dangerous good transportation by road from risk analysis

Upload: shaileshgadbail

Post on 02-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    1/11

    Dangerous good transportation by road: from risk analysis

    to emergency planning

    B. Fabiano*, F. Curro, A.P. Reverberi, R. Pastorino

    DIChePChemical and Process Engineering Department, G.B. Bonino, University of Genoa, Via Opera Pia, 15-16145 Genoa, Italy

    Abstract

    Despite the relative recent move towards inherent safe materials, the relentless drive of consumerism requires increased quantities of

    dangerous goods to be manufactured, transported, stored and used year on year. The safety and effectiveness of road transport systems is to beconsidered a strategic goal in particular in those countries, like Italy, in which 80% of goods are transported by this means. In this paper, we

    face the risk from dangerous good transport by presenting a site-oriented framework for risk assessment and developing a theoretical

    approach for emergency planning and optimisation. In the first step, we collected field data on a pilot highway and developed a database

    useful to allow a realistic evaluation of the accident frequency on a given route, by means of multivariate statistical analysis. To this end, we

    considered both inherent factors (such as tunnels, bend radii, height gradient, slope etc), meteorological factors, and traffic factors (traffic

    frequency of tank truck, dangerous good truck etc.) suitable to modify the standard national accident frequency. By applying the results to a

    pilot area, referring to flammable and explosive scenarios, we performed a risk assessment sensitive to route features and population exposed.

    The results show that the risk associated to the transport of hazardous materials, in some highway stretches, can be at the boundary of the

    acceptability level of risk set down by the well known F/N curves established in the Netherlands. On this basis, in the subsequent step, we

    developed a theoretical approach, based on the graph theory, to plan optimal emergency actions. The effectiveness of an emergency planning

    can normally be evaluated in term of system quickness and reliability. As a case study, we applied the developed approach to identify optimal

    consistency and localisation in the pilot area of prompt action vehicles, properly equipped, quick to move and ready for every eventuality.

    Applying this method results in an unambiguous and consistent selection criterion that allows reduction of intervention time, in connectionwith technical and economic optimisation of emergency equipment.

    q 2005 Elsevier Ltd. All rights reserved.

    Keywords: Accident frequency; Hazardous materials; Emergency; Transportation

    1. Introduction

    Despite the relative recent move towards inherent safe

    materials, the relentless drive of consumerism has required

    increased quantities of dangerous goods to be manufactured,

    transported, stored and used year on year (Thomson, 1998).

    Of the different way of transportation, rail has higher

    damage potential, as larger quantities are transported by this

    means. However, considering the damage it may cause to

    life and properties, transport by road is more hazardous, as

    roads often pass through populated areas, especially in

    developing countries. The recent EEC Directive 96/82/EC

    implies the evaluation of risk in highly industrialised areas

    by means of Quantitative Area Risk Analysis techniques. It

    must be evidenced that certain dangerous substances are

    transported along particular Italian road routes in quantities

    that would exceed the threshold for safety notification or

    declaration, set down in Italy by Seveso II Directive, if

    stored in a fixed installation. On the other side, it must be

    remembered that EEC Directive 94/55/EC implies the

    harmonisation of the different national legislation on

    transport of hazardous materials by road. The safety and

    efficiency of road transport is to be considered a strategic

    goal in particular in those countries, like Italy, in which

    about 80% of goods is transported by this means, with a

    30% increase with reference to the 2010 forecast. In

    particular, Italian highways are very crowded with trucks,

    considering that 17% of the whole good traffic by road of

    EU (15 Countries) is transported on these highways.

    Moreover, the number of cars is still steadily increasing,

    Journal of Loss Prevention in the Process Industries 18 (2005) 403413

    www.elsevier.com/locate/jlp

    0950-4230/$ - see front matter q 2005 Elsevier Ltd. All rights reserved.

    doi:10.1016/j.jlp.2005.06.031

    * Corresponding author. Tel.:C39 010 3532585; fax:C39 010 3532586.

