dahod, gujarati.e. 70643.57 ha, additional area reported is26314.17ha comprising wrd, gldc, gwrdc...
TRANSCRIPT
Pradhan Mantri Krishi Sinchayee Yojana (PMKSY)
District Irrigation Plan (2016-2020)DAHOD, GUJARAT
DAHOD
Pradhan Mantri Krishi Sinchayee Yojana (PMKSY)
District Irrigation Plan (2016-2020)DAHOD, GUJARAT
DAHOD
1
Contents Executive Summary .................................................................................... 5
Introduction ............................................................................................... 8
Background ............................................................................................................................................. 8
Vision ..................................................................................................................................................... 13
Objective ................................................................................................................................................ 13
Strategy/Approach ............................................................................................................................... 14
Programme Components .................................................................................................................... 15
Rationale/ Justification Statement .................................................................................................... 16
Methodology ......................................................................................................................................... 16
CHAPTER I ............................................................................................... 18
General Information of the District ................................................................................................... 18
1.1 District Profile ....................................................................................................................... 18
1.2 Demography .......................................................................................................................... 19
1.3 Biomass and Livestock .............................................................................................................. 20
1.4 Agro-Ecology, Climate, Hydrology and Topography............................................................. 21
1.5 Soil Profile ................................................................................................................................... 22
CHAPTER II .............................................................................................. 24
District Water Profile .............................................................................................................................. 25
2.1 Area wise & Crop wise Irrigation Status ................................................................................. 25
2.2 Production and Productivity of Major Crop........................................................................... 29
Table 10: Major Agriculture crops ................................................................................................. 30
2.3 Production of Horticulture Crops ............................................................................................ 30
2.4 Irrigation Based Classification ................................................................................................. 30
CHAPTER III ............................................................................................ 31
Water availability in Dahod District .................................................................................................. 31
3.1 Status of Water Availability ...................................................................................................... 31
3.2 Status of Ground Water ............................................................................................................ 33
3.3 Status of Canal Command Area ............................................................................................... 36
3.4 Existing type of Irrigation ......................................................................................................... 37
2
CHAPTER IV ............................................................................................. 39
Water Requirement ............................................................................................................................. 39
4.1 Domestic Water Demand .......................................................................................................... 39
4.2 Crop Water Requirement ......................................................................................................... 40
4.3 Livestock Water Demand ......................................................................................................... 42
4.4 Industrial Water Demand ......................................................................................................... 43
4.5 Water Demand for Power Generation .................................................................................... 43
4.6 Total Water Demand of the district for various sectors ....................................................... 43
4.7 Water Budget .............................................................................................................................. 44
CHAPTER V .............................................................................................. 46
Strategic Action Plan for Irrigation in District under PMKSY ....................................................... 46
5.1 Department wise Coverage of Area .......................................................................................... 46
5.2 Component wise Coverage of Area .......................................................................................... 47
5.3 Department wise Strategic Action Plan .................................................................................. 48
5.4 Component wise Strategic Action Plan ................................................................................... 49
5.5 Additional Area & Employment Generation: (Output & Outcome).................................... 53
5.6 Year wise Strategic Action Plan and Block wise total amount ............................................. 53
5.7 Monitoring and Evaluation ....................................................................................................... 54
5.8 Suggestions ................................................................................................................................. 55
Annexure .................................................................................................. 56
Annexure-1- Department wise Summary of Strategic Action Plan ............................................... 56
Annexure-2 Strategic Action Plan of Water Resource Department .............................................. 58
State Irrigation ..................................................................................................................................... 58
Taluka - Devgadh Bariya ................................................................................................................. 58
Taluka: Dahod .................................................................................................................................. 68
Taluka: Dhanpur .............................................................................................................................. 92
Taluka: Fatehpura ............................................................................................................................ 99
Taluka: Garbada ............................................................................................................................. 109
Taluka: Limkheda .......................................................................................................................... 119
Taluka: Zalod .................................................................................................................................. 126
Panchayat Irrigation .......................................................................................................................... 159
Annexure-3 – Strategic Action Plan of GWRDC ............................................................................ 166
3
Annexure-4 Strategic Action Plan of GLDC ................................................................................... 167
Annexure-5 Strategic Action Plan of GSWMA ............................................................................... 169
Annexure-6 Strategic Action Plan of GGRC ................................................................................... 169
List of Figures
Figure 1: Block wise Demographic Profile ............................................................................................ 20
Figure 2: Gross Irrigated and Rainfed Area ......................................................................................... 26
Figure 3: Area under Horticulture Crops .............................................................................................. 26
Figure 4: Block wise irrigational area .................................................................................................... 26
Figure 5: Block wise Domestic Water Requirement ............................................................................ 40
Figure 6: Crop Water Demand & Existing Water Potential ............................................................... 42
Figure 7: Water requirement for various sectors in 2015 and 2020 ................................................. 44
Figure 8: Dept. wise coverage of area (in %) ........................................................................................ 46
Figure 9: Component wise Coverage of Area (in %) ............................................................................ 48
Figure 10: Department wise Fund Distribution under PMKSY (in %) ............................................. 48
Figure 11: Component wise Fund Distribution under PMKSY (in %) .............................................. 49
Figure 12: Year wise Financial Outlay under PMKSY ......................................................................... 54
List of Tables
Table 1: District Profile ............................................................................................................................ 18
Table 2: Demographic Profile of Dahod ................................................................................................ 19
Table 3 & Figure 3: Social Category wise Population Distribution ................................................... 20
Table 4: Block Wise No of Livestock in Dahod District as per 2012 Livestock Census .................. 21
Table 5: Block Wise No of Livestock in Dahod District as per 2012 Livestock Census .................. 21
Table 6: Area wise and Crop wise Irrigation Status of Agriculture Crops (2013-14) in Dahod
District ....................................................................................................................................................... 25
Table 7: Block wise Area under Various Crops (Area in hectare) ...................................................... 28
Table 8: Block wise Area under Horticultural Crops .......................................................................... 28
Table 9: Major Agriculture crops ........................................................................................................... 30
Table 10: Horticulture Crops .................................................................................................................. 30
Table 11: Classification based on Irrigation .......................................................................................... 30
Table 12: Block wise Water availability from Canal (Major and Medium Irrigation) .................... 32
Table 13: Block wise water availability from Ground Water Sources ............................................... 32
Table 14: Water Availability from various sources .............................................................................. 33
Table 15: Ground Water status of Dahod .............................................................................................. 33
Table 16: Block wise Canal and other services Command .................................................................. 36
Table 17: Block wise Area under various irrigation infrastructure ................................................... 37
Table 18: Domestic Water Demand (MCM) ......................................................................................... 39
4
Table 19: Block wise Crop Water Requirement (in MCM) ................................................................. 40
Table 20: Crop wise Water requirement ............................................................................................... 41
Table 21: Livestock Water Requirement ............................................................................................... 42
Table 22: Animal wise Water Requirement .......................................................................................... 43
Table 23: Industry wise water demand .................................................... Error! Bookmark not defined.
Table 24: Present Water Demand of the district for various sectors ................................................ 43
Table 25: Total Water Demand of the district for various sectors 2020 .......................................... 44
Table 26: Block wise Water Budget ....................................................................................................... 45
Table 27: Dept. wise coverage of area .................................................................................................... 46
Table 28: Department wise Fund Distribution under PMKSY .......................................................... 48
Table 29: Component wise Financial Outlay for PMKSY ................................................................... 50
5
Executive Summary
Pradhan Mantri Krishi Sinchai Yojana (PMKSY) is a national mission to improve farm
productivity and to ensure better utilization of the resources in the country. There are
various objective mentioned in the guidelines of PMKSY Scheme, but its major objective
is to achieve convergence of investments in irrigation at the field level, expand cultivable
area under assured irrigation (Har Khet ko pani), improve on-farm water use efficiency
to reduce wastage of water, enhance the adoption of precision-irrigation and other water
saving technologies (More crop per drop), enhance recharge of aquifers and introduce
sustainable water conservation practices by exploring the feasibility of reusing treated
municipal based water for peri-urban agriculture and attract greater private investment
in precision irrigation system. The scheme also aims at bringing concerned
Ministries/Departments/Agencies/Research and Financial Institutions engaged in
creation/use/recycling/potential recycling of water, brought under a common platform,
so that a comprehensive and holistic view of the entire "water cycle" is taken into
account and proper water budgeting is done for all sectors namely, household,
agriculture and industries.
Thisreport focuses primarily on the scheme to understand fundamental demand and
funds required to fulfil the water necessity of Dahod Distirct. In the report all water
related components are analyzed and subjected to extract the data composing all the
necessary information. Mentioned below is the extract of the report providing clear
impression of demand and availbilty related to various components, on the basis of
several departments.
District Water Profile: The Dahod district having an area of 3655sq km forms a
border district in the eastern part of the Gujarat and comes under the tribal and drought
prone area. District receives medium intensity monsoon rainfall of 372 to 1104 mm
during SW monsoon with an average of 745 mm. It will be good to harness the available
monsoon rainfall runoff for artificial recharge to the ground water through construction
of check dams, recharge shaft, percolation tanks, site specific recharge bore wells / dug
wells, etc.In Dahod district, the overall stage of groundwater development is moderate
(49.87%), all the seven talukas have been categorized as safe. However, there is low yield
in inland hard rock areas.
Yield per Hectare of Major Crops: The yield levels of major crops in the district, in
Kharif season is higher under rainfed conditions, where as in summers and Rabi
cultivation is done in irrigated conditions. Major irrigation of horticulture crop is being
done in irrigated area, while only 10% of the fruits production land is reported to be
rainfed. Yields in Dahod district are reported to be less because of various factors. By
enhancing the water resources availability for irrigation purpose through rainwater
6
harvesting, soil & water conservation measures, the productivity of crops can be
enhanced further.
Existing Type of Irrigation: There is 16850 ha. of total canal area reported in the
district out of which 7203.2 ha. is developed area. There are large number of tube wells
and bore wells reported in the district area adding to the ground water potential along
with 46 community ponds under surface water. There is also large number of wells,
reported to be the most viable source of irrigation. There are wells in each block and
Limkheda block has highest no. i.e. 9905 wells out of 31649 total wells.
Availability of Water Sources &Demand for Water Sources:As calculated, a
total of 110.39 MCM surface water and 372.53 MCM ground water is available at Dahod
district. In current scenario, the total water demand of the district is 1674.33MCM and
the estimated water demand for the year 2020 is 1692.27 MCM.
Component wise Planned Coverage of Area & Financial Outlay: Out of total
area 70643.57 ha covered, 42% of the total i.e. 29822.4 ha of land is being covered
under per drop more crop component, followed by Har Khet ko Pani component which
shares 22234 ha (31%). Major share in the total amount is of AIBP with 64% i.e.107585
lakhs followed by Har Khet ko Pani having 17% in the total share. Cost invested in per
drop more crop scheme is 13% of the total i.e. 21249 lakh rupees. Funds distributed by
ATMA is Rs. 117.7003 Lakh
Department wise Planned Coverage of Area & Financial Outlay:The overall
area covered under various departments is 70643.57 ha. out of whichWater Resource
Department is expected to cover an area of 37104 hectare under Panchayat and State
irrigation activities. Gujarat Green Revolution Company Ltd. (GGRC) which is
implementing all the micro irrigation schemes of the state is expected to cover a total
area of 23550.4 ha under drip and sprinkler irrigation. Gujarat State Watershed
Management Agency (GSWMA) is expected to cover a total area of 5653.17 ha under
various component of watershed.
Total planned outlay in strategic action plan of Dahod district is 167664 lakh rupees.
Out of the total cost 72%is incurred by State Irrigation Water Resource Department,
which counts to121158.55 lakhs, along with 13% of Panchayat Irrigation Water Resource
Department having cost of 22162 lakhs. GGRC has 6% of the total share of amount. It
will incur 10550.58 lakh in four years
Strategic Action Plan under PMKSY: Year wise financial outlay for the four years
can is calculated in the report, i.e. in financial year 2016-17, a budget of Rs. 20658.5 lakh
is required. In the subsequent three years, Rs. 121048.0 lakh, Rs. 14924.4 lakh and
7
Rs.11033.3 lakh budget is estimated for various departments. Major share of the amount
will be spent in 2017-18 as reflected by various departments.
Expected Output and Outcome: Out of total area mentioned in the PMKSY Scheme
i.e. 70643.57 ha, additional area reported is26314.17ha comprising WRD, GLDC,
GWRDC and PMKSY Watershed total area.
The employment generation is being calculated for Dahod district by taking 40% cost of
watershed dept. and 20% cost of all other dept. as labor charge, which is 35411.851
Lakhs. This cost is divided by Rs.178 to generate total Man-days. The total man-days
after calculation come to19894298. All this generates total number of individuals who
will be employed for 4 years under the project: 13626.23.
The PMKSY interventions are likely to generate an additional income of Rs.
6631.171lakh to the farmers of the district. This is based on the assumption thatat least
60% of potential utilised and Rs.42,000 per ha incremental income from rainfed to
irrigated farming.
8
Introduction
Background
Preparation of decentralized area specific district planning process visualized in various
plans took concrete shape through the years and initiatives like specific guidelines on
methodologies and processes for preparation of district plans; framework for
preparation of perspective plan, medium term and annual plans by then planning
commission in 1969 and the 73rd and 74th constitutional amendments conferring
constitutional status to Panchayats at district and sub district level, local self-
government in urban areas; constitution of district planning committee to consolidate
the plans prepared at Panchayats and municipalities and preparation of a draft
development plan for the whole district.
The decentralized planning process was strengthened further through emphasis by
planning commission on preparation of district level plans and making it an integral
part of the process of preparation of the states 11th five year plan . Planning commission
issued guidelines in August 2006 on the preparation of the district plans. The guideline
defines the district planning as „…the process of preparing an integrated plan for the
local government sector in a district taking into account the resources (natural, human
and financial) available and covering the sectoral activities and schemes assigned to the
district level and below and those implemented through local governments in a state.
The document that embodies this statement of resources and their allocation for various
purposes is known as the District Plan”.
Government of India through a resolution in National Development Council on 29th May
2007 conceived a special Additional Central Assistance Scheme to address the slow
growth of agriculture and allied sectors by incentivizing states to draw up plans for their
agriculture sectors more comprehensively. The NDC resolution states "GoI will
introduce a new Additional Central Assistance scheme to incentivize states to draw up
plans for their agriculture sector more comprehensively, taking agro-climatic
conditions, natural resource issues and technology into account, and integrating
livestock, poultry and fisheries, etc. This will involve a new scheme for Additional
Central Assistance (ACA) to State Plans, administered by the Union Ministry of
Agriculture over and above its existing Centrally Sponsored Schemes, to supplement the
state-specific strategies including special schemes for beneficiaries of land reforms. The
newly created National Rainfed Area Authority will, on request, assist states in planning
for rainfed areas".
9
The NDC in its resolution advised the states to prepare a comprehensive district
agriculture plans (C-DAP) that will fully utilize available resources and will include
allied agriculture sectors. Further, GOI issued a manual on preparation of
comprehensive district agriculture plans to help the states prepare C-DAP. As per these
guidelines, the objective of district planning is „to design an integrated and participatory
action plan for the development of local area in general and agriculture and allied
sectors in particular‟. The objectives of Comprehensive District Agriculture Plan (C-
DAP) are:
To prepare a Comprehensive District Agriculture Plan (C-DAP) through
participatory process involving various organisations and stakeholders.
To enable optimum utilisation of scarce natural, physical & financial resources.
To assess and plan for the infrastructure required to support the agriculture
development.
To establish linkages with the required institutional support services, like credit,
technology transfer, ICT, research etc.
To evolve an action plan for achieving sustainable agricultural growth with food
security and cropping system that will improve farmers‟ income.
The guidelines wanted the state/district authorities to (i) ensure that the agricultural
plans are prepared for the district and then integrated into the agricultural plans of the
state based on the agro-climatic conditions, availability of technology, trained
manpower and natural resources; (ii) the local needs / crops / feed and fodder / animal
husbandry / dairying / fisheries / priorities are reflected in the plan; (iii) the
productivity gaps for important crops and livestock and fisheries are reduced; and (iv)
the returns to the farmers from these are maximized.
The latest move in the process of strengthening of decentralized planning process was
the Government of India guidelines issued in 2015 in the form of a template for the
preparation of District Irrigation Plan (DIP) and State Irrigation Plan (SIP) as part of
the Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) program and made the
preparation of DIP and SIP mandatory for the state to receive funds from the program.
The present District Irrigation Plan (DIP) report is a product of these long drawn efforts
of Government of India to strengthen the decentralized planning process in the country
focusing on the vital resource i.e., water.
Water is of vital importance for human & animal life, maintenance of ecological balance
and promotion of developmental activities. Considering its vital importance and ever
increasing demand for water in the face of population growth, urbanization &
industrialization &considerations of climatic change, making water, an increasingly a
scarce resource, available to multiple uses, planning and management of water
10
resources, utilization of water economically, optimally and equitably assumes greater
importance.
According to the 12th Five Year Plan, the water budget estimates of India by Ministry of
Water Resources suggests an availability of 1123 Billion Cubic Meters (BCM) against a
current estimated demand of 710 BCM. The Standing Committee of the Ministry of
Water Resources estimates that this water demand will rise to 1093 BCM by 2025.
Though the existing water availability in the immediate future seems to be adequate,
with the near constant supply of water resources in the face of increasing demand on
account of population growth, urbanisation and industrialization will strain the water
supply-demand balance.
The per capita water availability which stood at 5,177 cubic meters in 1951 was reduced
to 1820 cubic meters in 2001 while the international prescribed limit is 1800 cubic
meters. The projected per capita availability of water is 1341 cubmic meters in 2025 and
1140 cubmic meters in 2050 suggesting the shortage of water in the medium term1.
Further, the all India water balance estimates does not reflect the variations in water
balance across time and space- certain areas having a positive water balance and the
others facing acute shortage. The problem is further accentuated by water quality
related issues.
With the abundant surface and ground water supply in the first five decades since
Independence, more than 80 percent of the total available water resources were
allocated for irrigation purposes and the rest meeting the domestic and industrial
demands. In a recent study2 on the demand for water from agriculture, domestic and
industrial uses in 2000, 2025 and 2050 seems to suggest that domestic demand (34
BCM in 2000, 66 BCM in 2025 and 101 BCM in 2050) and industrial demand (42 BCM
in 2000, 92 BCM in 2025 and 161 BCM in 2050) for water will utilize the total balance
water available while agriculture demand for water will be (605 BCM in 2000, 675 BCM
in 2025 and 637 BCM in 2050). This change is partly because of the changing sectoral
contributions of India‟s GDP but also partly because of dynamics of irrigation
development in the country where the initial expansion in area under irrigation is
propelled by the availability of abundant water resources and availability of good quality
land. This is no longer the case in many of the states where the availability of land and
water are serious constraints for further expansion of irrigation. Further, as per then
planning commission up to March 2012 out of 141 million hectares of net sown area in
the country 114 (or 81%) million hectares is Irrigation Potential Created (IPC) and 88
1 Ministry of Water Resources (2011): Strategic Plan for Ministry of Water Resources, Government of India, New
Delhi. 2Amarasinghe, U.A., Shah T., Turral, H. and Anand, B.K. 2007. India’s water future to 2025-2050:
Business-as-usual scenario and deviations. Research Report 123, International Water Management
Institute, Colombo.
11
(or 62%) million hectares is Irrigation Potential Utilised (IPU) leaving almost 20% of
irrigated potential unutilized. This leaves 40 percent of the net sown area in the country
dependent on rainfall which makes farming a high risk and less productive.
The competing demands for water resources and the emerging issues and concerns were
to be addressed through certain basic principles and commonality in approaches in
dealing with planning, development and management of water resources3 under an
Integrated Water Resource Management framework. The main objectives of water
resource management as delineated in National Water Policy 2012 are:
Planning, development and management of water resources need to be governed by
common integrated perspective considering local, regional, State and national
context, having an environmentally sound basis, keeping in view the human, social
and economic needs.
Principle of equity and social justice must inform use and allocation of water.
Good governance through transparent informed decision making is crucial to the
objectives of equity, social justice and sustainability. Meaningful intensive
participation, transparency and accountability should guide decision making and
regulation of water resources.
