  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    1/14

    Thursday, February 5, 2015

    Coordinated by:

    Briefing on:

    DC CLEAN RIVERS PROJECT

    First Street Tunnel

    Chairperson James A. Turner

    District of Columbia Water and Sewer AuthorityGeorge S. Hawkins, General Manager

    Briefing for the:

    Residents of

    Presented by:

    John Kennedy and Tom Lindberg, DC Clean Rivers Project

    Emanuel Briggs, DC Water

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    2/14

    Agenda

    Separate and combined sewer systems explained

    Why Combined Sewer Overflows (CSOs) are a concern

    Long Term Control Plan (DC Clean Rivers Project)

    13-mile tunnel system and structures Northeast Boundary Tunnel facts, figures, and alignment

    First Street Tunnel facts and figures

    Status of construction

    Truck routes Tunnel Boring Machine delivery schedule

    Contact information and Questions & Answers

    2

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    3/14

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    4/14

    Combined Sewer Overflows (CSOs)

    Combined sewer overflows contaminatereceiving waters

    Primary concerns:

    Elevated bacteria levels

    Low dissolved oxygen in water Potential for fish stress or fish deaths

    Negative effects on other aquatic life

    Aesthetics: contributes to trash inwaterways

    Limit fishable conditions

    Contribute nutrients and sediments thatnegatively affect the Chesapeake Bay

    CSO 017 to Anacostia River (during Hurricane Floyd)

    CSO 017 during dry weather conditions

    4

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    5/14

    DC Clean Rivers Project(DC Waters Long Term Control Plan)

    To comply with the U.S. Environmental Protection Agencys (EPA)

    Combined Sewer Overflow (CSO) Control Policy, DC Water is

    implementing a schedule

    for numerous projects

    to control combinedsewer overflows into:

    Anacostia River

    Potomac River

    Rock Creek

    2002

    DC Water completed a Long Term Control

    Plan (LTCP)

    2005

    DC Water entered into a consent decree

    agreement with EPA and DC government

    2011 DC Clean Rivers Project Execution

    2025

    Projected DC Clean Rivers ProjectCompletion

    5

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    6/14

    Tunnel System

    AnacostiaRiver

    Potomac

    River

    DC WaterBlue PlainsAWWTP

    U.S.CapitolBuilding

    NE BoundaryTunnel & area

    projectsAug 2016

    Sept 2025

    NE BoundaryTunnel & area

    projectsAug 2016

    Sept 2025

    First StreetTunnel

    Oct 2013 Mar 2016

    First StreetTunnel

    Oct 2013 Mar 2016

    Mine four large storage/conveyancetunnels, totaling 13 miles

    Construct a tunnel dewatering pumpingstation at Blue Plains

    Replace pumping station at Poplar Point

    Construct M Street Diversion Sewer

    Build two tunnel overflow structures

    Project schedule:

    Tunnels south of Robert F. Kennedy (RFK)

    Stadiumoperational by 2018 Northeast Boundary Tunneloperational by 2022

    Anacostia River water quality will be

    greatly enhanced by reducing CSOs

    from 82 to 2 events per year by

    capturing 98% of CSOs

    N

    RFKStadium

    Joint BaseAnacostia-Bolling

    Blue PlainsTunnel

    Sept 2011 Nov 2015

    Blue PlainsTunnel

    Sept 2011 Nov 2015

    AnacostiaRiver Tunnel

    Nov 2013 Aug 2017

    AnacostiaRiver Tunnel

    Nov 2013 Aug 2017

    M StreetDiversion Sewer

    May 2012Dec 2014

    Poplar PointPumping Station

    Dec 2014 Mar 2017

    6

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    7/14

    Northeast Boundary TunnelAt a Glance

    Major component of DC Waters DC Clean Rivers Project, required under

    a Federal Consent Decree

    Increase the capacity of the existing sewer system in the District,

    significantly mitigating sewer flooding and improving the water quality of

    the Anacostia River

    Approximately 27,000 feet long, 23 feet in diameter, and between 80 to

    160 feet below ground

    Diversion facilities will be constructed near chronic flood areas along the

    tunnel alignment to relieve the existing sewer system

    Ventilation control facilities will also be constructed

    Captured flows will be delivered to Blue Plains for treatment prior to

    discharge to the Potomac River

    7

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    8/14

    Northeast Boundary Tunnel Alignmentand Chronic Flood Areas

    8

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    9/14

    9

    First Street TunnelAt a Glance

    Constructed to mitigate sewerflooding and basement backups inBloomingdale and LeDroit Park

    Provides 8 million gallons of storage

    2,700 feet long, with four shafts Mined from Channing Street NW to

    Rhode Island Avenue NW using aTunnel Boring Machine (TBM)

    70 to 120 feet below the ground

    23-foot inner diameter tunnel Five Construction Staging Areas

    Temporary below-ground pumpingstation

    9

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    10/14

    TBM Mobilizationand Assembly

    TBM parts havestarted to arriveon site

    CS-MS Base Slaband Permanent Liner

    Poured base slab

    Poured permanentliner lift 1

    First Street Diversion Chamber

    Drilled secant and soldier piles

    V StreetDropShaft and AditFreeze System

    Completedinstallation of pipes

    Started freeze formation at drop shaft

    Pump StationDrop Shaft and Adit

    Completedinstallation of pipes

    Started freeze for-mation at drop shaft

    Drill and installfreeze pipe at adit

    Poured drop shaftcollar

    Adams Street

    Drop Shaft Drill and install

    freeze pipesunderway

    Adams Street

    A/FST Connection Drill and install

    freeze pipesunderway

    First Street Tunnel isApproximately 37 Percent Complete

    10

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    11/14

    Delivery ofTunnel Boring Machine Sections

    The First Street Project Tunnel Boring Machine(TBM) was recently refurbished in Germany

    The TBM is being delivered in sections to theChanning Street Construction Staging Area over

    the next two weeks

    Delivery will temporarily restrict access to theMcMillan Reservoir entrance on First Street

    There will be a few days when certain sections

    will require offloading using a large crane

    On days of offloading, the crane will be inFirst Street travel lanes

    TBM assembled in Germany

    TBM being prepared for assembly

    at the Channing StreetConstruction Staging Area

    11

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    12/14

    The TBM will be delivered insections to the Channing Street

    Construction Staging Area using

    Irving Street, Michigan Avenue,

    and North Capitol Street

    Oversized loads will have policedetail

    No additional street closings will

    be required

    No additional on-street parking

    will be affected

    N

    Channing St

    CSA

    FirstStNW

    Truck Routes

    Legend

    Truck traffic leaving site

    In-bound truck traffic

    Channing Street CSA

    Flagger as needed12

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    13/14

    Tunnel Boring MachineDelivery Schedule

    The first of the deliveries began onWednesday, January 28

    The second delivery arrived on Monday,

    February 2

    The next delivery is tentatively scheduledfor Thursday, February 5

    Final delivery of TBM equipment will be

    during the week of February 9

    The First Street Tunnel project will becompleted in the Spring of 2016

    Thank you for your patienceand understanding

    13

    TBM midshield bottom section

  • 8/9/2019 DC Water DivP_Tunnel_Forum_Pres_ANC 1B-FINAL 2015 02 05

    14/14

    Contacts

    Tom LindbergPublic Outreach ManagerFirst Street TunnelDCCleanRiversProject,DCWater

    Email: [email protected]: 202-787-4478

    Emanuel BriggsManager, Community Outreach

    External Affairs, DC WaterEmail: [email protected]: 202-787-2003