datp process

Upload: warya-rawigunan

Post on 02-Jun-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 Datp Process

    1/8

    External Corrosion Direct Assessment Summary

    ECDA is a four-step process. Each step is mandatory for an effective ECDA program. ECD

    requires integration of information:

    1) Pre-assessment - combining a pipelines physical characteristics, operating history a

    prior inspections;

    2) Indirect inspection - conducting complementary above the ground eld voltage & curre

    examinations);3) Direct examination - exposing pipe for surface measurements including remaining w

    thickness and

    4) Post-assessment integrating all as a comprehensive integrity assessment includi

    validating the process and the estimating the time interval until the next integrity evaluati

    is required.

    The ECDA Standard - NACE RP 0502

    The NACE ECDA Standard is intended to address external corrosion for onshore ferro

    pipe. ECDA is a continuous improvement process. Through successive ECDA application

    a pipeline operator will identify and address locations where corrosion activity has occurre

    is occurring, or may occur. As such, ECDA provides an advantage over alternative integr

    assessment methodologies such as in line inspection (ILI) and pressure testing by locati

  • 8/10/2019 Datp Process

    2/8

  • 8/10/2019 Datp Process

    3/8

    Pre-assessment:

    Pre-assessment requires the integration of historical, construction, operations and maintenance

    records. This can be a simply meeting of company experts, using paper records pulled from

    different departmental ling cabinets. Eventually the integration of electronic records from

    these diverse departments can be used with rules devised by the experts (i.e. the integrity or

    with consequences, risk assessment modeling) to presort the huge amounts of information

    and present the summaries on a simple map. Maps have been found useful to bring together

    abstract integrity evaluations as a magnitude at a location. Once the volumes of data have been

    organized then decisions can be made. These decisions are the beginning of any integrity or

    risk management program.

    The typical records which are available in various departments should be: purchasing and

    construction les, up to date alignment sheets, operating history, foreign crossing history, thirdparty adjacent construction and one call notices, land use and typical vegetation descriptions,

    topography and elevation diagrams, leak and rupture locations and reports, maintenance

    history with forensic reasons for the pipe replacements and other repairs, current and prior

    above ground inspection reports, previous ILI reports, coating condition and other observations

    of electrolytes and soils in excavation reports, corrosion survey reports for test lead, CIS, DCVG

    or other above ground inspections, and there could be more. Data integration is neither trivial

    nor inexpensive.

    The minimum set of data to be collected is organized into ve sets of elements; pipe related,

    construction related, soils and environment related, corrosion protection, and pipeline operations

    considerations. These ve are further subdivided into individual data items as detailed in the

    NACE standard. Each element has been provided with comments which help the operator

    judge how each element may impact the tool(s) selection, the denition of the ECDA region(s),

    and the interpretation of the above ground inspections to determine the integrity of the pipe line.

    The NACE standard requires more data than in the prescriptive requirements of B31.8S.

  • 8/10/2019 Datp Process

    4/8

    Denitions are provided to reduce the uncertainty especially when current jargon has one

    department collecting the same observation but with a different label and unfortunately a different

    set of units. Consistency in collecting data over the years is essential. As a hint databases can

    be designed to have the jargon on the screen but use the standard denitions and units in the

    background for each of the elds. The data is needed to correlate the voltage/current readings

    with the observed wall loss in those sites excavated. The operator needs to prove that the

    integrity assessment algorithms and assumption can link similar sites with similar soils, pipe

    and coating materials, and therefore similar patterns in voltage/current readings will suggest the

    similar distributions and depths of corrosion pits and general wall loss.

    The outcome from Pre-assessment provides the operator with three essential conclusions:

    1. ECDA is a viable process to measure integrity2. Two complimentary tools chosen to inspect the corrosion protection performance

    3. The start and nish locations of each ECDA region.

    The NACE Standard provides guidance for the selection of appropriate complementary above

    ground inspection techniques. Not all the locations along the pipeline are suitable for ECDA

    inspections. A convenient concept used to select the appropriate inspection technology from

    a list of possibilities is to complete the current path. The wire from the multimeter to the pipe

    is the easy trace, but the path back starts across the coating or damage, travels through the

    soil to the ground bed and back up the wire lead. This return path can sometimes become

    interrupted. Rock backll, paved roads, lack of soil moisture (high resistivity), coating shielding

    liquid pockets, and other local situations can interrupt this return path and make the inspection

    invalid. With greater experience the ECDA Tool Selection Matrix will be able to give probability

    of detection and the probability of identication (POD & POI), the chance of nding and the

    chance of detecting severe corrosion rather than a yes /no indication.