    E-mail address: [email protected] (B. Fabiano).

    http://www.elsevier.com/locate/jlphttp://www.elsevier.com/locate/jlp
  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    2/11

    making a place on the road increasingly a scarce

    commodity. Empirical evidence shows that though

    improvement in transport safety, in Italy a consistent

    number of serious accidents on motorways and highways

    keeps occurring, evidencing that the risk connected to

    dangerous goods transport is comparable with the fixed

    plants one.Analysis of the risks presented by the transportation of

    hazardous materials presents a very different risk than a

    fixed facility: detailed information on shipments is not

    available on a national, regional, or local level in contrast

    with fixed facility inventories (Pine & Marx, 1997). As

    reported by different researchers, a specifically tailored

    QRA methodology can represent an effective tool to assess

    the risk to people associated with the transport of dangerous

    substance. The selection of the best route for transport has

    been widely investigated (List, Mirchandani, Turnquist, &

    Zografos, 1991) and was recently formulated as a

    minimum cost flow problem, which consists of determin-

    ing, for a specific hazardous substance, the cheapest flow

    distribution, honouring the arc capacities, from the origin to

    the destination vertices (Leonelli, Bonvicini, & Spadoni,

    2000). Poor appreciation of factors related to road

    conditions such as road class, designated speed limits,

    traffic density, as well as of the population characteristics, is

    likely to result in a risk assessment insensitive to route

    specifics and over- or under-estimating the overall level of

    risk (Davies, 1999).

    In this paper, a site-oriented risk analysis procedure is

    tested in a pilot area, starting from an in-depth inventory of

    hazardous materials transported and from a statistical

    analysis of traffic and accidents observed in the area. Infact, it must be observed that to ensure that a local

    emergency plan is complete, it must take into account the

    nature and extent hazardous materials are transported by

    road in the area. The results are then discussed and a

    mathematical model for optimising emergency planning is

    presented. A main focus in the management of emergencies

    has been on resources and logistics; in other words, having

    what and who you need it to meet the crisis within an urgent

    time frame (Kowalski, 1995). The importance of the ability

    of the emergency response services to minimize the damage

    was recently highlighted by a pilot project carried out in the

    Netherlands, where the evaluation method of external safetyrisk included three new criteria, additional to individual risk

    and societal risk (Wiersma & Molag, 2004):

    self-rescue i.e. the ability of the people in the vicinity

    of the accident to safe themselves;

    controllability i.e. emergency response services;

    consequences i.e. analysis of representative scenarios

    in terms of number of fatalities, injuries and material

    damage.

    The criterion of controllability is focused on the ability of

    the emergency response services to minimize the magnitude

    and to prevent escalation of the accident. In case of accident

    in hazmat transportation and subsequent release into the

    environment, it is very important to have at ones disposal

    information on each chemical hazardous product involved,

    trained and skilful personnel and suitable prompt action

    vehicles, properly equipped to be employed if the above

    mentioned hazardous release would happen. To this end, inthe last phase of this paper, the optimisation algorithm is

    developed for solving the problem of optimal location of

    emergency vehicles in the pilot area.

    2. Theoretical structure

    2.1. Transportation risk analysis

    Generally speaking, the concept of risk is the relation

    between frequency and the number of people suffering from

    a specified level of harm in a given population from the

    realization of specified hazards (Vrijling, Van Hengel, &

    Houben, 1995).

