dai kin project checklist

Upload: humaid-shaikh

Post on 20-Feb-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/24/2019 Dai Kin Project Checklist

    1/29

    1 Rev. 11-18-2011

    Daikin Project ChecklistIt is Hoffman & Hoffmans policy to only allow contractors who have completed the three days of

    Daikin VRV Basic and Advanced Trouble Shooting and Commissioning training to install Daikin

    VRV systems.

    Proper Daikin terms were included in quotation and a copy of quote has been placed in Greensboro order file

    Date: __________________ Job Location: ____________________________________

    Project Size: ______ Tons Salespersons Name: ______________________________

    ______ Outdoor Units Owners Name: __________________________________

    ______ Indoor Units Contractors Name: _______________________________

    Contractors Address: _____________________________

    Engineers Name: _____________________ Engineers Company: _____________________________

    Who was hired to supervise the contractors commissioning process:

    Name Telephone

    Days of Assistance: ____________________

    Contractors Advanced Trained Installer: ____________________________________________

    Name(s) Telephone

    Contractors Person Responsible for Start-up: ____________________________________________

    Name Telephone

    Previous Jobs Completed by Installer: ____________________________________________

    Anticipated Installation Start Date: ___________________________________________

    Name of person I reviewed Commissioning Documents with: _________________________________

    The following documents were Personallyreviewed at submittal delivery with Contractor:

    ___________________________________________________________________________________

    Name Date

    Reviewed Daikin Engineering Documents (DED)

    Reviewed Request for Supervised Commissioning Form (RCF)

    Reviewed Pre-Commissioning Checklist (PCC)Reviewed Commissioning Request Procedure (CRP)

    Submittal

    Provide VRV express file

    * At the completion of each phase transmit copy to Greensboro order file

    PhaseI

    -Pre-construction

    PO #__________________________JOB NAME: __________________________

  • 7/24/2019 Dai Kin Project Checklist

    2/29

    2 Rev. 11-18-2011

    Project Walk by H&H Project Mgr.: _________________________________________________________

    Name Date

    Stage of Construction: __________________________________________________

    Personally reviewed Installation Notes (ATTACHED)with Contractors Onsite:

    _____ Reviewed Daikin Engineering Documents (DED)

    _____ Reviewed Request for Supervised Commissioning Form (RCF)

    _____ Reviewed Pre-Commissioning Checklist (PCC)

    _____ Reviewed Commissioning Request Procedure (CRP)

    _____ Submittal has been reviewed

    ______________________________________________________________________________________

    Contractor Name Date

    * At the completion of each phase transmit copy to Greensboro order file

    Walk of Site: ______________________________________________________________________

    Name Date

    Systems: __________________________________________________________________________

    Review Install Notes with: ____________________________________________________________

    Name

    Pointed Out Areas of Concern:

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    Recommendations:

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    _____________________________________________________________________________________________

    Recommendations given to: ____________________________________________________________

    Name Date

    Recommendations were: ____________________________________________________________

    Made during walk of site / Telephoned / Emailed / Etc.

    * At the completion of each phase transmit copy to Greensboro order file

    PhaseIIBeginning

    OfConstruction

    PhaseIIIMidConstruction

  • 7/24/2019 Dai Kin Project Checklist

    3/29

    3 Rev. 11-18-2011

    Completion of Pre-Commissioning Checklist (PCC) (Please send completed copy to order file in GSO)

    Completion of Request for Supervised Commissioning Form (RFC)

    Scheduled Supervised Commissioning

    Commission Dates: ________ _______ ________ ________

    Commissioned by: ____________________________________________________

    Commissioning Notes:

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    __________________________________________________________________________________________________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    __________________________________________________________________________________________________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    _________________________________________________________________________________________

    Completed by: ____________________________________________________________________________

    Name Date

    * At the completion of each phase transmit copy to Greensboro order file

    PhaseIVJobStart-Up

  • 7/24/2019 Dai Kin Project Checklist

    4/29

    Notes for Refrigerant Piping Page 1 of 2 Rev. 11-11-11

    Notes for VRV Refrigerant Piping

    1.

    All joints shall be brazed except at the indoor units which shall be flared

    2.

    All piping shall be installed in accordance with the mechanical design. Any deviation shall be

    submitted for prior approval to the mechanical engineer prior to installation. Selected copper

    tube must be of suitable wall thickness for higher operation pressures.

    3.

    Flaring: Flared tube ends should have a smooth, even round flare of sufficient length to fully

    engage the mating surface of the flare nut, without protruding into the threads. Use only PVEor POE refrigeration oil when making flares. Dedicated flare block and tool is recommended.

    Only use synthetic oil on the flare tool.

    4.

    All piping exterior to building, shall be a minimum of type L, ACR rated straight pipe for R-

    410A or as specified. All piping on the building interior shall be L, ACR rated rolled soft

    copper or line set for R-410A or as specified, piping (after annealing) shall have sufficient wall

    thickness for a continuous operating pressure of 600 PSI per ASME B 31.5-2010.

