daily program feb-2012
TRANSCRIPT
-
8/13/2019 Daily Program Feb-2012
1/38
S.l.
No.Description Work Program of January 1,2012 Achievement of December 31,2011 Rem
300mm (16No) pipe Installation
Base CC (15rm) Side CC (30 rm)
CC casting of 2 nos gully hole and 1 no manhole
Singles Laying 2nd layer(520mm thick) / Ch 78-137
Singles Laying 1st layer(520mm thick)/Ch 78-137
Rebar fabrication of longitudinal sleepers (Ch 0-
78)
Rebar fabrication of longitudinal sleepers(Ch 0-78)
in progress
3 Pre-cast pile driving(Seg-1A) Identify pile for load testAll materials of load test reached at site and preparation
in progress
4 Segment 2A Settlement Record Settlement Record in progress for 70th day
Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)
Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
300mm sand blanket laying 300mm sand blanket laying in progress
Back filling at Navy gate Back filling at Navy gate in progress
Earth excavation (CH 1000-1040) Earth excavation (CH 1000-1040) in progress
Wall casting at Navy gate (Ch 1100-1125) /3rd lift
/yard side Rebar fabrication executed
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-400)
Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress
9 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
10 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress
11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress
12 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)
13 RCC Drainage Pipe Concrete pouring(500mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)
14 PDB Relocation Old pole removing Old pole removing in progress
15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 1,2012
Segment 15
Yard Drainage(Seg-1A)1
RMG (Seg-1A)2
6
Rail Relocation8
Segment-2
Open Deep Drain7
-
8/13/2019 Daily Program Feb-2012
2/38
S.l.
No.Description Work Program of January 2,2012 Achievement of January 1,2011 Remarks
CC Casting of Cable trench. Base CC (15rm)
CC Casting of 1 no manhole. CC casting of 2 nos gully hole
Singles Laying 2nd layer(520mm thick) / Ch 78-
137
Singles Laying 2nd layer(520mm thick) / Ch 78-137
in progress
Rebar fabrication of longitudinal sleepers (Ch 0-
78)
Rebar fabrication of longitudinal sleepers(Ch 0-78)
in progress
3 Pre-cast pile driving(Seg-1A) Preparation of load test Preparation of load test in progress
4 Segment 2A Settlement Record Settlement Record in progress for 71th day
Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)
Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
300mm sand blanket laying 300mm sand blanket laying in progress
Back filling at Navy gate Back filling at Navy gate in progress
CC Casting (CH 1000-1040) Earth excavation finished (CH 1000-1040)
Earth Excavation (Ch 1125-1140)Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard
side
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600)
9 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
10 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress
11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress
12 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)
13 RCC Drainage Pipe Concrete pouring(800mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)
14 PDB Relocation Old pole removing Old pole removing in progress
15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,000 Nos)
17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
6
Rail Relocation8
Segment-2
Open Deep Drain7
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 2,2012
Segment 15
1
RMG (Seg-1A)2
-
8/13/2019 Daily Program Feb-2012
3/38
S.l.
No.Description Work Program of January 3,2012 Achievement of January 2,2011 Remarks
Base CC (15rm) Earth excavation (15rm)Singles Laying 2nd layer(520mm thick) / Ch 78-
137
Singles Laying 2nd layer(520mm thick) / Ch 78-137
in progress
Rebar fabrication of longitudinal sleepers (Ch 0-
78)
Rebar fabrication of longitudinal sleepers(Ch 0-78)
in progress
3 Pre-cast pile driving(Seg-1A) Preparation of load test Preparation of load test in progress
4 Cable Trench (Seg-1A) CC Casting Earth Excavation executed.
5 Segment 2A Settlement Record Settlement Record in progress for 72th day
Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)
Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
300mm sand blanket laying 300mm sand blanket laying in progress
Back filling at Navy gate Back filling at Navy gate in progress
Rebar fabrication of Base (CH 1000-1040) CC Casting (CH 1000-1040)
Earth Excavation (Ch 1125-1140)Wall casting at Navy gate (Ch 1100-1125) /3rd lift /yard
side
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing(Ch 0-600) Sleepers & Rail bit fixing in progress(Ch 0-600)
10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
11 Electric Sub station Shuttering of slab (2nd portion) Shuttering of slab (2nd portion) in progress
12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress
13 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)
14 RCC Drainage Pipe Concrete pouring(800mm=05 Nos)) Concrete Pouring (500mm dia=05Nos)
15 PDB Relocation Old pole removing Old pole removing in progress
16 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
17 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,200 Nos)
18 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 3,2012
Segment 16
Yard Drainage1
RMG (Seg-1A)2
7
Rail Relocation9
Segment-2
Open Deep Drain8
-
8/13/2019 Daily Program Feb-2012
4/38
S.l.
