decision making in the eia process

Upload: igiegie-oghenegueke

Post on 07-Apr-2018

231 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/6/2019 Decision Making in the EIA Process

    1/25

    Decision making in the EIA process

    By

    Dr. Rim-Rukeh Akpofure

    OutlineThe concept of decision-making

    Importance of decision- making in the EIA process

    An Overview of the EIA Process

    Identify Stages/Steps in EIA Process where decisions (Interim and Final) are taken.

    Case Studies

    Bibliography

    OBJECTIVES

    To describe the role and contribution of EIA in the decision-making process.

    RELEVANCE

    The EIA process was introduced with the express intention of incorporating environmental

    considerations into decision-making on major proposals. All of those involved in EIA require

    an understanding of how the decision-making process operates and the particular contribution

    made by EIA.

    The Concept of Decision Making

    Decision making can be regarded as the mental or cognitive processes resulting in the selection

    of a course of action among several alternatives. Every decision making process produces a

    final choice. The output can be an action or an opinion of choice.

    To make a decision the following must be considered:

    Objectives must first be established

  • 8/6/2019 Decision Making in the EIA Process

    2/25

    Objectives must be classified and placed in order of importance

    Alternative actions must be developed

    The alternative must be evaluated against all the objectives

    The alternative that is able to achieve all the objectives is the tentative decision

    The tentative decision is evaluated for more possible consequences

    The decisive actions are taken, and additional actions are taken to prevent any adverse

    consequences from becoming problems and starting both systems (problem analysis and

    decision making) all over again

    Importance of Decision - Making in the EIA process

    The EIA process was introduced with the express intention of incorporating environmental

    considerations into decision-making on major proposals. It is a policy management tool for both

    planners and decision-makers. EIA is an important tool in deciding about the final shape of a

    project. Not only does it help officials in making decisions about the project, it helps the project

    proponent achieve their aims more successfully

    EIA is an aid to decision-making. For the decision-maker to make any reasonable decision,

    alternative actions must be developed, and the alternative must be evaluated against all the

    objectives. The EIA process provides these alternatives upon which the decision maker utilizes.

    For example, the EIA process provides a framework for considering location and design issues

    and environmental issues upon which decisions are made. It can be an aid to the formulation of

    development actions, indicating areas where a project can be modified to minimize or eliminate

    altogether its adverse impacts on the environment. The consideration of environmental impacts

    early in the planning life of a development can lead to environmentally sensitive development;

    to improved relations between the developer, the planning authority and the local communitiesand to a smoother planning permission process. EIA can be the signal to the developer of

    potential conflict; wise developers may use the process to negotiate green gain solutions,

    which may eliminate or offset negative environmental impacts, reduce local opposition and

    avoid costly public inquiries.

    For example a local authority, it provides a systematic examination of the environmental

    implications of a proposed action (project), and sometimes alternatives, before a decision is

    taken. EIA is not a substitute for decision-making, but it help to clarify some of the trade offs

  • 8/6/2019 Decision Making in the EIA Process

    3/25

    associated with a proposed development action, which should lead to more rational and

    structured decision-making.

    An Overview of the EIA Process

    The basic steps in the EIA processes are as depicted in Figure 1.0:

    Fig 1.0: Simplified EIA Process

    Pro ect Pro osal

    Screening

    Initial EEEIA Re uired No EIA Re uired

    Sco in

    EBS

    Im act Anal sis

    Miti ation & EMP

    Review

    Decision

    A rovedNot A roved

    Re-Submit IMM

    Public Partici ation

    Public Partici ation

  • 8/6/2019 Decision Making in the EIA Process

    4/25

    Project screening: Determines whether or not an EIA is necessary. The number of projects

    that could be subject to EIA is potentially very large. Yet many projects may not have

    substantial or significant environment impact. A screening mechanism seeks to focus on those

    projects with potentially significant adverse environmental impacts or whose impacts are not

    fully known. Those with few or no impacts are screened out and allowed to proceed to the

    normal planning permission and administrative processes without any additional assessment.

    Screening is carried out by the regulatory agencies usually after a site visit. This is initiated by

    the project proponent submitting the Terms of Reference (TOR) to the regulator. Upon receipt

    of the TOR, the regulators carrys out a site (project location) verification exercise and a detail

    review of the TOR. At the end of the screening exercise, one of the following three decisions is

    possible.

    (a) The project is not likely to cause significant adverse environment effects, or such effects

    can be mitigated. The project is therefore permitted and the project classified as category 1 and

    to undergo only technical review.

    (b) The project is likely to cause significant adverse environmental effects; or there is public

    concern on the environmental effects of the project. The project is therefore permitted and

    classified as category II and to undergo mandatory (full) scale EIA process.

    (c) The anticipated adverse environmental effects are considered to be significant and

    cannot be mitigated. The development application is refused.

