day 1 item n 4-3--presentation--inspectability of piping

16
9/23/14 1 Review of Piping Inspec0on Programs at the VMT Your Integrity Management Partner From wellhead to burner 6p, Dynamic Risk’s integrity management solu6ons provide you the informa6on to make effec6ve decisions for your en6re asset base. Sept 25, 2014 Confiden6al / Dynamic Risk Project Team Work Product Project Drivers APSC assessments iden6fied areas of interest (TAPS 2012 Annual Report Pipeline and VMT Facili:es Corrosion Monitoring) Includes 36inch relief piping (included in PHMSA Consent Agreement) Framing Session Highlights Perform Risk Assessment Pursue pigging alterna6ve 36inch relief line plus 48inch A and B header inspec6on is ini6al priority Recommended strategy for design development Modify piping to enable inspectability, including ILI tools Alyeska’s Project Z716* VMT Below Ground Crude Oil Piping Summary * This slide is adapted from Alyeska’s presenta6on to Dynamic Risk May 7, 2014.

Upload: others

Post on 09-Apr-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

9/23/14  

1  

Review  of  Piping  Inspec0on  Programs  at  the  VMT  

Your  Integrity  Management  Partner From  wellhead  to  burner  6p,  Dynamic  Risk’s  integrity  management  solu6ons  provide  you  the  informa6on  to  make  effec6ve  decisions  for  your  en6re  asset  base.  

Sept 25, 2014

Confiden6al  /  Dynamic  Risk  Project  Team  Work  Product  

•  Project  Drivers  –  APSC  assessments  iden6fied  areas  of  interest  (TAPS  2012  

Annual  Report  Pipeline  and  VMT  Facili:es  Corrosion  Monitoring)  –  Includes  36-­‐inch  relief  piping  (included  in  PHMSA  Consent  Agreement)    

•  Framing  Session  Highlights  –  Perform  Risk  Assessment  –  Pursue  pigging  alterna6ve  –  36-­‐inch  relief  line  plus  48-­‐inch  A  and  B  header  inspec6on  is  ini6al  priority  

•  Recommended  strategy  for  design  development  – Modify  piping  to  enable  inspectability,  including  ILI  tools  

Alyeska’s  Project  Z716*    VMT  Below  Ground  Crude  Oil  Piping  Summary  

*  This  slide  is  adapted  from  Alyeska’s  presenta6on  to  Dynamic  Risk  May  7,  2014.  

9/23/14  

2  

Table  1:  Current  Inspec6on  Ac6vi6es  at  the  VMT  Asset  Name     Ac0vity   Status   Dynamic  Risk  Commentary  

EMB  to  East  Tank  Farm  (ETF)(near  tanks  1  &  3)     Pipe  is  inspected  every  6me  it  is  exposed.  

Cathodic  protec6on  records/  coupon  measurements  not  available.  No  record  of  pipe  exposure  and  inspec6on.    

•  Detailed  review  of  historical  coupon  and  cathodic  protec6on  records  should  be  conducted.    

•  Planned  for  ILI-­‐  Specific  ILI  procedures  required.  

ETF  Headers  A  &  B   Annual  3-­‐hr  sta6c  head  pressure  test.  Pipe  is  inspected  every  6me  it  is  exposed.  

Cathodic  protec6on  records/  coupon  measurements  not  available.    No  record  of  pipe  exposure  and  inspec6on.  Pressure  test  records  not  

available.    

•  Detailed  review  of  historical  coupon  and  cathodic  protec6on  records  should  be  conducted.    

•  Planned  for  ILI-­‐  Specific  ILI  procedures  required.  

•  Pressure  tes6ng  being  performed  of  pipe  body  not  to  recognized  industry  prac6ce.    

ETF  to  West  Metering  Building  (WMB)  

Annual  3-­‐hr  sta6c  head  pressure  test.  Pipe  is  inspected  every  6me  it  is  exposed.  

Cathodic  protec6on  records/  coupon  measurements  not  available.  No  record  of  pipe  exposure  and  inspec6on.  Pressure  test  records  not  

available.    

•  Detailed  review  of  historical  coupon  and  cathodic  protec6on  records  should  be  conducted.    

•  Planned  for  ILI-­‐  Specific  ILI  procedures  required.  

•  Pressure  tes6ng  being  performed  of  pipe  not  to  recognized  industry  prac6ce.    

