dart timing and change management

12
DART SYSTEM IN PRODUCTION PREPAREDNESS PREPARATION Now through 2013: On-Ramp to DART 2011 2012 2013 Q1 Q2 Q3 Q4 Q1 Q2Q3Q4Q1 Q2 Q3 Q4

Upload: umdart

Post on 17-May-2015

1.412 views

Category:

Business


0 download

TRANSCRIPT

Page 1: DART timing and change management

DART SYSTEM IN PRODUCTION

PREPAREDNESS

PREPARATION

Now through 2013: On-Ramp to DART

2011 2012 2013

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Page 2: DART timing and change management

DART SYSTEM IN PRODUCTION

PREPAREDNESS

PREPARATION

Now through 2013: On-Ramp to DART

2011 2012 2013

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

This is a high level view of our timeline, by calendar year.

Page 3: DART timing and change management

DART SYSTEM IN PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

Now through 2013: On-Ramp to DART

2011 2012 2013

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Delivery of DART featuresby Blackbaud

Testing, training and unit readiness are the focus before Go Live in Spring 2012.

Page 4: DART timing and change management

DART SYSTEM IN PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

Now through 2013: On-Ramp to DART

2011 2012 2013

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Comprehensive Testing

End User Training &

Unit Readiness

Delivery of DART featuresby Blackbaud

Testing, training and unit readiness are the focus before Go Live in Spring 2012.

Page 5: DART timing and change management

PRODUCTION

PREPAREDNESS

PREPARATION

DART Change Management Update

2011 2012

Q3Q2Q1Q4Q3Q2Q1

This is a high level view of our preparation activities leading up to Go Live.

DART Goes Live

Comprehensive Testing Production use of the system

Page 6: DART timing and change management

PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

DART Change Management Update

2011 2012

Comprehensive Testing

Create Training Materials & Systems (E.g., Job Aids, Online Help)

Production use of the system

Q3Q2Q1Q4Q3Q2Q1

Pilot Training End User Training

Ongoing Training

The project team will prepare and test training materials.

Page 7: DART timing and change management

PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

DART Change Management Update

2011 2012

Comprehensive Testing

Create Training Materials & Systems (E.g., Job Aids, Online Help)

Production use of the system

Q3Q2Q1Q4Q3Q2Q1

Pilot Training End User Training

Ongoing Training

The project team will prepare and test training materials.Community members will receive training relevant to their

job responsibilities before Go Live.

Page 8: DART timing and change management

PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

DART Change Management Update

2011 2012

Comprehensive Testing Production use of the system

Q3Q2Q1Q4Q3Q2Q1

Unit Liaisons will help prepare each unit for the transition.

Page 9: DART timing and change management

PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

DART Change Management Update

2011 2012

Comprehensive Testing Production use of the system

Q3Q2Q1Q4Q3Q2Q1

UL Kick-off

Unit Liaison Meetings & Work (Identify System inputs/impacts, Who Needs Training & Access, Communicate/Share) Stabilization

Unit Readiness

ULs attend meetings, complete preparation activities, and provide information on training, access, and other project news.

Unit Liaisons will help prepare each unit for the transition.

Page 10: DART timing and change management

PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

DART Change Management Update

2011 2012

Comprehensive Testing Production use of the system

Q3Q2Q1Q4Q3Q2Q1

Communicate Project Updates (Newsletters, Talking Points, Demos, Meetings, Dev Council) Prepare for Go Live Stabilization

Communications, demos, and presentations will continue.

Page 11: DART timing and change management

PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

DART Change Management Update

2011 2012

Comprehensive Testing

Create Training Materials & Systems (E.g., Job Aids, Online Help)

Production use of the system

Q3Q2Q1Q4Q3Q2Q1

UL Kick-off

Pilot Training End User Training

Unit Liaison Meetings & Work (Identify System inputs/impacts, Who Needs Training & Access, Communicate/Share) Stabilization

Unit Readiness

Communicate Project Updates (Newsletters, Talking Points, Demos, Meetings, Dev Council) Prepare for Go Live Stabilization

Ongoing Training

Page 12: DART timing and change management

DART SYSTEM IN PRODUCTION

DART Goes Live

PREPAREDNESS

PREPARATION

Now through 2013: On-Ramp to DART

2011 2012 2013

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4

Comprehensive Testing

End User Training &

Unit Readiness

Production use of the systemDelivery of

DART featuresby Blackbaud

After Go Live, everyone will use DART.

Stabilization Period