No.Description Work Program of January 4,2012 Achievement of January 3,2011 Remarks
Side CC (30rm) Base CC executed (30rm)
Pipe Installation 30 rm(300mm dia)
Wall casting of 01 No Manhole Base Casting of 02 Nos Gully hole & 01 No Manhole
Ballast Laying (300mm thick) / Ch 78-137Singles Laying 2nd layer(520mm thick) / Ch 78-137
finished
Rebar fabrication of longitudinal sleepers (Ch 0-
78)
Rebar fabrication of longitudinal sleepers(Ch 0-78)
in progress
3 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sand bagging for load test in progress
4 Cable Trench (Seg-1A) CC Casting Earth Excavation executed.5 Segment 2A Settlement Record Settlement Record in progress for 73th day
Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)
Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)
Pre-cast Bracing installation
Clearing & Grubbing Clearing & Grubbing in progress
300mm sand blanket laying 300mm sand blanket laying in progress(500 sqm)
Back filling at Navy gate Back filling at Navy gate in progressBase casting (CH 1000-1040) Rebar fabrication of Base (CH 1000-1040)
Bracing fixing (6rm)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
11 Electric Sub station Shuttering & Rebar binding of slab (2nd portion)Shuttering & Rebar binding of slab (2nd portion) in
progress
12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress
13 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)
14 RCC Drainage Pipe Concrete pouring(800mm=03 Nos,900mm=02 Nos) Concrete Pouring (800mm=03Nos & 900mm=02 Nos)
15 PDB Relocation Old pole removing Old pole removing in progress
16 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
17 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=10,500 Nos)
18 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
7
Rail Relocation9
Segment-2
Open Deep Drain8
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 4,2012
Segment 16
RMG (Seg-1A)2
Yard Drainage1
-
8/13/2019 Daily Program Feb-2012
5/38
S.l.
No.Description Work Program of January 7,2012 Achievement of January 6,2011 Remarks
1 Yard DrainageBase Casting of 02 Nos Gully hole & 01 No Man
hole.
Rebar binding of Base (02 Nos Gully hole & 01 No Man
hole)
Shingles Laying (180mm thick) / Ch 78-137Ballast layer compaction (300mm thick) / Ch 78-
137 finished
Longitudinal sleeper casting (Ch 0-10)Rebar fabrication of longitudinal sleepers(Ch 0-10)
finished.
3 Pre-cast pile driving(Seg-1A) Sand bagging for load test Sand bagging for load test in progress
4 Sheet Pile Driving Preparation of Pile shifting to bank.
5 Cable Trench (Seg-1A) CC Casting CC Casting executed.
6 Segment 2A Settlement Record Settlement Record in progress for 77th day
Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)
Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
300mm sand blanket laying 300mm sand blanket laying in progress(500 sqm)
CC Casting (Outlet point) Soling executed.
Wall casting / Port side/1st lift (CH 1015-1040) Rebar fabrication executed (CH 1015-1040)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
11 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
12 Electric Sub station Shuttering & Rebar binding of slab (2nd portion)Shuttering & Rebar binding of slab (2nd portion) in
progress
13 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress
14 Transverse Sleeper Concrete pouring (10 Nos) Concrete pouring in progress(10Nos)
15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=10,500 Nos)
17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 7,2012
Segment 17
RMG (Seg-1A)2
8
Rail Relocation10
Segment-2
Open Deep Drain9
-
8/13/2019 Daily Program Feb-2012
6/38
S.l.
No.Description Work Program of January 9,2012 Achievement of January 8,2011
15 m Base CC casting (300mm) 15m Earth Excavation
Wall Casting of 03 Nos Gully hole . Rebar binding executed (wall of 03 Nos Gully hole)
Shingles Laying (180mm thick) / Ch 78-137Shingles Laying (180mm thick) / Ch 78-137 in
progress
Longitudinal sleeper casting (Ch 0-10)Rebar fabrication of longitudinal sleepers(Ch 0-10)
in progress.
3 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
4 Water Supply Line Leak test of 50m pipe (250mm dia) 50 m pipe welding completed (250mm dia)
5 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress
Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)
Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
PVD Driving FDD test executed at 300mm sand blanket
Wall casting / Navy side/2nd lift (CH 1015-1040) Wall casting / Port side/1st lift (CH 1015-1040)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
11 Electric Sub station Slab casting of 2nd portion executed
12 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress
13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,400 Nos)
15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA
7
Rail Relocation9
Segment-2
Open Deep Drain8
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 9,2012
Segment 16
RMG (Seg-1A)2
Yard Drainage(Seg-1A)1
-
8/13/2019 Daily Program Feb-2012
7/38
Remarks
Assistant Engineer
NCT Back-up/CPA
-
8/13/2019 Daily Program Feb-2012
8/38
S.l.
No.Description Work Program of January 10,2012 Achievement of January 9,2011
300mm Pipe installation(15rm) 15 m Base CC casting executed.
Wall Casting of 03 Nos Gully hole and base casting
of 02 Nos Gully hole.Wall Casting of 03 Nos Gully hole executed
Rolling of Shingles Layer (180mm thick) / Ch 78-
137Shingles Laying (180mm thick) / Ch 78-137 finished
Rebar fabrication of longitudinal sleepers(Ch 0-
10) in progress.
Rebar fabrication of longitudinal sleepers(Ch 0-10)
in progress.
3 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
4 Water Supply Line Leak test of 50m pipe (250mm dia) 50 m pipe welding completed (250mm dia)
5 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress
Sand bagging for preloading work (2000 Nos) Sand bagging of preloading work in progress (1200 Nos)
Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
PVD Driving PVD Driving in progress
Earth Excavation (CH 1040-1060)
Wall casting / Yard side/2nd lift (CH 1015-1040) Wall casting / Navy side/2nd lift (CH 1015-1040)executed.
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
10 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
11 Sheet Pile Concrete pouring of Sheet Pile(01 Nos) Concrete pouring of Sheet Pile(01 Nos) in progress
12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=11,300 Nos)
14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 10,2012
Segment 16
RMG (Seg-1A)2
Yard Drainage(Seg-1A)1
7
Rail Relocation9
Segment-2
Open Deep Drain8
-
8/13/2019 Daily Program Feb-2012
9/38
Remarks
Assistant Engineer
NCT Back-up/CPA
-
8/13/2019 Daily Program Feb-2012
10/38
S.l.
