data taking and r elated works for r scan above 3.8 gev
DESCRIPTION
Data Taking and R elated Works for R Scan above 3.8 GeV. Guangshun Huang University of Science and Technology of China. Group Meeting. R Scan Strategy ( B ig P icture). Charm baryons. 6%. 3.5%. Y(2175)?. Babar. P hase I : pre-study, 7 days - PowerPoint PPT PresentationTRANSCRIPT
Data Taking and Related Works for R Scan above 3.8 GeV
Guangshun HuangUniversity of Science and Technology of China
Group Meeting
R scan 2
R Scan Strategy (Big Picture)
• Phase I: pre-study, 7 days Machine study at 2.0, 2.5 and 4.2(4.6) GeV, MC tuning, …• Phase II: scan continuum region, 100 days 15 points in 2.03.6 GeV, step 100 MeV, 100k+ hadrons<3 GeV.•Phase III: scan resonance region, 2 months 100 points in 3.84.6 GeV, 100k events, step 2, 5,10, 20 MeV. Single/separated beam for beam associated background study. (108 hadrons at 4040, 4160, 4415 for radiative decay search?)
6%
3.5%
Y(2175)?
Charm baryons
to extend?
Babar
R scan 3
Desired Energy Points in 3.854.6 GeV
• R measured by BESII (63)• R interpolated (42)
105 in total
R scan 4
Expected Instantaneous Luminosity and Data Taking Time for 100k Hadrons
L(Ebeam) E∝ beam-10 (Ebeam>1890 MeV)
R scan 5
Energy Points in 3.854.6 GeV (1)105-point fine scan, 100k events each point, assuming that L(Ebeam) E∝ beam
-10, Lmax = 0.65×1033 cm-2s-1 at 1.89 GeV
R scan 6
Energy Points in 3.854.6 GeV (2)105-point fine scan, 100k events each point, assuming that L(Ebeam) E∝ beam
-10, Lmax = 0.65×1033 cm-2s-1 at 1.89 GeV
60 days
11 hr*
10 hr*
* Scale recent 4260 and 4360 data taking
R scan 7
More Realistic: from XYZ data taking• From Weimin Song:
R scan 8
More Realistic: from XYZ data taking
1.035
0.78 pb-1/hr
R scan 9
More Realistic: from XYZ data taking• The plan: 105 energy points, 100k events integrated luminosity 4.9 8.4
pb-1 each point, average 6.6 pb-1, total 695 pb-1;• To simplify the experiment, 8 pb-1 will be taken at each energy (20% up
on average);• Assuming the same rate of data accumulation, we need 8/0.78 10.3 hrs
at each point, and total 8*105/0.78/24 45 days;• Assuming 1 hr beam tuning time at each point, we need 105 hrs 4.4 5
days;• J/, ’ fast scan for energy calibration, 6 times, 4 hrs each time, total 1 day;• Separated beam data taking, 2 points for 12 hrs, 1 point for 2 days, total 3
days;• Sum of above is 54 days. Remaining 6 days are reserved for trigger/BEMS
study, maintenance, unexpected events;• In practice, 1 point per 12-hr BEPCII shift, 105 points = 52.5 days, but to be
adjusted subject to actual situation.
R scan 10
Shift
• Weekly chiefs from USTC:– Wenbiao, Haiping, Guangshun.
• Record keeping:– One student per week, possibly with help from
other institutions.• Shifters:– All of us. Highest priority during data taking!
R scan 11
Energy Calibration• Fit of J/, ’ fast scan: Bingxin
R scan 12
Webpage
R scan 13
Progress Plot • Initially all points grey out;• Points become solid after data taking;• Current point blinking.
“地铁运行图”
R scan 14
Other Plots (illustrative only here)#
onlin
e ha
dron
s
Ecm or point
Lact
ual/L
plan
Ecm or point
Ecm or pointDate
R scan 15
Summary Tables (examples here)Overall:
Ecm(GeV)
Nhad (expected)
Lum. actual (plan)
(1/pb, online)
Testimated(hour)
Tactual(Tpure)(hour)
3.4 20000 1.6583(1.4935) 8.4+4 10(4.8)3.4 Separated beam 4 5.3(4.0)
2.8 50000 3.0993(3.0680) 28+8 37(17.5)
2.4 50000 2.3409(2.3329) 34+12 94(35.4)2.4 Separated beam 4 6.5(4.1)
2.23 35000 1.4657(1.5000) 42+12 45.6(27.9)
Each point:
R scan 16
Data Quality Check
• Preparation should start immediately: auto-mated scripts to generate plots;
• Similar to Liang Yan’s work for 2012 scan.
R scan 17
TOF Calibration
• Shengsen needs helper, ideally based at IHEP. Training should start soon.
R scan 18
Summary• We are going to take data soon;• Please pay full attention – get ready for it!
19
LundArlw tuning
Must introduce auto-tuning mechanism:• tuning with the Professor package;• tuning with Ronggang's grid method: list of
parameters; lot of MCs need to be generated in advance;
• to include known cross sections/branching fractions in MC, just let LundArlw handle unaccounted parts?
20
BaBar measurements using ISR