    The model required for our purposes is focused on a

    proper evaluation of the expected frequency of accidents. If

    the route is divided into road stretches, each characterized

    by different characteristics, the expected number of fatalities

    as consequence of an accident occurred on the road stretch r

    and evolving according to a scenario S, can be expressed as:

    DrZX

    S

    frNr;SPS (1)

    where:fr frequency of accident in the rth road stretch

    [accident yearK1]

    Nr,S number of fatalities caused by the accident evolving

    according to a scenario S in the rth road stretch

    [fatalities accidentK1]

    PS probability of evolving scenarios of type S, following

    the accident initialiser (i.e. collision; roll-over; failure

    etc.) []

    Transportation network can be considered as a number of

    vertices linked one another by a number of arcs. As shown

    in the following paragraph, the vertices represent origin-destination points, tool-gates, storage areas on the transpor-

    tation network and the arcs are the roads connecting

    vertices. An arc between two vertices is characterized by

    a different number of road stretches and the expected

    number of fatalities for the arc is:

    DZX

    r

    X

    S

    frNr;SPS (2)

    where Nr,S is the total number of fatalities according to

    Eq. (3):

    Nr;SZ AinS kvCA

    offS dPPF;S (3)

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413404

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    3/11

    being the in-road and the off-road number of fatalities

    calculated respectively as:

    Ninr;SZA

    inS kvPF;S (4)

    Noffr;SZA

    offS dPPF;S (5)

    where:AinS consequence in-road area associated with scenario S

    [m2]

    AoffS consequence off-road area associated with scenario S

    [km2]

    PF,S probability of fatality for accident scenario S []

    k average vehicle occupation factor []

    v vehicle density on the road area [vehicle mK2]

    dP population density [inhabitants kmK2]

    The frequency of an accident involving a scenario S, on

    the r-th road stretch, can be expressed as:

    fr;SZfrPS (6)

    frZgrLrnr (7)

    grZg0;r

    Y6

    jZ1

    hj (8)

    where:

    gr expected frequency on rth road stretch

    [accident kmK1 vehicleK1 yearK1]

    Lr road length [km]

    nr number of vehicles [vehicle]

    g0,r national accident frequency [accident kmK1

    vehicleK1 yearK1]

    hj local enhancing/mitigating parameters []

    As is well known, various factors influence the accidents:

    mechanical, environmental, behavioural, physical, road

    intrinsic descriptors. A statistical multivariate analysis was

    performed, by comparing historical accident data related to

    the whole regional highways and data directly collected on

    the field on each stretch, in order to highlight relevant

    intrinsic road factors and meteorological, traffic conditions

    etc. (Fabiano, Curro, Palazzi & Pastorino, 2002).

    Table 1 shows the parameters suitable to influence

    accident rates and grouped into three categories: intrinsic

    characteristics, meteorological conditions and traffic con-

    ditions. Thevalues of the parameters are in the range 0.82.5.

    2.2. Emergency planning

    The effectiveness of an action aimed at facing an

    emergency situation can normally be evaluated in terms of

    systems quickness and reliability. To approach the

    optimisation problem we adopted the graph-theory,

    recently introduced by Beroggi and Wallace (1994) in

    computing optimal course of action for emergency

    response. Generally speaking, a linear graph may be

    defined as a set N of objects named vertices Vi (iZ1,.,n)

    and a set A of arcs linking couples of vertices (Vi,Vj). Indetails, a graph is a couple G(N,A) where NZ[V1,.,n] is a

    set of vertices and AZai;jZVi; VjjVi; Vj2N is a class

    of elements called arcs. Between two vertices, several

    oriented arcs may exist: the maximum number of the same

    oriented arcs between two vertices is called P and the

    graph is a P-graph. The set of vertices N can be run

    according to different ways: as tail, leading to the research

    in breadth (breadth-first), or as a pile, leading to research in

    depth (depth-first) or backtracking (Tarjan, 1972). In order

    to solve the minimum intervention time problem, a label

    d(i) is assigned to every vertex Vi, defining the path

    between vertices and a pointer pred(i), which shows the

    predecessor of Vi in the considered path. The sequence

    starts from a temporary value for d(i) which has to be

    modified, by iteration, as to reach the right value. After a

    comparative survey on various shortest path algorithms

    (Dreyfus, 1969) we considered the Dijkstra algorithm

    (Dijkstra, 1959) of label setting, as follows:

    1. d(s)Z0; d(i)Zx; pred(i)Zs;

    2. d(h)Zmin[d(i)/d(i) not exact]; d(h) becomes exact;

    3. if Vi2A(h) and di not exact, d(i)Zmin[d(i),d(h)Cc];

    eventually pred(i)Zh;

    4. if every value d(i) is exact, then stop, if not go to 2.