    5.

    Dry Nitrogen: Dry nitrogen must be used during all brazing (pressure regulated to 3 PSI) to

    prevent copper plate or oxidation formation.

    6.

    Pressure testing: Tighten down stop valves before any pressure testing to prevent nitrogen

    from leaking back through condenser and contaminating refrigerant.Pressure testing shall be done in three (3) steps.

    Step 1 Leak check 3 minutes at 150 PSI

    Step 2 Leak check after 5 minutes at 325 PSI

    Step 3 Leak check after 24 hours at 550 PSI (450 psi for systems with vertical Air Handlers)

    Always check flare nuts for leaks using bubble solution. Be sure to use a recommended product.

    Do not use a watered down fairy liquid solution.

    7.

    Leak testing and evacuation shall be done in accordance with the US EPA Green Chill Best

    Practices Guideline Ensuring Leak-Tight Installation of Commercial Refrigerant Equipment.

    8.

    Evacuation procedures: Evacuation procedures shall be performed as follows:

    A.

    Evacuate the system to 4000 microns. Break the vacuum with dry nitrogen to a pressure of2-3 PSI and hold for 15 minutes.

    B.

    Evacuate system to 1500 microns and maintain for 20 minutes. Break the vacuum with dry

    nitrogen to a pressure of 2-3 PSI and hold for 15 minutes.

    C.

    Evacuate system to below 500 microns and hold for 60 minutes.

    D.

    Evacuate system to below 300 microns and hold for 24 hours.

    Vacuum pump check valve should be used to prevent mineral oil from being drawn into the

    system. These procedures must be adhered to, documented and included in the contractors

    price.

    9.

    Refrigerant charging: Weigh in additional refrigerant with digital scales. Calculate charge based

    on total line length plus lb/ft of diameter. Check with each unit model for correct multiplier.

    After the amount of refrigerant to be added is determined write it down on the label on the

    back side of the front cover. After the vacuum/drying is complete, charge the additional

    refrigerant in its liquid state through the liquid stop valve service port.

    Make sure to use installation tools you exclusively use on R410A installations to withstand the

    pressure and to prevent foreign material from mixing into the system.

  • 7/24/2019 Dai Kin Project Checklist

    5/29

    Notes for Refrigerant Piping Page 2 of 2 Rev. 11-11-11

    Notes for VRV Refrigerant Piping Continued

    10.

    All refrigerant piping and Refnets exterior to the building shall have aluminum jacket covering

    the insulation in accordance with the following specifications.

    Equivalent to Pabco-childers metals aluminum roll jacketing, .016 thick, complying with

    3105/3003 standard alloys, stucco empossed finish with polysurlyn moisture retarder. Provide

    " aluminum band clamp every 10 to 12.

    11.

    Insulation techniques: All pipe work must be insulated along its full run using code compliant

    (25/50 rated), Armaflex model UT/Solaflex, " thick, high temperature and UV resistant

    closed cell insulation.

    Insulation of pipes should be done after performing work required by note 8 (air tight test and

    vacuum drying). Insulate the liquid piping, the HP/LP gas piping, the gas piping, the equalizer

    pipe (between the outside units for the outside multisystem) and these pipe connections.

    Insulation shall withstand temperatures of 248 degrees F or more for the HP/LP gas piping, the

    equalizer pipe and gas piping.

    Cover flare nuts on the fan coils using the insulation provided or condensation will occur causing

    leaks.

    12.

    Un-insulated joints will condense moisture around the fittings. Line components: Do not install

    driers, oil traps, sight glasses or any other line component in the pipe work as this will affect the

    performance and warranty.

    13.

    VRV systems shall be installed in accordance with ASHRAE 15.

    14.

    VRV systems shall be installed by a manufacturer certified and trained contracting company and

    shall have documentation of VRV installation & commissioning training. Field Superintendentshall have VRV training and certification.

    Certification, training and commissioning documentation to be furnished with the contractors

    bid and/or notice to proceed.

    VRV supplier shall include a special VRV tool kit allowance for the installing contractor consisting

    of:

    A.

    Standard R-410A gauge kit with multiple tools

    B.

    Torque wrench set

    C.

    R-410A flare tool

    D.

    R-410A plastic flare size gauge

    If installing contractor does not currently have these special tools.

    15.

    In applications where the Refnet kits are installed in an environment requiring fire-rated

    material to be used, it is necessary for the installer to obtain from a third part supplier and to

    utilize, for installation, fire-rated materials that meet all applicable building codes and other

    requirements. The factory supplied insulation should be discarded in a manner meeting all

    applicable law.