No.Description Work Program of January 14,2012 Achievement of January 13,2011
1 Yard Drainage(Seg-1A) Side CC Casting/30rm/300mm dia pipe Shuttering executed
2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-
30) in progress.
Rebar fabrication of longitudinal sleepers(Ch 20-30)
in progress.
3 Seg-1A(mosque portion) Soling work Soling work in progress
4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm
dia
Painting of Pipe & wrapping by Polythene/250mm dia in
progress.
6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress
7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (40,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
PVD Driving PVD Driving in progress
Base Casting (CH 985-1015) Rebar binding executed.
Wall casting / Yard side/2nd lift (CH 1015-1040) Rebar binding executed.
Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (02 Nos) in progress
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
11 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,300 Nos)
14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 14,2012
8
Rail Relocation10
Segment-2
Open Deep Drain9
-
8/13/2019 Daily Program Feb-2012
11/38
Remarks
Assistant EngineerNCT Back-up/CPA
-
8/13/2019 Daily Program Feb-2012
12/38
S.l.
No.Description Work Program of January 15,2012 Achievement of January 14,2011
Side CC Casting/30rm/300mm dia pipe Shuttering executed
Wall casting of 03 Nos Gully hole and 01 No Man
holeShuttering executed
2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-
30) in progress.
Rebar fabrication of longitudinal sleepers(Ch 20-30)
in progress.
3 Seg-1A(mosque portion) Soling work Soling work in progress
4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm
dia
Painting of Pipe & wrapping by Polythene/250mm dia in
progress.6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress
7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
PVD Driving PVD Driving in progress
Base Casting (CH 1000-1015) Base Casting (CH 985-1000)
Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (06 Nos) in progress
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
11 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Rebar fabrication and Shuttering executed.
12 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,200 Nos)
15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 15,2012
8
Rail Relocation10
Segment-2
Open Deep Drain9
Yard Drainage(Seg-1A)1
-
8/13/2019 Daily Program Feb-2012
13/38
Remarks
Assistant Engineer
NCT Back-up/CPA
-
8/13/2019 Daily Program Feb-2012
14/38
S.l.
No. Description Work Program of January 16,2012 Achievement of January 15,2011 Remarks
Side CC Casting/30rm/300mm dia pipe
Wall casting of 01 No Gully hole and 01 No Man
holeWall casting of 02 Nos Gully hole and 01 No Man hole .
2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-
30) in progress.
Rebar fabrication of longitudinal sleepers(Ch 20-30)
in progress.
3 Seg-1A(mosque portion) Soling work Soling work in progress
4 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
5 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm
dia
Painting of Pipe & wrapping by Polythene/250mm dia in
progress.
6 Cable Trench (Seg-1A) Brick masonry of wall Brick masonry of wall in progress
7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
PVD Driving PVD Driving in progress
Wall casting 1st lift(CH 985-1015) Base Casting (CH 1000-1015)
Pre-cast Bracing Casting (06 Nos)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit f ixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
11 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Rebar fabrication and Shuttering executed.
12 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
14 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=13,600 Nos)
15 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 16,2012
1 Yard Drainage(Seg-1A)
9 Open Deep Drain
10 Rail Relocation
8 Segment-2
-
8/13/2019 Daily Program Feb-2012
15/38
S.l.
No.Description Work Program of January 17,2012 Achievement of January 16,2011 Remarks
02 Nos 300mm dia pipe,01 No 700mm dia pipe
fixing.
Shuttering & Rebar fabrication of 02 Nos Gully hole. Wall casting of 01 No Gully hole and 01 No Man hole
2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 20-
30) in progress.
Rebar fabrication of longitudinal sleepers(Ch 20-30)
in progress.
3 Seg-1A(mosque portion) Sand filling & Soling work Sand filling & Soling work in progress
4 Sub-station Building Plaster work Plaster work in progress.
5 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
6 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm
dia
Painting of Pipe & wrapping by Polythene/250mm dia in
progress.
7 Cable Trench (Seg-1A) Plastering of wall.
8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)
9 Segment-2 Clearing & Grubbing Clearing & Grubbing in progress
Soling & CC work (CH 1015-1030) Earth Excavation executed.
Wall casting 1st lift(CH 985-1015) Shuttering & Rebar fabrication executed.
Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (06 Nos)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bi t fixing in progress (Ch 0-600)
12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting (10 Nos) in progress.
13 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
15 Interlocking Block ILB production (Quantity=13000 Nos) ILB production in progress (Quantity=12,250 Nos)
16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 17,2012
1 Yard Drainage(Seg-1A)
11 Rail Relocation
Open Deep Drain10
-
8/13/2019 Daily Program Feb-2012
16/38
S.l. No. Description Work Program of January 18,2012 Achievement of January 17,2011 Remarks
Side CC Casting of 10rm 02 Nos 300mm dia pipe,01 No 700mm dia pipe fixing.
Shuttering & Rebar fabrication of 02 Nos Gully hole.Shuttering & Rebar fabrication of 02 Nos Gully hole and
02 Nos Manhole.
2 RMG Track(Seg-1A)Rebar fabrication of longitudinal sleepers(Ch 30-
40) in progress.
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
3 Seg-1A(mosque portion) Sand filling & Soling work Sand filling & Soling work in progress
4 Sub-station Building Plaster work Plaster work in progress.
5 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
6 Water Supply Line/Seg-1A Painting of Pipe & wrapping by Polythene./250mmdia
Painting of Pipe & wrapping by Polythene/250mm dia inprogress.