Water needs to be managed as a common pool community resource held, by the
state, under public trust doctrine to achieve food security, support livelihood, and
ensure equitable and sustainable development for all.
Water is essential for sustenance of eco-system, and therefore, minimum ecological
needs should be given due consideration.
Safe Water for drinking and sanitation should be considered as pre-emptive needs,
followed by high priority allocation for other basic domestic needs (including needs
of animals), achieving food security, supporting sustenance agriculture and
minimum eco-system needs. Available water, after meeting the above needs, should
be allocated in a manner to promote its conservation and efficient use.
All the elements of the water cycle, i.e., evapo-transpiration, precipitation, runoff,
river, lakes, soil moisture, and ground water, sea, etc., are interdependent and the
basic hydrological unit is the river basin, which should be considered as the basic
hydrological unit for planning.
Given the limits on enhancing the availability of utilizable water resources and
increased variability in supplies due to climate change, meeting the future needs will
depend more on demand management, and hence, this needs to be given priority,
especially through (a) evolving an agricultural system which economizes on water
use and maximizes value from water, and (b) bringing in maximum efficiency in use
of water and avoiding wastages.
3Ministry of Water Resources, National Water Policy, 2012, Government of India, New Delhi.
12
Water quality and quantity are interlinked and need to be managed in an integrated
manner, consistent with broader environmental management approaches inter-alia
including the use of economic incentives and penalties to reduce pollution and
wastage.
The impact of climate change on water resources availability must be factored into
water management related decisions. Water using activities need to be regulated
keeping in mind the local geo climatic and hydrological situation.
The National Water Policy 2012 drives the water resource management program
planning and management in the country. Government of India launched Pradhan
Mantri Krishi Sinchayee Yojana (PMKSY) to address the constraints to providing
assured irrigation as well as increasing efficiency and productivity of current water use
to bring more prosperity to the rural areas. Priorities of Government of India were
reflected in the Hon‟ble President‟s address to the joint Session of the Parliament of 16th
Lok Sabha where he indicated that “Each drop of water is precious. Government
is committed to giving high priority to water security. It will complete the
long pending irrigation projects on priority and launch the ‘Pradhan
Mantri Krishi Sinchayee Yojana’ with the motto of ‘Har Khet Ko Paani’.
There is a need for seriously considering all options including linking of
rivers, where feasible; for ensuring optimal use of our water resources to
prevent the recurrence of floods and drought. By harnessing rain water
through ‘Jal Sanchay’ and ‘Jal Sinchan’, we will nurture water
conservation and ground water recharge. Micro irrigation will be
popularized to ensure ‘Per drop-More crop”.
PMKSY has been approved with an indicative outlay of Rs.50,000 crore over a period of
five years from 2015-16 to 2019-20. The programme is an amalgamation of on-going
schemes of Ministry of Water Resources, River Development and Ganga Rejuvenation,
Ministry of Agriculture & Cooperation and Ministry of Rural Development. The existing
schemes AIBP, CADWM, MI, SWMA, and Watershed & Convergence with MGNREGA
were brought together under the umberella program of PMKSY. Further the scheme
seeks convergence with scheme likeMahatma Gandhi National Rural Employment
Guarantee Scheme (MGNRES), Rashtriya Krishi Vikas Yojana (RKVY), Jawaharlal
Nehru National Solar Mission and Rural Electrification programmes (JLNNSM&REP),
Rural Infrastructure development Fund (RIDF), Member of Parliament Local Area
Development Scheme (MPLAD), Member of Legislative Assembly Local Area
Development Scheme (MPLALAD), Local body funds (LBF), Working Plan of State
Forest Department (WPSFD) etc.
13
The PMKSY will be implemented in an area development mode only by adopting a
decentralized state level planning and projectised execution structure that will allow the
state to draw up their own irrigation development plans based on DIPs and SIPs with a
horizon of 5-7 years. The program will be supervised and coordinated utilizing the
existing mechanism and structure available under Rashtriya Krishi Vikas Yojana
(RKVY) program with state agriculture department acting as the State Nodal Agency for
implementation of PMKSY. However, the implementing departments for the four
components like AIBP, PMKSY (Har Khet Ko Pani), PMKSY (Per drop more crop) and
PMKSY (watershed development) will be decided by the respective program
ministry/department.
The funds under this program would be provided to the states as per the pattern of
assistance of Centrally Sponsored Schemes (CSS) decided by the Ministry of Finance
and NITI Aayog. During 2015-16 the existing pattern of assistance of ongoing scheme
will be continued. An outlay of Rs. 50,000 crore has been approved for 2015-20. The
financial assistance provided to the state governments from this centrally sponsored
scheme is subject to fulfillment of certain conditions. Firstly, a state will become eligible
to access PMKSY fund only if it has prepared the District Irrigation Plans (DIP) and
State Irrigation Plan (SIP), excepting for the initial year, and the expenditure in water
resource development for agriculture sector in the year under consideration is not less
than the baseline expenditure, which is defined as the average of the expenditure in
irrigation sector irrespective of the department in the state plan in three years prior to
the year under consideration. Secondly, State will be given additional weightage for
levying charges on water and electricity for irrigation purposes, so as to ensure
sustainability of the programme. Thirdly, interstate allocation of PMKSY fund will be
decided based on (i) share of percentage of unirrigated area in the state vis-à-vis
national average including prominence of areas classified under Dessert Development
Programme (DDP) and Drought Prone Area Development Programme (DPAP) and (ii)
increase in percentage share of expenditure on water resource development for
agriculture sector in State Plan expenditure in the previous year over three years prior to
it (iv) improvement in irrigation efficiency in the state.
Vision The overreaching vision of Pradhan Mantri Krishi Sinchayee Yojana (PMKSY) will be to
ensure access to some means of protective irrigation to all agricultural farms in the
country, to produce „per drop more crop‟, thus bringing much desired rural prosperity.
Objective The objectives of the PMKSY program are to:
a) Achieve convergence of investments in irrigation at the field level (preparation of
district level and, if required, sub district level water use plans).
14
b) Enhance the physical access of water on the farm and expand cultivable area under
assured irrigation (Har Khet ko pani),
c) Integration of water source, distribution and its efficient use, to make best use of
water through appropriate technologies and practices.
d) Improve on-farm water use efficiency to reduce wastage and increase availability both
in duration and extent,
e) Enhance the adoption of precision-irrigation and other water saving technologies
(More crop per drop).
f) Enhance recharge of aquifers and introduce sustainable water conservation practices
g) Ensure the integrated development of rainfed areas using the watershed approach
towards soil and water conservation, regeneration of ground water, arresting runoff,
providing livelihood options and other NRM activities.
h) Promote extension activities relating to water harvesting, water management and
crop alignment for farmers and grass root level field functionaries.
i) Explore the feasibility of reusing treated municipal waste water for peri-urban
agriculture, and
j) Attract greater private investments in irrigation.
Strategy/Approach To achieve these objectives PMKSY adopted strategies that include
a) Creation of new water sources; repair, restoration and renovation of defunct water
sources; construction of water harvesting structures, secondary & micro storage,
groundwater development, enhancing potentials of traditional water bodies at village
level like Jal Mandir (Gujarat); Khatri, Kuhl (H.P.); Zabo (Nagaland); Eri, Ooranis
(T.N.); Dongs (Assam); Katas, Bandhas (Odisha and M.P.) etc.
b) Developing/augmenting distribution network where irrigation sources (both assured
and protective) are available or created;
c) Promotion of scientific moisture conservation and run off control measures to
improve ground water recharge so as to create opportunities for farmer to access
recharged water through shallow tube/dug wells;
d) Promoting efficient water conveyance and field application devices within the farm
viz, underground piping system, Drip & Sprinklers, pivots, rain-guns and other
application devices etc.;
e) Encouraging community irrigation through registered user groups/farmer producers‟
organisations/NGOs; and
f) Farmer oriented activities like capacity building, training and exposure visits,
demonstrations, farm schools, skill development in efficient water and crop
15
management practices (crop alignment) including large scale awareness on more crop
per drop of water through mass media campaign, exhibitions, field days, and extension
activities through short animation films etc.
Programme Components PMKSY has the following four programme components
1 Accelerated Irrigation Benefit Programme(AIBP) a) To focus on faster
completion of ongoing Major and Medium Irrigation including National Projects.
2 PMKSY (Har Khet ko Pani) a) Creation of new water sources through Minor
Irrigation (both surface and ground water); b) Repair, restoration and renovation of
water bodies; strengthening carrying capacity of traditional water sources, construction
rain water harvesting structures (Jal Sanchay); c) Command area development,
strengthening and creation of distribution network from source to the farm; d) Ground
water development in the areas where it is abundant, so that sink is created to store
runoff/ flood water during peak rainy season. e) Improvement in water management
and distribution system for water bodies to take advantage of the available source which
is not tapped to its fullest capacity (deriving benefits from low hanging fruits). At least
10% of the command area is to be covered under micro/precision irrigation. f) Diversion
of water from source of different location where it is plenty to nearby water scarce areas,
lift irrigation from water bodies/rivers at lower elevation to supplement requirements
beyond IWMP and MGNREGS irrespective of irrigation command. g) Creating and
rejuvenating traditional water storage systems like Khatri, Kuhl etc. at feasible locations.
3 PMKSY (Per Drop More Crop) a) Programme management, preparation of
State/District Irrigation Plan, approval of annual action plan, Monitoring etc. b)
Promoting efficient water conveyance and precision water application devices like drips,
sprinklers, pivots, rain-guns in the farm (Jal Sinchan); c) Topping up of input cost
particularly under civil construction beyond permissible limit (40%), under MGNREGS
for activities like lining inlet, outlet, silt traps, distribution system etc. d) Construction of
micro irrigation structures to supplement source creation activities including tube wells
and dug wells (in areas where ground water is available and not under semi critical
/critical /over exploited category of development) which are not supported under AIBP,
PMKSY (Har Khet ko Pani), PMKSY (Watershed) and MGNREGS as per block/district
irrigation plan. e) Secondary storage structures at tail end of canal system to store water
when available in abundance (rainy season) or from perennial sources like streams for
use during dry periods through effective on-farm water management; f) Water lifting
devices like diesel/ electric/ solar pumpsets including water carriage pipes,
underground piping system. g) Extension activities for promotion of scientific moisture
conservation and agronomic measures including cropping alignment to maximise use of
available water including rainfall and minimise irrigation requirement (Jal sarankchan);
16
h) Capacity building, training and awareness campaign including low cost publications,
use of pico projectors and low cost films for encouraging potential use water source
through technological, agronomic and management practices including community
irrigation. i) The extension workers will be empowered to disseminate relevant
technologies under PMKSY only after requisite training is provided to them especially in
the area of promotion of scientific moisture conservation and agronomic measures,
improved/ innovative distribution system like pipe and box outlet system, etc.
Appropriate Domain Experts will act as Master Trainers. j) Information Communication
Technology (ICT) interventions through NeGP-A to be made use in the field of water use
efficiency, precision irrigation technologies, on farm water management, crop alignment
etc. and also to do intensive monitoring of the Scheme.
4 PMKSY (Watershed Development)
a) Effective management of runoff water and improved soil & moisture conservation
activities such as ridge area treatment, drainage line treatment, rain water harvesting,
in-situ moisture conservation and other allied activities on watershed basis. b)
Converging with MGNREGS for creation of water source to full potential in identified
backward rainfed blocks including renovation of traditional water bodies
Rationale/ Justification Statement In reference to the status and need of irrigation, the water resource management including
irrigation related priorities was identified for Dahod district by the peoples‟ representatives of
district with support from administration and technical experts. For instance the reports of
Strategic Research and Extension Plan (SREP) prepared under ATMA program, Comprehensive
District Agriculture Plan (C-DAP) prepared as part of Rashtriya Krishi Vikas Yojana (RKVY),
Potential Linked Credit Plans (PLP) of NABARD and the Integrated District Development Plan
etc identified number of irrigation related issues for Dahod district including the (i) protection
of crops from abiotic stress factors including flashfloods; (i) promoting water use efficiency
through sprinkler and drip irrigation; (iii) promoting protected polyhouse cultivation to
minimize risk factors and enhance quality and productivity; (iv) Improvement of on-farm water
delivery and efficiency of existing irrigation systems; (v) promotion of soil conservation of arable
& non-arable land through engineering measures; (vi) creation of new water harvesting
structures, check dams, ponds, tanks, etc and (vii) land improvement measures.
Methodology During the course of preparation of District Irrigation Plan (DIP) the team visited
Dahod district to collect data and have interaction with all the stakeholders.
Methodology adopted to prepare DIP is outlined in brief as under:
17
Collection of primary and secondary data from multiple sources including Season
and Crop Reports, Statistical Handbook, District Census Handbook and other
published documents and websites of different departments.
Meetings with state government departments and related institutions were held
and meeting through VC was also held with state level authorities.
GIS maps of the area‟s/clusters were studied to understand the land morphology,
topography of the district.
Discussions and interviews were held with officers of agriculture department,
horticulture department, sub division soil conservation office, Agriculture
Technology Management Agency (ATMA), District Watershed Development
Agnecy (DWDA) of District Rural Development Authority (DRDA), Animal
Husbandry department, Water resource department and identified the key issues
and key focus areas of the region. Discussion with District Development Manager
of NABARD for Dahod district was also held during the visit.
Team members also participated in the State Level workshop and held active
discussions with GoI officers, State Level officers and scientists of various
institutions including Indian Meteorological Department (IMD) and Krishi Vigyan
Kendra (KVK) office etc.
On the basis of detailed discussion and analysis of data, the team arrived at the
projections of various components of PMKSY and Department wise plan for four years
from 2016-17 to 2019-20 was prepared which is given in Annexure V
18
CHAPTER I
General Information of the District
1.1 District Profile
Dahoddistrict is situated in the eastern part of main peninsular shield of Indian
subcontinent. The district forms part of Mahi river basin, which is one of main rivers in
Gujarat. Major occupation of the district has being agriculture and animal husbandry.
The district is tribal and drought prone. Dahoddistrict has a geographical area of about
3655 sq.km (as per state territory) and about 3712 sq. km as per village papers.
The district was a part of Panchamahal district in 1999. The administrative divisions of
the district have been reconstituted recently. The district comprises of seven talukas viz.
Devgad Baria, Dhanpur, Dahod, Fatehpura, Garbada, Zalod& Limkheda. Total No of
villages of the district are 696.
Latitude and Longitude:
The latitude of Dahod district is
20.30 to 23.30 North and longitude
is 73.15 to 74.30 East. The district is
covered by Madhya Pradesh state,
Rajasthan state and other districts
of Gujarat viz. Vadodara & Godhra.
Name of the District
District code
Dahod 20
Latitude Longitude
20.30 to 23.30 N 73.15 to 74.30 E
Table 1: District Profile
Administrative Setup:
The district has 8 talukas for its Administrative control as well as for development. Out
of 8 Talukas 5 Talukas are having Tribal Population. The headquarters of the district is
Dahod taluka. The District Collector is the overall administrative head. Down below
there are various district level officers of the State Government to perform/execute the
various regulatory/development functions assigned to them. There are 696 villages in
the districts and 470 panchayats in the district.
19
Although in the report 7 Talukas have been considered as Sanjeli blocks data is not
available from all the sources seperatly. Data of this particular block is along with the
data Zalod block in the district.
1.2 Demography
As per the 2011 census, the population of the district was 2127086 out of which number
of males and females were 1,068,651 and 1,058,435 respectively. As per 2011 census,
90.99% population of Dahod district lives in rural areas. The total population of Dahod
district living in rural areas is 1,935,461, of which males and females are 970,963 and
964,498 respectively. In rural areas of Dahod district, sex ratio is 993 females per 1000
males. If child sex ratio data of Dahod district is considered, figure is 950 girls per 1000
boys. Child population in the age 0-6 is 387,164 in rural areas of which males were
198,501 and females were 188,663. The child population comprises 20.44 % of total
rural population of Dahod district.
Literacy rate in rural areas of Dahod district is 56.36 % as per census data 2011. Gender
wise, male and female literacy stood at 67.98 and 44.78 percent respectively. In total,
872,552 people were literate of which males and females were 525,140 and 347,412
respectively.
Name of the
Blocks/ Taluka
No. of
Villages Covered
Population
Male Female Total Children (0-6 Yrs.)
Fatepura 102 119947 118169 238,116 45,435
Zalod & Sanjeli 160 238932 234341 473,273 87,946
Limkheda 152 152511 153758 306,269 57,532
Dohad 89 242015 238830 480,845 83,813
Garbada 39 99978 98901 198,879 42,476
Devgadbaria 91 124446 124889 249,335 38,906
Dhanpur 90 90822 89547 180,369 38,722
Total 723 1,068,651 1,058,435 2,127,086 394,830
Table 2: Demographic Profile of Dahod
20
Figure 1: Block wise Demographic Profile
Caste wise total population of the district is 2127086, the district was having 43942
schedule caste members (2.1%), 1608718 (75.6%) schedule tribe members, which
records to be the highest caste population in the district and 474426 (22.3%) general
members during 2011. Block wise SC, ST and general population is detailed in Table.
SC ST General Total
Blocks/ Taluka No. of Member No. of Member No. of Member No. of Member
Fatepura 3620 222551 11945 238116
Zalod & Sanjeli 6574 428774 37925 473273
Limkheda 6258 194022 105989 306269
Dohad 10882 394119 75844 480845
Garbada 5619 191130 2130 198879
Devgadbaria 9421 49930 189984 249335
Dhanpur 1,568 128192 50609 180369
Total 43942 1608718 474426 2127086
Table 3& Figure 3: Social Category wise Population Distribution
1.3 Biomass and Livestock
The major source of livelihood other than agriculture is animal husbandry in the district
of Dahod. In 2012, it was reported that there are total of 2561340 cattles and draft
animals (including buffalo). Among the small animals, the blocks of Jalhod (159090),
11
22
1423
9
12
8Fatepura
Jhalod
Limkheda
Dohad
Garbada
Devgadbaria
Dhanpur
2.1
75.6
22.3
SC
ST
General & OBC
21
Devgadbaria(135956) and Dahod (127547) had a large no of poultry. Similarly, the
blocks of Jalhod (122516) and Limekheda (115028) had a large number of goats; the
blocks of Dahod (2067) Jalhod (1545) had large no of sheep in the district.
Name of
Block/Taluka
Small Animals
Poultry (No.)
Ducks (No.)
Pigs (No.)
Goats (No.)
Sheep (No.)
Devgadbaria 135956 10 10 114993 15
Dhanpur 119934 841 0 86372 0
Dahod 127547 0 0 94445 2067
Fatepura 118386 491 0 97860 656
Garbada 39240 0 0 47901 680
Zalod & Sanjeli 159090 844 0 122516 1545
Limkheda 113236 2088 0 115028 14
Total 813389 4274 10 679115 4977 Table 4: Block Wise No of Livestock in Dahod District as per 2012 Livestock Census
Among the large animals the blocks of Jalhod (57624), Dahod (51255) and Fatepur
(40575) had a large no of indigenous cow population. The blocks of Dahod (1804), and
Jalhod (754) had the largest number of hybrid cow population. The blocks of Jalhod
(56202) and Limkheda (54450) had the largest number of buffalo population.
Name of Block/Taluk
a
Large Animals
Indigenous Cow (Nos.)
Hybrid Cow (No.)
In Descriptive Buffalo
(No.)
Draft Animal (Buffalo/yak/bulls/a
ny other (Nos.)
Total (Small +Large
animals)
Devgadbaria 26395 441 46868 67258 391946
Dhanpur 27718 373 31994 54598 321830
Dahod 51255 1804 44253 77183 398554
Fatepura 40575 146 53806 68080 380000
Garbada 27877 85 20654 35754 172191
Zalod & Sanjeli
57624 754 56202 99189 497764
Limkheda 39539 339 54450 74361 399055
Total 270983 3942 308227 476423 2561340 Table 5: Block Wise No of Livestock in Dahod District as per 2012 Livestock Census
1.4 Agro-Ecology, Climate, Hydrology and Topography
The district has semi-arid climate with three distinguished seasons i.e. kharif (June to
September), winter (October to January) and summer (February to May). The district
receives the rainfall through South-West monsoon which normally starts from middle of
June, July and August are the richer months for rainfall. The average monthly rainfall of
the district is 201.25 mm. Average number of rainy days in the district is 36.3. The more
22
rainfall received in the months of July and August and there after rainfall declined in the
months of September and October. However, scanty and uneven rainfall pattern is not
uncommon.