    Table 1

    Local enhancing and mitigating parameters

    Parameter

    Intrinsic characteristics h1 Straight road

    Road bend (radiusO200 m)

    Road bend (radius!200 m)

    h2 Plane road

    Slope road (gradient!5%)

    Steep slope road (gradientO5%)

    Downhill road (gradient!5%)

    Steep downhill road (gradientO5%)

    h3 Two lanes for each carriageway

    Two lanes and emergency lane for

    each carriageway

    Three lanes and emergency lane for

    each carriageway

    h4 Well lighted straight tunnel

    Other tunnels

    Bridge

    Meteor. cond. h5 Fine weather

    Rain

    Heavy rainFog

    Snow/ice

    Traffic charact. h6 Low intensity!500 vehicle/h

    Medium intensity!1250 vehicle/h

    with heavy traffic!125 truck/day

    High intensityO1250 vehicle/h

    High intensityO1250 vehicle/h with

    heavy trafficO250 truck/day

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413 405

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    4/11

    We developed the optimisation algorithm as schematised

    in Fig. 1. Every vertex corresponds to a toll gate, a fire

    brigade station or to a storage area and the algorithm allots

    the exact value for d(i) at the last iteration for every vertex.

    3. Case-study

    The methodology previously presented was applied to a

    pilot area, referring to the routes starting from the Genoa

    port area (the most important in the Mediterranean basin)

    towards four direction: the industrialized North Italian and

    Central Europe districts, France and South of Italy (Fig. 2).

    All of these highways are characterized by high truck

    traffic (mainly ADR) and inherent factors (ascribed to road

    out-of-date: the year of construction of A7 is 1935)

    determining to a major accident risk, with reference to both

    individual and social risk, defined according to the Dutch

    limits.

    3.1. Data collection and analysis

    The value of traffic and accidents for the four highways

    in the area are shown in Table 2. In particular, it can be

    noticed that A7 highway is characterized by values higher at

    least an order of magnitude than the accident frequency

    (6.0!10K8

    ) calculated by other researchers for certain typeof load threatening accidents (James, 1986), thus approach-

    ing the calculated values for urban road.

    By considering the daily ADR traffic on the different

    highway sections, it results that the higher values of

    dangerous goods fluxes correspond to the intersection

    between the highways A10 (West riviera) and A12 (East

    riviera), in the stretch between the towns of Bolzaneto and

    Busalla and in the starting stretch, from the central port of

    Genoa (Genova Ovest toll-gate) to the connection between

    the highways A10 and A7.

    The substances transported are shown in Fig. 3: it is

    important to notice the high striking transport percentages of

    chlorine and ethylene oxide.

    The immediate causes of accident are summed up in

    Fig. 4.

    The proportion of severe accidents on these highways

    during the years 19951999 is in the range 6070% of the

    total accidents, defining a severe incident as one involving

    death, serious injuries, a fire or explosion, or more than EUR

    25000 worth of damage.

    3.2. Modelling

    In order to obtain a correct evaluation of the density ofthe population which might be exposed to Hazmat hazards

    from transport, it is necessary to include data on the

    population density along the route and on the so-called

    motorist density, taking into account, as well, the proportion

    which may be considered particularly vulnerable or

    protected. Otherwise, all individuals within a threshold

    distance from road stretches run the same risks regardless of

    their location.

    The population density along a route segment can vary

    with time, such as from day to night, and from month to

    month. The average density on the route can be calculated

    starting from the collected statistical data relevant to

    average daily traffic, average speed and geometrical data

    of carriageway and lanes, in each highway stretch

    considered.

    Also on-road population can vary during the day: in order

    to evaluate correctly the number of on-road population

    involved in the accident, the response and the variations in

    the motorist density as a consequence of an accident, were

    considered.