WMB  to  near  shore  line     Annual  3-­‐hr  sta6c  head  pressure  test.  Pipe  is  inspected  every  6me  it  is  exposed.  

Cathodic  protec6on  records/  coupon  measurements  not  available.    No  record  of  pipe  exposure  and  inspec6on.  Pressure  test  records  not  

available.    

•  Detailed  review  of  historical  coupon  and  cathodic  protec6on  records  should  be  conducted.    

•  Pressure  tes6ng  being  performed  of  pipe  not  to  recognized  industry  prac6ce.    

•  Addi6onal  supplementary  inspec6ons  between  all  girth  welds  should  be  considered.  

•  Should  be  considered  for  ILI  program  to  achieve  opera6ng  confidence.  

Over  water  piping  to  Berths  4  &  5  

Annual  3-­‐hr  sta6c  head  pressure  test.  By  the  end  of  2014,  100%  of  the  girth  welds  will  be  externally  inspected,  por6ons  of  insula6on  will  be  permanently  removed,  and  girth  welds  will  be  inspected  by  Visual,  UT,  EMAT  and/or  GWT  technologies.  

Pressure  test  records  not  available.  External  Inspec6on  

program  is  In  progress.  

•  Girth  weld  inspec6on  technology  is  appropriate  and  acceptable.  

•  Pressure  tes6ng  being  performed  of  pipe  is  not  to  recognized  industry  prac6ce.    

•  Addi6onal  supplementary  inspec6ons  between  all  girth  welds  should  be  considered.  

•  Should  be  considered  for  ILI  program  to  achieve  opera6ng  confidence.    

VMT  Assets  Proposed  for  ILI  

9/23/14  

3  

 Alyeska  Pipeline  Project  

Management  Process  

Identify(FEL 0)

Approve?

STOP

Appraise(FEL 1)

Approve?

Develop(FEL 2)

Approve?

Appraise(FEL 3)

Approve?

Execute

Close

FEL: Front End Loading is a formalized process to develop communicate and reach stakeholder alignment for a definitive project scope to improve the efficiency and reliability of project delivery.

START: Year 0

Year 1

END: Year 2

GATE: An approval process after each FEL step to reduce the number of changes in later project stages.

STOP: Each gate in the process allows for the project to be cancelled or shelved. N

O

NO

NO

NO

Review

Review

Review

Review

2 Years: The Project Management Process is implemented in 2 year cycles

Alyeska Pipeline Project Management Process

IFR: Issue for ReviewIFC: Issue for Construction

Table  2:  Drai  Plan  of  Inspec6on  Ac6vi6es  at  the  VMT  

 

                                                                                                           

*  Pressure  testing  to  49CFR195.Subpart  E    

Asset  Name  

Relief  Piping  (36”)  

Process  Piping  (24”)  

Process  Piping  (48”)  

 Notes  

 Schedule  Estimate*   Dynamic  Risk  Commentary  

East  Metering  Bldg  (EMB)   455’   425’     Abandon  below  ground    piping  

Install  above  ground  piping     FEL  1:    9/2013  FEL  2:    12/2014  FEL  3:    7/2015  IFR:    11/2015  IFC:    12/2015  

Implementation:  4/2015-­‐10/2017  

 

• Review  procedures  for  piping  abandonment-­‐  ensure  compliance  with  best  industry  practice  and  evaluate  for  long  term  issues.  

• Review  procedures  for  ILI.  

EMB  to  East  Tank  Farm  (ETF)(near  tanks  1  &  3)    

1,100’     2  x  1,100’  Install  (3)  pig  launchers  Modify  (2)  valves  Install  (1)  36”  pig  receiver  

East  Tank  Farm    Headers  A  &  B       2  x  2,135’    

ETF  to  West  Metering  Building  

(WMB)       2  x  2,900’     Install  (2)  pig  receivers  

WMB  to  near  shore  line         ~1,300’  

~1,000’     (information  not  available  to  Dynamic  Risk)  

• Review  pressure  test  procedure.  Consider  conducting  hydrostatic  test  program  to  industry  standards*.      

• Review  configuration  of  piping  for  ILI  of  this  segment.  

Over  water  piping  to  Berths  4  &  5  (girth  welds  and  

saddles)  

    1,000’  1,500’  

100%  girth  weld  inspection,  annual  spot  inspections,    annual  3-­‐hour  leak  test  at  service  pressure,  EMAT,  GWT  and/or  UT**  

Expect  completion  end  of  2014  

• Review  pressure  test  procedure.  Consider  conducting  hydrostatic  test  program  to  industry  standards.      