The average maximum temperature during summer months recorded was 42.9°C and
minimum temperature at 21.85° C. During winter months, the average temperature
ranges between 12.6°C and 43.4°C. Similarly, during rainy season, between the months
of June and September, average maximum temperature recorded was 37.3°C and
minimum temperature at 23.7°C. Source: IMD, Ahmeadabad
Agro Ecological Zone Type
Type of Terrain Normal Annual Rainfal (mm)
Average Monthly Rainfall (mm)
No of Rainy Days (No)
Gujarat Plains and Hill Region
Majority of soil is Sandy Loam
846 201.25 36.3
Average Monthly Temperature (°C)
Period
Summer(April-May) Winter(Oct-Mar) Rainy(June-Sept)
Min. Max. Mean Min. Max. Mean Min. Max. Mean
21.85 42.9 32.4 12.6 43.4 28 23.7 37.3 30.5
1.5 Soil Profile& Land Use
The soil of the district can be divided broadly into three categories depending upon the
source rock, namely the phyllite, granites and basalts. The granite normally gives rise to
sandy soil but where weathering is intense, sandy loam is produced. The phyllite
produced yellowish brown light soils but where weathering is deep, black soil produced.
The basaltic rock gives rise to variegated soil depending upon the degree of weathering.
The first stage of weathering produce light soil with splinters of morum where as in the
second stage medium soil of light brown to brownish black colour is produced. These
medium soils are more than a meter depth. The black cotton soils produced by intense
weathering of basalts are however deep, heavy and become sticky when saturated. They
have high fertility value.
Land Use: Total geographical area of the district is 371715 hectare. Net area under
cultivation of different crops is 224300 hectare. The percentage of net area sown to total
geographical area is 60.34%. Gross cropped area of the district is reported to be 310440
hectare.
23
24
25
CHAPTER II
District Water Profile The district of Dahod falls in Agro Ecological Sub Region (ICAR) of Madhya Bharat
plateau, Western Malwa plateau, Eastern Gujarat plain, Vindhyan and Satpura range
and Narmada Valley hot. It has moist semi-arid eco-sub region prominent. Agro Climate
zone of the district is middle Gujarat zone. The district has subtropical climate. It is hot
during summer and cold in winter. It receives rains ranging between 1000mm to
1150mm during the year. Major crops produced in the district are Maize, paddy, wheat,
gram and tur etc. there is also production of horticulture crops like mango, custard
apple, cabbage, bringal, and garlic etc.
2.1 Area wise & Crop wise Irrigation Status
The total area under cultivation in the district is 437059 ha. excluding the horticulture
production. The total irrigated area is 175998 ha i.e. 40% of the total land, leaving 60%
for it in Rainfed cultivation. The cereal crops produced in kharif season are mainly
maize and paddy along with tur in pulses, in Rabi season cultivation of gram is practiced
the most along with wheat in cereals. Crop wise area under irrigated and rainfed
situation is highlighted in the following table:
Crop Type
Kharif (Area in ha.) Rabi (Area in ha.) Summer(Area in ha.)
Total (Area in ha.)
Irri. Rain. Total Irri. Rain. Total Irri. Rain. Total Irri. Rain. Total
Cereals 13015 141297 154312 83531 430 83961 0 0 0 96546 141727 238273
Coarse Cereals
0 216 216 0 0 0 0 0 0 0 216 216
Pulses 0 22285 22285 28908 17785 46693 2879 0 2879 31787 40070 71857
Oil Seeds
0 35993 35993 495 0 495 612 0 612 1107 35993 37100
Fibre 387 1565 1952 0 0 0 0 0 0 387 1565 1952
Other crops
3499 23705 27204 37680 17785 55465 4992 0 4992 46171 41490 87661
Total 16901 225061 241962 150614 36000 186614 8483 0 8483 175998 261061 437059
*Any other crops means pulses, sugar crop, spicies & condiments, vegetables, other edible crop,
medicinal crop, fodder crops and other non-edible crops
Table 6: Area wise and Crop wise Irrigation Status of Agriculture Crops (2013-14) in Dahod District
26
Figure 2: Gross Irrigated and Rainfed Area
The district was having a total area of 24799 ha under horticulture crops during 2013-14. Out of the total area under horticulture crops fruits, vegetables, flowers and spices have area share of 26%, 55.5%, 16.4% and 2.2% respectively.
Figure 3: Area under Horticulture Crops
Out of all the blocks Zalod has most of the irrigational area. It has almost 25% of437059
ha. of total land. The graph below shows about area wise irrigation in all the blocks of
Dahod district.
Figure 4: Block wise irrigational area
40.3
59.7
Irrigated
Rainfed
26.0
55.5
16.42.2
Fruit
Vegetable
Spices
Flower
16.1
10.1
10.0
16.19.9
24.9
12.9Dahod
Garbhara
Dhanpur
Devgadhbarai
Fatehpura
Jalhod
Limkheda
Crops Area (ha)
Fruits 6443
Vegetables 13763
Flowers 4056
Spices 537
Total Area 24799
27
Further the table block wise area under various crops in irrigated and rainfed situation
is highlighted:
1. Block: Dahod
Crop Type
Kharif Rabi Summer Total
Irr RF Tot Irr RF Tot Irr RF
Tot Irr RF Tot Cereals 1415 2052
5 21940 1022
0 49 10269 0 0 0 11635 2057
4 32209
Coarse Cereals
0 22 22 0 0 0 0 0 0 0 22 22
Pulses 0 2125 2125 5784 3510 9294 235 0 235 6019 5635 11654
Oil Seeds
0 12378 12378 35 0 35 39 0 39 74 12378 12452
Fibre 110 0 110 0 0 0 0 0 0 110 0 110
Others 767 2178 2945 6882 3510 10392 588 0 588 8237 5688 13925
Total 2292
37228
39520
22921
7069 29990
862 0 862 26075
44297
70372
2. Block: Garbada
Crop Type
Kharif Rabi Summer Total
Irr RF Tot Irr RF Tot Irr RF
Tot Irr RF Tot
Cereals 656 10971 11627 6516 145 6661 0 0 0 7172 11116 18288
Coarse Cereals
0 11 11 0 0 0 0 0 0 0 11 11
Pulses 0 763 763 3248 5175 8423 262 0 262 3510 5938 9448
Oil Seeds
0 5876 5876 20 0 20 41 0 41 61 5876 5937
Fibre 87 0 87 0 0 0 0 0 0 87 0 87
Others 288 763 1051 3701 5175 8876 561 0 561 4550 5938 10488
Total 1031 18384 19415 13485 10495 23980
864 0 864 15380 28879
44259
3. Block: Dhanpur
Crop Type
kharif Rabi Summer Total
Irr RF Tot Irr RF Tot Irr RF
Tot Irr RF Tot Cereals 1050 12740 13790 9505 100 9605 0 0 0 10555 1284
0 23395
Coarse Cereals
0 75 75 0 0 0 0 0 0 0 75 75
Pulses 0 3135 3135 3232 2420 5652 197 0 197 3429 5555 8984
Oil Seeds
0 715 715 8 0 8 40 0 40 48 715 763
Fibre 140 370 510 0 0 0 0 0 0 140 370 510
Others 119 3305 3424 3938 2420 6358 407 0 407 4464 5725 10189
Total 1309 20340
21649 16683 4940 21623 644 0 644 18636 25280
43916
4. Block: Devgadhbariya
Crop Type
kharif Rabi Summer Total
Irr RF Tot Irr RF Tot Irr RF
Tot Irr RF Tot
Cereals 2672 27396 30068
19646 20 19666 0 0 0 22318 27416 49734
Coarse Cereals
0 40 40 0 0 0 0 0 0 0 40 40
Pulses 0 4659 4659 2811 911 3722 270 0 270 3081 5570 8651
Oil Seeds
0 1161 1161 27 0 27 380 0 380 407 1161 1568
Fibre 50 80 130 0 0 0 0 0 0 50 80 130
28
Others 420 5051 5471 3243 911 4154 670 0 670 4333 5962 10295
Total 3142 38387
41529 25727 1842 27569 1320 0 1320 30189
40229
70418
5. Block: Fatehpura
Crop Type
kharif Rabi Summer Total
Irr RF Tot Irr RF Tot Irr RF
Tot Irr RF Tot
Cereals 1526 14145 15671 6229 37 6266 0 0 0 7755 14182 21937
Coarse Cereals
0 26 26 0 0 0 0 0 0 0 26 26
Pulses 0 3753 3753 2516 1302 3818 195 0 195 2711 5055 7766
Oil Seeds
0 2012 2012 231 0 231 40 0 40 271 2012 2283
Fibre 0 242 242 0 0 0 0 0 0 0 242 242
Others 1288 3753 5041 4130 1302 5432 519 0 519 5937 5055 10992
Total 2814 23931 26745 13106 2641 15747 754 0 754 16674 26572 43246
6. Block: Zalod & Sanjeli
Crop Type
kharif Rabi Summer Total
Irr RF Tot Irr RF Tot Irr RF
Tot Irr RF Tot
Cereals 2325 34145 36470
19595 46 19641 0 0 0 21920 34191 56111
Coarse Cereals
0 42 42 0 0 0 0 0 0 0 42 42
Pulses 0 4570 4570 8815 3165 11980 890 0 890 9705 7735 17440
Oil Seeds
0 11814 11814 50 0 50 72 0 72 122 11814 11936
Fibre 0 395 395 0 0 0 0 0 0 0 395 395
Others 602 5375 5977 12191 3165 15356 1417 0 1417 14210 8540 22750
Total 2927 56341 59268
40651 6376 47027 2379 0 2379 45957 62717 108674
7. Block: Limekheda
Crop Type
kharif Rabi Summer Total
Irr RF Tot Irr RF Tot Irr RF
Tot Irr RF Tot
Cereals 3371 21375 24746
11820 33 11853 0 0 0 15191 21408
36599
Coarse Cereals
0 0 0 0 0 0 0 0 0 0 0 0
Pulses 0 3280 3280 2502 1302 3804 830 0 830 3332 4582 7914
Oil Seeds
0 2037 2037 124 0 124 0 0 0 124 2037 2161
Fibre 0 478 478 0 0 0 0 0 0 0 478 478
Others 15 3280 3295 3595 1302 4897 830 0 830 4440 4582 9022
Total 3386
30450
33836
18041 2637 20678
1660 0 1660 23087
33087
56174
Table 7: Block wise Area under Various Crops (Area in hectare)
Horticultural crops in various blocks are mentioned in the table below. Among all the
blocks Limekheda has horticulture cultivation area highest.
Blocks Area (ha) Blocks Area (ha)
Dahod 2468 Limkheda 6847
Garbada 1850 Zalod 4240
Dhanpur 2887 Fatepura 2346
D.bariya 4161 Total 24799
Table 8: Block wise Area under Horticultural Crops
29
2.2 Production and Productivity of Major Crop
Maize, gram, paddy, wheat and tur & udid are the major agricultural crops cultivated in
the district. These crops have an area share of more than 90 per cent in gross
agriculture area of the district.
The district produced a total of 117164.4 quintal maize, 18325.04 quintal tur, 22479
quintal wheat and 32537.7 quintal gram during 2013-14. The details of the area,
production and yield of various crops of Dahod district can be observed in table
Rainfed Irrigated Total
Crops Area (ha)
Prod. (Qtl)
Yield (kg/ha
)
Area (ha)
Prod. (Qtl)
Yield (kg/ha
)
Area (ha)
Prod. (Qtl)
Yield (kg/ha
)
Kharif
Paddy 25768 221672.32 6288 13015 297019 15691.8 38783 518691 21980
Jowar 15 0 0 0 0 0 15 0 0
Bajri 0 0 0 0 0 0 0 0 0
Maize 11551
4 932146.6
2 5982 0 0 0
115514
932147 5982
Ragi 0 0 0 0 0 0 0 0 0
Mung 236 116.25 375 0 0 0 236 116 375
Math 0 0 0 0 0 0 0 0 0
Udid 9270 57195.9 4319 0 0 0 9270 57196 4319
Tur 12605
160508.34
9041 0 0 0 12605 160508 9041
Groundnut 453 5825.58 7716 0 0 0 453 5826 7716
Castor 224 3530.9 8308 0 0 0 224 3531 8308
Sesamum 154 562.44 2224 0 0 0 154 562 2224
Cotton 1465 1699.4 580 387 0 0 1852 1699 580
Tobacco 0 0 0 0 0 0 0 0 0
Guar seed 20 0 0 95 527 1758 115 527 1758
Soyabean 22842 179766.54 4722 0 0 0 22842 179767 4722
Rabi
Wheat 413
2436.7 4130 5280
9 107110
2 15119 53222
1073539
19249
Jowar 10 0 0 32 352 1100 42 352 1100
Maize 0 0 0 3066
9 571057 13034
30669
571057 13034
Gram 17784
164857.68 6489 2864
2 265511 6489 46426 430369 12978
Rapeseed & mustard
0 0 0 92
1534 10002 92 1534 10002
Summer
Groundnut 0 0 0 612 12295 12054 612 12295 12054
Maize 0 0 0 2872 12608 3073 2872 12608 3073
30
Table 9: Major Agriculture crops
2.3 Production of Horticulture Crops
Table - 6 clearly mentions about various horticulture crops under fruits, vegetables,
spices and flowers. These are being produced across all the blocks in the district. Area
per crop per block and its production in metric tons is being mentioned. There is also a
block wise mention of productivity in Dahod district. In the table below it is the total
area of all the crops, whereas fruits have 90% (5799 ha.) of its area under irrigated and
10% (644 ha.) as unirrigated, on the other hand vegetables, spices and flowers have its
total area as irrigated.
Area in Ha, Production in MT
Name of Taluka
Fruit Vegetable Spices Flower Total
Area Productivity
Prod Area Productivity
Prod Area Productivity
Prod Area Product
ivity Prod Area
Productivity
Prod
Dahod 631 7.0 4444 1423 16.7 23750 336 9.9 3339 78 8.9 691 2468 13.1 32224
Garbada 446 6.7 2975.5 1037 15.3 15904 288 11.5 3321 79 8.6 683 1850 12.4 22883.5
Dhanpur 591 7.5 4428.5 1634 16.1 26269 589 13.0 7633 73 8.9 648 2887 13.5 38978.5
D.bariya 1049 7.4 7731 2156 16.6 35784 863 14.4 12387 93 8.9 830 4161 13.6 56732
Limkheda 2010 7.0 14011 3423 16.5 56635 1263 14.7 18533 151 8.8 1325 6847 13.2 90504.5
Zalod 1194 7.2 8648.5 2560 16.6 42370 446 15.5 6894 40 8.8 350 4240 13.7 58262.5
Fatepura 522 7.0 3652.5 1530 16.1 24616 271 12.9 3500.5 23 8.5 196 2346 13.6 31965
Total 6443 7.1 45891 13763 16.4 225328 4056 13.7 55608 537 8.8 4723 24799 13.4 331550
Table 10: Block wise productivity of Horticulture Crops
2.4 Irrigation Based Classification
Gross irrigated area of the district is 200153 hectares. In all the blocks, Zalod has
highest proportion of irrigated area with 50078 hectares. Totally rainfed area is higher
than the gross irrigated area and here as well Jalhod block has highest area of totally
rainfed area i.e. 62836 hectares.
Area in ha
Name of block/ taluka
Irrigated Un-lrrigated or totally rainfed
Total area / cultivated area
Dahod 28480 44360 72840
Devgadh bariya 34245 40334 74579
Dhanpur 21464 25339 46803
Fatepura 18968 26624 45592
Garbada 17185 28924 46109
Zalod 50078 62836 112914
Limkheda 29733 33288 63021
31
Total 200153 261705 461858
Table 11: Classification based on Irrigation
CHAPTER III
Water availability in Dahod District
3.1 Status of Water Availability
There is the availability of both ground and surface water in the district. Detailed
description of surface and ground water are separately given below with tables.
32
The table below represents surface water in the district. The major source of water in the
district is canals. The surface water is distributed through canals in Rabi season the
most. No block reports to utilize surface water in Kharif season. Most of the canal water
is in Dahod block with 23.67 MCM, along with it there are also various Water Bodies
including Rain Water Harvesting (check dams) for storage of surface water, these holds
total 11.5 MCM water in the block area. Devgabdaria Block also reports the utilization of
canal water in summer season.
Figure in MCM
Blocks Kharif Rabi Summer Total
Dahod - 28.5 - 28.5
Devgadbaria - 9.35 2.34 11.69
Dhanpur - 13.26 - 13.26
Fatepura -
Garbada - 1.5 - 1.5
Zalod & Sanjeli - 20 - 20
Limekheda - 23.67 - 23.67
Total - 96.28 2.34 98.62 Table 12: Block wise Water availability from Canal (Major and Medium Irrigation)
Kharif Rabi Summer Total
Various Water Bodies including Rain Water Harvesting (Check Dams)
11.5 11.5
Source: State Irrigation Department
As per the data provided by Gujarat Water Resource Development Corporation, Ground
water is available in all the seven blocks of the district. Zalodblock has the highest
ground water availability of 87.07 MCM, followed byLimekheda (64.32 MCM). The
availability of ground water in the district has been discussed in further paragraph.
Figures in MCM
Blocks Kharif Rabi Total Blocks Kharif Rabi Total
Dahod 41.36 13.92 55.28 Garbada 24.12 8.27 32.39
D'Baria 31.81 7.43 39.24 Limkheda 50.24 14.09 64.33
Dhanpur 32.06 17.40 49.46 Zalod&Sanjeli 69.85 17.22 87.07
Fatepura 34.98 9.90 44.88 Total 284.32 88.22 372.54
Table 13: Block wise water availability from Ground Water Sources
Water availability in the district from various water sources, throughout all seasons is
mention below in the table:
Figures in MCM
33
Sources Kharif Rabi Summer Total
Surface Water
107.78 2.34 110.12
Ground Water 284.32 88.22
372.54
Total 284.32 196 2.34 482.66
Table 14: Water Availability from various sources
3.2 Status of Ground Water
As per Central Ground Water Board notification, the status of ground water in all the
blocks of the Dahod district is safe. Block wise status of ground water and total draft and
recharge details are given in following table.
Taluka/ Block
Status of block as per central ground water board notification
OE Critical Semi-Critical
Safe Saline
Devgadh baria Safe
Dhanpur Safe
Dohad Safe
Fatepura Safe
Garbada Safe
Limkheda Safe
Zalod & Sanjeli Safe
Total Table 15: Ground Water status of Dahod
The stage of ground water development at year 2011, for all the talukas of the Dahod
district computed range from 33.98% to 56.94% and all units of assessment (talukas)
have been categorized as Safe, based on the stages of ground water development and the
long-term trend of pre and post monsoon ground water levels. The average stage of
groundwater development for district is 49.87%. (District Ground Water Brochoure,
CGWB, 2013)
3.2.1 Hydrogeology
The groundwater in Dahod district occurs under confined and unconfined condition.
Unconsolidated shallow alluvium and weathered, jointed and fractured rock support
unconfined aquifers whereas interflow zones of basalts, inter trappean beds,
encountered at depth, deep seated fractures and shear zones give rise to confined
conditions. All the geological formations occurring in the district form aquifers,
however, the phyllite, schist & quartzite are the most extensive aquifers in the district.
The deccan trap formation is second most extensive aquifer in the district. Granite and
gneiss also form aquifer in small area in the south part of the district. Alluvium forms a
potential but limited aquifer and occurs as scattered isolated patches along river
courses, valley fills, flood plain and abandoned palaeochannel deposits.
34
Generally, water level follows topographic configuration. As part of the hard rock,
phyllite, quartzite, schists, basalts, sandstone and limestones are forming aquifers.
Alluvium and valley fills materials form potential aquifers in the vicinity of rivers and
piedmont zone but their distribution is patchy with limited extension, rarely exceeding a
few square kilometer in area.
From the analysis of the water level trend of the Dahod district from 2003 to 2012, it is
observed that, during pre-monsoon, the water level has a rise of 0.0213 m/yr
(Khandania) to 0.084 m/yr
(Devgadh Baria) and also has
a fall of 0.018 m/yr (Zalod) to
0.4679 m/yr (Dhanpur).