    Two classes of motorist density are to be considered: the

    former refers to the carriageway, where the accident occurs,

    the latter considers the opposite carriageway, were the

    ghoul effect causes the slowing down of the traffic.

    Fig. 1. Modified Dijkstra algorithm.

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413406

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    5/11

    In order to evaluate the probability of death in the area

    involved, the consequence model was applied making

    reference to event trees for every type of accident

    consequence: pool fire, flash fire, jet fire, BLEVE, fireball, UVCE, release of toxic substances.

    Average individual risk, defined as the frequency at

    which an individual may be expected to sustain a given level

    of harm from the realization of a specific hazard (Dantzig

    & Kriens, 1960), has been determined averaging the

    estimating individual risk levels for all the individuals in

    the selected area, as above-described. For individual risk,

    we considered the upper acceptability criterion set down in

    the Netherlands in new situations or new developments,

    corresponding to 10K6 yearK1.

    The same technique was secondly adopted for the

    evaluation of societal risk. Societal risk analysis can lead,via the generation of expectation values (average number of

    lives lost) to the consideration of the need for, and cost

    benefit, of risk reduction measures, even if it involves many

    generalising assumptions and averaging (Purdy, 1993). In

    all concepts, the most stringent of the personally and the

    socially acceptable level of risk determines the acceptable

    level of risk. So both criteria have to be satisfied ( Vrijling

    et al., 1995). The same acceptability criterion for individual

    Fig. 2. Pilot area.

    Table 2

    Daily traffic and accident frequency

    Highway Daily traffic [n] Accident per km per 10 millions of vehicles

    Length [km] Total Heavy vehicle Light vehicle Total Heavy vehicle Light vehicle

    A26 83.7 34946 7172 27774 6.29 6.63 4.97

    A12 48.7 52105 8139 43966 5.16 5.22 4.84

    A10 45.5 55025 9190 45835 6.06 7.20 6.95

    A7 50.0 33721 6353 27368 9.83 9.92 9.81

    A7-Stretch 1 1.9 30075 6123 23952 8.63 11.77 7.83

    A7-Stretch 2 3 31620 6235 25385 4.04 7.32 3.24

    A7-Stretch 3 2.9 27758 5134 22624 6.47 11.04 5.43

    A7-Stretch 4 14.3 15476 3250 12226 6.56 7.66 6.27

    A7-Stretch 5 5 12289 2768 9521 13.4 17.82 12.09

    A7-Stretch 6 5.8 12042 2746 9296 7.45 6.88 7.62

    A7-Stretch 7 6.6 11823 2512 9311 4.56 6.61 4.01

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413 407

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    6/11

    and societal risk was considered by Alp and Eelensky

    (1996), in developing a rigorous mathematical platform on

    which risk assessment can be built. It must be evidenced that

    the societal acceptable risk criterion is not standardized in

    the different EU Countries. So, in the absence of a national

    statistical reference, we adopted again the F/N limit curves

    established in the Netherlands, dividing as well the so-called

    Alarp region into two bands: the acceptability criterion of

    the risk so modified is explained in Table 3, where P is the

    cumulative frequency per year and Nthe number of fatalities

    (Hj & Kroger, 2002).The results of the risk evaluation for the pilot area are

    summarized in Fig. 5.

    To reduce intervention time, the localization of prompt

    action vehicles must found on scientific statement, as

    previously explained, taking into consideration the concept

    of minimum pathway. The main constraint the theoretical

    approach is based upon is that the emergency vehicle can

    not be placed in any site of the concerned provincial

    territory, but only in the Fire Brigades Central Department

    or in one of the six detachment. Central Department and the

    six detachments are to be considered as vertices in the final

    graph, which will solve the problem.

    In the same way, it is possible to indicate the hazardousareas, where production, transformation and hazardous

    substances storage take place, as vertices of the final

    Fig. 3. Inventory of hazardous material traffic.

    Fig. 4. Immediate causes of accident.