7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress
8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
150mm local sand laying 150mm local sand laying in progress
200mm sand blanket laying 200mm sand blanket laying in progress
Rebar fabrication of Base (CH 1015-1030) Soling & CC work (CH 1015-1030)
Rebar fabrication of Wall 1st l ift(CH 985-1015)/Navyside.
Wall casting 1st lift(CH 985-1015)/Yard Side
Pre-cast Bracing Casting (06 Nos) Pre-cast Bracing Casting (05 Nos)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bi t fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.
13 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
15 Interlocking Block ILB production (Quantity=13000 Nos)
16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 18,2012
1 Yard Drainage(Seg-1A)
Segment-29
11 Rail Relocation
Open Deep Drain10
-
8/13/2019 Daily Program Feb-2012
17/38
S.l. No. Description Work Program of January 20,2012 Achievement of January 19,2011 Remarks
Rebar fabrication of 03 Nos Gully hole
Wall Shuttering of 02 Nos Man hole Wall casting of 02 Nos Gully hole
Rebar fabrication of longitudinal sleepers(Ch 30-
40) in progress.
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
Pre-cast sleepers shifting to Seg-1
3 Seg-1A(mosque portion) Soling work Soling work in progress
4 Service Area Sub-base material laying Bed preparation finished
5 Sub-station Building Plaster work & Parapet shuttering Plaster work & Parapet casting in progress.
6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
7 Water Supply Line/Seg-1APainting of Pipe & wrapping by Polythene./250mm
dia
Painting of Pipe & wrapping by Polythene/250mm dia in
progress.
8 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress
9 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
150mm local sand laying 150mm local sand laying in progress
200mm sand blanket laying 200mm sand blanket laying in progress
Shuttering of wall (CH 1015-1030) Base casting (CH 970-990)
Back filling(CH 990-1015)/Navy side. Wall casting 1st li ft(CH 990-1015)/Navy Side
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rai l bit fixing in progress (Ch 0-600)
13 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.
14 Road Type-1 Sub base material placement (2nd layer) Sub base material placement (2nd layer) in progress
15 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
16 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=11000 Nos)
17 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-210
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 20,2012
1 Yard Drainage(Seg-1A)
12 Rail Relocation
Open Deep Drain11
RMG Track(Seg-1A)2
-
8/13/2019 Daily Program Feb-2012
18/38
S.l. No. Description Work Program of January 21,2012 Achievement of January 20,2011 Remarks
Rebar fabrication of 03 Nos Gully hole Rebar fabrication of 03 Nos Gully hole in progress
Wall Shuttering of 02 Nos Man hole Wall Shuttering of 02 Nos Man hole in progress
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress
3 Seg-1A(mosque portion) Rebar binding of raft foundation. Soling work finished.
4 Service Area Sub-base material compaction. Sub-base material laying finished.
5 Sub-station Building Plaster work & Parapet casting. Plaster work & Parapet shuttering.
6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress
8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
PVD Driving 300mm sand blanket compaction finished.
200mm sand blanket laying 200mm sand blanket laying in progress
Wall casting 2nd lift (CH 990-1015)/Navy Side Earth excavation (CH 950-970)
Soling & CC (CH 950-970)/Navy side. Back filling(CH 990-1015)/Navy side.
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rai l bit f ixing (Ch 0-600) Sleepers & Rail bit f ixing in progress (Ch 0-600)
12 Pre-cast Sleepers Pre-cast Sleepers casting (10 Nos) Shuttering & Rebar fabrication executed.
13 Road Type-1 Field density test of sub-base. Sub base material placement (2nd layer) finished.
14 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
15 Interlocking Block ILB production (Quanti ty=13000 Nos) ILB production (Quantity=12000 Nos)
16 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 21,2012
1 Yard Drainage(Seg-1A)
RMG Track(Seg-1A)2
Segment-29
11 Rail Relocation
Open Deep Drain10
-
8/13/2019 Daily Program Feb-2012
19/38
S.l. No. Description Work Program of January 22,2012 Achievement of January 21,2011 Remarks
1 Yard Drainage (Seg 1A) Man hole wall casting (01 No) Man hole wall casting (01 No)
Concrete Pouring (CH 0-20)
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
Pre-cast sleepers shifting to Seg-1 Pre-cast sleepers shifting to Seg-1 in progress
3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.
4 Service Area Sub-base material compaction. Sub-base material laying finished.
5 Sub-station Building Plaster work . Plaster work & Parapet casting.
6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress
8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
200mm sand blanket laying 200mm sand blanket laying in progress
Wall casting 2nd lift (CH 990-1015)/Yard Side Wall casting 2nd lift (CH 990-1015)/Navy Side
CC (CH 950-970) Soling (CH 950-970)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rai l bit f ixing (Ch 0-600) Sleepers & Rail bit f ixing in progress (Ch 0-600)
12 Laboratory / Field Test Regular Test (ILB/Cylinder) Trial Mix design (40 Mpa)
13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=11500 Nos)
14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 22,2012
11 Rail Relocation
Open Deep Drain10
RMG Track(Seg-1A)2
Segment-29
-
8/13/2019 Daily Program Feb-2012
20/38
S.l. No. Description Work Program of January 23,2012 Achievement of January 22,2011 Remarks
1 Yard Drainage (Seg 1A) Man hole wall casting (01 No) Shuttering executed.
Rebar fabrication of longitudinal sleepers(Ch 30-
40) in progress.
Concrete Pouring (CH 0-10)
3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.