  • 7/24/2019 Dai Kin Project Checklist

    6/29

    C C

    -

    ;

    -

    u

    i

    i

    ,

    i

    )

    ~

    ~

    %

    /

    /

    ~

    :

    '

    i

    .

    p

    e

    c

    t

    i

    O

    h

    c

    :

    :

    :

    I

    0

    3

    4

    .

    s

    L

    I

    S

    c

    (

    N

    e

    a

    S

    v

    c

    q

    r

    l

    o

    o

    o

    s

    H

    m

    e

    P

    a

    e

    s

    d

    o

    m

    t

    o

    b

    O

    o

    H

    e

    B

    s

    o

    n

    a

    i

    n

    P

    H

    o

    a

    c

    a

    m

    to

    b

    O

    X

    s

    d

    A

    h

    o

    H

    n

    y

    o

    u

    o

    h

    u

    I

    n

    a

    a

    h

    p

    a

    w

    s

    m

    m

    n

    o

    g

    d

    M

    u

    n

    n

    t

    a

    l

    i

    a

    o

    a

    o

    o

    3

    A

    a

    p

    e

    o

    Y

    u

    n

    c

    o

    c

    n

    w

    h

    a

    0

    1

    4

    O

    C

    C

    U

    p

    t

    h

    w

    c

    p

    b

    e

    o

    n

    a

    e

    d

    p

    p

    i

    R

    .

    y

    b

    r

    e

    d

    s

    m

    i

    y

    c

    o

    d

    a

    m

    e

    e

    o

    h

    p

    e

    P

    p

    n

    s

    d

    i

    m

    l

    a

    o

    n

    y

    e

    d

    y

    o

    h

    F

    e

    1

    T

    a

    S

    o

    e

    h

    o

    p

    w

    s

    v

    c

    n

    ~

    ~

    ~

    m

    I

    '

    -

    '

    -

    I

    3

    1

    3

    N

    8

    I

    H

    /

    4

    ;

    3

    1

    3

    =

    1

    8

    I

    1

    1

    8

    4

    8

    4

    4

    4

    5

    8

    1

    C

    "

    a

    N

    3

    1

    4

    i

    n

    b

    n

    o

    n

    o

    D

    9

    A

    a

    p

    p

    N

    e

    3

    .

    1

    n

    b

    n

    c

    n

    O

    8

    t

    e

    m

    i

    n

    M

    n

    d

    m

    ,

    7

    S

    o

    b

    e

    5

    1

    3

    8

    U

    C

    h

    p

    e

    6

    C

    "

    b

    O

    H

    e

    1

    t

    Y

    u

    5

    L

    q

    U

    d

    p

    p

    c

    O

    n

    o

    p

    .

    3

    8

    n

    b

    g

    c

    4

    C

    .

    U

    p

    p

    p

    i

    n

    b

    n

    c

    o

    d

    n

    s

    t

    3

    P

    p

    n

    o

    p

    j

    D

    c

    b

    n

    2

    H

    L

    g

    S

    p

    p

    c

    c

    o

    N

    e

    }

    .

    3

    1

    n

    b

    b

    n

    c

    o

    s

    d

    1

    g

    p

    p

    c

    U

    D

    e

    o

    p

    (

    H

    o

    5

    6

    V

    a

    b

    Z

    D

    c

    o

    K

    a

    b

    P

    n

    C

    c

    p

    a

    C r

    n

    ~

    =

    j

    ;;

    Goo .' - ....

    +- '

    . . . . .

    ~ : : . = g : ~ - : ~

    :

    _:

    ~ _ ~ _ ~ _ : i ~ _ ;

    2 ~ - . ~ _

    ---- : : :

    -

    ~ e : ~ : ; : ' ; ; ~ : ; ;

    .;::

    ......

    ' ,;: 6

    -=-

    ;;;0>-

    ~ ~ H H H ~ H H

    I

    - - - ' " , '4 r -

    --

    I

    I

    8 \ - ~

    ~ s : s ; ~ ; ;

    ~ ' $ . G . v . -

    s

    d..

    -

    -

    =

    =

    e

    .-

    e:

    -:;

    .

    I / -Z

    91/.

    Dimensions

    o

    'J,

    Ul

  • 7/24/2019 Dai Kin Project Checklist

    11/29

    NOTE: CONTRACTOR TO PROVIDE

    5/16

    THREADED

    ROD HANGERS

    WITH

    DOUBLE SIDED RUBBER (1/2 THICK)

    ISOLATORS AT EACH SUSPENSION BRACKET

    4

    EACH)

    ON

    BRANCH SELECTOR FOR SUSPENSION

    OF

    UNIT

    1/4-

    SERVICE FTG.

    (TYP) EACH V L ~

    (LP) SUCTION SREFRG. LlNE ____

    (TO OUTDOOR UNIT) _____

    CONTRACTOR TO INSTALL

    LINE

    SIZE

    SHERWOOD MODEL WAS REFRIGERANT

    SHUT-OFF VALVES WITH ACCESS FITTING.