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413408

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    7/11

    graph. To complete the construction of the final graph, it

    was necessary to take into consideration highly hazardous

    areas along the highway. We considered as vertices of the

    graph inlet and outlet toll-gates, fire brigade districts and

    central department, as well as production, transformation

    and storage sites of dangerous substances. The obtained

    final graph is depicted in Fig. 6.

    The arcs, which link vertices together, represents normal

    way and highway units, between all areas taken into

    consideration.In order to evaluate the considered graph, we allotted to

    each arc a corresponding scalar, defined cost of the arc.

    This scalar value corresponds to a time: the Average Run

    Time (in minutes) needed to reach from a vertex the

    subsequent one. Time was calculated considering distances

    between vertices and assuming two average speeds:

    80 km hK1 as highway speed and 30 km hK1 as urban

    speed.

    4. Results and discussion

    The results of transport risk analysis in the area show that

    the risk associated with the transport of hazardous materials

    on the highways considered, in a number of stretches

    (Fig. 5), is at the limit of the acceptable level of risk set

    down according to the criterion schematised in Table 3 and

    previously discussed. The results are similar to those

    reported by Milazzo et al. (2002) who presented risk

    analysis in an urban area, where flammable substances wereprevalent in road transportation. They concluded that

    overall societal risk was not acceptable on the basis of the

    Dutch risk criteria and that the risk associated with the road

    transportation is higher for N!20, while the risk associated

    with railway transportation become dominant for NO20.

    On these bases, strategies for the reduction of risks and

    emergency management in the area must be developed. As a

    first approach, the opportunity of limiting hazardous

    Table 3

    Acceptability criterion of the risk

    Evaluation of the risk Criterion Explanation

    Acceptable risk P!(10K5/N2) No need for detailed studies. Check that risk maintains at this level

    Tolerability region A (10K5/N2)!P!(10K4/N2) Tolerable risk if cost of reduction would exceed the improvements gained

    Tolerability region B (10K4/N2)!P!(10K3/N2) Tolerable only if risk reduction is impracticable or if its cost is grossly in disproportion to

    the improvement gained

    Unacceptable risk PO(10K3/N2) Risk intolerable: risk cannot be justified even in extraordinary circumstances

    Fig. 5. Risk characterization in the different highways stretches.

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413 409

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    8/11

    materials travelling during particular time bands must be

    considered. As an example, about 53% of ADR traffic is

    focused in the time interval 8 a.m.1 p.m.

    A second strategic opportunity consists in imposing a

    different highway route for hazardous materials transport.

    For example, an alternative route from Genoa to Milan is

    represented by A26 highway, from Genoa Voltri towards

    Alessandria: this highway, being more recent and charac-

    terized by lower intrinsic risk factors, could gather also the

    traffic from East and Genoa central port. However, the

    practical utilization of this option is made difficult by

    the need of crossing a long urban stretch, characterized by

    high risk level (as depicted in Fig. 5). A solution for risk

    reduction is therefore the construction of a slip road

    connecting Genoa central port and highway A26, even if

    the feasibility of this option is obviously constrained by

    economical and environmental impact issues. Therefore arisk reduction could pass through a redefinition of the

    transportation network and in defining proper emergency

    plans.

    Table 4 depicts a selection of the complete flow sheet

    reporting the vertices and the costs of the arcs. In the first

    row are indicated all 36 vertices of the graph. In the

    following rows, are reported the distances of each vertex

    from the other ones and respective forerunner, correspond-

    ing to the cost of the arc. From Table 4, we can notice that

    the route stretching from vertex 1 to vertex 4 and including

    vertices 2 and 3 has a total cost of 31 min. In the same way,

    vertex 36 is distant from vertex 1 130 min, according to the

    considered route. By applying the method to the whole

    transportation network, it is possible to know all distances

    (in minutes) of each vertex 1, 2, 3, ., 36 from all the other

    36 vertices.