Similarly from the analysis of
the post-monsoon data of
2003 to 2012, the rise shown
inwater level varies from
0.0028 m/yr (Dadhela) to
0.1060 m/yr (Devgadh Baria)
and also has a fall of 0.0215
m/yr (Limkheda) to 0.4109
m/yr (Dhanpur). Hence, from
the analysis it is observed
that, at Dhanpur, during both
pre-monsoon and post-
monsoon has a trend of
falling water level.
3.2.2 Ground Water Quality
Variation in chemical quality
of ground water is due to
hydrogeological factors
controlled by rock types,
depicting aerial distribution
of various water quality
features. In terms of electrical conductance (EC), measure of total dissolved salts in
ground water is vary in between 597 to 4430 μS/cm during May 2012. The chloride
content of the district also vary with in 28 to 880 mg/l. Nitrate content in the district is
very high varying within 2 to 430 mg/l. At six places, namely Dahod (45mg/l), Dadhela
(47 mg/l), Sukhsar (47 mg/l), Wadia (85 mg/l), Dhanpur (100 mg/l), Garbara (430
mg/l), where found above 45 mg/l is unsuitable drinking and domestic purpose.
Similarly, fluoride content is varying within 0.6 to 6.7 mg/l. At Khandania (1.5 mg/l),
Dahod (2.5 mg/l) and Garbara (6.70 mg/l) are found above the maximum permissible
35
limit and not suitable for the drinking purpose. Iron is the heavy metal that found in the
groundwater of the district is varying from 0 to 7.7 mg/l. The maximum value found at
Zalod is 7.70 mg/l and also found the maximum permissible limit, unsuitable for
drinking and domestic purpose (BIS 2012: IS10500). At Sukhsar (0.75 mg/l), Dhanpur
(0.88 mg/l) and Wadia (2.20 mg/l) are also found above the maximum permissible
limit of 0.3 mg/l and unsuitable for drinking purpose comparing to BIS 2012: IS10500.
In other chemical ion, total hardness in terms of CaCO3, is found above the BIS
maximum permissible limit of 600 mg/l at Garbara (980 mg/l) found unsuitable for
drinking and domestic purpose. In other area, TH varies within 250 to 460 mg/l with a
value of more than 200 mg/l found at 12 places. (Source: Groundwater Brochure
Dahod District)
36
3.3 Status of Canal Command Area
Command area in the district across all the blocks, as discussed with state Irrigation
department is mentioned in the table below. Dahod block shows the maximum
difference in total area and developed area. In this block undeveloped area is more than
the developed area. The total area in canal command is 16850 ha. out of which 7023.2
ha. is developed and 9646.8 ha. is undeveloped. Area in
Hectares
Name of the Taluka
Information of Canal Command
Total Area
Developed Area
Undeveloped Area
Dahod 4536.7 2507.93 2028.77
Dbaria 2514 950 1564
Dhanpur 1376 550 826
Fatehpura 0 0 0
Garbada 435.3 91.3 344
Limbkheda 4010 1753.97 2256.03
Zalod & Sanjeli 3978 1350 2628
Total 16850 7203.2 9646.8
Table 16: Block wise Canal and other services Command
37
3.4 Existing type of Irrigation
As mentioned in the previous section, the total area of canals is 13143 ha., whereas area
of ponds isnot being mentioned, the total number of ponds are 46 in the district. Most
number of ponds is in Dahod and Zalod block. Wells are reported to be the most viable
source of irrigation. There are wells in each block and Limkheda block has highest no.
i.e. 9905 wells, least no. of wells are in Garbada block of the district. Total area covered
under wells does not depend on the no of wells in the block. As mentioned Garbada
block has least no of well but covers are of 2500 ha., on the other hand Zalod block has
6647 wells but the area covered by these wells is very less.
Area in Hectares
Taluka
Canal (Area)
Pond Well Tube well
Nos. Area Nos. Area Nos. Area
Dahod 4536.7 11 NA 3722 5011 NA 1325
Devgadbaria 2514 2 NA 1047 3680 NA -
Dhanpur 1376 1 NA 1875 3300 NA 750
Fatehpura - 7 NA 7502 7437 NA 550
Garbada 435.3 10 NA 951 2500 NA 180
Limkheda 1818 4 NA 9905 7425 NA -
Zalod & Sanjeli 2463 11 NA 6647 1715 NA 1420
Total 13143 46 NA 31649 31068 NA 4225 Table 17: Block wise Area under various irrigation infrastructure
38
39
CHAPTER IV
Water Requirement This Chapter deals with the current (2015) and projected (2020) demand for water from
various sectors. It mentions the water requirement and potential of the departments in
fulfilling those requirements. The demand has been worked out on the basis of data
collected from different departments. The unit for volume of water has been chosen as
million cubic meters (MCM) instead of Billion cubic meters as suggested in the
guidelines.
4.1 Domestic Water Demand
Growth rate of district‟s population has been considered through census data of 2001
and 2011. In reference to 2011 census, population‟s growth rate is 14.9% in the district.
Table 4.1 below indicates the block-wise population. Current population (in 2015) has
been calculated based on the population growth rate between 2001 and 2011 along with
projected population which has been calculated similarly.
Domestic water consumption schemes are formulated assuming daily requirement of
water for people residing in urban areas of the district @ 140 Litres and for population
in rural areas, as 100 Litres per capita per day (lpcd). Using the same norms domestic
water supply demand has been worked out and given in table 4.1 below:
Sr. No.
Blocks Population in 2015
Present Water Demand (MCM)
Projected population
in 2020
Gross Water Demand in
2020 (MCM)
1 Fatepura 273810 10.4 314854 11.9
2 Zalod & Sanjeli
544217 20.6 625795 23.7
3 Limkheda 352179 13.3 404970 15.3
4 Dohad 552924 20.9 635807 24.0
5 Garbada 228691 8.6 262972 9.9
6 Devgadbaria 286710 10.8 329688 12.5
7 Dhanpur 207406 7.8 238497 9.0
Total 2445936 92.49 2812582 106.36 Table 18: Domestic Water Demand (MCM)
The annual water requirement has been indicated in Million cubic meters. It can be
inferred from the table that considering the growth rate of population of the district, the
quantity of water required shall be approximately 106.36 MCM which is 13.04%, i.e.
13.87 MCM more than the present water requirement.
40
Figure 5: Block wise Domestic Water Requirement
4.2 Crop Water Requirement
The existing farming system in Dahod district is Agriculture along with animal
husbandry, which is followed by horticulture with both agriculture and animal
husbandry. The major cropping system in the district
undertheexistingfarmingsystemsisprimarily Rice- Wheat, Maize- Gram, Udid/Tur-
Wheat/Gram, Rice-Gram and Maize-Wheat. Paddy, Maze, tur, wheat and gram are the
predominant crops in the district area.
Area under different crops has been discussed in Chapter 2 (Table 2.2) taking above
parameters water demand of different crops has been worked out. Existing water
potential available (being utilized) has been assumed as the water used in irrigated land.
Block Crop Area Sown (ha)
Irrigated area (ha)
Water Potential Required / Cr0p Water
Demand (MCM)
Existing Water
Potential (MCM)
Water Potential
to be Created (MCM)
Dahod
Agriculture and
Horticulture Crops
72840 28480 190.3 97.9 92.4
Devgadh bariya 74579 34245 285.6 163.2 122.5
Dhanpur 46803 21464 162.3 95.0 67.4
Fatepura 45592 18968 152.7 79.3 73.4
Garbada 46109 17185 174.1 99.4 74.7
Zalod & Sanjeli 112914 50078 366.0 184.6 181.4
Limkheda 63021 29733 224.2 121.3 102.9
Total 461858 200153 1555.3 840.7 714.6 Table 19: Block wise Crop Water Requirement (in MCM)
10
.4
20
.6
13
.3
20
.9
8.6 1
0.8
7.8
11
.9
23
.7
15
.3
24
.0
9.9
12
.5
9.0
0.0
5.0
10.0
15.0
20.0
25.0
30.0
Fatepura Jhalod Limkheda Dohad Garbada Devgadbaria Dhanpur
Gross Water Demand in 2015 (MCM) Gross Water Demand in 2020 (MCM)
41
It can be concluded from the table that in 7 blocks, a total water potential of 714.6MCM
needs to be created in the district to fulfill the requirement of crops. The crop wise water
requirement has been taken based upon discussion with Agriculture Universities and
department officials as per practice prevailing in the State which is as under:
Crops Per crop water requirement/ ha (mcm)
Crops Per crop water requirement/ ha (mcm)
Kharif Sugarcane 0.018
Paddy 0.005 Isabgul 0.0032
Jowar 0.0035 Fennel 0.007
Bajri 0.0035 Tobacco 0.0063
Maize 0.0035 Summer
Ragi 0.002 Groundnut 0.0075
Mung 0.0024 Bajra 0.0065
Math 0.0024 Paddy 0.017
Udid 0.0024 Maize 0.0098
Tur 0.0024 Mung 0.007
Groundnut 0.003 Udid 0.007
Castor 0.005 Sesamum 0.0035
Sesamum 0.002 Horticulture
Cotton 0.005 Banana 0.025
Tobacco 0.0042 Fruits 0.012
Guar seed 0.0035 Vegetables 0.006167
Soyabean 0.0024 Chillies 0.009
Rabi Fennel 0.007
Wheat 0.0052 Cumin 0.0032
Jowar 0.007 Fenugreek 0.0059
Maize 0.007 Other spices 0.0032
Gram 0.003 Flower 0.006
Rapeseed & mustard
0.0035
Table 20: Crop wise Water requirement
42
Figure 6: Crop Water Demand & Existing Water Potential
The figure above clearly signifies about the water potential in the district and the
demand. Demand is highest in Zalod block of the district.
4.3 Livestock Water Demand
The water requirement of livestock has been taken from livestock census 2007 & 2012,
as discussed in first chapter 1.3. The table below represents the animal wise water
requirement as well as total water requirement of the district for animals.
Block Total number of live stock
Present water
demand (MCM)
Water demand in
2020 (MCM)
Existing Water
potential (MCM)
Water potential to be created
(MCM)
Devgadbaria 391946 3.58 4.13 3.58 0.55
Dhanpur 321830 2.90 3.34 2.90 0.45
Dahod 398554 4.34 5.00 4.34 0.67
Fatepura 380000 4.06 4.68 4.06 0.62
Garbada 172191 2.10 2.42 2.10 0.32
Zalod & Sanjeli
497764 5.32 6.14 5.32 0.82
Limkheda 399055 4.23 4.88 4.23 0.65
Total 2561340 26.52 30.60 26.52 4.07 Table 21: Livestock Water Requirement
Water requirement for each of the animal is estimated based on the following
assumption as per the secondary data received from Animal husbandry department.
Animal Daily Water Demand (Liter)
Animal Daily Water Demand (Liter)
Milch Cow/ Buffalo 65 Pig 7
Dry Cow/ Buffalo 60 Sheep/ Goat 5
19
0.3
28
5.6
16
2.3
15
2.7
17
4.1
36
6.0
22
4.2
97
.9
16
3.2
95
.0
79
.3 99
.4
18
4.6
12
1.3
0.0
100.0
200.0
300.0
400.0
Dahod D.Bariya Dhanpur Fatepura Garbada Jhalod Limkheda
Crop Water Demand Existing Water Potential
43
Calf 10 Camel 24
Heifer 20 Broiler Birds (Per 1000 birds)
459
Horse 40 Layer Birds (Per 100 birds)
18
Mare 50 Table 22: Animal wise Water Requirement
For projecting the water demand of livestock, growth rate as deduced from census has
been considered during calculations. It is assumed that present water requirement of
animal is met from existing water usage and hence existing potential is equal to existing
demand.
4.4 Industrial Water Demand
Industrial water demand of Dahod district is negligible. Hence it is not considered for
the estimation of total water demand of the district.
No Significant requirement of water for industrial use.
4.5 Water Demand for Power Generation
None of the power generation activities are carried in the district area, as reported.
4.6 Total Water Demand of the district for various sectors
This section presents the total water demand of the district and has been calculated by
summing up all major sectors consuming water. The current water demand in 2015 has
been indicated in Table 4.8(a) and the projected water demand has been depicted in
Table 4.8 (b).
Block Demand from Components (MCM) Total
(MCM) Domestic Crop Livestock Industrial Power
Dohad 20.91 190.33 4.34 0 0 215.57
Devgadbaria 10.84 285.62 3.58 0 0 300.04
Dhanpur 7.84 162.35 2.90 0 0 173.09
Fatepura 10.35 152.67 4.06 0 0 167.08
Garbada 8.65 174.08 2.10 0 0 184.82
Zalod & Sanjeli
20.58 366.04 5.32 0 0 391.95
Limkheda 13.32 224.22 4.23 0 0 241.77
Total 92.49 1555.31 26.52 0.00 0.00 1674.33
Table 23: Present Water Demand of the district for various sectors
44
The present water demand of the district has been assessed to be 1674.33 MCM
annually, with Zalod being the block with maximum requirement of water for irrigation
of crops (366.04 MCM). Also it is a block which requires most of the water i.e. 391.95
MCM. Mentioned below is the graphical representation of water demand in various
districts.
Figure 7: Water requirement for various sectors in 2015 and 2020
Block Demand from Components Total
(MCM) Domestic Crop Livestock Industrial Power
Dohad 24.04 190.33 5.00 0 0 219.37
Devgadbaria 12.47 285.62 4.13 0 0 302.22
Dhanpur 9.02 162.35 3.34 0 0 174.71
Fatepura 11.91 152.67 4.68 0 0 169.26
Garbada 9.94 174.08 2.42 0 0 186.44
Zalod & Sanjeli
23.66 366.04 6.14 0 0 395.85
Limkheda 15.31 224.22 4.88 0 0 244.41
Total 106.36 1555.31 30.60 0.00 0.00 1692.27
Table 24: Total Water Demand of the district for various sectors 2020
During 2020, total water requirement of the district has been assessed at 1692.27MCM.
And as the above graph represents, water require in domestic and livestock purpose will
increase subsequently.
4.7 Water Budget
A total of 110.39 MCM surface water and 372.53 MCM ground water is available at
Dahod district. It is clear from the table that Fatepura block has no surface water
mentioned in the district and Dahod block had most of the surface water i.e 40 MCM. In
all the blocks there is availability of ground water, Limkheda block has 87.07 MCM of
ground water, highest in all the blocks.
5.5
92.9
1.6
Domestic
Crop
Livestock
6.3
91.9
1.8
45
In the current scenario total water demand of the district is 1674.33 MCM and the
estimated water demand for the year 2020 is 1692.27 MCM.
All the blocks have huge demand of water at present as well as in the coming years. As
mentioned in the table below highest water demand of water is in Zalod Block with
391.95 MCM, reaching up to 395.85 MCM in 2020. All other blocks also require water
and it ranges between 130 to 230 MCM, as represented in the table.
Figures in MCM
Name of Existing water availability Water Demand Water Gap
Blocks Surface water
Ground water
Total Present Projected (2020)
Present Projected (2020)
Dahod 40 49.46 89.46 215.57 219.37 126.11 129.91
D'Baria 11.96 55.17 67.13 300.04 302.22 232.91 235.09
Dhanpur 13.26 39.24 52.5 173.09 174.71 120.59 122.21
Fatepura 44.87 44.87 167.08 169.26 122.21 124.39
Garbada 1.5 32.4 33.9 184.82 186.44 150.92 152.54
Zalod & Sanjeli
20 64.32 84.32 391.95 395.85 307.63 311.53
Limkheda 23.67 87.07 110.74 241.77 244.41 131.03 133.67
Total 110.39 372.53 482.92 1674.33 1692.27 1191.41 1209.35 Table 25: Block wise Water Budget
46
CHAPTER V
Strategic Action Plan for Irrigation in District under PMKSY
5.1 Department wise Coverage of Area
The report forecasts action plan for irrigation inDahod district for four financial years
(2016-2020). The total area covered under Pradhan Mantri Krishi Sinachyi Yojna in the
upcoming years will be 70726.57 ha. The total area is further segregated department
wise in table 5.1. It provides details about total area covered under each department‟s
work.
Table 26: Dept. wise coverage of area
Department wise Coverage of Area
Estimated Area
to be Covered
under PMKSY
(ha.)
Proposed
Additional
area brought
under
irrigation
Narmada, Water Resources, Water Supply and Kalpsar Department
(WRD)
Panchayat Irrigation Department
18287 16325
State Irrigation Department
18900
Gujarat Water Resource Development Corporation Ltd. (GWRDC)
1883.2 1883.2
Gujarat Land Development Corporation (GLDC) 2452.8 2452.8
Gujarat Green Revolution Company Ltd. (GGRC) 23550.4 NA
Gujarat State Watershed Management Agency (GSWMA) 5653.17 5653.17
Total 70726.57 26314.17
Figure 8: Dept. wise coverage of area (in %)
26
2733
33
8
Panchayat Irrigation (WRD) State Irrigation (WRD) GWRDC GLDC GGRC GSWMA
47
As the table and graph above shows, out of the total area planned to cover under
PMKSY, Water Resource Department is expected to cover an area of 37187 hectare
under Panchayat and State irrigation activities. Activities covered under WRD are
Renovation of Canals, Pipe line project, RRR of Water bodies, water harvesting
structures etc. Gujarat Green Revolution Company Ltd. (GGRC) which is implementing
all the micro irrigation schemes of the state is expected to cover a total area of 23550.4
ha under drip and sprinkler irrigation. As per the plan of Gujarat Land Development
Corporation (GLDC), a total of 672 individual and community ponds will be created
along with 196 water harvesting structures during upcoming 4 years. These structures
are expected to irrigate a total area of 2452.8 ha in the district. Gujarat State Watershed
Management Agency (GSWMA) is expected to cover a total area of 5653.17 ha under
various component of watershed.
PMKSY-Watershed Component (erstwhile named as Integrated Watershed
Management Programme) is one of the flagship program of Govt. of India. The main
objectives of this is to restore the ecological balance by harnessing, conserving and
developing degraded natural resources such as soil, vegetative cover and water. Gujarat
is one of the largest States in context of land area treatment under PMKSY-Watershed
project. The important activities carried out under this projects are Soil moisture
conservation, Water harvesting, Vegetative cover and Plantation, Agricultural
production and Productivity improvement, Dairy development, Agro processing,
Livelihood and Income Generating Activities etc. In Gujarat PMKSY-Watershed
component is implemented through a State Level Nodal Agency constituted as Gujarat
State Watershed Management Agency (GSWMA), an autonomous society supported
under the Rural Development Department (RDD) of Government of Gujarat. GSWMA
has vision of “Enhancing the quality of rural population through Sustainable, Equitable
and Participatory Natural resources Management” and also has Mission of “Creating
sustainable rural livelihoods through scientific and Integrated Watershed Development
Approach”.
5.2 Component wise Coverage of Area
Previously, the area covered by various departments is being mentioned. In the figure
given below the area covered under various components is discussed. 42% of the total
i.e. 29822.4 ha of land is being covered under per drop more crop component, followed
by Har Khet ko Pani component which shares 22317 ha (32%) of the total area. There is
also 18% and 8% of the total area covered under component AIBP and PMKSY
Watershed respectively.
48
Figure 9: Component wise Coverage of Area (in %)
5.3 Department wise Strategic Action Plan
Total planned outlay in strategic action plan of Dahod district is 167744.3 lakh rupees.
Out of the total cost 72%, which is 121238.6 lakhs of total, is incurred by State Irrigation
Water Resource Department, along with 13% of Panchayat Irrigation Water Resource
Department having cost of 22162 lakhs. GGRC has 6% of the total share of amount. It
will incur 10550.58 lakh in four years, as mentioned in the table. GWRDC, GSWMA and
GLDC have 2%, 6% and 1% of the total share in the funds planned for next four years.
ATMA have only 117.7 lakh of 167664 lakh in its budget for future.
