daily progress review for 10-09-2013
TRANSCRIPT
7/27/2019 Daily Progress Review for 10-09-2013
http://slidepdf.com/reader/full/daily-progress-review-for-10-09-2013 1/3
Attendees:DNV ETA
Shashank Mr.T.K.DattaMr. SK HaldarMr.SHOAIB AHMED KHA
Sno Issue/Discipline Deliberation Action byCompletion
ScheduleRemarks
I. Building Package
Admin. Building-Ground
floor (Civil)
1 False ceiling Completed
2 False flooring material received at site on 08/09/2013. L&T 8/24/2013
3 Cleaning of ground floor Vacuum cleaning completed on 26.08.2013 L&T 8/25/2013
4 Painting of Primerprimer & 1st coat paint completed in control room & ground floor of admin
building.exrenal painting is in progress.L&T
23-08-13 to
26-08-13
5 False flooring fixing To be done after the MCS Panel & Cable Termination L&T
6 Doors Shutters fixing In progress L&T24-08-13 to
26-08-13
7 Sanitary works Sensor materials yet to receive L&T 8/31/2013
8 RCC hume pipeTo excavate & lay RCC hume pipes for Soak pit to Septic tank connection. Activityyet to start.
L&T20-08-13 to31-08-13
9 Epoxy flooring in battery room
Hold due to revised drawing required for UPS & battery location. Vendor visited
(Sika India Product) site on 24-08-13. Materials will reach to site 10 days after
placing order by L&T.
Technip/L&T26-08-13 to
31-08-13
10 Hand rails Materials yet to receive at site L&T26-08-13 to
31-08-13
11 Final painting Will be done at last L&T 5/9/2013
12 Overhead Tank
ONGC asked L&T to procure 5000 L capacity Sintex tank compatible with
structural arrangement. This is an additional item and to be procured on cost plus
basis.
L&T/Technip24-08-13 to
28-08-13L&T to take action.
Admin. Building-First
floor (Civil)
1 Gypsum partition Work in progress L&T 31/08/2013
2 Flase ceiling Tiles fixing is in progress,duct to be provided in revised conference room. L&T 31/08/2013
3 Wooden shutters In progress. L&T24-08-13 to
31-08-13
4 Aluminum doors fixing Materials recived at site,manpower not available L&T01-09-13 to
05-09-13
DAILY SITE PROGRESS REVIEW MEETING HELD AT ONGC SITE OFFICE, ODALAREVU DATED 10th September 2013 AMONG ONGC, DNV AND L&T REGARDING COMPLETION OF
BALANCE WORKS FOR EARLY PRODUCTION (G1-11), ODALAREVU.
ONGC L&T
Mr. PavanMr. B.R.V.P.PrasadMr. R.Reddy
ONGC
Page 1 of 3DNV L&T
7/27/2019 Daily Progress Review for 10-09-2013
http://slidepdf.com/reader/full/daily-progress-review-for-10-09-2013 2/3
Sno Issue/Discipline Deliberation Action byCompletion
ScheduleRemarks
5 Painting of Primer Application of primer coat & 1st coat is completed L&T 9/10/2013
6 Plumbing & Sanitary Sensor materials yet to receive L&T 31/08/2013
7 External painting 1st coat painting is completed. L&T 5/9/2013
8 Vinyl flooring To be done at the end L&T 14/09/2013
II. Admin. Building (E&I)
1 Panel Erection Erection completed for all panels. L&T 31/08/2013
2
Deputation of Honey well
representative for panel Termination ONGC to decide,as commissioning of 1 hvac unit is completed. ONGC 31/08/2013 After commissioning of HVAC
3 Panel Cable Termination Panel Cable termination is in progress. L&T 11/9/2013
4 Smoke detectors at Ground floor Fixing of smoke detectors at ground floor is completed. L&T 26/08/2013
5 Light fittings at first floor After the false ceiling work L&T06-09-13 to
10-09-13In Progress
7 Methanol pumps Tray To be done L&T 8/27/2013 In Progress
8 EJB-Umbilical area Junction box identification & relocation to be done near Umbillical area L&T
9 Mod bus Cable procurement L&T submitted proposal to ONGC regarding the procurement on 23-08-13 L&T To be received from L&T's other site
10 Temporary Power supplyPower cable connection in DG building & Switch gear building for Temporary
power arrangement for 750 KVA DG is in progress.L&T 31/08/2013
III. Mechanical
Methanol Tank (TK-33)
1 Cutting & Grinding works completed L&T
2 welding & RT completed L&T21-08-13 to
24-08-13
3 Leak detected during testing, Hydrotest preparation is in progress. L&T25-08-13 to
28-08-13
4 Calibration, Strapping & dewatering-After hydrotesting of tank. L&T 30/08/2013
Piping
1 TK-33 Connecting piping In progress, fitup completed,welding to be done.PVSV-8030 not available. L&T27-08-13 to
06-09-13
2 Methanol unloading pumps pipingFlame proof pump not available at site,connecting piping is in progress,detailed
support drawing for piping is to be submitted by technipL&T
pipe support padestial will be ready on
29/08/2013
Modifications of Methanol tank (TK-
33)
ONGC
Page 2 of 3DNV L&T
7/27/2019 Daily Progress Review for 10-09-2013
http://slidepdf.com/reader/full/daily-progress-review-for-10-09-2013 3/3
Sno Issue/Discipline Deliberation Action byCompletion
ScheduleRemarks
3 PR-3 Piping In progress L&T 7/9/2013
4 Painting works In progress L&T 14/09/2013
Civil
1 Methanol unloading pump foundation Completed on 23-08-13 L&T 23/08/2013
2Box Culvert near Methanol unloading
pumpsCompleted on 06/09/2013 L&T 15/09/2013
HVAC-Admin bldg
Ground floor
1 Precision unit spares ETA didn’t confrim the date ETA Date to be confirm by ETA
2 Precision unit power for Testing 1 number unit tested & commissioned on 31/08/2013 L&T 28/08/2013Temporary power arranged,testing is in
progress.
3 Return air grill Material received on today 07/09/2013 11/9/2013
4Commissioning of precision unit
number 2
emerson techician not reported to site since defective parts have not supplied by
ETA.31/08/2013
Testing of 1 unit is completed,trial run is
going on, no document submitted by
ETA/EMERSON
5 Water line connection in HVAC room To be done L&T 28/08/2013
HVAC-Admin bldg First
floor
1 Roof Top unit plenum erection Erection completed,connection yet to do ETA 29/08/2013
2 Insulation of duct outside building yet to start.insulation manpower not available to site. ETA 4/9/2013
3 Fixing of droppers Work in progress ETA 8/9/2013
ONGC
Page 3 of 3DNV L&T