4 Service Area Sub-base material laying Sub-base material laying in progress
5 Sub-station Building Plaster work . Plaster work in progress
6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
7 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress
8 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (30,000cft)
Clearing & Grubbing Clearing & Grubbing in progress
200mm sand blanket laying 200mm sand blanket laying in progress
Wall casting 1st lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Navy Side
Earth Excavation (CH 935-950) Soling & CC (CH 950-970)
Ballast mixing & laying(Ch 0-600) Ballast mixing & laying in progress (Ch 0-600)
Sleepers & Rail bit fixing (Ch 0-600) Sleepers & Rail bit fixing in progress (Ch 0-600)
12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=10500 Nos)
14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 23,2012
11 Rail Relocation
Open Deep Drain10
RMG Track(Seg-1A)2
Segment-29
-
8/13/2019 Daily Program Feb-2012
21/38
S.l. No. Description Work Program of January 24,2012 Achievement of January 23,2011 Remarks
1 Yard Drainage (Seg 1A) Man hole wall casting (01 No)
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.3 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.
4 Service Area Sub-base material laying & compaction Sub-base material laying & compaction in progress
5 Sub-station Building Plaster work . Plaster work in progress
6 Segment-2A Surcharge Removing Surcharge Removing in progress.
7 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
8 Cable Trench (Seg-1A) Plastering of wall. Plastering of wall in progress
9 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (40,000cft)
PVD Driving
200mm sand blanket laying 200mm sand blanket laying in progress
Wall casting 2nd lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Yard Side
Earth Excavation (CH 935-950) Earth Excavation (CH 935-950) In progress
Bracing fixing (06 Nos)
12 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
13 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quanti ty=13200 Nos)
14 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 24,2012
RMG Track(Seg-1A)2
Segment-210
Open Deep Drain11
NCT BACK UP PROJECT CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
22/38
S.l.
No.Description Work Program of January 25,2012 Achievement of January 24,2011 Remarks
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
2 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.
3 Service Area Sub-base material compaction Sub-base material laying finished.
4 Sub-station Building Plaster work . Plaster work in progress
5 Segment-2A Surcharge Removing Surcharge Removing in progress.
6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
PVD Driving PVD Driving in progress.
150mm local sand laying. 150mm local sand laying in progress.
Wall casting 2nd lift (CH 970-990)/Yard Side Wall casting 1st lift (CH 970-990)/Yard Side
CC ,Soling (CH 935-950) Earth Excavation (CH 935-950)
Bracing fixing (06 Nos)
10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
11 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=13000 Nos)
12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 25,2012
RMG Track(Seg-1A)1
Segment-28
Open Deep Drain9
NCT BACK UP PROJECT CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
23/38
S.l.
No.Description Work Program of January 26,2012 Achievement of January 25,2011 Remarks
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
2 Seg-1A(mosque portion) Rebar binding of raft foundation. Rebar binding of raft foundation in progress.
3 Service Area Lean concrete casting
4 Sub-station Building Bricks masonry work
5 Segment-2A Surcharge Removing Surcharge Removing in progress.
6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (42,000cft)8 Segment-2 150mm local sand laying. 150mm local sand laying in progress.
Wall casting 2nd lift (CH 970-990)/Yard Side
Rebar binding of Base (CH 935-970) CC ,Soling (CH 935-950)
10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
11 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=14200 Nos)
12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of January 26,2012
RMG Track(Seg-1A)1
Open Deep Drain9
NCT BACK-UP PROJECT CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
24/38
S.l.
No.Description Work Program of January 30,2012 Achievement of January 29,2011 Remarks
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
2 Yard Drainage Base casting of 03 Nos Gully holes & wallcasting of 01 No Manhole.
Rebar fabrication and shuttering executed.
3 Sub-station Building Bricks masonry work Bricks masonry work in progress.
FDD Test of 150mm local sand layer
FDD Test of 200mm sand blanket layer
5 Segment-2A Surcharge Removing Surcharge Removing in progress.
6 Sheet Pile Driving Pile shifting to bank. Pile shifting to bank in progress
7 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (45,000cft)
Wall casting 1st lift (CH 955-970)/Navy Side Wall casting 1st lift (CH 935-955)/Navy Side
9 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
10 Interlocking Block ILB production (Quantity=13000 Nos) ILB production (Quantity=14200 Nos)
11 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
NCT BACK UP PROJECT, CHITTAGONG
Work Program of January 30,2012
RMG Track(Seg-1A)1
Open Deep Drain8
Segment-24
NCT BACK-UP PROJECT, CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
25/38
S.l.
No.Description Work Program of February1,2012 Achievement of January 31,2011 Remarks
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
2 Yard Drainage Net cement finishing of Gully hole.
Bricks masonry work Bricks masonry work in progress.
Bricks masonry work of Safety Tank. Bricks masonry work of Safety Tank in progress.
Settlement plate fixing (08 Nos)
300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion in
progress.
5 Segment-2A Surcharge Removing Surcharge Removing in progress.(70,000 cft)
6 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
7 Road Type-1 Sub-base work
Wall casting 1st l if t (CH 935-955)/Yard Side Wall casting 1st l if t (CH 955-970)/Yard Side
9 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
10 Interlocking Block ILB production (Quantity=15000 Nos) ILB production (Quantity=14,500 Nos)
11 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
C C U OJ C , C GO G
Work Program of February 1,2012
RMG Track(Seg-1A)1
Open Deep Drain8
Segment-24
Sub-station Building3
NCT BACK-UP PROJECT, CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
26/38
S.l.