    The region is dened by two complementary tools and although the complete; start to nish,

    distance from A to D maybe suitable for ECDA a short section may have to use an alternate

    inspection tool say to measure what is happening under a paved parking lot were an

    electromagnetic approach is more convenient. This suggest there now will be segments A to B

    for the rst two tools selected, B to C under the pavement with different inspection techniques

    and C to D for the rst set of tools again.

  • 8/10/2019 Datp Process

    5/8

    Direct Examination:

    The object of the direct examination step is to dig at least those indications wh

    most severe. Excavations are also needed to collect information that will help pred

    corrosion rates. The following activities are to be completed in this the third ECDA s

    1. Categorization of indications found in step two into minor, moderate, severe

    severe; the latter two classications are to be are immediately excavated;

    2. Excavation and data collection is done in areas were corrosion activity is mos

    operator must have procedures for what data is to be collected before durin

    excavation.

    3. Measurement of the coating damage and corrosion defects underneath. T

    is to extend the bell hole either way until no severe coating damage or nocorrosion is found for at least ve feet.

    4. Evaluations of the remaining strength of the defects can be done using th

    cluster length and maximum depth, and the methodology of B31G, RST

    similar engineering analyses such as API RP 579,

    5. Root cause analysis will help determine the appropriate mitigation activit

    future corrosion is mitigated.

    6. In-Process evaluation is an interim check on the assumptions. If smaller tha

    defects are found then the criteria for severe, moderate or minor can be

    worse then the operator needs to perform additional excavations or ree

    appropriateness of using ECDA for the integrity evaluation. A small sample si

    leads to erroneous assumptions.

    Essentially a prudent operator follows a well proven procedure. The pipe is excavat

    normal safety rules, the coating and ditch inspected, while samples of liquids and oth

    related deposits are taken as the coating is removed and the pipe cleaned to barecorrosion wall loss; the depth, axial and circumferential extent of the defect photog

    measured. Next operators should use some form of crack detection technology suc

    or MPI to inspect for cracks particularly if mechanical damage is suspect. All immed

    and most of the scheduled defects uncovered at each site will be repaired while the p

    exposed for examination. The corrosion defect geometry can be put into the

    calculation to provide the immediate or scheduled classication. The NACE RP 050

    provides additional guidance on classication and repair.

    In-process evaluation is an essential real time component of the analysis. The EC

    helps nd representative corrosion but might not nd all the corrosion defects in an EC

    If corrosion defects are found that exceed allowable limits then it should be assume

    similar defects might be in the same ECDA Region. These feed back loops are in

    quality processes as shown below.

    The most difcult determination is the number of bell holes an operator is required t

    If the above ground inspections nd locations were the criteria are not met the

    must occur. The operator should immediately excavate multiple severe indication

    moderate or severe indications in regions of moderate prior corrosion, and moderate

    in regions of prior severe corrosion. The remaining severe indications, the remainin

    indications in regions of moderate prior corrosion and minor indications in region

    prior corrosion need to be scheduled for later action. The in process evaluation and

    Indirect Inspection:

    The objective of the indirect inspection step is to estimate areas of active corrosion. Different

    survey crews probably conduct individual inspections in different years. Each set of results will

    need to be superimposed for comparison. It is important to maintain a meta data set or an

    estimate of quality for these survey results. The survey monuments for the alignment sheet, the

    air photography, the prior year inspections could all have location opinions that differ from the

    current survey crew. The CIS crew might use GPS with a +/- half a foot accuracy while the original

    alignment sheet survey could be +/- 60 feet. Eventually someone will have the responsibility to

    align these records onto the map prior to making integrity decisions. It is preferable to keep the

    accuracy always with the original record since this essential quality term allows the interpreter

    to control how far drawings can slide around over each other on the light table to see if theinspections or other ECDA indications fall roughly on top of each other. The meta data wrapper is

    needed for constructing error bars, these guide the analyst in determining how far the image can

    be safely manipulated. Today this electronic manipulation will probably occur in a information

    system software package which is designed for geographical measurements and allows rubber

    banding of known reference locations such as that provided by Baseline Technologies.

    Once the indications from the above ground inspections are aligned with the Pre-assessment

    and historical knowledge, the excavation sites can be located and prioritized for the examination

    step. These would be classied as severe; those with the highest likelihood of corrosion activity,

    moderate; possible or questionable corrosion activity, or minor; lowest likelihood of corrosion

    activity. NACE provides a table to guide operators when deciding how to place locations in

    the severity classication. The two inspections should provide consistent results both between

    inspections and with the Pre-assessment hypotheses.

