daily progress review for 10-09-2013

3
Attendees: DNV ETA Shashank Mr.T.K.Datta Mr. SK Haldar Mr.SHOAIB AHMED KHA Sno Issue/Discipline Deliberation Action by Completion Schedule Remarks I. Buil di ng Package Admin. Building-Ground floor (Civil) 1 False ceil ing Compl eted 2 False flooring material received at site on 08/09/2013. L&T 8/24/2013 3 Cleaning of ground floor Vacuum cleaning completed on 26.08.2013 L&T 8/25/2013 4 Painting of Primer primer & 1st coat paint completed in control room & ground floor of admin building.exrenal painting is in progress. L&T 23-08-13 to 26-08-13 5 False flooring fixing To be done after the MCS Panel & Cable Termination L&T 6 Doors Shutters fixing In progress L&T 24-08-13 to 26-08-13 7 Sanitary works Sensor materials yet to receive L&T 8/31/2013 8 RCC hume pipe To excavate & lay RCC hume pipes for Soak pit to Septic tank connection. Activity yet to start. L&T 20-08-13 to 31-08-13 9 Epoxy f looring in battery r oom Hold due to revised drawing required for UPS & battery location. Vendor visited (Sika India Product) site on 24-08-13. Materials will reach to site 10 days after placing order by L&T. Technip/L&T 26-08-13 to 31-08-13 10 Hand rails Materials yet to receive at site L&T 26-08-13 to 31-08-13 11 Final painting Will be done at last L&T 5/9/2013 12 Overhead Tank ONGC asked L&T to procure 5000 L capacity Sintex tank compatibl e with structural arrangement. This is an additional item and to be procured on cost plus basis. L&T/Technip 24-08-13 to 28-08-13 L&T to take action. Admin. Building-First floor (Civil) 1 Gypsum partition Work in progress L&T 31/08/2013 2 Flase ceiling Tiles fixing is in progress,duct to be provided in revised conference room. L&T 31/08/2013 3 Wooden shutters In progress. L&T 24-08-13 to 31-08-13 4 Aluminum doors fixing Materials recived at site,manpower not available L&T 01-09-13 to 05-09-13 DAILY SITE PROGRESS REVIEW MEETING HELD AT ONGC SITE OFFICE, ODALAREVU DATED 10th September 2013 AMONG ONGC, DNV AND L&T REGARDING COMPLETION OF BALANCE WORKS FOR EARLY PRODUCTION (G1-11), ODALAREVU. ONGC L&T Mr. Pavan Mr. B.R.V.P.Prasad Mr. R.Reddy ONGC Page 1 of  3 DNV  L&T

Upload: tushar-srivastava

Post on 14-Apr-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

7/27/2019 Daily Progress Review for 10-09-2013

http://slidepdf.com/reader/full/daily-progress-review-for-10-09-2013 1/3

Attendees:DNV ETA

Shashank Mr.T.K.DattaMr. SK HaldarMr.SHOAIB AHMED KHA

Sno Issue/Discipline Deliberation Action byCompletion

ScheduleRemarks

I. Building Package

Admin. Building-Ground

floor (Civil)

1 False ceiling Completed

2 False flooring material received at site on 08/09/2013. L&T 8/24/2013

3 Cleaning of ground floor Vacuum cleaning completed on 26.08.2013 L&T 8/25/2013

4 Painting of Primerprimer & 1st coat paint completed in control room & ground floor of admin

building.exrenal painting is in progress.L&T

23-08-13 to

26-08-13

5 False flooring fixing To be done after the MCS Panel & Cable Termination L&T

6 Doors Shutters fixing In progress L&T24-08-13 to

26-08-13

7 Sanitary works Sensor materials yet to receive L&T 8/31/2013

8 RCC hume pipeTo excavate & lay RCC hume pipes for Soak pit to Septic tank connection. Activityyet to start.

L&T20-08-13 to31-08-13

9 Epoxy flooring in battery room

Hold due to revised drawing required for UPS & battery location. Vendor visited

(Sika India Product) site on 24-08-13. Materials will reach to site 10 days after

placing order by L&T.

Technip/L&T26-08-13 to

31-08-13

10 Hand rails Materials yet to receive at site L&T26-08-13 to

31-08-13

11 Final painting Will be done at last L&T 5/9/2013

12 Overhead Tank

ONGC asked L&T to procure 5000 L capacity Sintex tank compatible with

structural arrangement. This is an additional item and to be procured on cost plus

basis.

L&T/Technip24-08-13 to

28-08-13L&T to take action.