No.Description Work Program of February 2,2012 Achievement of February 1,2011 Remarks
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
2 Yard Drainage Net cement finishing of Gully hole. Net cement finishing of Gully hole in progress.
Bricks masonry work Bricks masonry work in progress.
Bricks masonry work of Safety Tank. Bricks masonry work of Safety Tank in progress.
Settlement plate fixing (08 Nos)
300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion in
progress.
5 Segment-2A Surcharge Removing Surcharge Removing in progress.(70,000 cft)
6 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (35,000cft)
7 Rail Relocation Sub-base work at Navy area (CH 620-820)
8 Road Type-1 Sub-base work Sub-base work in progress
Wall casting 2nd lift (CH 950-970)/Navy Side Wall casting 1st lift (CH 935-955)/Yard Side
10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
11 Interlocking Block ILB production (Quantity=15000 Nos) ILB production (Quantity=12,500 Nos)
12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Sub-station Building3
Work Program of February 2,2012
RMG Track(Seg-1A)1
Open Deep Drain9
Segment-24
NCT BACK-UP PROJECT, CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
27/38
S.l.
No.Description Work Program of February 4,2012 Achievement of February 3,2011 Remarks
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
Net cement finishing of Gully hole. Base casting of 01 Nos Gully hole & 01 No Manhole
Wall casting of 02 Nos Gully hole.
Bricks masonry work Bricks masonry work in progress.
Bricks masonry work of Safety Tank. Bricks masonry work of Safety Tank in progress.
Base casting of fuel tank.
Sunshade Casting Sunshade Casting in progress.
300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion in
progress.
5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)
6 Segment-1 Surcharge material placement (50,000 cft) Surcharge material placement in progress (50,000cft)
Commissioning of Relocated Line. Rail fixing at Navy area (CH 620-820) finished.
8 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.
Wall casting 3rd lift (CH 950-970)/Navy Side Wall casting 3rd lift (CH 925-950)/Navy Side
Bracing fixing (near sub-station)
10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
11 Interlocking Block ILB production (Quantity=15000 Nos) ILB production (Quantity=13,500 Nos)
12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Work Program of February 4,2012
RMG Track(Seg-1A)1
Segment-24
Yard Drainage2
Rail Relocation7
Sub-station Building3
Open Deep Drain9
NCT BACK-UP PROJECT, CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
28/38
S.l.
No.Description Work Program of February 6,2012 Achievement of February 5,2011 Remarks
Rebar fabrication of longitudinal sleepers(Ch 30-
40) .
Rebar fabrication of longitudinal sleepers(Ch 30-40)
in progress.
Net cement finishing of Gully hole.
Base CC Casting of 300 mm dia pipe (40rm) Earth excavation & Levelling.
Bricks masonry work & Plastering of Wall.Bricks masonry work & Plastering of Wall in
progress.
Rebar fabrication & Shuttering of slab of septic
tank.Bricks masonry work & Plastering completed.
Base casting of Fuel tank.
Sunshade Casting Sunshade Casting in progress.
300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion in
progress.
5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)
6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (60,000cft)
Commissioning of Relocated Line. Rail fixing at Navy area (CH 620-820) finished.
8 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.
Wall casting 3rd lift (CH 950-970)/Navy Side Wall casting 3rd lift (CH 925-950)/Navy Side.
Bracing fixing (near sub-station)
10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
11 Interlocking Block ILB production (Quantity=15000 Nos) ILB production (Quantity=13,500 Nos)
12 Dismantling work CC Dismantling (Seg-2) CC Dismantling(Seg-2) in progress
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Rail Relocation7
Sub-station Building3
Open Deep Drain9
Work Program of February 6,2012
RMG Track(Seg-1A)1
Segment-24
Yard Drainage2
NCT BACK-UP PROJECT, CHITTAGONG
-
8/13/2019 Daily Program Feb-2012
29/38
S.l.
No.Description Work Program of February 8,2012 Achievement of February 7,2011 Remarks
Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting (10 Nos)
Side CC ,40rm(300mm dia pipe) Base CC,40rm
Bricks masonry work & Plastering of Wall.Bricks masonry work & Plastering of Wall in
progress.
Slab Casting of Septic tank
Base casting of Fuel tank
Sunshade Casting Sunshade Casting in progress.
300 mm sand blanket laying at remaining portion.300 mm sand blanket laying at remaining portion in
progress.
5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)
6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (60,000cft)
Old line removal
8 Boundar Wall Bricks masonry work near sub-station
9 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.
Wall casting 3rd lift (CH 970-990)/Navy Side Wall casting 3rd lift (CH 950-970)/Navy Side
Bracing fixing (near sub-station)
11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
12 Interlocking Block ILB production ILB production in progress.
13 Dismantling work Navy gate.
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Work Program of February 8,2012
RMG Track(Seg-1A)1
Segment-24
Yard Drainage2
Rail Relocation7
Sub-station Building3
Open Deep Drain10
NCT BACK-UP PROJECT, CHITTAGONG
W k P f F b 9 2012
-
8/13/2019 Daily Program Feb-2012
30/38
S.l.
No.Description Work Program of February 9,2012 Achievement of February 8,2011 Remarks
Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting in progress (10 Nos)
Side CC ,40rm(300mm dia pipe) Pipe fixing executed.
Bricks masonry work & Plastering of Wall.Bricks masonry work & Plastering of Wall in
progress.
Sunshade Casting Sunshade Casting in progress.
300 mm sand blanket laying. 300 mm sand blanket laying in progress.
