dan bauer - cdms project managerall experimenters meeting - december 15, 2008 cdms status, upgrades...

14
Dan Bauer - CDMS Project Manager All experimenters meeting - December 15, 2008 Status, Upgrades and Plans Summary of running at Soudan Cryogenic and Detector Upgrades The Future - SuperCDMS@SNOLAB

Upload: bathsheba-wheeler

Post on 29-Jan-2016

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

CDMSStatus, Upgrades and Plans

Summary of running at Soudan

Cryogenic and Detector Upgrades

The Future - SuperCDMS@SNOLAB

Page 2: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

CDMS (2006)

Current CDMS sensitivity

Maximum livetime = 85%(limited by cryo servicingneed for calibration data)

>2 years of stable data taking at Soudan

Average livetime ~ 75%

Xenon 10Gamma Calibration~10% of livetime

CDMS (Feb 2008)

DAMA

MSSM

We now have >1700 kg-days of exposure, sufficient to have world’s best spin-independent WIMP sensitivity for all WIMP masses.Approaching 10 Zeptobarn cross section!

Page 3: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Cryogenic Upgrades - UPS

• Replaced UPS for cryogenics system

– Underground diesel generator backs up entire cryogenics system

– Aging UPS was used to ‘bridge’ cryogenics control systems

– Installed new 30 kVA unit to carry whole cryogenics system

– Remote control and monitoring of UPS from the surfaceUnderground diesel generator UPS remote monitoring

Page 4: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Cryogenic Upgrades - Replaced Ebox

• Have lived for 2 years with small leaks in vacuum bulkhead (Ebox)

– Air freezes out on cold surfaces, can cause vacuum bursts

– If Helium gets in, it can reach detectors and affect signals

– Occasional ~1 week warming to 4-77K has been necessary

• Problem was due to custom-design of Ebox

– Warping of rectangular box made large o-ring seals difficult

• Solution was to buy large commercial vacuum cross

– Had vendor weld high-vacuum detector electrical connections into commercial vacuum plates

• Decided to warm to room temperature in October to install

– Takes about 2 weeks to warm, another 2 weeks to cool down

– Actual work at room temperature about 2 weeks

Page 5: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Cryogenics Upgrades - Ebox

Old ebox (note the black sealant) Stripline detector connections extracted

New Ebox being installed Reinstalling the stripline connections

Page 6: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Cryogenic Upgrades - Serviced Cryocooler

• Cryocooler removes excess heat at 4K and 77K

– We cannot run 30 detectors without this

• Servicing involves replacing cold head at room temperature

• Why did we want to do this now?

– Had 150% of recommended hours on the cold head

– Valves or piston could begin sticking at some point

– No evidence of performance problems but want to run another 2-3 years at Soudan, so this was a good time to do this

– Fortunately, the vendor (Sumitomo) can replace the cryocooler head without disturbing the delicate connections to e-stem

– Challenge was supporting these connections during the operation

• New head should last for length of CDMS operation at Soudan

Page 7: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Cryogenic Upgrades - Cryocooler

Supporting the cryocooler and estem during the cold head replacement The cryocooler cold head

Page 8: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

An interesting incident during cooldown

• Dilution refrigerator uses 1K pot to condense 3He

– 1K pot is filled from He bath via needle valves

– Pumping on 4He in pot lowers temperature to 1.4K

• At this temperature, liquid Helium is a superfluid

– Superfluid Helium tends to creep

– Distance it can travel depends on surface roughness

• Small amount of air was accidentally introduced in bath

– Plated out in needle valves, allowing superfluid Helium connection between 1K pot and 4K bath

• Result was a 1K pot temperature >1.9K and very poor condensation of 3He

• Had to warm again above 77K and pump away air

– Now understand earlier instability with pot temperatures

Page 9: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Additional work planned in 2009

• Soudan underground power feed

– Near maximum capacity and getting old

– Study underway to determine whether upgrades needed

– May be possible to run separate feed for water pumps

• CDMS would like to install He liquefiers at Soudan

– He costs are skyrocketing and availability is an issue• 36% increase in costs this summer

• Several recent instances where supply was very tight

• CDMS uses about 70l/day

– Purchased 3 cryocooler-based liquefiers in FY2008• Plan phased installation during 2009-2010

• Sufficient capacity to reduce He consumption by x10

– Requires additional power (8 kw/liquefier)

Page 10: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Detector Issues

• Many detectors have failed in the oldest two towers

– These towers are now 6 years old and have seen many thermal cycles

– Will do postmortem on failures when towers replaced; most suspected to be cold electronics and wire bonds

– Net loss of about 1 kg Ge for the next three months

• New issues with Si detectors in this run

– Many of our Si detectors show signs of charge leakage through the crystal

– Run at reduced charge bias to avoid heating of phonon sensors

– Si detectors are no longer crucial for WIMP search

Page 11: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

Larger detectors to be deployed in 2009Remove two oldest towerslose 1.5 kg Ge, 0.6 kg Si(mostly not working anyway)

New SuperCDMS detectorseach 3” dia x 1” => 0.64 kg of Gewith new phonon sensor designto improve fiducial volume

Page 12: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

SuperCDMS@Soudan

• Replace CDMS II detectors with SuperCDMS detectors

– 0.25 kg Ge/0.1 kg Si --> 0.64 kg Ge

– Each new tower has 5 Ge detectors => ~3 kg mass

– Each also has two Ge endcap veto detectors• Improves ability to reject backgrounds from nearby materials

• First ‘Supertower’ due in March 2009

– Will bring Ge mass to 6 kg

• Remaining 4 supertowers in early 2010

– Total deployed Ge mass will be 15 kg

• Two year run will yield x3 sensitivity improvement over the best that CDMS II will produce (x10 better than currently published).

Page 13: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

The Future: SuperCDMS@SNOLAB

• Science goals– Increase sensitivity by x50 (compared with current published)

– Reach WIMP-nucleon cross section of 10-46 cm2

– Find WIMP signal and compare with LHC

• Technical goals– Increase detector mass in stages up to 100 kg by 2012

– Stay background free

– Challenge to deal with existing backgrounds at Soudan

– New setup needed at SNOLAB to reduce neutron background

• Current status– First Soudan stage funded by DOE/NSF; full 15 kg funding requested

– SNOLAB experiment has CD-0 and Stage 1 approval from FNAL Director

– DMSAG2 review of the field in 2009 will likely determine funding prospects

Page 14: Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008 CDMS Status, Upgrades and Plans Summary of running at Soudan Cryogenic and

Dan Bauer - CDMS Project ManagerAll experimenters meeting - December 15, 2008

CDMS is the only DM experiment with demonstrated control of backgrounds

Expected Background: 0.6 0.5 surface events and < 0.2 neutrons

Make sure any events here are WIMPS, not background!