    Project scooping: This seeks to identify at an early stage, from all of a projects possible

    impacts and from all the alternatives that could be addressed, those that are the crucial,

    significant issues, scoping is generally carried out in discussions between the developer, the

    regulators and ideally the public. It is often the first stage of negotiation and consultation

    between a developer and other interested parties. Scoping begin with the identification of

    individuals, communities, local authorities and statutory consultees likely be affected by the

    project.

  • 8/6/2019 Decision Making in the EIA Process

    5/25

    In Nigeria, this aspect of EIA process is called public forum, where regulators, communities

    (likely to be impacted), local authorities and Community Based Organizations (CBOs),

    Community Development Association (CDAs) and non-government organizations (NGOs) are

    invited by the developer. Here, the developer presents the technical details and environmental

    implication of project for public scrutiny.

    Establishing Environmental Baseline:Environmental baseline data study includes land, water,

    noise, air, human beings, historical sites among others. This aspect of the EIA process is

    executed by a team of multi-disciplinary experts that are usually external consultants to the

    developer. The size of the team may vary from two to twelve and even larger. For some

    projects, the average is three or four. However, a team of 17 relevant specialist types has been

    recommended and this should include among others, medical personnel, ecologist; process /

    mechanical engineer, chemists, archaeologist and soil scientist. A team should cover the main

    issues involved.

    Baseline studies should involve the biophysical and socio-economic environments (see Table

    1.0).

    Table 1.0: Information describing the site and its environment

    1. Population proximity and numbers.2. Flora and Fauna (including both habitats and species) in particular, protected species and

    their habitats.3. Soil, agricultural quality, land-use pattern, geology and geomorphology.4. Water; aquifers, water courses and shoreline, including the type, quantity, composition

    and strength of any existing discharges.

    5. Air, climatic factors, air quality.6. Landscape and topography.7. Architectural and historic heritage, archaeological sites and features and other material

    assets.8. Recreational uses.9. Socio-economic variables such as employment, nutritional status, educational facilities,

    health institutions, etc._______________________________________________________

    Identification of Impacts: Impact identification brings together project characteristics and

    baseline environmental characteristics with the aim of ensuring that all potentially significant

    environmental impacts (adverse or favourable) are identified and taken into account in the EIA

  • 8/6/2019 Decision Making in the EIA Process

    6/25

    process. A wide range of methods has been developed and the methods are divided into the

    following categories:

    (a) checklists(b) matrices(c) quantitative methods(d) networks(e) overlay maps.When choosing a method, the following salient issues should be considered:

    * to ensure compliance with regulations;

    * to provide a comprehensive coverage of a full range of impacts including social, economic, andphysical;

    * to distinguish between positive and negative, large and small, long-term and short-term,

    reversible and irreversible impacts;

    * to identify secondary, indirect and cumulative impacts as well as direct impacts;

    * to distinguish between significant and insignificant impacts;

    * to allow a comparison of alternative development proposals.

    * to consider carrying within the constraint of an areas carrying capacity.

    * to incorporate qualitative as well as quantitative information;

    * to be easy and economical to use;

    * to be unbiased and to give consistent results;

    * to be of use in summarizing and presenting impacts in the EIS (Environmental Impact

    Statement).

    Prediction ofImpacts

    The object of prediction is to identify the magnitude and other dimensions of identified change

    in the environment with a project or action in comparison with the situation without that project

    or action. Prediction involves the identification of potentials change in indicators of such

    environment receptors. Table 2.0 provides a view of the scope of the environment and the

    environmental receptors that may be affected by a project. Table 3.0 shows that prediction

    should also identify direct and impact impacts, the geographical extent of impacts (e.g local;

    regional, national), whether the impacts are beneficial or adverse and the duration of the

  • 8/6/2019 Decision Making in the EIA Process

    7/25

    impacts. The reversibility or otherwise of impacts, their permanency, and their cumulative and

    synergistic impacts should also be predicted.

    Another important distinction associated with prediction of impacts is that magnitude (ie. Size)

    and the significance (ie. The importance for decision-making) of the impacts. Magnitude does

    not always equate with significance. For example, a large increase in one pollutant may still

    result in an outcome within generally accepted standards, whereas a small increase in another

    may take it above the applicable standards (Fig. 2.0).

  • 8/6/2019 Decision Making in the EIA Process

    8/25

    Table 2.0: Environmental Receptors

    Physical Environment Indicators

    Air and atmosphere air qualityWater resources and water

    bodies

    Water quality and quantity

    Soil and geology Classification, risks (e.g.

    erosion, contamination).

    Flora and Fauna Birds, mammals, vegetation

    Human beings Physical and mental health andwell being

    Landscape Characteristics and quality oflandscape

    Cultural heritage Conservation areas; historic and

    archaeological sites.Socio-economic Direct employment, labour,

    market characteristics; servicesemployment.

    Demography Population structure and trends.

    Housing Supply and demand

    Local services Health, education etc

    Socio-cultural lifestyles, social problems,

    quality of life, communityconflict

    Table 3.0: Types of Impact

    * Physical and socio-economic

    * Direct and indirect

    * Short-run and long-run

    * Local and strategic

    * Adverse and beneficial

    * Reversible and irreversible

    * Quantitative and qualitative

    * Distribution by group and / or area

    * actual and perceived

    * relative to other development.