Figure 10: Department wise Fund Distribution under PMKSY (in %)
Detailed department wise break up of financial outlay can be observed in the following
table:
Table 27: Department wise Fund Distribution under PMKSY
18
32
42
8
AIBP Har Khet ko Pani Per Drop More Crop PMKSY Watershed
13
72
216
6
Panchayat Irrigation (WRD) State Irrigation (WRD) GWRDC GLDC GGRC GSWMA
49
Department wise estimated amount 2016-17 2017-18 2018-19 2019-10 Total
Water Resource Department
Panchayat Irrigation 6521.0 6611.0 5000.0 4030.0 22162.0
State Irrigation 4014.7 108404.3 5463.4 3356.2 121238.6
GWRDC 689.0 689.0 689.0 689.0 2756.1
GLDC 351.7 351.7 351.7 351.7 1406.7
GGRC 3246.3 2434.7 2434.7 2434.7 10550.6
GSWMA 5808.8 2608.5 955.5 139.9 9512.7
ATMA 27.0 28.8 30.2 31.8 117.7
Total 20658.5 121128.0 14924.4 11033.3 167744.3
5.4 Component wise Strategic Action Plan
Major share in the total amount forms partof AIBP with 64% i.e.107584.7 lakhs followed
by Har Khet ko Pani having 17% in the total share. Cost invested in per drop more crop
scheme is 13% of the total i.e. 21249 lakh rupees. There is cost involved in PMKSY
Watershed scheme by 5% of the total. AIBP components are to be executed mainly by
Narmada, Water Resources, Water Supply and Kalpsar Department (WRD). Har Khet
ko Pani component will be implemented by WRD, SSNNL and GWRDC. Per drop more
crop component will be executed by GGRC. Water shed component will be taken care of
by the Rural Development Department through GSWMA and extension & training
component will be executed by ATMA. Funds distributed by ATMA is Rs. 117.7003 Lakh
However, all the stakeholders need to have coordination among them to have the
maximum irrigation efficiency and to avoid duplicity
Figure 11: Component wise Fund Distribution under PMKSY (in %)
Detailed component wise break up of financial outlay can be observed in the following
table.
64
17
13
5
1 0
AIBP HKP PDMC PMKSY Watershed MGNREGA Capacity Building
50
Table 28: Component wise Financial Outlay for PMKSY (in Lakh)
Component wise estimated amount 2016-17 2017-18 2018-19 2019-20 Total
AIBP 1446.1 103739.6 1222.3 1176.8 107584.7
Har Khet ko Pani 6725.4 9423.5 7911.8 5220.1 29280.7
Per Drop More Crop 6651.3 5327.7 4804.7 4464.7 21248.6
PMKSY Watershed 4780.8 2248.0 736.8 130.3 7895.9
MGNREGA 1028.0 360.4 218.7 9.6 1616.8
Capacity Building 27.0 28.8 30.2 31.8 117.7
Total 20658.5 121128.0 14924.4 11033.3 167744.3
Component wise major activities and their details proposed for the district is highlighted in the
following table.
5. Strategic Action plan for Irrigation in District under PMKSY
Concerned Ministry/
Department Component Activity
Total Number
/ Capacity
(cum)
Command Area/
Additional Irrigation Potential
(ha)
Period of
Implementation
(5/7 years)
Estimated cost
(in lakh)
MoWR - Dept of State
Irrigation AIBP
Major Irrigation - Pipe line project
6 10000 4 102000
MoWR - Dept of State
Irrigation
Medium Irrigation - Renovation of Canals
358 2934 4 5584.65
NWR&WS - Dept of
Panchayat Irrigation
Har Khet ko Pani
RRR of Water bodies WRD 131 9551.00
6496
MoWR - Dept of State
Irrigation RRR of Water bodies WRD 231 1711 4 4663.88
MoWR - Dept of State
Irrigation Lift Irrigation WRD 6 866 4 1088
NWR&WS - Dept of
Panchayat Irrigation
Lift Irrigation WRD 80 2464
4968
MoWR Lift Irrigation GWRDC 40.8 1856 4 2654.08
MoWR Exploratory Tubewells
GWRDC 13.6 27.2 4 102
MoWR Farm Ponds by GLDC 560 806.4 4 627.2
MoWR Sim Pond by GLDC 112 470.4 4 560
MoWR WHS by GLDC 196 1176 4 219.5
51
MoWR Dept of State
Irrigation
State planne Scheme of Irrigaiton
New Checkdams WRD (for 4 Years)
38.6 3389 4 7902.021
MOA & FW-DAC&FW
Per drop more crop
(Micro- irrigation)
DPAP Drip 8831.4 14130.2 4 9495.5
MOA & FW-DAC&FW
DPAP Sprinkler 5887.6 9420.2 4 1055.1
MOA & FW DAC & FW -
Dept of Panchayat Irrigation
Per Drop more crop
(Supplementry Water
management activities)
Water harvesting Structures -Village / Community Ponds
191 3973
6963
Water harvesting Structures -Checkdam
264 2299
3735
DoLR-MoRD
PMKSY Watershed
Newly created WHS
DoLR-MoRD Cause way cum Chek dam 13 140 4 Years 33.77
DoLR-MoRD Check dam 316 2044 4 Years 1410.362
DoLR-MoRD Village/Community Pond 2 4.5 4 Years 18
DoLR-MoRD Farm Pond 67 771 4 Years 24.4366
DoLR-MoRD Pond Inlet 7 0 4 Years 12
DoLR-MoRD Cement Nala Plug (Small
Check Wall) 29 0 4 Years 22.794
DoLR-MoRD Renovated WHS
DoLR-MoRD Deepening/Desiltation Of
Pond 25 75.67 4 Years 53.0445
DoLR-MoRD De-siltation of Checkdam 13 24 4 Years 3.62
DoLR-MoRD Repairing of Checkdam 19 50 4 Years 14.436
DoLR-MoRD Renovation of Checkdam 18 42 4 Years 47
DoLR-MoRD De-siltation of Checkwall 16 0 4 Years 58
Well Recharge - Ground
Water 166 396 4 Years 254.88
DoLR-MoRD Renovation of Checkwall 3 0 4 Years 4.32
DoLR-MoRD Land Development
DoLR-MoRD Farm Bunding 210386
4 Years 153.2
DoLR-MoRD Afforestation 95.0
4 Years 20.4
DoLR-MoRD Agriculture Demo 24
4 Years 2.1
Land leveling 1652.8 14 4 Years 181.8
DoLR-MoRD Soil Moisture Conservation
Check wall 232 328 4 Years 1079.651
Earthen bund 100
4 Years 42.96
Protection Wall 119
4 Years 300.332
Waste weir 15
4 Years 22.50231
Countour Trenches 9000
4 Years 3.6035
Earthern Dam 19
4 Years 57
Field Outlet 1772 7 4 Years 230.1613
Gabion structure 27
4 Years 21.06
Gully plug 1080.6 169.5 4 Years 76.73194
52
Loose boulder Checks 5240 0 4 Years 9.95
Nala Plug 2323 961.5 4 Years 253.302
Stone bunding 36485.36 551 4 Years 452.4287
Pond 11 50 4 Years 43
DoLR-MoRD Cement Nala Plug (Small
Check Wall) 75 25 4 Years 54.54762
DoLR-MoRD Production & Micro Enterprises
DoLR-MoRD Livestock (Animal
Camp+Husbandary) 1044
300.488
9
Agro Processing 63
43.534
DoLR-MoRD Agriculture 5270.4
1264.555
DoLR-MoRD
Others(Horticulture/Minaral Micture and
deworming/sheep goets/Micro enterprises)
673
274.6358
DoLR-MoRD Monitoring, Evaluation, Learning and Documentation (MELD)
DoLR-MoRD Monitoring & Evaluation
175
DoLR-MoRD Consolidation
405.86
DoLR-MoRD Administration
Administration
433.6
Repairs and Development
Causeway on connecting
roads 1
1.40878
Check / Protection wall 0
0.87999
Drinking water facility 1
0.95
Rain water harvesting
system 0
0.00051
Recharge / Repair of open
wells 0
0.2527
Repair / development of
artificial water bodies 12
24.22835
Pond Waist Wair 0
0.11302
Pond Repairing 0
0.4105
Washing Ghat 1
1.04
DoLR-MoRD Others 5
7.6
MGNREGA
Land Development
DoLR-MoRD Farm Bunding 15000
9.635
DoLR-MoRD Soil Moisture Conservation
DoLR-MoRD Check wall 121
538.5
DoLR-MoRD Protection Wall 141
323.57
DoLR-MoRD Field Outlet 8
0.6
DoLR-MoRD Nala Plug 44
34.642
DoLR-MoRD Straggred Contour
trenching(Terrace Talavadi) 182.3636
2.54784
DoLR-MoRD Stone bunding 18270
3.654
53
Pond 2
5
DoLR-MoRD Countour trenches 10000
2
DoLR-MoRD Newly created WHS
Pond Inlet 1
1.5
DoLR-MoRD Check dam 186
587.85
DoLR-MoRD Renovated WHS
Renovation of Checkdam 4
3
Deepening/Desiltation Of
Pond 13
48
DoLR-MoRD De-siltation of Checkdam 2
0.8
DoLR-MoRD Others(Horticulture/Minaral Micture and deworming/sheep
goets/Micro enterprises)
DoLR-MoRD Nursery raising 3
2.25
DoLR-MoRD Vermi compost 258
53.21
ATMA
Traing , Demonstration and Extension Activies
Trainings-859
Trainees- 19194
117.7003
Total
167744.3
5.5 Additional Area & Employment Generation: (Output & Outcome)
Out of total area mentioned in the PMKSY Scheme (mentioned under 5.1 and 5.2) i.e.
70726.6 ha., additional area reportedis26314.17 ha comprising WRD, GLDC, GWRDC and
PMKSY Watershed total area.
The employment generation is being calculated for Dahod district by taking 40% cost of
watershed dept. and 20% cost of all other dept. as labor charge, which is 35451.391
Lakhs. This cost is divided by Rs.178 to generate total Man-days. The total man-days
after calculation come 19916512. All this generates total number of individuals who will
be employed for 4 years under the project:13641.4.
The PMKSY interventions are likely to generate an additional income of Rs. 6631.171lakh
to the farmers of the district. This is based on the assumption of at least 60% of
potential utilised and Rs. 42,000 per ha incremental income from rainfed to irrigated
farming.
5.6 Year wise Strategic Action Plan
Year wise financial outlay for the four years can be observed in Fig. In the first year of
implementation, i.e. in financial year 2016-17, a budget of Rs. 20658.5 lakh is required.
In the subsequent three years, Rs. 121048.0 lakh, Rs. 14924.4 lakh and Rs. 11033.3 lakh
budget is estimated for various departments. Year wise financial outlay is illustrated in
fig-12. Major share of the amount will be spent in the 2017-18 as reflected by various
departments.
54
Figure 12: Year wise Financial Outlay under PMKSY
5.7 Monitoring and Evaluation
The Strategic Action Plan of PMKSY will be monitored by the respective departments
through the regular reporting system and component wise progress will be monitored by
the District Level Irrigation Committee. Further, the activities, outputs and outcomes
will be reported in web based MIS of PMKSY for review at state and national level. Some
of the key indicators that will be used to monitor and evaluate the progress of PMKSY
include:
Annual irrigation water supply per unit irrigated area measured as the ratio of
total volume of irrigation water supplied at intake divided by total area irrigated
in all seasons
Potential created and utilized measured as the ratio of total potential utilized
(measured crop area) to irrigation potential created
Output (agricultural production) per unit irrigated area measured as the ratio of
total value of agriculture production divided by the total irrigated area.
Output (agricultural production) per unit irrigation water supply measured as the
ratio of total value of agriculture production divided by the total volume of
irrigated water supplied.
Total Operations & Maintenance (O&M) cost per unit irrigated area measured as
the total Management, Operation and Maintenance (MOM) costs for the system
divided by total area irrigated (potential utilized).
Total Operations & Maintenance (O&M) cost per unit volume of water supplied
measured as total Management, Operation and Maintenance (MOM) costs for the
system divided Total volume of water supplied (all uses)
12.3
72.2
8.9
6.6
2016-17 2017-18 2018-19 2019-20
55
Equity performance measured as actual area irrigated in head, middle and tail divided
by Command area in head, middle and tail.
GSWMA has its own structural arrangements (GSWMA, District Watershed
Development Unit, PIA, and Watershed Committee) from state to village level for
implementation of program and has system of internal monitoring of project activities
through different means. GSWMA has its own web based monitoring system as Soil
Water Resource Management System (SWaRSys). The said system is online and helps
not only for the monitoring/documentation of all the main project activities but also
facilitates to collect and collate monthly and quarterly data from District level
offices.For preparation of DIP, the watershed component information is collected from
various levels and incorporated in this document for the years 2016-20.
5.8 Suggestions
For successful implementation of PMKSY plan it is suggested that:
All the stakeholders should convene meeting of Panchayat Samities and then
finalize the village plan and prepare DPR.
There should not be any duplicity of project.
The Department should supplement each other so that the maximum irrigation
efficiency is achieved.
Agriculture and Horticulture Department should take micro irrigation projects in
the command of minor irrigation projects which are either completed or likely to
be completed in near future.
All the irrigation projects should have a component of water conveyance so that
the each drop of water is judiciously utilized.
Where ever feasible, solar pump sets should be installed.
All the structures planned should be geo tagged and marked on map, so that social
monitoring of the projects can be conducted. This will also avoid the duplicity.
Priority should be given to projects to minimize the gap in potential created and
potential utilized.
Execution of the scheme should be expeditiously completed.
There should be smooth fund flow for timely completion of the project and to avoid cost
escalation.
56
Annexure
Annexure-1- Department wise Summary of Strategic Action Plan
1. Strategic Action Plan of Water Resource Department (WRD)
WRD - Panchayat Irrigation Dept.
Components Work 2016-17 2017-18 2018-19 2019-20 Total Additional
Area
Har Khet Ko Pani
RRR of Waterbodies 1241 2258 1467 1530 6496 9551.00
Lift Irrigation 1875.0 1460.0 1163.0 470.0 4968 2464
Per Drop More Crop (Suplementry
Water Management
activities)
Water Harvesting Structures - Checkdam
1119 837 1030 749 3735 2299
Water Harvesting Structures - Villages /
Community Ponds 2286 2056 1340 1281 6963 3973
Total 6521 6611 5000 4030 22162 18287
WRD - State Irrigation Dept.
Components Work 2016-17 2017-18 2018-19 2019-20 Total Command Area
AIBP Major Irrigation 0 102000 0 0 102000 10000
Medium Irrigation 1446.05 1739.55 1222.3 1176.75 5584.65 2934
HKP RRR of Waterbodies 866.6 1378.83 968.05 1450.4 4663.88 1711
Lift Irrigation 0 0 1088 0 1088 866
WRD Checkdams 1702.08 3285.941 2185 729 7902.021 3389
Total 4014.73 108404.3 5463.35 3356.15 121238.6 18900
2. Strategic Action Plan for Gujarat Water Resource Development Corporation (GWRDC)
GWRDC
Components
Work 2016-17 2017-18 2018-19 2019-20 Total Command
Area
HKP
Lift Irrigation GWRDC
663.52 663.52 663.52 663.52 2654.08 1856
Exploratory Tubewells GWRDC
25.5 25.5 25.5 25.5 102 27.2
Total 689.02 689.02 689.02 689.02 2756.08 1883.2
57
3. Strategic Action Plan for Gujarat Land Development Corporation (GLDC)
GLDC
Components Work 2016-17 2017-18 2018-19 2019-20 Total Command
Area
HKP
Farm pond 156.8 156.8 156.8 156.8 627.2 806.4
Sim pond 140 140 140 140 560 470.4
WHS 54.88 54.88 54.88 54.88 219.52 1176
Total 351.68 351.68 351.68 351.68 1406.72 2452.8
4. Strategic Action Plan for Gujarat Green Revolution Company Ltd. (GGRC)
GGRC
Components Work 2016-17 2017-18 2018-19 2019-20 Total Command
Area
Per Drop More Crop
Drip 2921.7 2191.3 2191.3 2191.3 9495.5 14130.2
Sprinkler 324.6 243.5 243.5 243.5 1055.1 9420.2
Total 3246.3 2434.7 2434.7 2434.7 10550.6 23550.4
5. Strategic Action Plan for Gujarat State Watershed Management Agency (GSWMA)
GSWMA
Components Work 2016-17 2017-18 2018-19 2019-
20 Total
Command Area
PMKSY Watershed
4781 2248 737 130 7896 5653.17
MGNREGA
1028.044 360.4175 218.6975 9.6 1616.8 0
Total 5808.8 2608.5 955.5 139.9 9512.7 5653.17
6. Strategic Action Plan for Agriculture Technology Management Agency (ATMA)
Components Work 2016-17 2017-18 2018-19 2019-20 Total
Capacity Building Training related to
irrigation 27.0 28.8 30.2 31.8 117.7
58
Annexure-2 Strategic Action Plan of Water Resource Department
State Irrigation
Taluka - Devgadh Bariya
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
Year 2016-17
3.1 D.Baria NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Nani jhari M.I.Tank 1 50 55.00
Total 1 50 55.00
4.1 D.Baria NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
8.1.1 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 Chekdem at Village Devi Rampura Faliya (Dev Kotar)
1 10 20.00
2 New Checkdem no.1 at Devi Rampura Mota Faliya
1 28 42.00
3 New Checkdem no.2 at Devi Rampura Mota Faliya
1 18 28.00
59
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
4 New Checkdem at Moti Khajuri (Nr.Hanumanji mandir)
1 10 20.00
5 New Checkdem Between Keliya and Janbusar (Naleshwar River)
1 10 20.00
6 New Checkdem Between Keliya and Vandar (Piapaliya Dara)
1 12 25.00
7 New Checkdem at village Ruvabari (Dasheli Faliya)
1 12 25.00
8 New Checkdem at village Ruvabari (Naravtbhai ni ghar ni bajuma)
1 12 25.00
9 New Checkdem at village Bhular (Patel Faliya)
1 12 25.00
10 New Checkdem at village Bhular (NishalFaliya)
1 15 25.00
11 New Checkdem at village Vandar (PatelFaliya)
1 15 25.00
12 New Checkdem at village Janbusra
1 15 25.00
13 New Checkdem at village Nagvav
1 12 20.00
14 New Checkdem at village Vadbher
1 12 20.00
60
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
15 New Checkdem at village Jhapatiya