    ALL VALVES SHALL INCORPORATE

    DUAL STEM SEAL DESIGN W/TEFLON

    PACKING INTERNAL PRIMARY SEAL.

    VALVE SHALL PERMIT OPERATION

    WITHOUT

    REMOVAL OF SEALS OR

    TEFLON

    GASKETS.

    PROVIDE W/INTERNAL BALL TYPE RELIEF

    PORT FOR DUAL DIRECTIONAL SHUT-OFF.

    PROVIDE FULL FLOW PORTS ON ALL SIZES

    1/4

    THROUGH

    7/8 .

    (HP) LIQUID

    REFRIG.

    LINE

    FROM OUTDOOR UNIT)

    (NOTE:

    SHUT-OFF

    VALVES SHALL BE

    ZERO-CLEARANCE TYPE. ALL BRONZE.

    BRAZED CONNECTIONS

    WITH

    1/4 SCHRADER

    TYPE SERVICE FIniNG IN VALVE. TYPICAL

    FOR EACH LINE).

    (HP) HOT GAS REFRIG. LINE

    FROM

    OUTDOOR

    UNIT)

    (LP)

    SUCTION

    REFRIG.

    LINE

    (FROM INDOOR UNIT)

    /

    (HP) LIQUID REFRIG. LINE

    (TO INDOOR UNIT)

    INSTALL BRANCH SELECTOR

    A MINIMUM

    OF

    12 x

    15-1/4

    CLEAR FOR ELECTRICAL

    ~ ~ ~ ~ f TO ELECTRIC BOX

    _ ~

    DETAIL

    TYPICAL BRANCH SELECTOR PIPING

    NOT TO SCALE

    ALL MECHANICAL EQUIPMENT SHALL BE IN COMPLIANCE WITH ASH RAE 90 1

  • 7/24/2019 Dai Kin Project Checklist

    12/29

    MAIN LINE

    SIDE

    OUTSIDE UNIT

    SIDE

    BRANCH SIDE

    MAX. 15

    degrees

    rot tion

    up

    HORIZONTAL

    PLAIN -

    NOTE: THIS SAME HORIZONTAL APPLICATION APPLIES TO HEADERS.

    DETAIL - M XIMUM ROT TION OF

    HORIZONTAL INSTALLED REFNET

    (

    REFER

    TO MANUFACTURERS INSTRUCTIONS)

  • 7/24/2019 Dai Kin Project Checklist

    13/29

    PRESSURE REDUCING

    VALVE

    HIGH

    PRESSURE

    H O S ~

    TAPE

    NITROGEN

    ~ PACKLESS

    VALVE

    \

    REfRIGERANT PIPING

    NOTES:

    NITROGEN

    USE DEDICATED

    MANIFORD. GAUGES AND

    HOSES TO GUARD AGAINST CROSS CONTAMINATION

    SERVICE PORT CHANGE

    DIAMETER

    1/4 ENLARGED TO 5/16

    DETAIL TYPICAL NITROGEN PURGING SET-UP

    NOT

    TO

    SCALE

  • 7/24/2019 Dai Kin Project Checklist

    14/29

    HANGERS

    (TYP)

    I

    I I I

    I I

    MIN. 20

    BEFORE ELBOW .. I

    RECOMMENDED

    EQUIPMENT

    CLEARANCES:

    3

    ABOVE

    12 ENTERING (3 PIPE)

    IN SPACE

    CONDITIONS

    THAT

    DO

    NOT ALLOW 3 ABOVE

    THE

    DEVICE MAINTAIN A 1

    AIR

    SPACE

    BELOW UPPER

    DECK

    AND INSTALL 1/2

    FOAM

    INSULATION ON

    THE

    TOP OF

    THE

    DEVICE.

    BRANCH

    SELECTOR

    UNIT

    HANGERS

    (TYP)

    I

    I I

    I

    MIN.

    20

    BEFORE

    ELBOW

    DETAIL - RECOMMENDED PIPE CLEARANCES

    FOR BRANCH SELECTOR UNITS

    ( REFER TO MANUFACTURERS INSTRUCTIONS )

  • 7/24/2019 Dai Kin Project Checklist

    15/29

    PROVIDE

    ALUMA STAND

    CONDENSING

    UNIT SUPPORT

    AS MANUFACTURED BY:

    PREaSION ALUMINUM PRODUTS,

    DEERFIELD

    BEACH, FL.

    CONDENSING UNIT SUPPORT SHALL

    MEET

    STATEWIDE BUILDING FOR USE IN COSTAL

    AND

    NOT-COSTAL ZONES

    PROVIDE STANDARD 1

    S FROM BASE TO

    BOTTOM

    OF

    RAIL

    lB

    r

    _ 1

    < .............

    . .

    ::>

    ........ . .

    ----

    DETAIL:

    GENERAL

    INSTALLAnON

    NOTES:

    1.

    REFER TO

    MANUFACTURERS

    INSTALLAnON

    DETAILS

    FOR

    PROPER INSTALLAnON.