  • 8/6/2019 Decision Making in the EIA Process

    9/25

    Fig. 2.0: Significance expressed as a function of impact magnitude and theimportance/sensitivity of the resources receptors.

    Another dimension is the unit of measurement, and the distinction between quantitative and

    qualitative impacts. Some indicators are more readily quantifiable than others (e.g. a change in

    the quality of drinking water, in comparison for example, with changes in community stress

    associated with a project).

    Predictions should be present impacts in explicit units for the purpose of evaluation.

    Quantification can allow predicted impacts to be assessed against local, national and

    international standards. Predictions should also include estimates of the probability that an

    impact will occur, which raises the important issue of uncertainty.

    There are many possible methods to predict impacts. A study carried out in the early 1980s

    identified 150 possible prediction methods used in just 140 EIA studies from the Netherlandsand North America. None provides a magic solution to the prediction problem. All methods are

    partial in their coverage of impacts, but some seek to be more holistic than others.

    Six types of predicting models have been identified. They are; mechanistic method, mass

    balance method, statistical method, physical, image or architectural method, field and laboratory

    experimental methods and analogue method. When choosing prediction methods, an assessor

    should be concerned about their appropriateness for the task involved, in the context of the

    resources available.

    Evaluation: Once impacts have been predicted, there is a need to assess their relative

    significance. Criteria for significance include the magnitude and likelihood of the impact and

    its spatial and temporal extent, the likely degree of the affected environments recovery, the

    value of the affected environment, the level of public concern and political repercussions.

    Evaluation methods are many and varied. They range from simple or complex, formal or

    Medium

    Significance

    LowSignificance

    High

    Significance

    MediumSignificance

    Magnitu

    de

    Importance/sensitivity

  • 8/6/2019 Decision Making in the EIA Process

    10/25

    informal, quantitative or qualitative, aggregated or disaggregated method. An example of the

    formal evaluation method is the comparison of likely impacts against legal requirements and

    standards (e.g. air quality standards, building regulation). Other methods of evaluation are;

    cost-benefit analysis technique; monetary valuation technique, scoring and weighting and multi-

    criteria methods.

    Mitigation: Mitigation is defined as measured envisaged in order to avoid, reduce, and it

    possible remedy significant adverse effects. Mitigation is not limited to one point in the

    assessment. Although it may follow logically from the prediction and assessment of the relative

    significance of impacts, it is in fact inherent in all aspects of the process. Mitigation measuresproposed for a particular action should be such that it is practicable and realistic.

    Public consultation and participation: One of the aims of the EIA process is to provide

    information about a proposal likely environmental impact to the developer, public and decision-

    makers, so that a better decision may be made. Consultation with the public and statutory

    consultees in the EIA process can help to ensure the quality, comprehensiveness and

    effectiveness of the EIA as well as to ensure that the various groups views are adequately taken

    into consideration in the decision-making process. Although EIA process may vary from

    country to country, it is an integral part of any EIA process worldwide.

    To ensure that public involvement achieves the aims set out, several criteria for effective public

    participation and consultation has been identified:

    (i) Identification of the groups/ individuals interested in or affected by the proposed

    development. This can be classified into two groups. The first consists of pressure groups;

    NGOs, CBOs, and CDAs. The second group consists of the people living near the proposed

    project who may be directly affected by it.

    (ii) Information flow must be two-ways. It must establish a dialogue between the public and

    decision-makers (both the project proponent and the authorizing body) and to ensure that

    decision-making assimilate the publics view into their decision.

    (iii) It must cater for different levels of technical sophistication and for special interests.

    (iv) Provision of pertinent and timely information by the developer.

  • 8/6/2019 Decision Making in the EIA Process

    11/25

    (v) An appropriate tool method of public participation and consultation should be used.

    (vi) Community members, general public as well as local authorities must have access to the

    decision process.

    Review of the EIAReports: The comprehensiveness and accuracy of EIA reports are matters

    of concern. Many EIA reports in Nigeria for example do not meet even the minimum

    regulatory requirements, much less provide adequate information on which to base decisions.

    In Nigeria, the Federal Ministry of Environment review EIA reports and act as a quality

    assurance process. However the FMEMV do not have the full range of technical expertise

    needed to assess the adequacy and comprehensiveness of an EIA report. To this end,

    consultants (usually experienced academicians) are brought into review the EIA report.

    Effective review criteria include amongst others.

    * ensure that all relevant information has been analyzed and presented.

    * assess the validity and accuracy of information contained in the report.

    * consider whether additional information is needed.

    * assess the significance of the projects environmental effects.

    * evaluate the need for mitigation and monitoring of environmental impacts, and

    * advise on whether a project should be allowed to proceed.

    Decisions on project

    In Nigeria, decisions to authorize projects are made by the Honourable Minister of FMEMV.

