Daily Log: Pascual, John Casimir T.
January 20, 2011
On the first day on the site we are introduced to the staff., we were required to attend
a safety orientation on the safety department. Sir Floyd, the safety officer oriented usabout the safety rules and procedures. We were required to have our own personal
protection equipment. After the orientation, we were turned over to Engr. Cid
Dimagiba, the project superintendent of tower C.
January 21, 2011
This day we were assigned and taught on stirrup estimate and basic excel
programming
January 24, 2011
This is the very first time we went outside of the office to go to the field. Engr. Cid
showed us a briefing about the whole site
January 25, 2011
This day we were taught how to compute for the elevation of the basement. We went
to tower B where we observe that is being done in the that tower
January 26, 2011
During this day we computed for the elevation but on the 2 nd floor of the building.
This is the first time I learned of the word soffit.
January 28, 2011
During this day this is the first time we computed for the volume of the concrete for
the concrete pouring that will occur on the evening.
January 31, 2011
We inspected the dried concrete that was poured yesterday evening. We took picturesfor the files. I observe that concrete pouring can last a whole night and more
February 01, 2011
We were introduced by one of the PS Sir Pat and to Engr. Frank the concrete engineer
in the Jazz Residence. He explained to us a brief discussion about concrete pouring
from the types of concrete strength to the concrete being self compacting
-
8/3/2019 Daily Log - Bakat
2/3
February 04, 2011
We gathered some important files for our fortnightly report. We interviewed various
engineers on the site for information to be included in our report.
February 07, 2011
We met Engr. Denise, the QS/QA in the project site. He explained to us how the
inspection process works for the rebar per floor.
February 08, 2011
During this meeting we took some photos for the report and gather some files. Then
we interview Engr. Floyd about the safety precaution made by the site
February 11, 2011
During this meeting Engr. Pat taught us about how to create a cutting list for the rebar
in the column and how to compute the number of rebar to be use. He also explain
splicing of the rebar, why is it right to splice in this part of the column and also how
to use the cutting list.
February 14, 2011
During this time we went outside to visit the excavated portion of the site. We also
visited the foundation of Tower B and its progress
February 15, 2011
Engr. Russel showed us the different foundation used in the site as well us contribute
some information about the site as well as his experience as being an engineer
February 08, 2011
Engr. Mark told us to go up to his tower to see the MAC(formwork use in the shear
wall to move fast in the construction) system of formworks. He show and explain howto jack up a tower crane on the building. He shows us the mac system and how it
works.
February 21, 2011
During this day we gather some data and interview the consultant of the
company(PMCI). Were head personally explain to us about the cash flow and s-curve
of the project.
-
8/3/2019 Daily Log - Bakat
3/3
February 22, 2011
During this day we were assigned to estimate the volume of concrete to be poured on
the site tonight. We were asked to go and measure the columns, beams, slab and shearwalls. Then we compute their volumes.
February 25, 2011
During this day Engr. Cid instructed us to go to the concrete pouring that was still in
process due to some technical problem with the supplier. We interviewed Engr. Frank
about the equipments use in the site. They have a leveling device for the concrete.
February 28, 2011
During this day we were taught of the importance of proper utilization of materials.Proper delivery and utilizing of the material will cause a positive effect in the
construction and avoid delay of the project.
March 01, 2011
I interviewed the QS/QA engineer about my report about Variation order and Time
extension and Quality Control
March 04, 2011
This was the last day of my practicum; We gathered documents for the completion of
our 4th fortnightly report. Before we leave the site, I notify Engr. Cid for a certificate
of completion who gave us the certificate at a later date (March 12, 2011).