    2. MANUFACTURERS DETAILS ARE

    FOUND

    AT

    WWW.ACSTANDS.COM. UNDER ENGINEERING

    DOCUMENTS/ALUM STAND.

    CONDENSING

    UNIT ROOF/GRADE

    SUPPORT

    (DOUBLE MODULE

    SYSTEM

    SHOWN)

    NOT

    TO

    SCALE

  • 7/24/2019 Dai Kin Project Checklist

    16/29

    ~

    \

    HANGERS

    TYP)

    1 - 1 -

    I

    I

    I

    I

    I

    I

    A

    I

    v A

    v

    MIN.

    20

    BEFORE

    EL OW

    -:

    O fP

    0

    D

    ~

    ORK

    PADS

    H

    DETAIL -

    RECOMMENDED

    PIPE CLEARANCES

    FOR INDOOR UNITS

    REFER

    TO

    MANUFACTURERS

    INSTRUCTIONS)

    )

  • 7/24/2019 Dai Kin Project Checklist

    17/29

    LENGTH

    L

    INCHES OFFSET RETURN

    ----

    ( LEEVE= = \

    L

    I

    I

    I

    GUIDE BRACKET

    NOTE: CALCULATION

    FOR

    EXPANSION

    AND

    CONTRACTION SHOULD

    BE

    BASED

    ON THE

    AVERAGE COEFFICIENT

    OF

    EXPANSION

    OF

    COPPER

    WHICH IS 0.0000094

    INCH PER INCH

    PER

    DEGREE

    F

    BETWEEN

    70

    degrees F

    AND

    212 degrees

    F.

    (EXAMPLE: EXPANSION

    OF

    A 100

    DEGREE

    F RISE FOR EACH 100 FT.

    OF

    ANY SIZE IS 1.128 INCHES)

    EXPANSION DIMENSION L FOR OFFSET RETURN

    TO

    BE BASED ON

    THE

    EXPECTED EXPANSION INCHES

    PER

    DIMENSION

    OF

    PIPE

    DETAIL - EXPANSION LOOPS

    PLAN VIEW

  • 7/24/2019 Dai Kin Project Checklist

    18/29

    UNISTRUT SUPPORT

    ALUMINUM JACKET

    OVER INSULATION

    REF. PIPE

    UNISTRUT

    PIPE CLAMP

    DETAIL

    REF

    PIPE UNISTRUT SUPPORT

    NOT TO SCALE

  • 7/24/2019 Dai Kin Project Checklist

    19/29

    REFRIGERANT

    PIPING

    FROM OUTSIDE UNIT

    OR

    INTERIOR BRANCH

    SELECTORS

    MIN. 20

    AFTER ELBOW

    LONG

    SWEEP

    ELBOW OR LONG

    BEND OF SOFT

    COPPER

    (TYP)

    TYPICAL

    VRV

    REFNET

    REFRIGERANT

    BRANCH PIPING

    DEVICE INSTALLED

    IN A TRUE AND LEVEL POSITION

    PARALLEL TO CEILING BELOW

    OR

    FLOOR STRUCTURE ABOVE

    MIN.

    40

    BETWEEN

    REFNET AND HEADER

    MIN. 20

    BEFORE ELBOW

    TO TYPICAL INTERIOR

    TERMINAL

    UNIT

    TO TYPICAL

    INTERIOR

    TERMINAL

    UNIT

    CAL VRV 4 OR 8

    CONNECTOR HEADER DEVICE

    DIAGRAM - PLAN VIEW

    OF

    REFNET & HEADER

    INSTALLATION

    FOR

    BRANCH REFRIGERANT PIPING

    ( REFER

    TO

    MANUFACTURERS INSTRUCTIONS

  • 7/24/2019 Dai Kin Project Checklist

    20/29

    REFRIGERANT PIPING

    FROM OUTSIDE

    UNIT

    OR INTERIOR BS

    BRANCH SELECTORS

    j

    MIN

    20

    AFTER ELBOW

    LONG SWEEP

    ELBOW OR LONG

    BEND OF SOFT

    COPPER (TYP)

    TYPICAL

    VRV

    REFNET DEVICE

    DIAGRAM

    THE REFNET

    KITS

    ARE SUPPUED WITH INSULATION

    INTENDED

    TO FIT OVER THE MAIN BODY OF THE REFNET

    JOINT AFTER INSTALLATION OF

    THE

    REFNET KIT IS

    COMPLETE

    IMPORTANT: SEE NOTE@) BELOW

    MIN

    40

    BETWEEN

    REFNETS

    MIN

    20

    BEFORE ELBOW

    TO TYPICAL INTERIOR

    TERMINAL UNIT

    TYPICAL VRV REFNET REFRIGERANT

    BRANCH PIPING DEVICE INSTALLED

    IN A TRUE AND LEVEL POSITION

    PARALLEL TO CEIUNG BELOW

    OR

    /FLOOR STRUemR ABO>l

    1 1 ~ ~ T O

    TYPICAL

    INTERIOR

    TERMINAL UNIT

    LONG SWEEP

    ELBOW OR LONG

    BEND OF

    SDFT

    COPPER (TYP)