    When making a decision, the authority is required to have regard to all the environmental

    information ie., the information contained in the EIA report and any comment made by the

    external reviewers and representations from members of the public as well as other material

    considerations. By any standards, making decisions on development projects is a complexundertaking. Weighing up the information to reach a decision involves not only considering the

    views of different interest groups and the importance of the environmental issues, but also

    determining whether the proposed project is in accordance with the countrys development plan.

    Monitoring after the decisionMonitoring involves the measuring and recording of physical, social and economic variables

    associated with development impacts (e.g. traffic flows, air quality, noise, employment). The

    activity seeks to provide information on the characteristics and functioning of variables in time

  • 8/6/2019 Decision Making in the EIA Process

    12/25

    and space, and in particular on the occurrence and magnitude of impacts. Monitoring can

    improve project management. It can be used, for example as an early warning system to

    identify harmful trends in a locality before it is too late to take remedial actions. It can help to

    identify and correct unanticipated impacts. Monitoring can also provide an accepted data base,

    which can be useful in mediation between interested parties. Monitoring is also essential for

    successful environmental impact auditing, and can be one of the most effective guarantees of

    commitment to undertakings and to mitigation measures.

    The aim of monitoring is to help ensure that mitigation measures are implemented in a timely

    manner in accordance with the terms of the project approval. Monitoring refers to the

    observation and oversight of mitigation activities at a project site. If monitoring reveals that

    mitigation measures are ignored or are not completed, sanctions could be imposed; these can

    include for example, stop-work orders, fines and restitution.

    The components of a monitoring programme would normally include the following:

    * a summary of the significant impacts identified in the EIA report.

    * the mitigation measures recommended for each significant measures.

    * the agency responsible for the monitoring of the mitigation measure.

    * the timing and / or frequency of the monitoring.

    * the reporting requirements.

    Decision-Making in the EIA Process

    EIA is part of a larger process of decision-making to approve a major proposal. Decision

    making is the process of choosing between alternatives courses of action. The process is

    essentially political in nature that is based on information from a number of different sources

    and involves making a large number of trade-offs. A balance must be struck between the

    benefits and costs; their environmental, economic and social elements must be weighed, and

    uncertainties and arguments over the significance of risks and impacts must be addressed.

    Decision making involves weighing the benefits and costs and making trade-offs among a

    range of considerations. In the context of EIA, it is a process of information gathering which is

    intended to facilitate environmentally sound decision-making. The process culminates in a final

    decision on whether or not a proposal is acceptable and under what conditions. When the term

    decision making is used in EIA, it is usually taken to mean final approval of a proposal.

  • 8/6/2019 Decision Making in the EIA Process

    13/25

    However, a series of interim decisions about the proposal are made throughout the EIA

    process (see Figure 3.0).

    Fig. 2.0: Decision making in the EIA process.

    Interim Decision: A series of decisions are made throughout the EIA process. Examples of

    such stages where interim decisions are made include:

    (a)Categorisation of Project: At the end of the screening exercise, one of the following threedecisions is possible. (i)The project is not likely to cause significant adverse environment

    effects, or such effects can be mitigated. The project is therefore permitted and the project

    classified as category 1 and to undergo only technical review. (ii)The project is likely to

    cause significant adverse environmental effects; or there is public concern on the

    environmental effects of the project. The project is therefore permitted and classified as

    category II and to undergo mandatory (full) scale EIA process. (iii) The anticipated

    Information

    from differentsources

    EIA Report

    Env. BaselineData

    Gathering

    Information from

    Screening

    Publicinvolvement

    Information

    from Scoping

    FINAL

    DECISIONMAKING

    Other Inputs e.g

    benefits-costanalysis

  • 8/6/2019 Decision Making in the EIA Process

    14/25

    adverse environmental effects are considered to be significant and cannot be mitigated. The

    development application is refused.

    (b)Project Options: Here decisions are taken based on possible options available. Guidingsuch decisions are technical, environmental and cost-benefits information.

    (c) Public Forum: if the proposed project is categorized as one, which causes significant

    environmental impact, (mandatory project) the project proponent (assisted by a consulting firm)

    organizes a public forum as part of the scooping process. The objective of the public forum is to

    inform the community people about the planned development and its likely ecological, socio-

    economic and cultural impacts. The approach is to invite the members of community

    development committee (CDC), youth leaders, women leaders, and members of the traditional

    council of the identified communities that are likely to be affected by the proposed project to a

    town hall (usually located at the local government headquarters). As this stage, decisions/ inputs

    from the public are carried on board.

    (d) Gathering of Ecological and Socio-economic Baseline Data: Another stage in the EIA

    process where interim decisions are taken and documented is during the gathering of ecological

    and socio-economic baseline conditions data of the project area. This is carried out through the

    use of experimental methods and questionnaires. At this stage, local people take part in the

    study by providing information through questionnaires administered to them by the consulting

    firm.