• Review  girth  weld  inspection  results.  

• Ensure  inspection  activities  account  for  technology  limitations.  

• Review  piping  configuration  for  ILI/  internal  inspection  program  acceptability.  

9/23/14  

4  

Table      3:  In-­‐Line  Inspec6on  Program    at  the  VMT  

    Ac0vity  Program  

Development  Status  

Implementa0on  

Status  Dynamic  Risk  Commentary  

East  Metering  Bldg  to  East  Tank  Farm  

(ETF)  (near  tanks  1  &  3)  

Install  above  ground  36”  piping  to  replace  36”  below  ground  piping.  36”  relief  header  and  (2)  48”  headers  are  planned  for  ILI  

Engineering  Design  

Pipe  replacement  in  

progress.      

•  Ini6al  approach  is  acceptable;  Plan  needs  to  account  for  piping  configura6on,  flow  veloci6es  and  valida6on  of  results.  

•  Consider  supplementary  inspec6ons  during  interim  period  leading  up  to  ILI  program.    

ETF  Headers  A  &  B   (2)  48”  headers  planned  for  ILI   Engineering  Design  

   ETF  to  West  Metering  Building  

(WMB)  (2)  48”  headers  planned  for  ILI   Engineering  

Design  

1)  In-­‐Line  Inspec6on  

A  cleaning  pig  

These  cleaning  and  inspec6on  tools  are  propelled  within  the  pipeline  by  the  product  stream    

An  MFL  pig  

9/23/14  

5  

Replace  Valves  and  “T”  

Expansion  Loop  Downstream  of  East  Metering  Building  

•  Loca6on  of  exis6ng  48-­‐inch  spool  pieces  between  flanges  –  convert-­‐able  to  a  launch  site  

Looking  west   Looking  east  

9/23/14  

6  

Spool  Piece  Concept  

•  Hot  tap  reroute  for  pipe  removal  •  Valves  for  reroute,  stopple  isola6on  •  Pup  removed  as  a  spool  piece  

Stopples  •  Hot  tap  and  valve  isola6on  – Add  flange  and  cut  through  pipe    – Mechanical  flow  blockage  

9/23/14  

7  

Typical  Pipeline  Valves  

•  Welded  Valve  in  Construc6on    

Cut  Away  Image  

Valve  with  Manual  Operator  

Table  4:  VMT  Assets  Not  Included  in  the  Proposed  ILI  Program  

 Asset  Name   Ac6vity   Status  

Dynamic  Risk  Commentary  

West  Metering  Bldg  to  Berths  4  

&  5  Considered  a  possible  candidate  for  an  ILI.  Modifica6ons   to   piping   required.     (Discussion  only)  

Unknown      

Over  water  piping  to  Berths  4  

&  5  

By  the  end  of  2014,  100%  of  the  over-­‐water  girth  welds   will   be   externally   inspected,   por6ons   of  insula6on  will  be  permanently  removed,  and  girth  welds  will  be  inspected  by  Visual,  UT,  EMAT  and/or  GWT  technologies.  Considered   a   possible   candidate   for   an   internal  crawler  inspec6on  tool.    (Discussion  only)  

In  progress  

•  Review  external  piping  inspec6on  findings  rela6ve  to  GWT,  EMAT  and  UT  limita6ons.        

   

9/23/14  

8  

VMT  ILI  Program  Considera6ons  

•  Excessive  tool  velocity  increases  the  uncertainty    in  sizing  depth  and  length  of  anomaly    – Pump  sta6ons  and  valves  on  TAPS  mainline  are  u6lized  to  control  ILI  tool  velocity    

– VMT  has  no  pumps,  just  gravity  and  valves  to  control  ILI  tool  velocity    

– VMT  has  steep  eleva6on  changes  and  short  ILI  segments  

An6cipated  Loca6on  of  Pig  Receiver  by  WMB  

9/23/14  

9  

Table  5  :  Reference  Anomalies  

Reference  Anomaly  (length  by  width)  as  a  

func0on  of  wall  thickness  (t)  

Detec0on  Threshold  

Probability  of  Detec0on  (POD)  

