dcr 20140721
TRANSCRIPT
![Page 1: DCR 20140721](https://reader031.vdocuments.us/reader031/viewer/2022020519/577cc6841a28aba7119e76e5/html5/thumbnails/1.jpg)
Daily Construction Report
(DCR)
WTG Type: Qty:
Time: Wind: Temp.:
Company Quantity Quantity
1 0
1 3
1 2
1 2
18 2
0 3
0 0
3 0
1 0
0 0
0 0
0 0
0 0
TOTAL: 26 12
Parts PMT Lift DTA Base S4 S3 S2 S1 Nacelle Hub/Nose BladesTotal 11 6 1 2 1 2 0 1 1 2 3
Parts PMT Lift DTA Base S4 S3 S2 S1 Nacelle Rotor IIP
TOTAL 1 0 1 1 1 1 0 1 1 0 0
Installation Lead Generator
Installation TA Chery picker
Commissioning TA
0
1.4 SCADA and Wind Control:
0
Truck driver
0
B 8
1.3 Commissioned:
Components Status arrived Status received Installed Activated ATP
Components
Activities MCC Energized
Turbine Delivery
B 6
B 7
0
CCC Start Reliability Run Completed Reliability Run
0
2.0 Overall Project Status:
SCADA 0 0 0
Visitor
Commissioning Lead
Receiver
Other
Other
Other
I 1 17-Jul-2014
Project Name:
I 2
Installation End IIP CCT
1.0 Status of components on Site:1.1 Delivered:
1.2 Installed:
TOTAL
TR/RR Completion
Wind Control 0 0 0 0
General Site Information Weather conditions that affect activities on site
Date:
Forklift
Truck
GE Site Manager: Precipitation:
Manpower EquipmentCategory Specification
Site Manager Crawler crane
EHS Manager Truck crane
Crane driver
0 0
I 3
B 1
B 2
B 3
B 4
B 5
240487773.xls.ms_office Page 1 of 5
![Page 2: DCR 20140721](https://reader031.vdocuments.us/reader031/viewer/2022020519/577cc6841a28aba7119e76e5/html5/thumbnails/2.jpg)
Daily Construction Report
(DCR)
Turbine
I 3 Rotor
I 3
I 2 S5 S3
Pad
I 3 Rotor
I 3 Rotor
I 3
I 2
Where What Who When Why Comments
Pad Company Manpower Start time End time Total time Work / Activities planned but not possible to perform
Comments:
7.0 Signatures
Internal work
complete rotor assemblyAssemble
3.0 Description of Todays' Work:3.1 Daily Progress Report - Today
Install
Internal work
Activity Components Comment
4.0 Work schedule:
Prepare
This document shall be signed by both Customer and GE Site Manager within one week from the Date of the report above, else shall be deemed as accepted by both Parties.
6.0 Supporting evidences / Comments
Customer Site Manager: GE Site Manager:
Date: Date:
General ElectricEnex
Signature Signature
5.0 Areas of Concern / Issues (where, what, who, when, why)
1-Ja
n-1
900
0-Ja
n-1
900
Activity
Crane assembly
Crane disassembly
Components Comment
4.1 Work planned for next working day
complete rotor assembly
240487773.xls.ms_office Page 2 of 5
![Page 3: DCR 20140721](https://reader031.vdocuments.us/reader031/viewer/2022020519/577cc6841a28aba7119e76e5/html5/thumbnails/3.jpg)
1.0 Components status:
1.1 WTG components delivered on site: 1.2 WTG components received on sitePa
d
PMT
Lift
DTA
Bas
e
S4 S3 S2 S1
Nac
elle
Hu
b/N
ose
Bla
des
PMT
Lift
DTA
Bas
e
S4 S3
I 3 1 1 1 1 1 1 N/A 1 1 1 3 1 1 1 1 1 1
I 2 1 1 1 1 N/A 1 1
I 1 1 1 N/A 1
B 4 1 1 N/A 1
B 3 1 1 N/A 1
B 2 1 1 N/A 1
B 1 1 N/A 1
B 5 1 N/A 1
B 6 1 N/A 1
B 7 1 N/A 1
B 8 1 N/A 1
TOTAL 11 6 1 2 1 2 0 1 1 2 3 11 1 1 1 1 1
Components
3.0 SCADA and Wind Control status:Arrived Received Installed Activated ATP
Wind Control
SCADA
![Page 4: DCR 20140721](https://reader031.vdocuments.us/reader031/viewer/2022020519/577cc6841a28aba7119e76e5/html5/thumbnails/4.jpg)
1.0 Components status: 2.0 Installation and Commissioning status:
1.2 WTG components received on site 2.1 WTG installation status: 2.2 WTG commissioning status:
S4 S3 S2 S1
Nac
elle
Hu
b/N
ose
Bla
des
PMT
Lift
DTA
Bas
e
S4 S3 S2 S1
Nac
elle
Ro
tor
IIP
Ener
gize
d
CC
CSt
art
Rel
iab
ility
Ru
n
N/A 1 1 1 2 1 1 1 1 1 N/A 1 1
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
N/A N/A
0 1 1 1 2 1 0 1 1 1 1 0 1 1 0 0 0 0 0
![Page 5: DCR 20140721](https://reader031.vdocuments.us/reader031/viewer/2022020519/577cc6841a28aba7119e76e5/html5/thumbnails/5.jpg)
2.0 Installation and Commissioning status:
2.2 WTG commissioning status:
CC
CSt
art
Rel
iab
ility
Ru
nR
elia
bili
ty R
un
co
mp
lete
dH
and
ed o
ver
to s
ervi
ce
0 0