1 12 20.00
Total 15 205 365.00
8.1.7 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Borsagar Irrigation Tank Renovation
1 12 25.00
2 Kelkuva New Village Tank 1 15 25.00
3 Nani Mangoi Tank Renovation and waist wear work
1 15 24.00
4 Singor Percolation Tank Renovation and waist wear work
1 12 18.00
5 Bara New Village Tank 1 40 55.00
Total 5 94 147.00
Year 2017-18
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lac)
3.1 D.Baria NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
61
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
1 Tidki M.I.Tank 1 100 49.00
2 Bhulav M.I.Tank 1 10 35.00
3 Borsagar M.I.Tank 1 40 50.00
4 Bara M I Tank 1 40 50.00
5 Antela MI Tank 1 45 55.00
6 Motizari Percolation Tank 1 15 25.00
Total 6 250 264
4.1 D.Baria NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
8.1.1 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdem at Village Antela
1 15 18.00
2 New Checkdem at Village Mandav
1 10 18.00
3 New Checkdem at Village Dukhli
1 12 12.00
4 New Checkdem at Village Dangariya fulpura
1 12 14.00
5 New Checkdem at Village Nadatod (Patel Faliya)
1 15 18.00
62
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
6 New Checkdem at Village Nagvav
1 15 20.00
7 New Checkdem at Moti Khajuri (Pujara Faliya)
1 12 20.00
8 New Checkdem Between Keliya and Janbusar (Paliya muvadavav kotar)
1 12 20.00
9 New Checkdem at Village keliya (mani faliya)
1 12 20.00
10 New Checkdem at Village Guna (Shikari faliya)
1 12 20.00
11 New Checkdem at Village Guna (Gadva kotar)
1 12 20.00
12 New Checkdem at Village Guna (Simada kotar)
1 15 25.00
13 New Checkdem at Village Guna (Aasaydi Nadol kotar)
1 15 25.00
14 New Checkdem at village Jhapatiya
1 10 20.00
15 New Checkdem at village Ruparel
1 10 20.00
16 New Checkdem at village Ruparel
1 10 20.00
17 New Checkdem at village Sevaniya
1 12 20.00
63
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
18 New Checkdem at village Panchiyasal
1 15 25.00
Total 18 226 355.00
8.1.7 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Bara New Village Tank 1 30 48.00
2 Devi Rampura (Mota Kotar) New Village Tank
1 10 42.00
Total 2 40 90.00
Year 2018-19
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3.1 D.Baria NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Sevaniya M.I.Tank 1 40 50.00
2 Sagtala M.I.Tank 1 70 90.00
3 Kalidungar Percolation Tank 1 15 25.00
4 Chasiya Percolation Tank 1 18 25.00
5 Shingor Percolation Tank 1 18 25.00
64
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
Total 5 161 215.00
4.1 D.Baria NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
8.1.1 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdem at Village Somaladhao (Dayra Faliya)
1 35 45.00
2 New Checkdem at Village Fangova (Borva Faliya)
1 10 15.00
3 New Checkdem at Village Dabhva
1 12 19.00
4 New Checkdem at Moti Khajuri (Devvala kotar)
1 12 19.00
5 New Checkdem at Moti Khajuri (Patel Faliya)
1 12 19.00
6 New Checkdem at Moti Khajuri (Amanvala Kotar)
1 15 25.00
7 New Checkdem at Village Rebari
1 22 28.00
8 New Checkdem at Village Motijhari (Chandoi River)
1 12 20.00
65
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
9 New Checkdem at Village Rama (Chandoi River)
1 15 20.00
10 New Checkdem at Village Bhathvada (Nadol Kotar)
1 20 30.00
11 New Checkdem at Village Kaliyakota (Chandoi River)
1 12 25.00
12 New Checkdem at Village Kaliyakota (Gorad Faliya)
1 15 20.00
13 New Checkdem at Village Kaliyakota (Bhavsing gema)
1 15 20.00
14 New Checkdem at village Fulpura
1 15 20.00
15 New Checkdem at village Fulpura
1 10 20.00
16 New Checkdem at village Beina (Serve no.366)
1 15 25.00
17 New Checkdem at village Simaladhasi
1 12 25.00
18 New Checkdem at village TImarva
1 10 20.00
Total 18 269 415.00
8.1.7 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
66
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
1 - - - -
Total 0 0 0
Year 2019-20
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lac)
3.1 D.Baria NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Rathvana muvada M.I.Tank 1 45 55.00
2 Panchela M I Tank 1 25 30.00
3 Ruvabari Percolation Tank 1 20 25.00
4 Vadodar Percolation Tank 1 15 25.00
5 Guna Percolation Tank 1 18 25.00
Total 5 123 160.00
4.1 D.Baria NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
8.1.1 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
67
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
1 Checkdem Renovation at village Antela
1 15 20.00
2 Checkdem Renovation at village Bhullar
1 20 25.00
3 New Checkdem at Village Bhathvada (Panam River)
1 15 20.00
4 New Checkdem at Village Gamdi (Gamadi Patel Faliya)
1 15 20.00
5 New Checkdem at Village Gamdi (Nr.High School)
1 12 20.00
6 New Checkdem at Village Rebari (Chandoi River)
1 20 30.00
7 New Checkdem at Village Chenpur (Nadi kotar)
1 15 25.00
8 New Checkdem at Village Chenpur (Kaliya kota Simada)
1 10 20.00
9 New Checkdem at Village Kopda (Kotar Par)
1 25 30.00
10 New Checkdem at Village Mendra (Kotar Par)
1 15 25.00
11 New Checkdem at village Jhab
1 15 25.00
12 New Checkdem at village Jhab
1 15 25.00
68
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lac)
13 New Checkdem at village Kunva
1 12 20.00
14 New Checkdem at village Kunva
1 10 20.00
Total 14 214 325
8.1.7 D.Baria MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
Taluka: Dahod
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Year 2016-17
3.1 Dahod NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Gadoi M.I. Scheme 1 120 70.00
Total 1 120 70.00
69
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
4.1 Dahod NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Jharikhurd 1 78 130.00
2 L.I.Scheme at Kheng 1 82 100.00
Total 2 160 230.00
8.1.1 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdam at Village Aagavada (Navapura Faliya)
1 15 20.00
2 New Checkdam at Village Aagavada (Kaliyakuva Faliya)
1 10 15.00
3 New Checkdam at Village Aagavada (Limdi Faliya)
1 10 15.00
4 New Checkdam at Village Aagavada (Gamtal Faliya)
1 15 18.00
70
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
5 New Checkdam at Village Dhamarda (Pat Faliya)
1 10 15.00
6 New Checkdam at Village Mandavav (Mavi Faliya)
1 10 15.00
7 New Checkdam at Village Vanbhri
1 10 15.00
8 New Checkdam on Kali River at Village Tanachhiya
1 25 40.00
9 New Checkdam at Village Tanachhiya (Jambudi Faliya)
1 25 40.00
10 New Checkdam on River Kali at Village Khuntkheda
1 25 40.00
11 New Checkdam at Village Himala (Nr. Smashan)
1 10 20.00
12 New Checkdam at Village Kotda Khurd (Nr.jarakh Tank)
1 10 20.00
Total 12 175 273.00
71
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8.1.7 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Aagavada (Navapura Faliya) New Village Tank
1 12 20.00
2 Aagavada (Kaliyakuva Faliya) New Village Tank
1 10 15.00
3 Aagavada (Limdi Faliya) New Village Tank
1 10 15.00
4 Aagavada (Joda Faliya) New Village Tank
1 10 15.00
5 Tank Renovation at Village Jalat (Daruniya Faliya)
1 10 15.00
6 Tank Renovation at Village Jalat (Sabelav Faliya)
1 10 15.00
7 Tank Renovation at Village Jalat (Jalasel Faliya)
1 10 20.00
72
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8 Tank Renovation at Village Dhamarda (Khant Faliya)
1 10 12.00
9 Tank Renovation at Village Dhamarda (Pat Faliya)
1 10 15.00
10 Tank Renovation at Village Dhamarda (RahDungari Talav)
1 10 15.00
11 Tank Renovation at Village Bordi Inami (Kadvaniyu Talav)
1 10 15.00
12 Tank Renovation at Village Bordi Sarkari (Futi Talav)
1 10 15.00
13 Tank Renovation at Village Chapri (Aamba Faliya)
1 10 15.00
14 Tank Renovation at Village Retiya
1 10 18.00
15 Tank Renovation at Village Kharod
1 10 18.00
16 Tank Renovation at Village Borvani
1 10 18.00
73
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
17 Tank Renovation at Village Khodva Navagam
1 10 18.00
18 Tank Renovation at Village Doki
1 10 15.00
19 Tank Renovation at Village Kharod (Kankari Dungari Faliya)
1 10 15.00
20 Tank Renovation at Village Khajuri
1 10 15.00
21 Rozam (Kathadiya Faliya) New Village Tank
1 10 15.00
22 Aanghvada New Village Tank 1 15 20.00
23 Tank Renovation at Village Moti Chajeli
1 15 25.00
24 Tank Renovation at Village Jalat (Daruniya Faliya)
1 12 18.00
25 Tank Renovation at Village Aagavada (Motu Talav)
1 15 20.00
Total 25 269 417.00
74
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Year 2017-18
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry / Department
Component Activity Total Number
Command Area / Irrigation
Potential (ha)
Estimataed Cost (in
Lacs)
3.1 Dahod NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Bawka M.I. Tank 1 335 70.00
2 Kharedi M.I. Tank 1 50 60.00
3 Simaliya Bujharg (Serve No.174) New Village Tank
1 41 50.00
4 Khapariya Percolation Tank 1 15 30.00
5 Simaliyakhurd Percolation Tank
1 13 25.00
6 Undar Percolation Tank 1 20 25.00
7 Vadbhara Percolation Tank 1 15 25.00
Total 7 489 285.00
4.1 Dahod NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Tanda 1 35 100
2 L.I.Scheme at Undara 1 38 110
Total 2 73 210.00
75
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8.1.1 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdam at Village Dashla (Parmar Faliya)
1 8 10.00
2 New Checkdam at Village Dashla (Dhedhiya Kotar)
1 10 12.00
3 New Checkdam at Village Dashla (Chikaliya Kotar)
1 10 15.00
4 New Checkdam at Village Ratigar (Parmar Faliya)
1 10 15.00
5 New Checkdam at Village Katvara (Vadi Faliya)
1 12 14.00
6 New Checkdam at Village Limdabara
1 10 20.00
7 New Checkdam on Vankiya Kotar at Village Limdabara
1 10 20.00
76
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8 New Checkdam on Dhola kotar at Village Uchvaniya
1 10 15.00
9 New Checkdam on Bhuri kui kotar at Village Uchvaniya
1 10 15.00
10 New Checkdam on Ubhapan kotar at Village Kotda Khurd
1 10 15.00
11 New Checkdam on Bhala pipar kotar at Village Uchvaniya
1 10 15.00
12 New Checkdam at Village Zarikhurd (Nr.Ukala Faliya)
1 10 20.00
13 New Checkdam at Village Zarikhurd (Muniya Faliya)
1 10 15.00
14 New Checkdam at Village Tanachiya (Nr.Parmar Faliya)
1 10 20.00
15 New Checkdam on Jada Kotar at Village Kharoda
1 10 20.00
77
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
16 New Checkdam at Village Kharoda
1 10 15.00
17 New Checkdam on River at Village Varam Kheda
1 12 20.00
18 New Checkdam at Village Bor Kheda (Nr.wel)
1 12 25.00
Total 18 184 301.00
8.1.7 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Khapariya (Kachala Faliya) New Village Tank
1 15 20.00
2 Dashla (Kathadiya Faliya) New Village Tank
1 15 20.00
3 Mini Tank at Village Simaliya khurd (Bhavada Kotar)
1 8 10.00
4 Tank Renovation at Village Vandariya
1 10 15.00
78
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
5 Tank Renovation at Village Moti Sarsi
1 10 15.00
6 Tank Renovation at Village Undar
1 10 15.00
7 Tank Renovation at Village Limdabar
1 10 15.00
8 Tank Renovation at Village Kheng (Dokar kuvi Talav)
1 10 15.00
9 Tank Renovation at Village Tanda (Khadu Talav)
1 10 20.00
10 Tank Renovation at Village Bandibar
1 10 15.00
11 Tank Renovation at Village Kheng (Chikaliya)
1 10 15.00
12 Tank Renovation at Village Tanachiya (Railway Crossing)
1 25 40.00
13 Tank Renovation at Village Tanachiya (kali Nadi)
1 30 50.00
79
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
14 Tank Renovation at Village Kotdakhurd (Khobari Faliya)
1 10 15.00
15 Tank Renovation at Village Himala
1 10 15.00
16 Tank Renovation at Village Timarda (Nr.Sanvariya Seth Madir)
1 15 18.00
17 Tank Renovation at Village Kahroda (Mundiya)
1 10 20.00
18 Tank Renovation at Village Kahroda (Mundiya - Muniya Faliya)
1 10 20.00
19 Tank Renovation at Village Kahroda (Irrigation Tank)
1 20 40.00
20 Tank Renovation at Village Kahroda
1 15 25.00
21 Tank Renovation at Village Aagavada (Mahudi Talav)
1 15 25.00
80
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
22 Tank Renovation at Village Nanikharaj (Futelu Talav)
1 15 25.00
23 Tank Renovation at Village Vadbara (JunuTalav)
1 15 28.00
24 Tank Renovation at Village Khapariya
1 15 25.00
25 Tank Renovation at Village Varamkheda
1 15 25.00
26 Tank Renovation at Village Borkheda
1 10 20.00
27 Tank Renovation at Village Katvara (Maniyavala Talav)
1 15 25.00
28 Tank Renovation at Village Simaliyakhurd (Mokhat Talav)
1 15 25.00
29 Tank Renovation at Village Nani Lacheli
1 15 28.00
Total 29 393 644.00
Year 2018-19
81
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry / Department
Component Activity Total Number
Command Area / Irrigation
Potential (ha)
Estimataed Cost (in
Lacs)
3.1 Dahod NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Rabdal M.I.Tank 1 212 60.00
2 Chosala M.I.tank 1 23 50.00
3 Chosala Jharan Faliya Percolation Tank
1 13 25.00
4 Kharoda Percolation Tank 1 15 30.00
Total 4 263 165
4.1 Dahod NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Salapada 1 40 80.00
Total 1 40 80.00
8.1.1 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
82
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
1 New Checkdam at Village Simaliya khurd (Kali Nadi Kotar Par)
1 15 18.00
2 New Checkdam at Village Simaliya khurd (Aamaliyar Faliya)
1 10 15.00
3 New Checkdam at Village Vankiya (Gam Tal Faliya)
1 10 15.00
4 New Checkdam at Village Nani Lacheli (Serve No.4/4)
1 12 18.00
5 New Checkdam on River Khan at Village Kharoda
1 10 20.00
6 New Checkdam on Vankad Kotar at Village Kharoda
1 5 10.00
7 New Checkdam on Masaniya Pipla Kotar at Village Kharoda
1 10 15.00
8 New Checkdam on River Khan at Village Nani Ranapur
1 15 30.00
83
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
9 New Checkdam on River Khan at Village Nani Chayan
1 15 25.00
10 New Checkdam on River Khan at Village Nava gam
1 25 40.00
11 New Checkdam on River Khan at Village Juna Pani
1 25 40.00
12 New Checkdam on River Khan at Village Ravali Kheda
1 25 40.00
13 New Checkdam at Village Vadbara
1 10 15.00
14 New Checkdam at Village Kathla (Nr. Nal Talav)
1 10 20.00
Total 14 197 321.00
8.1.7 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
84
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
1 Nani Lacheli (Serve No.31/3) New Village Tank
1 15 20.00
2 Nani Lacheli (Serve No.20/3) New Village Tank
1 18 22.00
3 Moti Lacheli (Amaliyar Faliya) New Village Tank
1 20 25.00
4 Vankiya (Nadani Faliya) New Village Tank
1 10 15.00
5 Tank Renovation at Village Kahroda (Bhabhor Faliya)
1 15 25.00
6 Tank Renovation at Village Bhatiwada (Kevadiyu Gam talav)
1 15 25.00
7 Tank Renovation at Village Bhatiwada
1 10 20.00
8 Percolation Tank Renovation at Village Cheysana (Zaran Faliya)
1 15 25.00
85
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
9 Tank Renovation at Village Khangela (Nava Faliya)
1 10 20.00
10 Tank Renovation at Village Khangela (Nava Faliya)
1 10 20.00
11 Tank Renovation at Village Khangela (Kikla Talav Faliya)
1 10 20.00
12 Tank Renovation at Village Khangela (Toli Dungari Faliya)
1 10 15.00
13 Tank Renovation at Village Khangela (Simal Khedi Faliya)
1 10 15.00
14 Tank Renovation at Village Varamkhedi
1 10 18.00
15 Tank Renovation at Village Motikharaj (Futelav Talav)
1 15 25.00
16 Tank Renovation at Village Nagrala (Bangla Faliya)
1 15 20.00
17 Tank Renovation at Village Nagrala
1 10 15.00
86
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
18 Tank Renovation at Village Khangela
1 10 15.00
19 Tank Renovation at Village Khangela (Gagrel Talav)
1 10 20.00
20 Tank Renovation at Village Khangela (Masaniya Talav)
1 10 15.00
Total 20 248 395.00
Year 2019-20
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry / Department
Component Activity Total Number
Command Area / Irrigation
Potential (ha)
Estimataed Cost (in
Lacs)
3.1 Dahod NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Retiya M.I. Tank 1 30 50.00
2 Kharoda M.I.tank 1 28 50.00
3 Bavka Nayakpura Percolation Tank
1 16 30.00
4 Khangela Percolation Tank 1 15 25.00
5 Kathla Percolation Tank 1 15 30.00
87
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
6 Limdi Aagavada Percolation Tank
1 13 25.00
Total 6 117 210.00
4.1 Dahod NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0.00 0
8.1.1 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdam at Village Moti Lacheli (Gari Faliya)