    (e) Public Display of the draft EIA report: Another stage of inputs/decisions into the EIA

    process is at the public display of the draft EIA report. The FMENV displays the draft EIA

    report submitted to it by the proponent at appropriate locations where the interested public will

    have access to it for at least 21 working days. Information in different media (newspapers and

    radio announcement) is made to notify the public of the display centers. Comments, inputs and

    complaints are also expected to be forwarded to the FMENV within the stipulated period of

  • 8/6/2019 Decision Making in the EIA Process

    15/25

    display. At the expiration of the display period, the FMENV constitutes a panel of experts, to

    review the draft EIA report at a public sitting. Members of the public are expected to make

    useful contributions to making the document acceptable.

    (f) Panel Review Meeting: Here members of the panel set up by Honourable Minister of

    Environment to review the EIA report submit their contributions to improve the report.

    FinalDecision:

    The information provided by EIA is based on technical analysis and public involvement. It is a

    synthesis of facts and values. How these components are reconciled and documented in the EIAreport can have an important bearing on the potential contribution it makes to decision-making.

    The usefulness of the EIA report for decision-making also depends upon the use of good

    practice at previous stages in the EIA process. The Final decision maker in the EIA process in

    Nigeria is the Honourable Minister in charge of the Federal Ministry of Environment. At a

    minimum, decision maker is expected to understand:

    y The basic concepts and purpose of EIA.y EIA requirements, principles and guidelines that is applicable.y The effectiveness of their implementation and the implication for decision making.y Limitations that may need to be placed on information and advice contained in the EIA

    report.

    y How EIA process and public measure up to internationally acceptable standards.y Issues associated with public consultation decision making including third party and legal

    challenges to the authorisation of proposals to EIA.

    When making decisions, those responsible seldom have time to read the EIA report, other than

    an executive summary. Typically, they rely upon the advice of their officials, whose views are

    likely to be shaped by their policy mandates and responsibilities. The general receptivity of

    decision-makers to the findings of an EIA report will reflect their confidence in the EIA process

    and its perceived acceptance by other parties. In this regard, public trust in the EIA process,

    which is built up over time, may carry particular weight.

    The factors that will be important in the final approval of a proposal include:

  • 8/6/2019 Decision Making in the EIA Process

    16/25

    y findings of significant impact contained in the EIA report;y inputs from interim stages; andy other external pressures or political inputs to decision-making.

    A summary of Information considered important for decision-makers is given in the Table 3.0

    below. It lists the key aspects of EIA reports which decision-makers need to take into account

    when making final approvals and setting conditions for project implementation. This listing is

    generic and should be reviewed to establish the aspects that are important locally.

    Table 3.0: Information Considered Important for Decision Makers

    Decision Making Stage Important InformationBackground Project background and the most important

    environmental issues involved

    Policy Context Basic development issue or problem beingaddressed (e.g. flooding, water shortage, etc); The

    relationship to environmental policies and plans

    Alternatives Alternatives to the proposal (including the bestpracticable environmental option (BPEO) orequivalent designation)

    Public involvement Key public views ; Concerns of affected

    communities ;

    Areas of agreement and disagreementImpact analysis Costs and benefits

    Distribution of gains and losses

    Mitigation and monitoring Adequacy of proposal measures

    Conclusion and recommendations main economic benefits, significant environmentaleffects and proposed mitigation measures

    The extent to which the proposal conforms to theprinciples of sustainable development

    Design and operational changes to improve theenvironmental acceptability of the project

    Checks and Balances in Decision- Making: A number of checks and balances are built into EIA

    processes to help ensure accountability and transparency. Such checks and balances include:

    y No decision will be taken until the EIA report has been reviewed and considered.y The findings of the EIA report and review are major determinant of approval and condition

    settings.

    y Public comment on the EIA report is taken into account in decision making.

  • 8/6/2019 Decision Making in the EIA Process

    17/25

    y Approvals can be refused or withheld, conditions imposed or modifications demanded at thefinal decision stage.

    y The decision is made by the FMENV other than the proponent.y Reasons for the decision and conditions attached to it are published.y There is a public right of appeal against the decision (where procedures have not been

    followed or they have applied unfairly).

    Range of Possible Outcomes Arising from Decision Making: There can be a number of different

    outcomes from decision making:

    y The proposal can be approved.y The proposal can be approved with conditions.y The proposal can be placed on hold pending further investigations.y The proposal can be returned for revision and re-submission.y The proposal can be rejected outright.

    Improving the Possible Action ofDecision Maker. The sustainable objective of EIA places a lot of

    task on the decision maker and hence it is important that the decision maker should be encouraged

    to:

    y Implement the sustainability commitments made at various International EnvironmentalFora.

    y Broaden their perspective of the environment and its values.y Better communicate information and reasons for decisions.y Apply the precautionary principle when addressing the environmental impacts of

    development proposals.

    y Look for improved ways of making trade-offs among environmental, economic and socialfactors.

    y Adopt more open and participatory approaches.y Use strategic tools to aid decision making including SEA for proposed policies and plans

    and environmental accounting to gain a realistic measure of macro-economic progress.