5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)
6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (70,000cft)
Old line removal Old line removal in progress.
8 Boundar Wall Bricks masonry work near sub-station Bricks masonry work near sub-station in progress.
9 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.
Wall casting 3rd lift (CH 970-990)/Navy Side
Bracing fixing (near sub-station)
11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
12 Interlocking Block ILB production ILB production in progress.(10,000 Nos)
13 Dismantling work Dismantling work at Navy gate. Dismantling work at Navy gate in progress.
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Rail Relocation7
Sub-station Building3
Open Deep Drain10
Work Program of February 9,2012
RMG Track(Seg-1A)1
Segment-24
Yard Drainage2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of Febr ar 11 2012
-
8/13/2019 Daily Program Feb-2012
31/38
S.l.
No.Description Work Program of February 11,2012 Achievement of February 10,2011 Remarks
Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting in progress (10 Nos)
Side CC ,40rm(300mm dia pipe) Pipe fixing executed.
CC Castng of 2 Nos Gullyhole & 01 No Manhole.
Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
Sunshade Casting Sunshade Casting in progress.
4 Sub-base work (Seg-1A) Water spraying & Rolling Shingles laying (200mm)
5 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)
6 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (70,000cft)
Old line removal Old line removal in progress.
8 Boundar Wall Plastering of wall near sub-station Bricks masonry work finished near sub-station .
9 Road Type-2 Improved Sub-grade & Sub-base work Improved Sub-grade & Sub-base work in progress.
Wall casting 3rd lift (CH 990-1010)/Navy Side Wall casting 3rd lift (CH 990-1010)/Navy Side
Bracing fixing (near sub-station)
11 Laboratory / Field Test FDD test of 300 mm sand blanket at Seg-2 Regular Test (ILB/Cylinder)
12 Interlocking Block ILB production ILB production in progress.(10,000 Nos)
13 Dismantling work Dismantling work at Navy gate. Dismantling work at Navy gate in progress.
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Sub-station Building3
Open Deep Drain10
Rail Relocation7
Work Program of February 11,2012
RMG Track(Seg-1A)1
Yard Drainage2
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of February 12 2012
-
8/13/2019 Daily Program Feb-2012
32/38
S.l.
No.Description Work Program of February 12,2012 Achievement of February 11,2011 Remarks
Pre-cast Sleepers casting (10 Nos) Pre-cast Sleepers casting in progress (10 Nos)
Wall casting of 01 No Manhole Side CC ,40rm(300mm dia pipe)
CC Castng of 2 Nos Gullyhole
Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
Sunshade Casting Sunshade Casting in progress.
4 Sub-base work (Seg-1A) Water spraying & Rolling Shingles laying (200mm)
5 Service Area Lean concrete casting(18 Mpa)
6 Segment-2 PVD Driving 300mm sand blanket completed.
7 Segment-2A Surcharge Removing Surcharge Removing in progress.(50,000 cft)
8 Segment-1 & 2 Surcharge material placement (70,000 cft) Surcharge material placement in progress (70,000cft)
Old line removal Old line removal in progress.
10 Boundar Wall Plastering of wall near sub-station Bricks masonry work finished near sub-station .
11 Road Type-2 Improved Sub-grade Improved Sub-grade work in progress.
Shuttering work (CH 1010-1030)/Navy Side Wall casting 3rd lift (CH 990-1010)/Navy Side
Bracing fixing (near sub-station)
13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
14 Interlocking Block ILB production ILB production in progress.(11,000 Nos)
15 Dismantling work Dismantling work at Navy gate. Dismantling work at Navy gate in progress.
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Work Program of February 12,2012
RMG Track(Seg-1A)1
Yard Drainage2
Open Deep Drain12
Rail Relocation9
Sub-station Building3
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of February 12,2012
-
8/13/2019 Daily Program Feb-2012
33/38
S.l.
No.Description Work Program of February 16,2012 Achievement of February 15,2011 Remarks
Wall casting of 01 No Gully hole.
CC Castng of 4 Nos Gullyhole
2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
3 Segment-1 Surcharge material placement (70,000 cft)Surcharge material placement in progress
(60,000cft)
Surcharge material placement Surcharge material placement in progress.
PVD Driving PVD Driving in progress.
5 Sub-base work (Seg-1A) RTG Track area
6 Service Area Lean concrete casting(18 Mpa) Lean concrete casting(18 Mpa) in progress.
7 Seg-2A Soil boring
8 Road Type-1 Sub-base work. Sub-base work in progress
9 Open Drain Work Soling,CC work (CH 1040-1050) Earth excavation executed.
10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
11 Interlocking Block ILB production ILB production in progress.(13,000 Nos)
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-24
Work Program of February 12,2012
Yard Drainage1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of February 18,2012
-
8/13/2019 Daily Program Feb-2012
34/38
S.l.
No.Description Work Program of February 18,2012 Achievement of February 17,2011 Remarks
1 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
2 RMG Track(Seg-1A) Concrete pouring (16 cum) Rebar binding and shuttering executed.
3 Segment-1 Surcharge material placement (70,000 cft)Surcharge material placement in progress
(60,000cft)
4 Pile Load Test(up lift) Up lift test for driven pre-cast pile (Seg-1A)
Surcharge material placement Surcharge material placement in progress.
PVD Driving PVD Driving in progress.