1 10 15.00
2 New Checkdam at Village Simaliya (Serve No.43)
1 10 12.00
3 New Checkdam at Village Nani Kharaj (Nr.Dungari Faliya)
1 10 20.00
4 New Checkdam on River Khan at Village Puasri
1 10 15.00
88
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
5 New Checkdam on Dahiya Kotar at Village Puasri
1 10 12.00
6 New Checkdam at Village Khangela
1 10 20.00
7 New Checkdam at Village Vijagadh
1 15 30.00
8 New Checkdam at Village Motikharaj
1 10 15.00
9 New Checkdam on River Khan at Village Motikharaj
1 10 20.00
10 New Checkdam on River Karad at Village Kathla
1 12 25.00
11 New Checkdam on River Darukadi at Village Kathla
1 10 20.00
12 New Checkdam at Village Kathla (Nr.Bridge)
1 12 25.00
13 New Checkdam at Village Bhitodi
1 12 25.00
89
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
14 New Checkdam at Village Moti Lacheli (Nr.Chotiya Kasna Sr.no.)
1 10 25.00
Total 14 151 279.00
8.1.7 Dahod MOA & FW DAC & FW Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Tank Renovation at Village Bavka (Harlav Talav)
1 10 15.00
2 Tank Renovation at Village Bavka (Rahelav Talav)
1 10 15.00
3 Tank Renovation at Village Bavka (Khankhor Talav)
1 15 20.00
4 Tank Renovation at Village Bavka (Madiya Dungari Talav)
1 15 15.00
5 Tank Renovation at Village Muvaliya (Gam Talav)
1 18 22.00
90
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
6 Tank Renovation at Village Khangela (Futelu Talav)
1 15 20.00
7 Tank Renovation at Village Khangela (Navapur Faliya)
1 15 25.00
8 Tank Renovation at Village Nagrala (Damra Faliya)
1 15 25.00
9 Irrigatin Tank Renovation at Village Bavka
1 20 28.00
10 Tank Renovation at Village Bavka (Kadvi Talav)
1 15 25.00
11 Tank Renovation at Village Chandavada
1 15 20.00
12 Tank Renovation at Village Vijagadh (Kakradaravalu Talav)
1 15 25.00
13 Tank Renovation at Village Gadoi (Puraniya Talav)
1 15 25.00
91
Sr.No. Name of the
blocks /Sub
districts
Concerned Ministry / Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
14 Tank Renovation at Village Simaliya Khurd (Dhabajariya Talav)
1 15 25.00
15 Tank Renovation at Village Bhitodi
1 15 28.00
16 Tank Renovation at Village Kathla (Parmar Faliya)
1 15 25.00
17 Tank Renovation at Village Kathla (Mavi Faliya)
1 15 28.00
18 Tank Renovation at Village Ratigar
1 15 28.00
19 Tank Renovation at Village Vankiya (Nahani Talav)
1 15 25.00
20 Tank Renovation at Village Moti Chajeli (Smashan Talav)
1 15 20.00
Total 20 298 459.00
92
Taluka: Dhanpur
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Year 2016-17
3.1 Dhanpur NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Gadhvel M.I.Tank 1 569 130.00
Total 1 569 130.00
4.1 Dhanpur NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Mandor 1 30 60.00
2 L.I.Scheme at Kaseta 1 25 50.00
3 L.I.Scheme at Motimadu 1 30 55.00
Total 3 85 165.00
8.1.1 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdem at Village Navanagar (Doban Faliya)
1 12 18.00
2 New Checkdem at Village Navanagar (Kadval Faliya)
1 15 20.00
3 New Checkdem at Village Kalakhut (Kotar)
1 12 18.00
93
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
4 New Checkdem at Village Aambakach (Kotar)
1 10 15.00
5 New Checkdem at Village Lili amba (Nadi par)
1 12 15.00
Total 5 61 86.00
8.1.7 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 New Village Tank at Undar
1 15 50
2 New Village Tank at Kantu
1 25 55
3 New Village Tank at Khokhbed
1 30 45
Total 3 70 150
Year 2017-18
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3.1 Dhanpur NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Aamlimenpur M.I.Tank 1 578 120.00
94
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
2 Nakti M.I.tank 1 80 70.00
3 Dhanpur M.I.tank 1 30 45.00
4 Kanjeta Percolation Tank 1 20 25.00
Total 4 708 260
4.1 Dhanpur NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdem at Village Nanimalu (Kotar par)
1 15 20.00
2 New Checkdem at Village Gahalvana (Nadi par)
1 10 15.00
3 New Checkdem at Village Ladavad (Nadi par)
1 15 18.00
4 New Checkdem at Village Kotma (Nadi par)
1 12 15.00
5 New Checkdem at Village Vankota (Nadi par)
1 10 15.00
6 New Checkdem at Village Vankota (Vav Faliya)
1 15 18.00
Total 6 77 101.00
95
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8.1.7 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
Year 2018-19
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3.1 Dhanpur NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Zabu M.I.tank 1 30 50
Total 1 30 50.00
4.1 Dhanpur NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
96
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
1 New Checkdem at Village Navanagar (Serve no.36)
1 10 20.00
2 New Checkdem at Village Navanagar (Serve no.44)
1 10 20.00
3 New Checkdem at Village Navanagar (Serve no.202)
1 15 20.00
4 New Checkdem at Village Khalata Garabadi (Juni Garabdi Patel Faliyu)
1 12 18.00
5 New Checkdem at Village Khalata Garabadi
1 10 15.00
6 New Checkdem at Village Jhabu (Nadi par)
1 12 15.00
7 New Checkdem at Village Jhabu (Dhartar Faliya)
1 20 25.00
8 New Checkdem at Village Biliya (Nadi par)
1 15 18.00
9 New Checkdem at Village Dumka (Damor Faliya)
1 15 18.00
10 New Checkdem at Village Mandor (Damor Faliya)
1 10 15.00
Total 10 129 184.00
97
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8.1.7 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
Year 2019-20
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3.1 Dhanpur NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Mandor M.I.tank 1 129 65
2 Ved M.I.tank 1 30 45
3 Navanagar Percolation Tank
1 20 25.00
Total 3 179 135.00
4.1 Dhanpur NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
98
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Total 0 0 0.00
8.1.1 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdem at Village Gangardi Faliya (Gohri Faliya)
1 12 18.00
2 New Checkdem at Village Panam (Katara Faliya)
1 10 15.00
3 New Checkdem at Village Kakadkhila
1 12 15.00
4 New Checkdem at Village Kansota (Nadi Par)
1 15 20.00
Total 4 49 68.00
8.1.7 Dhanpur MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 New Village Tank at Juni Garabdi
1 18 30.00
2 New Village Tank at Khalta Garabdi (Dhnakiya Faliyu)
1 20 30.00
3 New Village Tank at Khalta Khadda
1 15 25.00
99
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Total 3 53 85.00
Taluka: Fatehpura
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
Year 2016-17
3.1 Fatepura NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 FATEHGADHI M.I.TANK
1 100 70.00
2 Margala M.I.tank 1 220 90.00
3 Javesi M.I.tank 1 200 80.00
4 Fatepura lelava M.I.tank
1 25 30.00
5 Kundla Percolation Tank 1 30 35.00
Total 5 575 305.00
4.1 Fatepura NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Nana -Salara
1 22.00 60.00
100
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
2 L.I.Scheme at Mota -Salara
1 20.00 55.00
3 L.I.Scheme at Piapalara 1 18.00 60.00
Total 3 60 175.00
8.1.1 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
8.1.7 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Cont. A new village tank at jagola
1 15.00 47.00
101
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
2 Cont. A new village tank at bhichor ( jogi faliya )
1 20.00 40.00
3 Cont. A new village tank at patvel
1 20.00 50.00
4 Cont. A new village tank at salara ( jalam pura )
1 25.00 50.00
5 Cont. A new village tank at dungar
1 10.00 50.00
6 Cont. A new village tank at javeshi bhurikui
1 20.00 50.00
Total 6 110.00 287.00
Year 2017-18
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
3.1 Fatepura NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
102
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
1 NINDKA M.I.TANK 1 180 47.00
Total 1 180 47.00
4.1 Fatepura NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Balaiya 1 18 65.00
2 L.I.Scheme at Baria ni Hathod
1 18 65.00
3 L.I.Scheme at Lakhanpur
1 30 60.00
Total 3 66 190.00
8.1.1 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
103
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
8.1.7 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Cont. A new village tank at bhichor ( dungar faliya )
1 20.00 25.00
2 Cont. A new village tank at patisara
1 10.00 40.00
3 Cont. A new village tank at ghatawada
1 20.00 45.00
4 Cont. A new village tank at lakhanpur
1 20.00 46.00
5 Cont. A new village tank at sagdapada ( ubapana faliya )
1 20.00 50.00
104
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
6 Renovation to lakhanpur village tank increesing hight of west wear
1 12.00 16.00
7 Renovation to zer sr no. 49/2 village tank increesing hight of west wear
1 10.00 14.00
8 Renovation to ghatavada village tank increesing hight of west wear
1 10.00 20.00
9 Renovation to gadhra village tank increesing hight of west wear
1 20.00 24.00
Total 9 142.00 280.00
Year 2018-19
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
105
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
3.1 Fatepura NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Moti rel M.I.tank 1 90 60.00
2 Kanthagar M.I.tank 1 40 50.00
3 Jagola Percolation Tank 1 25 30.00
4 Moti Dhadheli Percolation Tank
1 30 35.00
Total 4 185 175.00
4.1 Fatepura NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Dungar 1 20 65.00
2 L.I.Scheme at Nindka 1 22 60.00
3 L.I.Scheme at Dhadhela 1 20 50.00
4 L.I.Scheme at Jagola 1 19 50.00
106
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
Total 4 81 225.00
8.1.1 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 Cont. A new check dam at lakhanpur
1 14.00 45.00
Total 1 14 45.00
8.1.7 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Cont. A new village tank at sagdapada ( khora faliya )
1 15.00 45.00
2 Cont. A new village tank at jagola ( mal faliya )
1 18.00 45.00
107
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
3 Cont. A new village tank at nani dhadheli
1 20.00 43.00
Total 3 53.00 133.00
Year 2019-20
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
3.1 Fatepura NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Jalai M.I.tank 1 130 80.00
2 Chhalor M.I.tank 1 40 60.00
3 Motibara Percolation Tank
1 20 30.00
4 Pali Hidoliya Percolation Tank
1 15 25.00
Total 4 205 195.00
4.1 Fatepura NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - 0 0 0
108
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
Total 0 0 0.00
8.1.1 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0
8.1.7 Fatepura MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Renovation to bhichor village tank increesing hight of west wear
1 11.00 25.00
2 Renovation to vavadi village tank increesing hight of west wear
1 10.00 15.00
109
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
3 Renovation to patwel village tank increesing hight of west wear
1 13.00 20.00
4 Renovation to nava talav village tank increesing hight of west wear
1 12.00 15.00
5 Renovation to zer pandor village tank
1 25.00 15.00
Total 5 71 90.00
Taluka: Garbada
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
Year 2016-17
3.1 Garbada NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Jharibujarg M.I.Tank 1 75 27.00
2 Patiya M.I.Tank 1 65 60.00
110
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
3 Minakyar M.I.Tank 1 151 100.00
Total 3 291 187.00
4.1 Garbada NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Zaribujarg babadev
1 50 100.00
Total 1 50 100.00
8.1.1 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Chekdem on River at Zaribujarg Village
1 12 25.00
2 New Chekdem on Kharod River at Zaribujarg Village (Behind Tank)
1 15 25.00
3 New Chekdem on Raski River at Boriyala Village
1 15 25.00
4 New Chekdem at Vadva Village (Nr.Pratap Hari sing Serve no.)
1 15 25.00
111
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
5 New Chekdem on Kali River at Jambua Village (Nr.survey no.41/2)
1 15 20.00
Total 5 72 120.00
8.1.7 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Constructing a New Village Tank at Simaliya Buzarg (Nr.serve no.174)
1 15 20.00
2 Village Tank Renovation at Bhe (Handiya Faliya)
1 15 20.00
3 Village Tank Renovation at Bhe (Gala Faliya)
1 15 20.00
4 Village Tank Renovation at Nalvai (Chhapari Faliya)
1 10 15.00
5 Constructing a New Village Tank at Nalvai (Nr.Verai Mandir)
1 15 20.00
6 Village Tank Renovation at Nalvai (Chhapari Faliya)
1 15 20.00
112
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
7 Kahodiya Village Tank Renovation at Rachharda
1 15 20.00
8 Village Tank Renovation at Rachharda
1 10 15.00
9 Village Tank Renovation at Abhlod Khobra
1 15 25.00
10 Village Tank Renovation at Abhlod Zarla
1 15 25.00
11 Village Tank Renovation at Abhlod Gadoi
1 15 25.00
12 Village Tank Renovation at Bhe Handiya
1 15 25.00
Total 12 170 250
Year 2017-18
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in Lacs)
3.1 Garbada NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Raski M.I.Tank 1 80 70.00
2 Nadhelav M.I. tank 1 150 70.00
113
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
3 Garabada Nava Faliya M.I. Tank
1 50 40.00
4 Boriyala M.I.tank 1 57 50.00
5 Charchoda Percolation Tank
1 35 40.00
6 Garabada Molu Percolation Tank
1 30 35.00
Total 6 402 305
4.1 Garbada NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Chekdem at Nimach Village (Nr.Patel Faliya)
1 10 15.00
2 New Chekdem on River Raski at Sahda Village
1 10 15.00
3 New Chekdem on kotar at Village Zaribujarg
1 15 25.00
4 New Chekdem on River Gangi at Nandva Village
1 15 25.00
114
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
Total 4 50 80.00
8.1.7 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Village Tank Renovation at Boriyala Divaniya
1 8 10.00
2 Village Tank Renovation at Aamli
1 8 12.00
3 Village Tank Renovation at Kharva
1 10 15.00
4 Village Tank Renovation at Matva
1 10 15.00
5 Village Tank Renovation at Nimach (Parmar Faliya)
1 5 10.00
6 Village Tank Renovation at Panchvada (Usra)
1 10 15.00
7 Village Tank Renovation at Bhilva
1 15 20.00
8 Village Tank Renovation at Vajelav
1 15 20.00
9 Village Tank Renovation at Bhe Vedaf
1 15 25.00
115
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
10 Village Tank Renovation at Gungardi (Nanu Talav)
1 15 25.00
11 Village Tank Renovation at Nalvai
1 15 20.00
12 Village Tank Renovation at Nani Nalvai
1 15 20.00
Total 12 141 207.00
Year 2018-19
5.Strategic Action Plan for Irrigation in District under PMKSY
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in Lacs)
3.1 Garbada NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Zari Gangarda M.I.Tank 1 198 80.00
2 Abhlod M.I.tank 1 130 60.00
3 Bhe Percolation Tank 1 20 25.00
Total 3 348 165
4.1 Garbada NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
116
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
8.1.1 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Chekdem at Jetpur (Magrol Faliya)
1 12 15.00
2 New Chekdem at Nansalai (Sarkari Padtar jamin)
1 15 20.00
Total 2 27 35.00
8.1.7 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Village Tank Renovation at Gangarda
1 15 25.00
2 Village Tank Renovation at Nava Faliya
1 15 20.00
3 Village Tank Renovation at Nava Faliya (Molu Talav)
1 15 25.00
4 Village Tank Renovation at Garbada (Gamtal)
1 15 25.00
117
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
5 Village Tank Renovation at Aamli Khajuri (Baipunki Tank)
1 15 20.00
6 Village Tank Renovation at Minakyar
1 15 25.00
7 Village Tank Renovation at Nailsure
1 15 20.00
8 Village Tank Renovation at Patiyazol
1 15 25.00
Total 8 120 185.00
Year 2019-20
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in Lacs)
3.1 Garbada NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Rabdal M.I.Tank 1 165 60.00
2 Gulbar M.I.tank 1 30 40.00
3 Nimach Percolation Tank 1 25 35.00
4 Khobra Percolation Tank 1 20 30.00
Total 4 240 165.00
4.1 Garbada NWR&WS Har Khet Ko Lift Irrigation by Panchayat
118
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
Pani Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Chekdem at Sanpoi (Banuma Kotar)
1 8 12.00
2 New Chekdem at Kadval (Kotarvali ser)
1 10 15.00
Total 2 18 27.00
8.1.7 Garbada MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Village Tank Renovation at Chandala
1 15 25.00
2 Village Tank Renovation at Simaliya Buzarg
1 15 25.00
3 Village Tank Renovation at Patiya
1 15 20.00
119
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in Lacs)
4 Village Tank Renovation at Tunki Anop
1 12 20.00
5 Village Tank Renovation at Tunki Vaju
1 15 25.00
6 Village Tank Renovation at Bharasda
1 15 25.00
7 Village Tank Renovation at Jambua
1 15 25.00
8 Village Tank Renovation at Jambua (Jabukhedi)
1 15 25.00
9 Village Tank Renovation at Gulbar
1 15 25.00
10 Village Tank Renovation at Abhlod
1 15 25.00
Total 10 147 240.00
Taluka: Limkheda
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Year 2016-17
3.1 Limkheda NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
120
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
1 KaliyaGota M.I.Tank 1 175 55.00
2 Dabhada M.I.Tank 1 95 95.00
Total 2 270 150.00
4.1 Limkheda NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 New Checkdam at Village Jada (Suki River Base)
1 30 50.00
Total 1 30 50
8.1.7 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
-
121
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
1 Tank Renovetion at Village Dhadhela
1 8 18.00
2 New Village Tank at Khadada 1 10 20.00
3 Tank Renovetion at Ghatapaliya
1 20 30.00
4 Constructing a F.P. wall (Nr.Manubhai Chauhan's House)
1 - 30.00
Total 4 38 98.00
Year 2017-18
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in Lacs)
1 Limkheda NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Jadakheriya M.I.Tank 1 95 105.00
2 Andhari Parpata M.I.tank 1 105 75.00
3 Munavani M.I.tank 1 30 50.00
122
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
4 Mandli M.I.tank 1 15 45.00
5 Karmadi Percolation Tank 1 20 35.00
6 Katholiya Percolation Tank 1 15 35.00
Total 6 280 345.00
4.1 Limkheda NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.7 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Renovation to Earthen Bund and weist wear of village Tank Handi
1 12 25.00
123
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
2 Renovation to Earthen Bund and weist wear of village Tank Kantholiya
1 12 25.00
3 New Village Tank at Shanagiya
1 12 15.00
Total 3 36 65.00
Year 2018-19
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in Lacs)
3.1 Limkheda NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Sarjumi M.I.Tank 1 105 65.00
2 Pata M.I.tank 1 30 50.00
3 Motamal Percolation Tank 1 15 25.00
4 Kanboi Percolation Tank 1 12 25.00
Total 4 162 165.00
4.1 Limkheda NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 - - - -
124
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Total 0 0 0.00
8.1.1 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.7 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Renovation to Earthen Bund and weist wear of village Tank Pahad
1 10 20.00
2 Renovation to Earthen Bund and weist wear of village Tank Padaliya
1 10 20.00
Total 2 20 40.00
Year 2019-20
125
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in Lacs)
3.1 Limkheda NWR&WS Har Khet Ko Pani
RRR of Water Bodies by Panchayat Irrigation Division
1 Paniya M.I.tank 1 80 60
2 Chhparvad M.I.tank 1 30 45
3 Jherjitgadh Percolation Tank 1 25 30
4 Kundha Percolation Tank 1 30 40.00
5 Methan Percolation Tank 1 30 45.00
Total 5 195 220.00
4.1 Limkheda NWR&WS Har Khet Ko Pani
Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
126
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8.1.7 Limkheda MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Renovation to Earthen Bund and weist wear of village Tank Chundadi
1 12 22.00
Total 1 12 22.00
Taluka: Zalod
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Year 2016-17
3.1 Zalod NWR&WS Har Khet Ko Pani RRR of Water Bodies By Pachayat Irrigation Division
1 Titodi M.I.Tank 1 420 94.00
2 Ghodiavagela M.I.tank 1 80 70.00
127
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3 Malwasi M.I.tank 1 70 65.00
Total 3 570 229
4.1 Zalod NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I. Scheme at Kaligam (Gurjer)
1 20 50.00
2 L.I. Scheme at Sharda 1 60 90.00
3 L.I. Scheme at Tagadola 1 45 60.00
4 L.I. Scheme at Parthampur 1 15 55.00
5 L.I. Scheme at Mundha 1 20 60.00
6 L.I. Scheme at Chakliya (Thanavala)
1 35 65.00
7 L.I. Scheme at Dungari 1 40 60.00
8 L.I. Scheme at Gheswa 1 80 225.00
9 L.I. Scheme at Pareva (Machad River C.D. Base)
1 25 50.00
128
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
10 L.I. Scheme at Nani Khuni (Bariya Faliya) (Govt. Well Based)
1 25 55.00
11 L.I. Scheme at Pipaliya (Dangi Faliya) (Machad River C.D. Base)
1 30 50.00
12 Mini L.I. Scheme at Pareva (Hathila Faliya )
1 35 40.00
13 Mini L.I. Scheme at Pareva (Panchayat Faliya )
1 35 40.00
Total 13 465 900.00
8.1.1 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 cont. a new checkdam at village velpura (nr.survey no.8)
1 12 25.00
2 cont. a new checkdam at village pudi (on patodi river)
1 10 40.00
129
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3 cont. a new checkdam at village simaliya (nana padala faliya)
1 12 25.00
4 cont. a new checkdam at village kaharavani (on river)
1 15 30.00
5 cont. a new checkdam at village kaharavani (dudka faliya) (on kotar)