    Discrepancies need to be resolved to see if the ECDA Regions were correctly chosen.Examinations of the severe category can begin while the discrepancies are still being

    investigated. This clarication of the discrepancies may require reevaluating the ECDA Region

    and possibly conducting a third complementary inspection.

  • 8/10/2019 Datp Process

    6/8

    analysis will help the operator decide to excavate and recoat or x the impressed CP system. A

    larger number of excavations can be expected if severe indications are indicated.

    If the inspections return no indications or moderate indications then at least two excavations are

    required at likely sites of corrosion for the rst application of ECDA. If the root cause investigation

    or in process evaluation steps at these two sites suggest the assumptions require modication,

    then the operator must conduct more excavations. If severe corrosion is found then the operator

    must return to the Pre-assessment step and consider if ECDA is appropriate, are the inspection

    techniques correct, and are there new start and nish points for the ECDA Regions?

    Post-Assessment:

    This stage prioritizes the mitigation and repair schedule, validates the process, and determines

    the period of time until the next integrity evaluation for each of the ECDA Regions. Priority and

    time require all the information gathered in the previous three steps. The standard assumes that

    all of the immediate defects will have all been addressed (CP xed, coating repaired or pipe cut

    out) and the scheduled defects prioritized so the worst will be xed rst during the interval until

    the next integrity evaluation. Any of the moderate and probably most of the minor indications

    will be expected to have been mitigated by either upgrading the cathodic protection system or

    excavating to evaluated the corrosion then recoating before burial.

    The distribution of defects remaining in the system will be a correlation of the Pre-assessment,

    Inspection and Excavation data to determine the classication by inspection categories; versus

    the number and size of the corrosion defects found in the associated bell holes. It is assumed

    that the severe indications will have a corrosion distribution skewed towards greater coating

    problems, and maybe wall loss, while the minor indications are locations of limited coating

    damage with little or insignicant wall loss. The largest defect in these distributions of defect

    size with the remaining moderate, and minor indications (the severe having been mitigated) andthe corresponding corrosion rate for each indication can be used in the performance regulations

    to predict the length of time until the defect could corrode sufciently to leak. The data to support

    both the estimate the size of the largest remaining defect and the corresponding corrosion rate

    may not be available early in the program.

    The prescriptive calculation for period between integrity evaluations is based on a conservative

    half life estimate in the ECDA standard. Essentially the remaining half life of a ECDA Region is

    determined by the size of the thinnest defect not repaired or replaced. The half life is determined

    by dividing the remaining wall thickness by the corrosion rate and multiplying the answer by

    0.43, a conservative constant.

    Once the direct examinations are initiated, expected correlations will be conrmed. When this

    information is correlated with soil analysis and other pre-assessment data, additional digs may

    still be required. The ndings during direct examination will improve the correlation between

    the CIS and DCGV voltage signals and the coating and pipe condition (general or pitting wall

    loss). The correlation would determine the further extent of additional excavations. Using soilmoistures and other analyses when combined with other pre-assessment data, may allow

    corrosion rates to be calculated. An estimate of the distribution of the defect sizes remaining

    behind after mitigation and the corrosion rate at each site will set the re-inspection intervals

    determined in step four, Post-assessment.

  • 8/10/2019 Datp Process

    7/8

  • 8/10/2019 Datp Process

    8/8

    Performance Measurement:

    Performance or ECDA Effectiveness of the immediate activity is obtained by digging two bell

    holes at selected locations. One location was to be categorized as scheduled (monitored if

    no Scheduled exist) and one were there will be no inspection indications found. If defects are

    found that are larger than expected and they would result in shorter intervals between integrity

    evaluations then the whole ECDA process shall be re-evaluated or repeated or an alternative

    integrity method such as ILI or hydro testing used.

    Long-term improvement in ECDA performance can be tracked from a decreasing number of

    excavations, the increase in total number of miles of pipe inspected, and/or the increase in

    inspection mileage by each of the tools employed. There are a variety of suggestions to show the

    integrity of the pipeline is improving. Monitoring change is the heart of continuous improvement.The ECDA process requires annual re evaluation and management of change. Assumptions

    are continually evaluated and discrepancies force review of these assumptions. The ow chart

    requires annual updating and reevaluation of the decisions made in prior iterations.

    The collection of interrelated records and data needs to be organized for internal and external

    auditing as well as to ensure continuous improvement. The historical data once veried remains

    stable but the new decisions made, the current integrity inspections and excavations and post

    assessment decisions need to be recorded in a consistent fashion. Section 7 of the NACE

    ECDA Standard provides guidance and each operator is encouraged to document their records

    in a clear concise, workable method that are pertinent to the four ECDA steps; pre-assessment,

    inspection, examination, and post-assessment.