  • 8/6/2019 Decision Making in the EIA Process

    18/25

    Local Case Studies

    Case study 1: Exploratory Drilling of an Oil Well (Ekedei Deep A)

    In 2001, the proponent commissioned a seismic company to carry out seismic exploratory of

    Amatolo/Ekedei area located in Yenagoa Local Government Area of Bayelsa State. The result

    confirmed the presence of large quantity of hydrocarbon in the deeper structure of Ekedei area.

    Consequently, the proponent planned to drill an exploratory well (Ekedei-Deep A) in the area.

    Major project activities include amongst others; the dredging of a 1.7km canal from the

    Sangana River to the drilling slot and the movement of a swamp drilling rig to the drilling slot

    and other associated drilling activities.

    In 2003, the project proponent began the EIA process for the exploratory drilling of Ekedei-

    Deep A by the submission of the Terms of Reference (TOR) to the regulatory agency

    (FMENV). The project proponent did what was required of them by legislation: organization of

    public forum for public participation, ecological and socio-economic baseline data gathering

    and panel review meeting.

    We then analyse the decision- making of the project taken within the framework of regulatory

    activities, public participation, conflict resolution, protection of natural resources and improved

    planning in the EIA process.

    First, at the end of the screening exercise, the following decision was taken by the regulatory

    Ministry: The project is likely to cause significant adverse environmental effects and or there is

    public concern on the environmental effects of the project. The project is therefore permitted

    and classified as category II and to undergo mandatory (full) scale EIA process.

    Secondly, let us consider the criterion of public participation. The project proponent organized a

    public forum with the objective of informing the community people (those that will be directly

    affected by the project activities), regulatory agencies, non-governmental organizations

    (NGOs), community based organizations (CBOs) and community development associations

  • 8/6/2019 Decision Making in the EIA Process

    19/25

    (CDAs) about the planned development. At the end of the public forum, community leaders

    expressed their happiness and promised the project owner of a cordial working environment.

    However, the people felt that they were left in the dark about major programme decisions such

    as; the schedule, technology and project design. The proponent were informed of the possibility

    of accessing the drilling slot through an existing and abandoned road without the proposed

    construction of the 1.7km canal by dredging from Sagana River to the drilling slot. Considering

    the environmental problems such as, salt water intrusion, loss of vegetation, erosion, disruption

    of fishing activity increased turbidity, flooding and alteration of the aquatic ecosystem. The

    alternative involves the reconstruction of an existing but abandoned road that leads directly to

    drilling slot was generally accepted. This is an example of interim decision.

    The proponent agreed that engaging their stakeholders in a mutual, cooperative problem solving

    process promoted project acceptability. Without public acceptance, proponents may not have

    accomplished its mission on schedule. Project acceptability results in a better planning process

    and a better decision.

    A compelling characteristic of the project exploratory drilling of Ekedei Deep A is the

    general acceptability the project received from the community people. Eventually a final

    decision was given to project an approval without any conditions.

    Case study 2: Construction of an 8-inch 38km crude oil pipeline project.

    It is estimated that the Samabri-Beseni basin holds up to a large quality of crude oil (actual

    amount of crude oil not disclosed) concentrated in the Samabri-Beseni Field.

    The field is located in Samabri/Beseni communities in Yenagoa Local Government Area of

    Bayelsa State. In the development of the oil field, the proponent had drilled a number of

    clusters of production wells and had proposed to construct an 8-inch 38km crude oil pipeline to

    transport crude petroleum to the nearest crude oil gathering facility.

  • 8/6/2019 Decision Making in the EIA Process

    20/25

    In 2004, the proponent submitted a Terms of Reference (TOR) to the regulatory agency

    (FMENV) seeking for approval to commence the EIA process. The proposed pipeline is

    planned to be a completely and continuously welded forming a continuous of carbon steel

    (diameter 8 inch) with a polythene coating for corrosion protection. The pipeline was planned

    to be lowered into a 0.9-1.1m deep trench and later back filled. Project activities also involve

    the clearing of vegetation along the acquired right of way (ROW) which is 30-50m wide. A

    fibre optic communication and sensing cable has also been buried in the pipeline trench for

    enhancement of leak detection capabilities.

    As a first step in the EIA process, the regulatory agency carried out a site verification exercise

    of the project area. Thereafter, the project was categorised as a project that will undergo full

    and mandatory EIA process (Category A). The proposed pipeline ROW is planned to traverse a

    thick forest reserve and a seasonal lake (Abuo Lake). At the end of the EIA process, an

    approval was given for the commencement of the project with a major modification (a change

    of the pipeline ROW), to avoid the thick forest reserve and a reduction in the number of river

    crossing.

    What went right? A well-conducted EIA resulted to the projects success. The projects

    success has been attributed to early, substantitive and continuous public involvement during all

    phases of the EIA process and project implementation.

    First, the project proponent, and regulatory agencies strove for democratic public involvement.