    TO TYPICAL INTERIOR

    TERMINAL UNIT

    PLAN VIEW OF TYPICAL REFNET

    INSTALLATION FOR BRANCH REFRIGERANT PIPING

    (

    REFER

    TO

    MANUFACTURERS INSTRUCTIONS)

  • 7/24/2019 Dai Kin Project Checklist

    21/29

    x

    .;t

    - - - - - -71

    I

    1

    /

    1 / 1

    1

    /

    1

    X

    1/

    1

    /

    ,< J45 deg. M X

    i

    1 / 1

    1 1

    L

    ~

    45 deg.

    MAX

    x

    :q.

    NOTE: IN CASES WHERE PIPING/TUBING NEEDS TO DROP BELOW OBJECTS,

    (BEAMS, DUCTS, CONDUITS, PIPES ETC.) PIPING SHALL HAVE LARGE RADIUS

    TURNS AS INDICATED ABOVE NO MORE THAN

    45

    DEGREES PER FITTING)

    TO PREVENT TRAPPING

    OF

    REFRIGERANT.

    DETAIL - PIPING OFFSET

    BELOW

    OBJECT

    ELEVATION VIEW

  • 7/24/2019 Dai Kin Project Checklist

    22/29

    Summary of the Commissioning Request Procedure

    The following outlines the procedure for smooth processing of the installing contractors

    commissioning request:

    1. Contractor completes the Request for Supervised Commissioning form

    2. Contractor submits the Request to Hoffman & Hoffman, Inc.

    3. Supervising personnel will contact the installing contractor to schedule the

    commissioning.

    4. Contractor completes the Pre-Commissioning checklist and submits to the Hoffman &

    Hoffman Coordinator a minimum of 48 hours prior to the scheduled commissioning.

    5. The contractor, salesperson and supervising personnel meet at the jobsite on the

    scheduled date to perform the Supervised Commissioning session.6. By completing and signing the Pre-Commissioning checklist, the contractor confirms and

    represents that the job is ready for commissioning. If upon arrival on the scheduled day

    for the commissioning it is found that any portion of the job is not ready for

    commissioning, the contractor shall be subject to additional fees.

    7. The installing contractor is responsible for arranging access to the equipment on the day

    of the commissioning. This includes notifying the necessary parties at the site to insure

    access to all components of the system. The contractor must provide any ladders, lifts,

    keys, or other devices necessary to access the equipment.

    This supervision of commissioning is to offer supervision of the contractor performing

    the commissioning onsite. The installing contractor must have adequate personnel

    onsite at the time of the assisted commissioning. The installing contractor is responsible

    for providing all service tools, test equipment, refrigerant, and other supplies necessary

    to conduct the commissioning.

  • 7/24/2019 Dai Kin Project Checklist

    23/29

    Request - 1- Ver. ELEC

    DAIKIN AC (Americas), Inc.

    1645 Wallace Drive, Suite 110Carrollton, TX 75006 USA

    TEL: 866-4DAIKINFAX: 972-245-1038www.daikinac.com

    Request for Supervised Commissioning SRO#:___________

    DATE REQUESTING Commissioning:___________________

    Instructions for submitting Supervised Commissioning request:Submit this form to the Service Coordinator at least 14 days prior to a requested assisted commissioning([email protected] FAX 972-245-1038). Within 3 business days of receipt of the request, theDaikin Area Service Manager will contact you to schedule the Commissioning and provide a SRO # toreference any future correspondence to this work order. The form must be filled in its ENTIRETYwith asignature and a Purchase Order to be placed on the schedule. Please refer to the Daikin ACcommissioning policy for full details regarding any fees associated with this Commissioning.

    Request will not be honored without required purchase order(s) from Distributor/Rep).

    Purchase Order P.O.) for Commissioning:

    __________________ Must Include to schedule)

    Note: Must be OPEN P.O. o r a Not to Exceed Amount Purchase order.

    C o n t r a c t o r I n f o r m a t i o n

    Company Name:

    City, State & Zip:

    Phone/Fax #:

    Contact:

    Email Address:

    Rep or Distributor Information (Must supply Purchase Order)

    Company Name:City, State & Zip:

    Contact:

    Phone:

    Email Address:

    Site Information: Must have specific job location address

    Job Name:

    Address:City, State & Zip:

    Contact:

    Phone:

    Equipment Information

    Number of Systems to be Commissioned _______________Note: each syst em will requir e a separate form

  • 7/24/2019 Dai Kin Project Checklist

    24/29

    Request - 2- Ver. ELEC

    DAIKIN AC (Americas), Inc.

