationMinimum
Econo Max Combined
Parameter
kWh
/ s
qu
are
foo
t
9
Unit Change Minimizes Some ParameterskWh/square foot to kWh/ton
Impact of Baseline on kWh/ton SavingsHeat Pump Heating
0
200
400
600
800
1000
1200
1400
1600
LPD/Density EconoChangeover
Glazing VentilationMinimum
Econo Max Combined
Parameter
kWh
/ t
on
co
oli
ng
10
Approaches
• Site specific approaches– Custom analysis– Field based monitoring– Field-data driven model– Energy bill adjusted parametric tool– Parametric tool (calculator)– Simplified analysis (e.g. lighting spreadsheet)
• Deemed approaches– Matrix method / decision framework– Deemed savings (vintage, building type, climate)– Unit rebate– Expected value deemed method
11
Decision Framework Matrix• Focus on most sensitive parameters; group results
Relative Impact on Savings of Baseline Parameter ChangesInternal Load (L) and Minimum Ventilation (V)
-80%
-60%
-40%
-20%
0%
20%
40%
60%
80%
L+E+G+V-M-
L+V- V- L+ L-V- L+V+ V+ L- L-V+ L-E-G-V+M+
Ch
an
ge
in T
ota
l Sa
vin
gs
HP kWh Gas Heat kBtu
12
Matrix Results; Provide Savings TableInternal Density
Base Condition L- L= L+
Savings Matrix1.0 w/sf 1.8 w/sf
call center
Ventilation Minimum
V- 15% = - - -
V= 20% + = -
V+ 25% ++ + = Condition Deemed Savings
From Gas Heat HP Heat
Table Gas Electric Electric
Above therms/ton kWh/ton kWh/ton
- - 36 214 433
- 27 182 557
= 44 363 985
+ 63 406 1336
++ 75 384 1479
13
Expected Value Deemed Savings
• Uses decision analysis methodology
– Typical for supply-side resource risk assessment
– Allows multiple parameters or influences
– Expert judgment can be applied to parameter probability distribution
14
Decision Tree for Expected Value Analysis
• Each influencing variable assigned states, each with– Probability of occurrence– Impact on savings
15
Parameter Savings Impact and ProbabilitiesParameter Sym Parameter variation Factors for % of neutral savings
in baseline BEFORE Gas Heat HP Heat
measure is installed Probability Gas Electric Electric
Internal Load L+ 1.8 LPD, 1.5 plug, 100 sf/person 20% 0.909 0.732 0.825
LPD = 1.8 w/sf LPD; eQuest defaults 45% 1.000 1.000 1.000
Density L- 1.0 w/sf LPD; eQuest defaults 35% 1.295 1.0003 1.212
Ventilation V+ 37.6 cfm/person 25% 0.659 1.027 1.162
Minimum = 31 cfm/person (typical) 50% 1.000 1.000 1.000
V- 22.6 cfm/person 25% 1.282 0.979 0.806
Glazing G+ Low-e Argon 10% 0.861 0.929 0.869
Type = Double Bronze 40% 1.000 1.000 1.000
G- Single Pane 50% 1.079 1.118 1.103
Economizer E++ B, double stage 5% 0.500 0.750
Changeover E+ C, single stage 30% 0.715 0.895
= D or Snap Disk 45% 1.000 1.000
E- Failed Economizer 20% 1.109 1.040
Economizer M+ 80% Max OSA 20% 0.897 0.964
Max OSA = 65% Max OSA 70% 1.000 1.000
M- 50% Max OSA 10% 1.082 1.029
16
Simplified Interaction AdjustmentSimplified correction adjustment factors – limit adjustment
Parameter Combination Impacts and Probabilities
Higher quality as runs limited cf multiple regression
Compare to Neutral LPD/ Density
Econo Changeover Glazing
Ventilation Minimum Econo Max
Factor of All
Combined Run
Combination Adjustment
Plus 1.212 1.040 1.103 1.162 1.029 1.663 1.517 0.912
Minus 0.825 0.895 0.869 0.806 0.964 0.499 0.424 0.850
Simplified approach to adjust for combination impact from multiple parameter changes
Parameter Combination Probability Gas Heat HP Heat
Gas Electric Electric
Interaction Lim+ All parameters increase 10% 0.865 0.924 0.912
factors avg() 25% 0.932 0.962 0.956
from full 1 Single Parameter change 30% 1.000 1.000 1.000
combination avg() 25% 1.215 0.825 0.925
Lim- All parameters decrease 10% 1.430 0.649 0.850
17
Program-wide Savings DistributionProbability of different savings results based on range of baseline influences and combinations
18
Program-wide Expected Value (EV)
• Range of possible savings shown• Expected value represents program-wide results
19
Compare Matrix & Expected ValueMatrix Framework• Whole building
understanding needed• Multiple saving values• Site specific savings• Gaming inputs possible• Representation difficult
beyond two parameters• Multiple possible savings or
rebates make it difficult for contractor delivery
• 1944 runs required for 5 parameters needing 243 cases (3 states @, 2 climates, 2 heat types)
Expected Value• No need for information
outside discipline• Single saving value• Program-wide savings• Cannot game• Multiple parameters can be
considered• Single savings and rebate
amount makes contractor planning and marketing easy
• 96 runs required for 5 parameters needing 12 cases (3 states @, 2 climates, 2 heat types)
20
Further Research
• Current analysis is an “example” without full development; need – further develop expected values – research into extant building characterization data – “committee of experts” to develop probabilities for parameters
• Evaluate the differences in expected value and range of results for (kWh/unit) vs. (kWh/sf) vs. (kWh/ton) results.
• Use a regression model for high impact parameters to determine acceptability of simplified interactive method
• Find and test other software tools for expected value analysis • Explore past program impacts on long term results as economy of
scale takes hold, explore influence factor for projection• Develop a step-by-step Expected Value Deemed Savings method
for use by others in the region
21
Seeking Approval of Deemed Expected Value as Provisional Savings Method
• Goal: Accelerate new measure adoption with balance between savings accuracy and information needed
• Next step in premium ventilation is to develop pilot program approach with evaluation– For ease of contractor delivery, would prefer single
rebate approach– Seeking approval to use the expected value
method for two-year pilot approach– After pilot and evaluation, can update and
continue or seek different approach• May also consider use of Deemed Expected Value
for other measures that come before RTF
22
Questions?
Contact Information:Reid Hart, PEAssociate Director, Technical Research Portland Energy Conservation, Inc. [email protected]