    The proponent organized a well-coordinated public forum where all stakeholders (community

    people, regulatory agencies, members of various community organizations) were in attendance.

    Critical issues such as project design, project schedule, health, safety and environment (HSE)

    issues and employment opportunities were openly discussed and generally acceptable decisions

    were taken. In addition, the proponent maintained continual community involvement especially

    at all levels of project implementation. A database was created with the names and addresses of

  • 8/6/2019 Decision Making in the EIA Process

    21/25

    key community informants so that the proponent could communicate with each of the identified

    key informants in the area. The proponent established a public affairs committee in the

    community. Weekly meetings were held to bring stakeholders concerns to the attention of the

    proponent and to disseminate information from the proponent to the community people.

    Community people remarked that the proponent was actually listening to our suggestions.

    Second, the proponent took a proactive approach to conflict resolution. Through extensive

    public involvement activities the proponent sought to identify, address and resolve conflicts

    rather than ignore them. For example, families that own Abuo Lake were identified and all

    contentions issues resolved amicably. As a notable testament to conflict resolution, there were

    no communal clashes, family conflict, and lawsuits.

    Third, the proponent and the stakeholders took proactive decisions that protected natural

    resources such as the thick forest area and Abuo Lake. Suggestions and selection of mitigation

    measures was not made in isolation of the community concerns. Public opinions were elicited

    early enough to be part of project planning, alternatives analysis and evaluation. An Impact

    Mitigation Monitoring (IMM) was carried out to ensure that the suggested mitigation measures

    were implemented ruing project execution.

    Fourth, the EIA process especially public forum, panel review meeting and ecological and

    socio-economic baseline data gathering helped the planning process. The proponent made

    spirited effort to maintain open and honest community people input was key to the evaluation of

    alternatives. In turn, the people were supportive of the proponents mitigation measures.

    The review process acknowledged an EIA report that was clearly and appropriately

    documented. The final decision was an approval without conditions.

  • 8/6/2019 Decision Making in the EIA Process

    22/25

    TAKING DECISION-MAKING PROCESS IN EIA TO THE NEXT LEVEL

    One important principle for effective decision making in the Environmental Impact Assessment (EIA)

    process is the principle of transparency. Transparency requires that all factors relevant to assessment of

    decisions are clearly identified by the decision-maker. A transparent process provides certainty in the

    EIA process through ensuring all obligations, opportunities and decisions in the procedure are clearly

    set out. It also partially provides accountability to participants and stakeholders, and makes the EIA

    decision-makers accountable. The integrity of an EIA system, rest squarely on the fact that all

    participants have faith in the outcomes, of the process and this can be achieved in part through having

    an open, transparent system with clearly defined objectives and processes and realistic opportunities for

    participation by all stakeholders.

    The way in which decisions are reached in EIA and the manner of their communication are two factors

    that contribute to the effectiveness of a particular process. EIA is considered to be effective when

    environmental impacts are accounted for by project decision-makers in the course of planning, and

    hence some weight is given to environmental factors during project decision-making.

    To take decision making in the EIA process in Nigeria to the next level requires a detailed examination

    of the present practices and procedures gap analysis and suggestions offered.

    1. During project screening, decisions taken by the regulatory agency is based on the informationsubmitted by the project proponent as per the terms of reference (TOR). It has been observed

    over the years that proponents are always economical with information regarding the project

    scope and details and hence regulatory agency categorise most project to undergo only technical

    review. The interim decision taken in such cases are not correct.

    2. During project scoping especially at the formal presentation of the proposal before community(open forum), presentation is too technical for the community people to understand and hence

    find it difficult to draw a nexus between project activities and the likely environmental impact.What transpire in most cases is monologue and not dialogue. It is not participative.

    3. At the stage of gathering environmental baseline data, the decision on the actual number ofsamples to be collect from the various environmental media is taken by the proponent which in

    most cases does not reflect on the size of the likely impacted area. Again, the application of

    socio-economic questionnaire to gather socio-economic data does not reflect the actual (real)

    situation and hence interim decision taken at this stage may not be correct.

  • 8/6/2019 Decision Making in the EIA Process

    23/25

    4. It has been noted that decision-making requires striking a balance between economic,

    environmental, social and other criteria. Thus it is a political process involving trade-offs rather

    than a purely scientific undertaking. At the final decision stage, trade-off process takes place

    largely behind closed doors, in practice, only a generalised understanding of how decisions are

    actually reached in such cases is evident to the public

    There is room for improvement in EIA process, and it can be achieved through having open

    communication processes or transparency in how decisions are reached.

    1. Project proponent should be candid, truthful, and more open about detail project activities.2. Public forum should be organised to make more participatory.3. At the screening stage, a standardised filtering table with check boxes should be developed to

    identify topics that apply to the proposal, and the level of assessment is subsequently

    determined by the regulatory agency.

    4. During scoping, another checklist should be developed to establish the key environmentalfactors to be addressed by the proponent for each of the screening topics. This is a generic

    check sheet which links environmental factors with environmental objectives established by the

    regulatory agency. Stating the environmental objectives that apply to a particular proposal

    during the scoping stage is a serious attempt to make the goals of EIA clear and provides a

    structure for what follows. Ultimately it leads to a more transparent way of reaching theconclusion that a particular proposal is environmentally acceptable, on the grounds that it is able

    to meet the regulatory objectives for individual environmental factors.

    Conclusion and Recommendations

    It is mandatory that, country such Nigeria that has diverse biological characteristics protect and

    develop its environmental values. The enactment of the EIA Act No. 86 of 1992 and the

    development of the EIA procedural guidelines is an important tool for the protection of the

    precious environment. A well-coordinated EIA for developmental projects are a sure path to

    sustainable development. Even though Nigeria has been implementing the EIA Act No. 86 of

    1992 for the past fifteen years there are still some aspects that need improvement and

    development and one of such aspect is the decision making process. Once these aspects are

    improved they will be more applicable to sustainable development of project execution.

  • 8/6/2019 Decision Making in the EIA Process

    24/25

    Bibliography

    Appiah-Opoku, S. (2001) Environmental Impact Assessment in Developing Countries: TheCase of Ghana. Environ. Impact Asses Rev 21: 59-71.

    Barber, B. (1984). Strong Democracy: Participatory Politics for a New Age. Berkeley:University of California Press.

    CEC: Centre for Environment Commission (1985). On the assessment of the effects of certain

    public and private projects on the environment. Official Journal L, 175: 5 CEC: Centre forEnvironmental Commission (1992). Towards sustainability, Brussels: CEC publications Inc.

    DOE (1989): Department of Environment) (Environmental assessment: a guide to the procedures. London: HMSO.

    Fehr, R. (1999). Environmental Health Impact Assessment: Evaluation of a ten-step Model.

    Epidemiology 19: 341-357.

    Glasson, J., Elson, M.J., van der Wee, M. and Bernett, B. (1994). Socio-economic ImpactAssessment of the Proposed Hinkley Point C Power Station. Oxford: Oxford Polytechnic

    Impacts Assessment Unit.

    Glasson, J., Therivel, R. and Chadwick, A. (1999). Introduction to Environmental Impact

    Assessment, London: UCL Press Limited.

    Jain, R. K., Urban, V. L. and Stacey, G. S. (1993). Environmental Impact Analysi,s New York:Van Nostrand Reinhold.

    Kakongo, J. O (1998) EIA and Good Governance: iIsues and Lessons from Africa,Environ.

    Impact Assess Rev 18: 289-305.

    Kemm, J. (2004). What is Health Impact Assessment and what can it learn from EIA?EnvironImpact Assess Rev. 24: 131-134.

    Munn, R. E. (1979). Environmental Impact Assessment: Principles and Procedures, New York:Wiley.

    Momtaz, S. (2002). Environment Impact Assessment in Bangladesh: A Critical Review,Elsevier Publisher 22:163-179.

    Portney, K. E. (1991). Public Environmental Policy Decision-making: Citizen Roles, In R.A

    Chechile and S. Charlisle (Eds) Enviornmental Decision Making: A MultidisciplinaryPerspective, New York: Van Nostrand Reinhold.

  • 8/6/2019 Decision Making in the EIA Process

    25/25

    Rim-Rukeh, A. and Imide, I. O. (2006). Pubic Participation and Consultation in Nigeria EIA

    Process: A Procedure Practice Gap Analysis. Journal of Nigerian Environmental Society(JNES) 3 (1 & 2): 23-30.

    Shepherd, A. (1997.) Post-Project Impact Assessment and Monitoring in: EnvironmentalMethods Review: Retooling Impact Assessment for the New Century, Atlanta G. A: ArmyEnvironmental Policy Institute.

    Shepherd, A. and Bowler, C. (1997). Beyond the Requirements: Improving Public Participation

    in EIA. Journal of Environmental Planning and Management 40 (6): 725-738.

    Singh, M. C. and Titi, V. (1992). Empowerment for Sustainable Development: TowardsOperational Strategies. Canada: IISD.

    Strong, A. L., Mandelker, D. R. and Kelly, E. D. (1996). Property Rights and Takings. Journal

    of the American Planning Association 62 (1): 5-16.

    Susskind, L. and Scrimshank, J. (1987). Breaking the Impasse: Consensual Approaches toResolving Public Disputes, New York: Basic Books.

    UNCED (1992): United Nations Conference on Environment and Development Principle 17, of

    the Rio Declaration on Environment and development.

    Utzinger, J., Wyss, K., Moto, D. D., Yemadji, N., Tanner, M. and Singer, B. H. (2005).Assessing Health Impacts of the Chad Cameron Petroleum development and pipeline project:

    challenges and a way forward, Environmental Impact Assessment Review 25: 63-93.

    WCED (1987): (World Commission and Environment and Development Our common Future,

    Oxford: Oxford University Press.