    1645 Wallace Drive, Suite 110Carrollton, TX 75006 USA

    TEL: 866-4DAIKINFAX: 972-245-1038www.daikinac.com

    Equipment Serial Number Information

    OUTDOOR UNIT(s)

    Outdoor Model #

    Outdoor SerialNumbers

    Quantityof Indoor

    Units

    Quantityof BSBoxes

    System 1

    System 2

    System 3

    System 4

    System 5

    System 6

    System 7

    System 8System 9

    System 10

    System 11

    System 12

    NOTE: if more than 12 Systems complete additional form

    Indoor UnitModel Number(s) and serial numbers:

    QTY Model # Serial No. QTY Model # Serial No.

  • 7/24/2019 Dai Kin Project Checklist

    25/29

    Request - 3- Ver. ELEC

    DAIKIN AC (Americas), Inc.

    1645 Wallace Drive, Suite 110Carrollton, TX 75006 USA

    TEL: 866-4DAIKINFAX: 972-245-1038www.daikinac.com

    Controller(s):

    Specialized Control(s)(Must complete Controls CHECKLIST)Model Number

    Itouch(DCS601C71) / WEB(DCS004A71)/ Bacnet (DMS502B71) / Lonworks(DMS504B71)

    Quantity Model Number Description

    Additional Accessor ies

    Manufacturer Model Number Description

    Status of Installation

    Refrigerant Piping Completed Yes No If no, anticipated completion date

    Electrical Wiring Completed Yes No If no, anticipatedcompletion dateDrain Piping Completed Yes No If no, anticipated completion date

    Please refer to the Daikin AC commissioning policy for full details regarding any fees associated with this Commission. Acommissioning date will not be scheduled until all required information is completed and submitted to Daikin AC. Within 3 businessdays a Daikin representative will contact you with a date. Please note:

    1. All equipment must be running and wiring issues identified prior to Daikin arriving onsite.2. You agree that you will be responsible for any tools and Freon needed on-site.3. Daikin request the system to be pressure tested to 550 PSIG for 24hrs.4. Daikin request a triple evacuated to below 500 microns and must hold 500 or below for 1 hr.

    5. Daikin requires a 2 wire, stranded, non-shielded, 18 gauge. This will ensure that there are nocommunication issues when the system is started up.

    The above must be achieved before DAIKIN arrives on-site to complete this commission. If thisis not completed when Daikin arrives you will be charged an extra fee.

    CCoonnttrraaccttoorrSSiiggnnaattuurree:Date Submitted:

    ..

    Internal Use Only SRO Number:________

  • 7/24/2019 Dai Kin Project Checklist

    26/29

    Checklist-1- Ver. ELEC

    DAIKIN AC (Americas), Inc.

    1645 Wallace Drive, Suite 110Carrollton, TX 75006 USA

    TEL: 866-4DAIKINFAX: 972-245-1038www.daikinac.com

    Pre-Commissioning Checklist required 48 hours before a scheduled

    commission.In an effort to provide the highest level of service, the following checklist is provided to insure that all

    necessary installation items are completed prior to a scheduled supervised commissioning of VRV andVRV-S systems. Please fill out the form completely and email to [email protected] FAX 972-245-1038. For a supervised system commissioning, submit this form at least48 hours prior to thescheduled commissioning. The below listed installation related items must be completed prior to ourarrival. Failure to complete the items listed below may result in additional charges per the Daikin ACCommissioning Policy. Please fill out 1 per system.

    Commissioning SRO#:___________INSTALLING CONTRACTOR AND SITE INFORMATION:

    Installing Contractor: Telephone:

    E-Mail: Fax:

    Job/Location Name:

    Site Address:

    City: State: Zip:

    Number of Outdoor Units: Number of Indoor Units:

    Install Completion Date: Requested Commissioning Date:

    SITE CHECKLIST

    1. REFRIGERANT PIPING Yes No(a) Has all system piping been completed in accordance with installation

    guidelines?

    (b) Has the system piping been pressure tested and leak checked?

    If the system has been pressure tested, what pressure was applied?PSIG

    (c) Was a standing pressure test performed?

    What was the duration of the standing pressure test? HOURS

    (d) Has the system piping been evacuated?

    How many microns was the system evacuated to?MICRONS

    How long was the evacuation held? HOURS

    (e) Has the total liquid line length been calculated?

    List the total line lengths for each pipe size used?1/4 O.D. 3/8 O.D. 1/2 O.D.

    (f) Has the additional refrigerant charge been calculated?

    If charge has been calculated what is the amount? LBS OZ

    (g) Has all system piping been insulated, including RefNET and flare connections?

  • 7/24/2019 Dai Kin Project Checklist

    27/29

    Checklist-2- Ver. ELEC

    DAIKIN AC (Americas), Inc.

    1645 Wallace Drive, Suite 110Carrollton, TX 75006 USA

    TEL: 866-4DAIKINFAX: 972-245-1038www.daikinac.com

    SITE CHECKLIST (cont.)