Admin. Building-First

floor (Civil)

1 Gypsum partition Work in progress L&T 31/08/2013

2 Flase ceiling Tiles fixing is in progress,duct to be provided in revised conference room. L&T 31/08/2013

3 Wooden shutters In progress. L&T24-08-13 to

31-08-13

4 Aluminum doors fixing Materials recived at site,manpower not available L&T01-09-13 to

05-09-13

DAILY SITE PROGRESS REVIEW MEETING HELD AT ONGC SITE OFFICE, ODALAREVU DATED 10th September 2013 AMONG ONGC, DNV AND L&T REGARDING COMPLETION OF

BALANCE WORKS FOR EARLY PRODUCTION (G1-11), ODALAREVU.

ONGC L&T

Mr. PavanMr. B.R.V.P.PrasadMr. R.Reddy

ONGC

Page 1 of  3DNV L&T

7/27/2019 Daily Progress Review for 10-09-2013

http://slidepdf.com/reader/full/daily-progress-review-for-10-09-2013 2/3

Sno Issue/Discipline Deliberation Action byCompletion

ScheduleRemarks

5 Painting of Primer Application of primer coat & 1st coat is completed L&T 9/10/2013

6 Plumbing & Sanitary Sensor materials yet to receive L&T 31/08/2013

7 External painting 1st coat painting is completed. L&T 5/9/2013

8 Vinyl flooring To be done at the end L&T 14/09/2013

II. Admin. Building (E&I)

1 Panel Erection Erection completed for all panels. L&T 31/08/2013

2

Deputation of Honey well

representative for panel Termination ONGC to decide,as commissioning of 1 hvac unit is completed. ONGC 31/08/2013 After commissioning of HVAC

3 Panel Cable Termination Panel Cable termination is in progress. L&T 11/9/2013

4 Smoke detectors at Ground floor Fixing of smoke detectors at ground floor is completed. L&T 26/08/2013

5 Light fittings at first floor After the false ceiling work L&T06-09-13 to

10-09-13In Progress

7 Methanol pumps Tray To be done L&T 8/27/2013 In Progress

8 EJB-Umbilical area Junction box identification & relocation to be done near Umbillical area L&T

9 Mod bus Cable procurement L&T submitted proposal to ONGC regarding the procurement on 23-08-13 L&T To be received from L&T's other site

10 Temporary Power supplyPower cable connection in DG building & Switch gear building for Temporary

power arrangement for 750 KVA DG is in progress.L&T 31/08/2013

III. Mechanical

Methanol Tank (TK-33)

1 Cutting & Grinding works completed L&T

2 welding & RT completed L&T21-08-13 to

24-08-13

3 Leak detected during testing, Hydrotest preparation is in progress. L&T25-08-13 to

28-08-13

4 Calibration, Strapping & dewatering-After hydrotesting of tank. L&T 30/08/2013

Piping

1 TK-33 Connecting piping In progress, fitup completed,welding to be done.PVSV-8030 not available. L&T27-08-13 to

06-09-13

2 Methanol unloading pumps pipingFlame proof pump not available at site,connecting piping is in progress,detailed

support drawing for piping is to be submitted by technipL&T

pipe support padestial will be ready on

29/08/2013

Modifications of Methanol tank (TK-

33)

ONGC

Page 2 of  3DNV L&T

7/27/2019 Daily Progress Review for 10-09-2013

http://slidepdf.com/reader/full/daily-progress-review-for-10-09-2013 3/3

Sno Issue/Discipline Deliberation Action byCompletion

ScheduleRemarks

3 PR-3 Piping In progress L&T 7/9/2013

4 Painting works In progress L&T 14/09/2013

Civil

1 Methanol unloading pump foundation Completed on 23-08-13 L&T 23/08/2013

2Box Culvert near Methanol unloading

pumpsCompleted on 06/09/2013 L&T 15/09/2013

HVAC-Admin bldg

Ground floor

1 Precision unit spares ETA didn’t confrim the date ETA Date to be confirm by ETA

2 Precision unit power for Testing 1 number unit tested & commissioned on 31/08/2013 L&T 28/08/2013Temporary power arranged,testing is in

progress.

3 Return air grill Material received on today 07/09/2013 11/9/2013

4Commissioning of precision unit

number 2

emerson techician not reported to site since defective parts have not supplied by

ETA.31/08/2013

Testing of 1 unit is completed,trial run is

going on, no document submitted by

ETA/EMERSON

5 Water line connection in HVAC room To be done L&T 28/08/2013

HVAC-Admin bldg First

floor

1 Roof Top unit plenum erection Erection completed,connection yet to do ETA 29/08/2013

2 Insulation of duct outside building yet to start.insulation manpower not available to site. ETA 4/9/2013

3 Fixing of droppers Work in progress ETA 8/9/2013

ONGC

Page 3 of  3DNV L&T