    In column B it is indicated maximum time needed to

    reach, from a vertex, all the other ones. For example, vertex1 is distant from all the other vertices 130 min as a

    Fig. 6. Final graph.

    Table 4

    Summary of the results (one prompt action vehicle)

    Vertex 1 2 3 4 5 6 7 [.] 33 34 35 36 A B

    Distance from 1 0 13 22 31 40 44 44 105 114 115 130 130 130

    Forerunner 0 1 2 3 4 5 5 32 33 34 34 34

    [.]

    Distance from 28 66 53 44 35 44 48 48 39 48 49 64 67 67

    Forerunner 2 3 4 8 4 5 5 32 33 34 34 34

    [.]

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413410

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    9/11

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    10/11

    maximum. It means that, starting from vertex 1, it is

    possible to reach vertex 36 (the further one from vertex 1) in

    a maximum time of 130 min. All other vertices can be

    reached in a shorter time.

    Moreover, starting from vertex 28, it is possible to reach

    all the other vertices in a maximum time of 67 min. From

    the final graph, we can observe that vertex 28 corresponds toNervi Highway toll-gate. It is obvious that if the prompt

    action vehicle is located near vertex 28, it will be able to

    reach all the other vertices corresponding to hazardous

    areas, in a maximum time of 67 min, representing, under

    this constraint, the minimum intervention time. Of course,

    the prompt action vehicle has to be placed inside the Fire

    Brigades Central Station or in one of the six Provincial

    District.

    Let us now take into consideration the option of two

    prompt action vehicles: also in this case they are to be

    placed inside the Fire Brigades Central Station or in one of

    the six Provincial District. From the elaboration (Table 5

    being a selection of this example), it results that the prompt

    action vehicles can be placed in vertices:

    1013 1015 1021 1026 1031 1032

    1315 1321 1326 1331 1332 1521

    1526 1531 1532 2126 2131 2132

    2632 631 3132

    If we place the two vehicles in vertices 15 and 31, vertex

    1 can be reached, starting from vertex 15, in 61 min and

    starting from vertex 31, in 88 min. In order to reduce action

    time to reach vertex 1, it is convenient to start from vertex15. The same logic must be followed for every vertex of the

    final graph. In the end, placing the two prompt action

    vehicles in vertices 15 and 31 it will be possible to reach all

    the vertices in a maximum time of 61 min. From data of

    Table 5, if we place the two vehicles in vertices 26 and 31 or

    26 and 32, it derives that all vertices can be reached in a

    maximum time of 58 min (column A).

    In conclusion, if we place the two prompt action

    vehicles in vertices 26 and 31 (Genova-Est and Rapallo

    highway toll-gates) or in vertices 26 and 32 (Genova-Est

    and Chiavari highway toll-gates), it will be possible to

    intervene in a maximum time of 58 min, which represents

    the minimum intervention time, under these conditions.

    This same logic can be followed whether three or more

    prompt action vehicles are available. It is noteworthy

    noting that, if we have at our disposal three prompt action

    vehicles placed in vertices 102132, it is possible to reach

    all vertices in a maximum time of 41 min (from Table 5).

    The same result is obtained in case we have at our disposal

    seven prompt action vehicles placed in the seven Fire

    Brigades provincial stations. It must be remarked that the

    resources necessary to control an accident and mitigate its

    consequences include an emergency management plan,

    trained manpower, appropriate equipment, available

    communication, plus knowledgeable and decisive leaders

    (Kowalski, 1995).

    5. Conclusions

    The risk from transporting dangerous goods by road andthe strategies proposed to select road load/routes are faced

    in this paper, by developing a site-oriented framework

    sensitive to route specifics and population exposed. The

    results of the risk evaluation evidenced some critical

    situations of the road transportation network in those

    highway stretches crossing urban areas and starting from

    Genoa port. Strategies for the reduction of risks may include

    distribution and limitation of ADR road traffic, improve-

    ment of highway section, alternative routes and appropriate

    emergency management. Considering this last issue, an

    optimisation algorithm, based on the graph theory was

    developed to select optimal consistency and localisation in

    the area of prompt action vehicles, properly equipped, quick

    to move and ready for every eventuality. Applying this

    method results in an unambiguous and consistent selection

    criterion that allows reduction of intervention time (41 min

    maximum), in connection with technical and economic

    optimisation of emergency equipment (three vehicles).