    2. ELECTRICAL CONNECTIONSYes No

    (a) Have all line voltage connections been made to Indoor/Outdoor units?

    (b) Have all control wiring connections been made?

    (c) Have the remote controllers been installed?

    (d) Are any Remote sensors being used?

    If so, where are they installed?

    (e) What type and gauge wirewas used for control wiring?(i.e. 18AWG stranded non-shielded)?

    TYPE: GAUGE:

    (f) What is the supplied line voltage?

    L1 L2 L3

    (g) If new construction, is building still being supplied with temporarypower?

    3. INDOOR UNITS / BRANCH SELECTOR BOXES Yes No

    (a) If using ducted fan coil units, has all duct work been connected?

    (b) Have the condensate drain lines been installed and was thesupplied vibration brake hose used?

    (c) Are any externally supplied condensate pumps being used?

    If yes, has condensate pump safety circuit been wired into indoorunit control board?

    (d) If using ducted fan coil units and factory installed return air filterhas been removed or if return air flow has been converted toreturn air to rear of unit, is any additional air filtration beingprovided?

    (e)Have Branch Selector boxes been wired for Line voltage and hascontrol wiring been connected?

    4. OUTDOOR UNITS Yes No

    (a) Have compressor shipping brackets been removed fromcompressor base?

    (b) Has outdoor unit been properly secured?

    (c) Has the outdoor unit been installed with proper clearances?

    (d) Has drainage of outdoor unit condensate been taken intoconsideration?

    I hereby certify that all items on t his lis t have been checked, and that all info rmation is co rrect.

    I further verify that the job is ready for commissi oning. I realize that if upon arrival to the commissioning the job is notready for start up, that I will be subject to additional fees as described in the Daikin Policies and Procedures Guide.

  • 7/24/2019 Dai Kin Project Checklist

    28/29

    Checklist-3- Ver. ELEC

    DAIKIN AC (Americas), Inc.

    1645 Wallace Drive, Suite 110Carrollton, TX 75006 USA

    TEL: 866-4DAIKINFAX: 972-245-1038www.daikinac.com

    Controls Checklist an Activation Keysi-Touch, BACnet Lonworks

    Send Form to: [email protected] PPlleeaasseeffii ll ll iinnAALLLLiinnffoorrmmaatt iioonnto activate

    Qualified Agent name:

    i - T o u c h C o n t r o l l e r

    MAC Address:white sticker on I-Touch

    Basic Software IDcase sensitive 7 digits

    Building LocationCity, State

    Building Type:(OFC,RES, Medical, BANK, etc )

    Number ofFloors

    Floor Size(area sq. ft.):

    24VAC Power toController:

    Yes No

    Number of Daikin Indoor Units Number of D3 Ports:

    Number of Daikin Outdoor units

    :

    Number of Systems:

    C r e s t r o n I n t e r f a c e w i t h i t o u c h ? Yes No

    WEB OPTION Yes No

    IP Address (must be static IP): WebSoftware ID:

    case sensitiveSubnet Mask:

    Default Gateway AddressHost Name:

    Preferred DNS Address:

    Alternate DNS Address: NOTE: MUST provide MAC address and Basic Software ID for WEB and PPD option

    P P D O p t i o n Yes No NOTE: MUST provide MAC address and Basic Software ID for the WEB and PPD option

    PPD Software ID:case sensitive

    Brand of KW Meter:

    Number of KW Meters: Model of KW Meter: B A C N E T

    : Yes No

    24VAC Power toController:

    Yes NoDevice Instance Number:

    Allowable range: 0-4194303)IP Address:

    (must be st atic IP):FRONT END SYSTEM

    MANUFACTURER:____________

    MODEL:_____________________

    Subnet Mask:

    Default Gateway Address:

    L O N W O R K S : Yes No

    24 VAC Power to Lonworks:Yes No

    FRONT END SYSTEMMANUFACTURER:________________

    MODEL:________________

    By completing these forms, you hereby certify that all items on this list have been checked, and that all information is c orrect. You further verify that the job isready for commissioning. You realize that if upon arrival to the commissioning the job is not ready for start up, that I will be subject to additional fees as describedin the Daikin Policies and Procedures Guide.

  • 7/24/2019 Dai Kin Project Checklist

    29/29

    DAIKINJlC

    bsolute comfort

    ommissioning

    Policies and

    Procedures

    Confirmation of Pre Commissioning Data

    I hereby certify that all

    items on

    this list have been checked and that all information is

    correct.

    I

    further

    verify that the

    job

    is ready for commissioning I realize

    that

    if upon arrival to

    the commissioning the

    job is

    not

    ready for

    start

    up

    that

    I

    will

    be

    subject

    to

    additional

    fees as

    described

    in

    the

    Daikin Policies and

    Procedures

    Guide.

    Contractor

    Signature:

    Date: