decontamination (industrial application)

33
1 DECONTAMINATION (INDUSTRIAL APPLICATION) M. Detilleux Belgatom

Upload: mariel

Post on 09-Feb-2016

63 views

Category:

Documents


2 download

DESCRIPTION

DECONTAMINATION (INDUSTRIAL APPLICATION). M. Detilleux Belgatom. Decontamination / Industrial Application. Reference to the PHARE Project Technical Design for Decommissioning Kozloduy NPP Units 1&2 Task 2 Decontamination and Cleaning Operations. Decontamination / Industrial Application. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: DECONTAMINATION (INDUSTRIAL APPLICATION)

1

DECONTAMINATION

(INDUSTRIAL APPLICATION)

M. DetilleuxBelgatom

Page 2: DECONTAMINATION (INDUSTRIAL APPLICATION)

2

Decontamination / Industrial Application

Reference to the PHARE ProjectTechnical Design for Decommissioning

Kozloduy NPP Units 1&2

Task 2Decontamination and Cleaning

Operations

Page 3: DECONTAMINATION (INDUSTRIAL APPLICATION)

3

Decontamination / Industrial Application

• Primary Circuit

• Nuclear Auxiliary Systems

• Reactor and Spent Fuel Pools

• Thermal Insulation Sheathing Materials

Page 4: DECONTAMINATION (INDUSTRIAL APPLICATION)

4

Primary Circuit

Primary Circuit Components The pipe works The SGs tubes and collectors The pressuriser The reactor vessel with the internals The main coolant pumps and isolation valves The hot portion of the SV01 circuit

Page 5: DECONTAMINATION (INDUSTRIAL APPLICATION)

5

Primary Circuit

Two steps• Soft Pre Decontamination

• Hard Decontamination

Page 6: DECONTAMINATION (INDUSTRIAL APPLICATION)

6

Soft Pre Decontamination

Preference to the APCE process

pH must be > 5.5 due to absence of stainless steel cladding in the RPV and in the pressuriser

The type of secondary wasteAPCE : liquid waste processed by SV03 systemCORD: highly active IERs

APCE process already used Experience of the staff and Availabilty of the

chemical dosing systems

Page 7: DECONTAMINATION (INDUSTRIAL APPLICATION)

7

Hard Decontamination

Main Guidelines considered

Objective to achieve the EU free release levels

Regenerative Cerium process selected as proven technology currently available

Page 8: DECONTAMINATION (INDUSTRIAL APPLICATION)

8

3 Options considered for the primary circuit

1. On-line hard decontamination of the 6 loops during the SE preparatory phase

2. No-Hard decontamination; at the end of the SE the components are dismantled, immobilised without decontamination

3. Hard decontamination in batches in an auxiliary unit on the dismantled components at the end of the SE phase

Page 9: DECONTAMINATION (INDUSTRIAL APPLICATION)

9

On-line Hard Decontamination

Must be performed during the SE preparatory phase (operability and tightness of the circuit)

Must have a reasonable assurance to reach the free release levels for most equipment

‼ In the case of KNPP, to much plugging rate of the SGs tube’s and to difficult to remove (or to drill) the plugs on an economical basis

Option abandoned

Page 10: DECONTAMINATION (INDUSTRIAL APPLICATION)

10

Cost Benefit Analysis

Cj = Aj + Nj . V . X

Cj = overall cost of option j

Aj = total cost for the process Nj = number of final packages V = volume of the final package X = final disposal unit cost

Page 11: DECONTAMINATION (INDUSTRIAL APPLICATION)

11

Aj Items for processing costs

Investment fixed costs Consumable costs

- Chemical reagents- Final packages- Products for final conditioning (cementation)- Steam, electrical energy, auxiliay fluids

Manpower costs (for decontamination and waste conditioning)

Personnel radiological exposure costs

Page 12: DECONTAMINATION (INDUSTRIAL APPLICATION)

12

Factors influencing Nj

Total weight criteria- Internal concrete shielding- Maximum weight (licensing and handling)

Chemical concentration- Limit for total salts content (240 gr / l)

Contact dose rate (handling and transportation)

Activity inventory- WAC for critical nuclides

Page 13: DECONTAMINATION (INDUSTRIAL APPLICATION)

13

No-Hard Decontamination

Direct dismantling after SE, and conditioning the cut equipment

For SGs tubes, two cases Without supercompaction With supercompaction

Page 14: DECONTAMINATION (INDUSTRIAL APPLICATION)

14

No-Hard Decontamination

Equipment Nj Criterion

6 loops

6 SGs tubes bundels

12 SGs collectors

1 pressuriser

6 Main coolant pumps

12 Main isolation valves

6

20 to 25

12

10

10

7

Weight

α activity, geometry

weight

weight

Weight

weight

Total 70

Page 15: DECONTAMINATION (INDUSTRIAL APPLICATION)

15

No-Hard Decontamination

With supercompaction ∆ cost = - 7% Less volume Additional costs

- More operations for cutting in small lenghts- More handling operations- More secondary waste- More Manpower and Man.Sv exposure costs

Page 16: DECONTAMINATION (INDUSTRIAL APPLICATION)

16

Hard Decontamination, SGs tube excluded

• Hard Decontamination in batches(segmented components)

Compared to option 1 2X more reagents Volume of liquid waste is lower Volume of sludges is unchanged

• SGs tubes :cutting, conditioning with or not SC

Page 17: DECONTAMINATION (INDUSTRIAL APPLICATION)

17

Hard Decontamination,SGs tubes included

Significative increase of the surfaces Increase of the size and the capacity

- of the decontamination unit (50 m² / batch in place of 10-20 m² / batch)

- of the waste conditioning unit

Page 18: DECONTAMINATION (INDUSTRIAL APPLICATION)

18

Results for Nj by option

Option

Nj

Soft pre decontamination before SE 19

No-hard decontamination 65 to 70

Hard decontamination (all equipment, ex SGs tubes) 25 to 30

Hard decontamination (all equipment) 19

Page 19: DECONTAMINATION (INDUSTRIAL APPLICATION)

19

Cost Benefit Analysis

Result (cheapest option) Soft decontamination after Reactor Final Shutdown

Hard decontamination (all equipment) during the differed dismantling (at the end of the SE)

Batch process applied on segmented components

Page 20: DECONTAMINATION (INDUSTRIAL APPLICATION)

20

SGs decommissioning alternate options

• SGs melting option (Yankee Row, Kewaunee, Obrigheim NPPs)

• SGs entombment option(Loviisa NPP)

Page 21: DECONTAMINATION (INDUSTRIAL APPLICATION)

21

Nuclear Auxiliary Systems

Cold portion of following systems

• SV 01 Purification system of the primary circuit

• SV 02 Liquid waste collecting system

• SV 03 Liquid waste processing system

• SV 04 Spent fuel storage pools cooling down and purification systems

Page 22: DECONTAMINATION (INDUSTRIAL APPLICATION)

22

Nuclear Auxiliary Systems

No APCE Soft Pre Decontamination• Technical reasons

Need to circulate solutions at high temperature (110 – 160 °C)

≠ Systems operated at low temperature and not provided with thermal insulation

Complexity of the pipework circuits, difficulty to arrange circulation decontamination loops

Page 23: DECONTAMINATION (INDUSTRIAL APPLICATION)

23

Nuclear Auxiliary Systems

No APCE Soft Pre Decontamination• Radiological reasons

Internal β-γ and α surfacic contamination is low

(1 to 2 order of magnitude than the primary circuit at the Reactor Final Shutdown)

Page 24: DECONTAMINATION (INDUSTRIAL APPLICATION)

24

Reactor and Spent Fuel Pools

Selection of the decontamination process Chemical

- Too large volumes- Unfavourable geometry for recirculation

Ultra-sonic- Industrial experience in western PWRs- Easy to be implemented- Removal of cruds with immersed filter cartridges- DFs in the range of 5 to 50

Page 25: DECONTAMINATION (INDUSTRIAL APPLICATION)

25

• Patented submerged filter system UWF 120-4

• Reactor vessel pool and spent fuel pool

• Reduces activity and turbidity

• Outage time reduction

Pool Cleaning Filtration

Page 26: DECONTAMINATION (INDUSTRIAL APPLICATION)

26

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-0105 1296"0"

Pool CleaningWorking Positions05.12.96

05.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-0105 1296"0"

Pool CleaningWorking Positions05.12.96

05.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

UWF Working Position

Page 27: DECONTAMINATION (INDUSTRIAL APPLICATION)

27

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-0205 1296"0"

Pool CleaningChange-out Position05.12.96

05.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-0205 1296"0"

Pool CleaningChange-out Position05.12.96

05.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

UWF Filterelement Change Out

Page 28: DECONTAMINATION (INDUSTRIAL APPLICATION)

28

Booster UWS 30-1

• Suction installation as a water jet pump

• Handling: dimension as a fuel assembly

• Suction direct at the machine

Page 29: DECONTAMINATION (INDUSTRIAL APPLICATION)

29

Bottom- and Wall Cleaning

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-1005 1296"0"

Pool Cleaning05.12.9605.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

Combination between UWF andBooster with bottom cleaner

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-1005 1296"0"

Pool Cleaning05.12.9605.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

Combination between UWF andBooster with bottom cleaner

Page 30: DECONTAMINATION (INDUSTRIAL APPLICATION)

30

Cleaning of the Reactor Vessel

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-0905 1296"0"

Pool Cleaning05.12.9605.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

Combination between UWF andBooster with corner extraction

A

8

B

C

7 6 5

D

E

F

8 67 5

A

B

C

4 23

D

E

1

F

V99999-33-0905 1296"0"

Pool Cleaning05.12.9605.12.96

Submersible Filter System UWF 120balduf Verfahrenstechnik GmbHD-71720 Oberstenfeld GermanyPhone +49 (0) 7062 94220

Combination between UWF andBooster with corner extraction

Page 31: DECONTAMINATION (INDUSTRIAL APPLICATION)

31

Thermal Insulation and sheathing Materials

Immediate Removal( after decontamination of the primary circuit)

Not suited for long term conservation Corrosion of sheating materials Generation of dust and aerosols from glass

wool materials

Page 32: DECONTAMINATION (INDUSTRIAL APPLICATION)

32

Conditioning options

• Thermal insulation material

Precompaction (50 t) into drums (110 kg / 210 l drum)

Supercompaction (910 t) Height reduction factor of 3

Immobilisation with concrete in the final package

Overall volume reduction factor = 4.7

Page 33: DECONTAMINATION (INDUSTRIAL APPLICATION)

33

Conditioning options

• Sheathing materials

Two options Pre compaction, supercompaction,

immobilisation (‼ aluminium)

Decontamination to reach free release levels