    References

    Alp, E., & Zelensky, M. J. (1996). Risk quantification for meteorology-and-

    direction-dependent hazards due to point and linear risk sources.

    Journal of Loss Prevention in the Process Industries, 9(2), 135145.Beroggi, G. E. G., & Wallace, W. A. (1994). Operational risk management:

    A new paradigm for risk analysis. IEEE Transactions on Systems, Man

    and Cybernetics, 24(10), 14501457.

    Dantzig, V. D., & Kriens, J. (1960). The economic decision problem of

    safeguarding the Netherlands against floods Report of Delta

    Commission 3. NL: The Hague p. 2.

    Davies, P. A. (1999). Loss Prevention Bulletin, 150, 22.

    Dijkstra, E. W. (1959). A note on two problems in connection with graphs.

    Numerische Matematik, 1, 269271.

    Dreyfus, S. E. (1969). An appraisal of some shortes-path algorithms.

    Journal of Operations Research, 17(3), 395412.

    Fabiano, B., Curro, F., Palazzi, E., & Pastorino, R. (2002). A framework for

    risk assessment and decision making strategies in dangerous food

    transportation. Journal of Hazardous Materials, 93(1), 115.

    Hj, N. P., & Kroger, W. (2002). Risk analyses of transportation on roadand railwayfrom a European Perspective. SafetyScience, 40(14), 337

    357.

    James, I. A. (1986). Dept. of Environment, Report DoE/RW, London, pp.

    85175.

    Kowalski, K. M. (1995). A human component to consider in your

    emergency management plans: the critical incident stress factor. Safety

    Science, 20, 115123.

    Leonelli, P., Bonvicini, S., & Spadoni, G. (2000). Hazardous materials

    transportation: a risk-analysis-based routing methodology. Journal of

    Hazardous Materials, 71(1), 283300.

    List, G. F., Mirchandani, P. B., Turnquist, M., & Zografos, K. G. (1991).

    Modeling and analysis for hazardous materials transportation. Risk

    analysis, routing/scheduling and facility location. Transportation

    Science, 25(2), 100114.

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413412

  • 7/27/2019 Dangerous Good Transportation by Road From Risk Analysis

    11/11

    Milazzo, L. S., Lisi, R., Maschio, G., Antonioli, G., Bonvicini, S., &

    Spadoni, G. (2002). Hazmat transport through Messina town: From risk

    analysis suggestions for improving territorial safety. J. Loss Prev

    Process Jud., 15, 347356.

    Pine, J. C., & Marx, B. D. (1997). Utilizing state hazardous materials

    transportation data in hazardous analysis. Journal of Hazardous

    Materials, 54, 113122.

    Purdy, G. (1993). Risk analysis of the transportation of dangerous goods by

    road and rail. Journal of Hazardous Materials, 33(2), 229259.

    Tarjan, R. (1972). Depth first search and linear graph algorithms. SIAM

    Journal of Computation, 1(2), 146160.

    Thomson, B. J. (1998). Proceeding of international workshop on safety in the

    transport Storage and use of hazardous materials. Tokyo, Japan: NRIFD.

    Vrijling, J. K., Van Hengel, W., & Houben, R. J. (1995). A framework for

    risk evaluation. Journal of Hazardous Materials, 43(3), 245261.

    Wiersma, T., & Molag, M. (2004). Development of new evaluation method

    for external safety risk L oss prevention, Vol. A. Praha, Czech Republic:

    PCHE PetroChemEng Publ pp. 1163-1170.

    B. Fabiano et al. / Journal of Loss Prevention in the Process Industries 18 (2005) 403413 413