Qualifiers  and  Limita0ons  

5t  by  5t   10%   90%   Extended  metal  loss  Length  and  width  >  3t  

2t  by  2t   15%   90%  Pits    

t  <  Length  and  width  <  3t  

5t  by  1t   35%   90%   Axial  Grooves  Width  <  t,  length  >  3t  

Table  5  was  taken  from  API  1163  

2)  Internal  Inspec6on  •  Access  Needed  –  hot  tap  required  or  other  entry  

–  One  Point  Launcher  /  Receiver  –  must  be  reversible    –  Pipe  must  be  open  to  air  –  stops  product  flow  

•  Mo6ve  Power    -­‐  Tool  not  driven  by  product  flow  •  Internal  robo6c    tools  provide  baqery  power  plus  tractor  •  Tethered  tools  (cable/  umbilical  /  extension  cord),  pulled  or  tractor    

for  mo6on  •  Naviga6on      

–  Reduced  diameters  (valves),  6ght  bends,  dead  legs    –  Reverse  direc6on,  enter  “T”s  and  dead  legs    

•  Communica6ons    by  tether,  wire,  fiber  op6c,  or  radio  link  (WiFi)  •  Real  6me  evalua6on  by  operator  not  later    

9/23/14  

10  

Preparing  Access  to  Pipe  over  the  Water  

3)  External  Inspec6on  

•  Corrosion  coupons  used  to  monitor  internal  corrosion  suscep6bility  –  Coupon  weight  loss  indicates  internal  

corrosion,  can  be  used  to  es6mate  corrosion  rate  

•  Ultrasonic  tes6ng  to  measure  wall  thickness  (external  and  internal  corrosion)  

 

9/23/14  

11  

Findings    

 1.  Documenta6on  provided  to  date  for  review  by  the  Dynamic  Risk  

project   team  has  not  been  of  sufficient  detail   to  conduct  a   full  and   complete   industry   standard   or   “best   industry   prac6ce”  procedure  review  and  comparison.  

2.  The  VMT  has  been  in  opera6on  since  1977,  and  the  majority  of  the   crude   oil   transport   lines   have   not   been   fully   assessed   for  external   or   internal   corrosion.   This   dura6on   of   6me   exceeds  accepted  industry  6melines  for  pipe  inspec6ons  as  required  for  effec6ve   assessment   of   industry   recognized   pipeline   threats,  i.e.,  external  and  internal  corrosion.  

 

Findings    3.    An  ILI  program  at  the  VMT  is  being  developed  for  the  36-­‐inch  

and  48-­‐inch  piping  from  the  East  Metering  Building  to  the  West  Metering  Building.    

 4.  The  48-­‐inch  piping  downstream  of  the  West  Metering  Building  

to  Berths  4  and  5  is  not  included  in  the  proposed  ILI  program  at  the  VMT  and  limited  informa6on  rela6ng  to  confirmed  inspec6on  plans  and  approaches  for  this  segment  was  provided  for  review.      

 

   

9/23/14  

12  

Findings  5.      The  following  elements  of  the  proposed  VMT  ILI  program  are  

being  addressed  in  a  manner  consistent  with  recognized  industry  prac6ce,  as  defined  within  the  industry  standards  referenced  within  this  report:  technology  selec6on,  vendor  selec6on,  procedure  for  valida6ng  results,  repor6ng.  

 6.  The  ILI  integrity  assessment  program  at  the  VMT,  if  executed  as  

described  for  those  pipe  segments  being  considered,  will  accommodate  periodic  maintenance  and  inspec6on  needs  and  will  improve  the  iden6fica6on  of  corrosion  threats  for  purposes  of  assessment  and  mi6ga6on.  

Findings  7.  The  current  corrosion  assessment  ac6vi6es  for  non-­‐ILI  pipe  

segments,  inclusive  of  pressure  tes6ng,  EMAT,  GWT  and  UT,  are  all  acceptable  inspec6on  technologies  for  evalua6on  of  pipeline  corrosion  in  applica6on  with  industry  standards  and  subject  to  each  technology’s  restric6ons  for  detec6on  and/or  assessment  of  corrosion-­‐caused  metal  loss.  However,  these  ac6vi6es  are  acceptable  only  if  performed  in  a  standard  integrity  assessment  methodology  using  appropriate  combina6ons  and  subject  to  procedures  that  account  for  technology  applica6on  and  accuracy  tolerance  limita6ons.      