6 Sub-base work (Seg-1A) Sub-base work for RTG Track Sub-base work for RTG Track in progress.
7 Service Area Lean concrete casting(18 Mpa) Lean concrete casting(18 Mpa) in progress.
8 Seg-2A Soil boring for sample collection Soil boring for sample collection in progress.
9 Road Type-1 Sub-base work. Sub-base work in progress
10 Open Drain Work Bracing welding (near Navy gate.) Earth excavation executed.
Wall casting CH 920-940/3rd lift/Yard side
Wall casting CH 940-950/1st lift/Navy side
11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
12 Interlocking Block ILB production ILB production in progress.(12,540 Nos)
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-25
g y ,
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of February 19,2012
-
8/13/2019 Daily Program Feb-2012
35/38
S.l.
No.Description Work Program of February 19,2012 Achievement of February 18,2011 Remarks
Wall casting of 01 No Gully hole.
CC Castng of 4 Nos Gullyhole
Side CC (8rm)
2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
3 RMG Track(Seg-1A) Rebar binding & Shuttering. Concrete pouring (16 cum)
4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress
5 Segment-1 Settlement Record Settlement Record in progress.
Surcharge material placement Surcharge material placement in progress.
PVD Driving PVD Driving in progress.
7 Seg-2A Soil boring for sample collection Soil boring for sample collection in progress.
8 Road Type-1 Existing Road excavation
9 Open Drain Work Bracing Fixing (near Navy gate.) Earth excavation executed.
Wall casting CH 920-940/3rd lift/Yard side
Wall casting CH 940-950/1st li ft/Yard side Wall casting CH 940-950/1st l if t/Navy side
10 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
11 Interlocking Block ILB production ILB production in progress.(12,400 Nos)
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-26
Yard Drainage1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of February 22,2012
-
8/13/2019 Daily Program Feb-2012
36/38
S.l.
No.Description Work Program of February 22,2012 Achievement of February 21,2011 Remarks
Rebar binding of Base (04 Nos Single Gully hole)
2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
3 RMG Track(Seg-1A) Rebar binding & Shuttering. Rebar binding & Shuttering in progress.
4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress
5 Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting.
6 Segment-1 Settlement Record Settlement Record in progress.
Surcharge material placement Surcharge material placement in progress.
8 Road Type-1 Sub-base work Sub-base work in progress
9 Open Drain Work Bracing Fixing (near Navy gate.) Bracing Fixing (near Navy gate.) in progress
Wall casting CH 900-920/2nd lif t/Yard side Rebar fabrication & Shuttering executed.
10 Truck Parking Area Sub-grade Preparation
11 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
12 Interlocking Block ILB production ILB production in progress.(11,800 Nos)
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-27
Yard Drainage1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of February 23,2012
-
8/13/2019 Daily Program Feb-2012
37/38
S.l.
No.Description Work Program of February 23,2012 Achievement of February 22,2011 Remarks
Base casting (04 Nos Single Gully hole) Rebar binding of Base (04 Nos Single Gully hole)
2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
3 RMG Track(Seg-1A) Rebar binding & Shuttering. Rebar binding & Shuttering in progress.
4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress
5 Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting. 200mm thick lean concrete casting in progress.
6 Segment-1 Settlement Record Settlement Record in progress.
Surcharge material placement Surcharge material placement in progress.
8 Segment-4 150mm local sand compaction 150mm local sand compaction in progress.
9 Segment-3 Dismantling work Dismantling work in progress.
10 Road Type-1 Sub-base work Sub-base work in progress
11 Open Drain Work Bracing Fixing (near Navy gate.) Bracing Fixing (near Navy gate.) in progress
Wall casting CH 900-920/2nd lif t/Yard side Rebar fabrication & Shuttering executed.
12 Truck Parking Area Sub-grade Preparation Sub-grade Preparation in progress.
13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
14 Interlocking Block ILB production ILB production in progress.(9,500 Nos)
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-27
Yard Drainage1
NCT BACK-UP PROJECT, CHITTAGONG
Work Program of February 25,2012
-
8/13/2019 Daily Program Feb-2012
38/38
S.l.
No.Description Work Program of February 23,2012 Achievement of February 22,2011 Remarks
Base casting (04 Nos Single Gully hole) Rebar binding of Base (04 Nos Single Gully hole)
2 Sub-station Building Bricks masonry work & Plastering . Bricks masonry work & Plastering in progress.
3 RMG Track(Seg-1A) Rebar binding & Shuttering. Rebar binding & Shuttering in progress.
4 RTG Track (Seg-1A) Sub-base work Sub-base work in progress
5 Yard Lean concrete (Seg-1A) 200mm thick lean concrete casting. 200mm thick lean concrete casting in progress.
6 Segment-1 Settlement Record Settlement Record in progress.
Surcharge material placement Surcharge material placement in progress.
8 Segment-4 150mm local sand compaction 150mm local sand compaction in progress.
9 Segment-3 Dismantling work Dismantling work in progress.
10 Road Type-1 Sub-base work Sub-base work in progress
11 Open Drain Work Bracing Fixing (near Navy gate.) Bracing Fixing (near Navy gate.) in progress
Wall casting CH 900-920/2nd lif t/Yard side Rebar fabrication & Shuttering executed.
12 Truck Parking Area Sub-grade Preparation Sub-grade Preparation in progress.
13 Laboratory / Field Test Regular Test (ILB/Cylinder) Regular Test (ILB/Cylinder)
14 Interlocking Block ILB production ILB production in progress.(9,500 Nos)
Project Manager Sub Assistant Engineer-1 Sub Assistant Engineer-2 Assistant Engineer
NCT Back-up/PBL NCT Back-up/CPA NCT Back-up/CPA NCT Back-up/CPA
Segment-27
Yard Drainage1