 

9/23/14  

13  

Findings  8.        The  planned  external  inspec6ons  of  over  water  girth  welds  

on  Berths  4  and  5  with  UT,  EMAT,  and/or  GWT  will  appropriately  address  the  corrosion  threats  documented  on  these  piping  segments.    

 9.  The  annual  sta6c  head  pressure  test  (per  33CFR156.70)  of  

the  piping  from  the  East  Tank  Farm  to  the  ends  of  Berths  4  &  5  is  not  in  alignment  with  accepted  industry  standards  for  pipeline  pressure  tes6ng,  rela6ve  to  pressure,  monitoring,  and  test  dura6on.  Considera6on  should  be  given  to  the  undertaking  of  addi6onal  assessment  measures  (49  CFR  195  Subpart  E).    

Recommenda6ons  -­‐  VMT  Inspec6on  Program  

•  Consider  49  CFR  Part  195  regula6ons  along  with  industry  standards  as  incorporated  by  reference,  as  guidance  when  developing  the  inspec6on  program  for  the  VMT  piping.    

 •  In  order  to  provide  increased  opera6ng  confidence,  

undertake  piping  configura6on  modifica6ons  necessary  to  perform  an  ILI  of  the  pipe  segments  downstream  of  the  West  Metering  Building  and/or  to  perform  a  hydrosta6c  test  program  to  pressures  that  will  exceed  normal  opera6ng  pressure,  as  per  guidelines  based  upon  49  CFR  Part  195  requirements.        

 

9/23/14  

14  

Recommenda6ons  -­‐  VMT  Inspec6on  Program  

•  Determine  piping  system  ILI  and  supplementary  inspec6on  periodicity  requirements  through  assessment  of  ILI  and  other  inspec6on  results  that  can  be  combined  with  predicted  corrosion  growth  rate  calcula6ons.  Periodicity  requirements,  as  developed  should  be  applied  within  future  inspec6on  program  planning.  

 •  Review  2014  inspec6on  results  of  girth  welds  over  water  to  

determine  if  girth  weld  integrity  is  an  issue  that  needs  to  be  addressed  within  the  VMT  facility  inspec6on  planning.  Ensure  that  piping  over  water  (or  other  piping)  inspec6on  ac6vity  (EMAT,  GWT  and/or  UT)  procedures  and  repor6ng  account  for  personnel  qualifica6ons  and  technology  limita6ons.  

 

Recommenda6ons  -­‐  VMT  Inspec6on  Program  •  API  1163  and  Alyeska  TAPS  experience  can  be  applied  as  

guidelines  when  developing  ILI  procedures  for  the  VMT;  however,  challenges  specific  to  the  VMT  (short  distances,  extreme  eleva6on  changes  and  absence  of  pumps  to  control  tool  speed)  will  challenge  the  ability  to  keep  the  ILI  tool  within  a  required  velocity  threshold  and  will  need  to  be  addressed.    Development  of  a  VMT-­‐specific  ILI  prac6ce  document  is  required  of  Alyeska,  who  should  communicate  the  development  of  this  document.    

9/23/14  

15  

Recommenda6ons  -­‐  VMT  Inspec6on  Program  •  Inves6gate  methods  and  technology  for  applica6on  of  

supplementary  inspec6ons  on  pipe  segments  designated  for  inclusion  within  the  proposed  ILI  program.  Results  can  provide  con6nued  opera6ng  confidence  during  the  interim  6me  period  leading  up  to  ini6a6on  of  the  ILI  program  and  receipt  of  final  repor6ng,  which  may  take  up  to  6  months  following  comple6on  of  the  pipe  segment  inspec6on.  

 •  Review  the  facility  specific  risk  and  integrity  assessment  

methodologies  outlined  in  API  1160,  and  supported  by  CEPA  recommended  prac6ce  for  Facili6es  Integrity  Management  when  next  upda6ng  the  MP-­‐166  series  of  integrity  documents  to  include  ILI  as  a  new  integrity  assessment  methodology.    

Recommenda6ons  -­‐  VMT  Inspec6on  Program  Monitoring  

 •  Con6nue  to  monitor  the  VMT  ILI  integrity  assessment  program  and  prac6ce  developments  with  specific  focus  on  the  ILI  vendor  selec6on  process,  applied  ILI  technologies,  ILI  data  valida6on  procedures  and  the  corrosion  assessment  and  repor6ng  process.    

9/23/14  

16  

Ques6ons  –  Original  Construc6on  Overview