1 25 30.00
6 cont. a new checkdam at village pareva (on juhi kotar)
1 20 25.00
7 cont. a new checkdam at village dumkheda (smashan kotar)
1 15 25.00
8 renovation of checkdam at village pareva (on machan river)
1 15 25.00
total 8 124 225.00
8.1.7 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting structures village / community ponds by panchayat irrigation division
130
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
1 renovation to rajpur village tank and west wear
1 25 35.00
2 cont. a new village tank at kharvani
1 20 50.00
3 cont. a new village tank at pavadi
1 15 50.00
4 cont. a new village tank at kala pipal
1 15 25.00
5 cont. a new village tank at hadamat khunta
1 20 25.00
6 cont. a new village tank at thala
1 15 49.00
7 cont. a new village tank at kadwal
1 17 40.00
8 cont. a new village tank at amba
1 12 30.00
9 cont. a new village tank at mundha
1 15 90.00
131
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
10 cont. a new village tank at garadu
1 20 45.00
11 cont. a new village tank at velpura
1 15 60.00
12 cont. a new check dam at sharada
1 20 50.00
13 cont. a new village tank at chhasiya
1 14 50.00
14 renovation to kadwal village tank increesing hight of west wear
1 12 24.00
15 renovation to vankol ( ghati faliya ) village tank increesing hight of west wear
1 14 24.00
16 renovation to gultora village tank increesing hight of west wear
1 22 20.00
17 renovation to dumkheda vadla village tank
1 20 25.00
132
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
18 renovation to kharavani irrigation tank and canal network
1 50 40.00
19 renovation to pipaliya village tank
1 25 40.00
20 renovation to pareva village tank
1 20 35.00
Total 20 386.00 807.00
Year 2017-18
Sr.No. Name of the blocks /Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in
Lacs)
3.1 Zalod NWR&WS Har Khet Ko Pani RRR of Water Bodies By Pachayat Irrigation Division
1 Suki M.I.Tank 1 250 150.00
2 Dantia M.I.tank 1 40 60.00
3 Vankol M.I.tank 1 65 50.00
133
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
4 Sarmariya M.I.Tank 1 170 112.00
5 Thala M.I.tank 1 325 70.00
6 Lakhana Muvada MItank 1 120 70.00
7 Devjini Sarsawani M.I.tank 1 45 35.00
8 Aalisimal Percolation Tank 1 25 30.00
9 Dholakhakhra Percolation Tank
1 22 35.00
10 Kachaldhara Percolation Tank
1 25 25.00
11 Karanba Percolation Tank 1 30 35.00
12 Pratham pur Percolation Tank
1 15 25.00
13 Garadu Dhavadiya Percolation Tank
1 12 25.00
14 Chakaliya Gundi Faliya Percolation Tank
1 18 30
134
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Total 14 1162 752.00
4.1 Zalod NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I. Scheme at Maghanisar 1 50 60
2 L.I. Scheme at Hadmatkhota 1 40 55
3 L.I. Scheme at Fulpura 1 35 50
4 L.I. Scheme at Chhansiya 1 40 65
5 L.I. Scheme at Gamdi 1 30 55
6 L.I. Scheme at Thuthikankashiya
1 35 55
7 L.I. Scheme at Kaslafaliya 1 30 50
8 L.I. Scheme at Mundaheda 1 25 45
9 L.I. Scheme at Balendiya 1 50 55.00
10 L.I. Scheme at Khakhariya 1 50 75.00
135
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
11 L.I. Scheme at Chakaliya (Borsad Faliya)
1 70 60.00
12 L.I. Scheme at Chakaliya Datgadh
1 50 65.00
Total 12 505 690
8.1.1 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.7 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
- -
1 Cont. A new village tank at chanasar
1 15.00 40.00
2 Cont. A new village tank at sharda
1 18.00 45.00
136
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3 Cont. A new village tank at thuthi kankasiya
1 10.00 50.00
4 Cont. A new village tank at maghanisar ( damor faliya )
1 12.00 40.00
5 Cont. A new village tank at timachi
1 14.00 45.00
6 Cont. A new village tank at kharvani ( juna pani )
1 20.00 45.00
7 Cont. A new village tank at pipaliya
1 15.00 50.00
8 Renovation to pareva dumkheda village tank increesing hight of west wear
1 15.00 21.00
9 Renovation to bilvani balendiya village tank increesing hight of west wear
1 15.00 20.00
137
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
10 Renovation to vagela ( boda faliya ) village tank increesing hight of west wear
1 10.00 20.00
11 Renovation to pipaliya village tank increesing hight of west wear
1 10.00 15.00
12 Renovation to titariya (samshan faliya ) village tank increesing hight of west wear
1 20.00 30.00
13 Renovation to melaniya village tank increesing hight of west wear
1 16.00 22.00
14 Renovation to sarmariya ( ghuni kotar ) village tank increesing hight of west wear
1 16.00 25.00
138
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
15 Renovation to sarmariya ( rampura faliya ) village tank increesing hight of west wear
1 15.00 24.00
16 Renovation to dant gadh village tank increesing hight of west wear
1 16.00 17.00
17 Renovation to chhayan village tank increesing hight of west wear
1 15.00 25.00
18 Renovation to titariya village tank increesing hight of west wear
1 18.00 24.00
Total 18 270.00 558.00
Year 2018-19
3.1 Zalod NWR&WS Har Khet Ko Pani RRR of Water Bodies By Pachayat Irrigation Division
139
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
1 Parthampur M.I.Tank 1 60 182.00
2 Malwasi devkamla M.I.tank 1 65 70.00
3 Kaligam M.I.tank 1 20 40.00
4 Dholi Danti M.I.tank 1 70 60.00
5 Limdi Kachunbar Percolation Tank
1 20 30.00
6 Kuni Percolation Tank 1 20 35.00
7 Chakaliya Padatiya Percolation Tank
1 25 25.00
8 Dhamankhobra Percolation Tank
1 20 25.00
9 Moti Handi Percolation Tank
1 30 35.00
10 Chakaliyadantgadh Percolation Tank
1 25 30.00
Total 10 355 532.00
140
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
4.1 Zalod NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I. Scheme at Kadval 1 20 45
2 L.I. Scheme at Sapoi 1 40 60
3 L.I. Scheme at Ghodiya 1 15 65
4 L.I. Scheme at Kaligam 1 20 55
5 L.I. Scheme at Parthampur 1 15 55
6 L.I. Scheme at Dungari 1 18 50
7 L.I. Scheme at Sutharvasa 1 17 60
8 L.I. Scheme at Chakliya 1 20 55
9 L.I. Scheme at Dhavadiya 1 45 60.00
10 L.I. Scheme at Jaferpura 1 40 55.00
11 L.I. Scheme at Moli (Bhuriher Faliyu)
1 50 60.00
141
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Total 11 300 620
8.1.1 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.7 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Renovation to chhasiya ( garasiya faliya ) village tank increesing hight of west wear
1 10.00 20.00
2 Renovation to karath kamboi village tank increesing hight of west wear
1 19.00 22.00
142
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
3 Renovation to garadu ( tal faliya ) village tank increesing hight of west wear
1 11.00 25.00
4 Renovation to mundha ( kaledi kuva ) village tank increesing hight of west wear
1 2.00 15.00
5 Renovation to kotada village tank increesing hight of west wear
1 19.00 24.00
6 Renovation to parthampur village tank increesing hight of west wear
1 20.00 25.00
7 Renovation to amba ( pateliya faliya ) village tank increesing hight of west wear
1 15.00 20.00
143
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8 Renovation to amba ( guneshiya faliya ) village tank increesing hight of west wear
1 10.00 20.00
9 Renovation to raliyati bhura village tank increesing hight of west wear
1 15.00 25.00
10 Renovation to vagela 33/b village tank increesing hight of west wear
1 16.00 20.00
11 Renovation to jetpur ( machhar faliya ) village tank increesing hight of west wear
1 16.00 25.00
12 Renovation to kaliya talav village tank canal & c.d. works
1 33.00 24.00
144
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
13 Cont.a new lift irrigation on new village tank chhasiya
1 30.00 45.00
14 Cont.a new lift irrigation on new village tank at titariya
1 24.00 48.00
15 Renovation to dhavadiya village tank increesing hight of west wear
1 10.00 25.00
16 Renovation to rukhdi ( pandav mandir ) village tank increesing hight of west wear
1 20.00 20.00
17 Renovation to kaligam ( ghati faliya ) village tank increesing hight of west wear
1 25.00 24.00
145
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
18 Renovation to mundhaheda village tank increesing hight of west wear
1 24.00 25.00
19 Renovation to lilva thakor village tank increesing hight of west wear
1 12.00 20.00
20 Renovation to dhola khakhra village tank increesing hight of west wear
1 16.00 20.00
Total 20 347.00 492.00
Year 2019-20
Sr.No. Name of the blocks /Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in
Lacs)
3.1 Zalod NWR&WS Har Khet Ko Pani RRR of Water Bodies By Pachayat Irrigation Division
1 Ghasiya M.I.Tank 1 150 45
146
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
2 Moti Handi M.I.tank 1 130 60
3 KarthVagivad M.I.tank 1 145 70
4 Therka M.I.tank 1 120 60
5 Sutharwasa M.I.tank 1 15 25
6 Mahudi Percolation Tank 1 12 25
7 Rampura Percolation Tank 1 20 30
8 Boda dungar Percolation Tank
1 25 35
9 Garadu Percolation Tank 1 30 40
10 Mundha Percolation Tank 1 15 25
11 Munda Heda Percolation Tank
1 20 30
Total 11 682 445.00
4.1 Zalod NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I. Scheme at Tadagola 1 20 55.00
147
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
2 L.I. Scheme at Dhara-Dungar
1 22 60.00
3 L.I. Scheme at Kaligam Satsera
1 18 45.00
4 L.I. Scheme at Chakaliya (Datgadh)
1 18 65.00
5 L.I. Scheme at Kaligam (Inami)
1 16 60.00
6 L.I. Scheme at Chhayan 1 22 70.00
7 L.I. Scheme at Rampura-1 1 14 60.00
8 L.I. Scheme at Timachi 1 15 55.00
Total 8 145 470.00
8.1.1 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
Drought Proofing through Check dams/ water harvesting Structures
1 - - - -
Total 0 0 0.00
148
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
8.1.7 Zalod MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Renovation to sankarpura ( ashram faliya ) village tank increesing hight of west wear
1 15.00 20.00
2 Renovation to gamadi ( nisarta faliya ) village tank increesing hight of west wear
1 16.00 25.00
3 Renovation to ghodiya ( vakavalu faliya ) village tank increesing hight of west wear
1 12.00 24.00
4 Renovation to chakaliya ( timbi faliya ) village tank increesing hight of west wear
1 13.00 20.00
149
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
5 Renovation to tadhagola village tank increesing hight of west wear
1 13.00 25.00
6 Renovation to chakaliya ( mahudi faliya ) village tank increesing hight of west wear
1 12.00 25.00
7 Renovation to kachaldhra village tank increesing hight of west wear
1 15.00 25.00
8 Renovation to kalapipal ( damor faliya ) village tank increesing hight of west wear
1 12.00 20.00
9 Renovation to mundha ( bandi faliya ) village tank increesing hight of west wear
1 4.00 20.00
150
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
10 Renovation to kuni village tank increesing hight of west wear
1 15.00 24.00
11 Renovation to rupakheda ( krishna faliya ) village tank increesing hight of west wear
1 20.00 25.00
12 Renovation to rupakheda kargil village tank increesing hight of west wear
1 20.00 20.00
13 Cont.a new lift irrigation on new checkdam at chakaliya
1 25.00 47.00
14 Renovation to raliyati bhura village tank increesing hight of west wear
1 15.00 20.00
Total 14 207.00 340.00
**Sangli was earlier the part of Jalhod distirict.
151
Taluka- Sangli
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Year 2016-17
3.1 Sanjeli NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 Kunda-Dhamela M.I.Tank 1 40 55.00
1 Kaliya hill M.I.tank 1 350 60.00
Total 2 390 115.00
4.1 Sanjeli NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Moli (Bhuriher Faliya)
1 30 50.00
2 L.I.Scheme at Vasiya1 1 15 55.00
3 L.I.Scheme at Vasiya2 1 20 50.00
4 L.I.Scheme at Partappura 1 10 60.00
5 L.I.Scheme at Mandali 1 18 50.00
6 L.I.Scheme at Kunda 1 18 40.00
152
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Total 6 111 305
8.1.1 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
0 0 0
8.1.7 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 CONT. A NEW VILLAGE TANK AT MOTA KALIYA
1 24.00 45.00
2 CONT. A NEW VILLAGE TANK AT MOTA KALIYA ( PANDOR FALIYA )
1 13.00 40.00
3 CONT. A NEW VILLAGE TANK AT GARADIYA
1 20.00 45.00
153
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Total 3 57.00 130.00
Year 2017-18
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in
Lacs)
3.1 Sanjeli NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 0 0 0.00
Total 0 0 0.00
4.1 Sanjeli NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 L.I.Scheme at Motakaliya 1 50 60.00
2 L.I.Scheme at Hirola (Kochar no.1)
1 30 50.00
3 L.I.Scheme at Dhalsimal 1 25 45.00
4 L.I.Scheme at Partappura 1 10 60.00
5 L.I.Scheme at Mandali 1 18 50.00
154
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
6 L.I.Scheme at Patela 1 20 50.00
7 L.I.Scheme at Chakisana 1 20 55.00
Total 7 173 370.00
8.1.1 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 - - - -
0 0 0
8.1.7 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Cont. A new village tank at trakada mahudi
1 20.00 45.00
155
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
2 Cont. A new village tank at itadi
1 15.00 45.00
3 Cont. A new village tank at chandana na muvada
1 25.00 50.00
4 renovation to chakisana village tank increesing hight of west wear
1 20.00 25.00
5 renovation to sanjeli village tank
1 18.00 25.00
6 renovation to moli village tank increesing hight of west wear
1 6.00 22.00
Total 6 104.00 212.00
Year 2018-19
156
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
Sr.No. Name of the blocks /Sub
districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential (ha)
Estimataed Cost (in
Lacs)
3.1 Sanjeli NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
4.1 Sanjeli NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 Gasali (Gagariya Faliya) 1 50 58.00
2 Bhamela (Mal Faliya) 1 50 55.00
3 Bhanpur 1 25 60.00
4 Garadiya 1 25 65.00
Total 4 150 238.00
8.1.1 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management
water harvesting Structures Checkdam by Panchayat Irrigation Division
157
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
activities)
1 Cont. A new check dam at vansiya
1 12.00 30.00
Total 1 12 30
8.1.7 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Cont. A new village tank at karamba
1 15.00 50.00
2 Cont. A new village tank at hirola
1 20.00 45.00
Total 2 35 95
Year 2019-20
3.1 Sanjeli NWR&WS Har Khet Ko Pani RRR of Water Bodies by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
158
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
4.1 Sanjeli NWR&WS Har Khet Ko Pani Lift Irrigation by Panchayat Irrigation Division
1 - - - -
Total 0 0 0.00
8.1.1 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Checkdam by Panchayat Irrigation Division
1 Cont. A new check dam at jitpura
1 15 50.00
Total 1 15 50.00
8.1.7 Sanjeli MOA & FW DAC & FW
Per Drop more crop (Supplementry Water management activities)
water harvesting Structures Village / Community Ponds by Panchayat Irrigation Division
1 Renovation to kadva na pad village tank increesing hight of west wear
1 22.00 20.00
159
Sr.No. Name of the blocks
/Sub districts
Concerned Ministry /
Department
Component Activity Total Number
Command Area /
Irrigation Potential
(ha)
Estimataed Cost (in
Lacs)
2 Renovation to vansiya village tank increesing hight of west wear
1 20.00 25.00
Total 2 42.00 45.00
Panchayat Irrigation Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
Name of the District : Dahod
Name of the block : Dahod
Sr. No.
Name of the Blocks/Sub Distri
cts
Concerned Ministry/
Department
Component
Activity Total Number
/ Capacity(CUM)
Command Area Irrigation Potential (Ha)
Existing
Irrigation Area (Ha)
2016-17 2017-18 2018-19 2019-20 2020-21
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 Dahod
MoWR AIBP Major irrigation
1 0 0 0 0.00 2100 21000.00
0 0.00 0 0.00
0 0.00
160
Medium Irrigation
1 4595 2595 261 583.00
261 689.00
261 506.00
261 372.00
0 0.00
6 Dahod
MoWR Har khetko
pani
RRR of Water bodies
17 400 225 60 150.00
60 150.00
60 150.00
55 150.00
0 0.00
21 State Planned Scheme for Irrigation
21.1
Dahod
Checkdams
0 0 0 30 100.00
45 90.00 80 200.00
5 90.00
0 0.00
19 4995 351 833.00
2466 21929.00
401 856.00
321 612.00
0 0.00
Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
Name of the District : Dahod
Name of the block : Garbada
Sr. No.
Name of the Blocks/Sub Distri
cts
Concerned Ministry/Department
Component
Activity Total Number
/ Capacity(CUM)
Command Area Irrigation Potential (Ha)
Existing
Irrigation Area (Ha)
2016-17 2017-18 2018-19 2019-20 2020-21
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 Garbada
MoWR AIBP Major irrigation
1 0 0 0 0.00 500 5000.00
0 0.00 0 0.00
0 0.00
Garbada
MoWR AIBP Medium Irrigation
1 477 105 40 35.00
40 35.00 40 35.00
25 30.00
0 0.00
6 Garbada
MoWR Har khetko
RRR of Water
34 577 200 54 80.60
115 394.83
99 487.05
109 595.40
0 0.00
161
pani bodies
21 State Planned Scheme for Irrigation
21.2
Garbada
Checkdams
0 0 0 15 29.57
47 127.94
25 95.00
25 94.00
0 0.00
36 1054 305 109 145.17
702 5557.77
164 617.05
159 719.40
0 0.00
Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
Name of the District : Dahod
Name of the block : Limkheda
Sr. No.
Name of the Blocks/Sub Distri
cts
Concerned Ministry/Department
Component
Activity Total Number
/ Capacity(CUM)
Command Area Irrigation Potential (Ha)
Existing
Irrigation Area (Ha)
2016-17 2017-18 2018-19 2019-20 2020-21
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 Limkheda
MoWR AIBP Major irrigation
1 0 0 0 0.00 2200 22000.00
0 0.00 0 0.00
0 0.00
2 Limkheda
MoWR AIBP Medium Irrigation
1 4010 1850 149 315.72
115 327.00
150 256.00
0 0.00
28 42.00
6 Limkheda
MoWR Har khetko
pani
RRR of Water bodies
26 671 260 165 561.00
155 639.00
55 181.00
36 180.00
0 0.00
21 State Planned Scheme for Irrigation
21.1
Limkheda
Checkdams
0 0 0 250 386.00
200 599.00
235 410.00
90 195.00
0 0.00
28 4681 2110 564 1262.72
2670 23565.00
440 847.00
126 375.00
28 42.00
162
Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
Name of the District : Dahod
Name of the block : Dhanpur
Sr. No.
Name of the Blocks/Sub Distri
cts
Concerned Ministry/Department
Component
Activity Total Number
/ Capacity(CUM)
Command Area Irrigation Potential (Ha)
Existing
Irrigation Area (Ha)
2016-17 2017-18 2018-19 2019-20 2020-21
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 Dhanpur
MoWR AIBP Major irrigation
1 0 0 0 0.00 1500 15000.00
0 0.00 0 0.00
0 0.00
2 Dhanpur
MoWR AIBP Medium Irrigation
1 1362 550 100 187.84
74 127.45
69 104.90
83 117.45
35 112.00
6 Dhanpur
MoWR Har khetko
pani
RRR of Water bodies
14 216 150 0 0.00 21 105.00
0 0.00 45 280.00
0 0.00
Har khetko
pani
Lift Irrigation
2 0 0 0 0.00 0 0.00 350 500.00
0 0.00
0 0.00
21 State Planned Scheme for Irrigation
21.1
Dhanpur
Checkdams
0 0 0 197 463.00
510 640.00
400 760.00
150 350.00
0 0.00
18 1578 700 297 650.84
2105 15872.45
819 1364.90
278 747.45
35 112.00
163
Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
Name of the District : Dahod
Name of the block : D'Baria
Sr. No.
Name of the Blocks/Sub Distri
cts
Concerned Ministry/Department
Component
Activity Total Number
/ Capacity(CUM)
Command Area Irrigation Potential (Ha)
Existing
Irrigation Area (Ha)
2016-17 2017-18 2018-19 2019-20 2020-21
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 D'Baria
MoWR AIBP Medium Irrigation
1 2514 950 99 220.79
95 148.00
75 100.00
155 360.00
20 25.00
6 D'Baria
MoWR Har khetko
pani
RRR of Water bodies
12 230 79 295 0 0 0 23 45.00
64 125.00
64 125.00
21 State Planned Scheme for Irrigation
21.1
D'Baria
Checkdams
0 0 0 171 324.74
260 1145.00
150 720.00
0 0.00
85 195.00
13 2744 1029
565 545.53
355 1293.00
248 865.00
219 485.00
169 345.00
164
Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
Name of the District : Dahod
Name of the block : Zalod
Sr. No.
Name of the Blocks/Sub Distri
cts
Concerned Ministry/Department
Component
Activity Total Number
/ Capacity(CUM)
Command Area Irrigation Potential (Ha)
Existing
Irrigation Area (Ha)
2016-17 2017-18 2018-19 2019-20 2020-21
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 Zalod MoWR AIBP Major Irrigation
1 0 0 0 0.00 2000 20000.00
0 0.00 0 0.00
0 0.00
2 Zalod MoWR AIBP Medium Irrigation
2 3978 1350 99 103.70
242 413.10
119 220.40
121 297.30
0 155.00
6 Zalod MoWR Har khetko
pani
RRR of Water bodies
50 440 90 40 50.00
40 60.00 40 70.00
40 80.00
40 90.00
Zalod MoWR Har khetko
pani
Lift Irrigation Scheme
0 0 0 0 0.00 0 0.00 516 588.00
0 0.00
0 0.00
21 State Planned Scheme for Irrigation
21.1
Zalod Checkdams
0 0 0 196 398.77
102 370.00
0 0.00 0 0.00
0 0.00
53 4418 1440
335 552.47
2384 20843.10
675 878.40
161 377.30
40 245.00
Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
165
Name of the District : Dahod
Name of the block : Fatepura
Sr. No.
Name of the Blocks/Sub Distri
cts
Concerned Ministry/Department
Component
Activity Total Number
/ Capacity(CUM)
Command Area Irrigation Potential (Ha)
Existing
Irrigation Area (Ha)
2016-17 2017-18 2018-19 2019-20 2020-21
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 Fatepura
MoWR AIBP Major Irrigation
1 0 0 0 0.00 1700 19000.00
0 0.00 0 0.00
0 0.00
6 Fatepura
MoWR Har khetko
pani
RRR of Water bodies
25 210 40 20 25.00
20 30.00 20 35.00
20 40.00
20 45.00
21 State Planned Scheme for Irrigation
21.1
Fatepura
Checkdams
0 0 0 0 0.00 123 234.00
0 0.00 0 0.00
0 0.00
26 210 40 20 25.00
1843 19264.00
20 35.00
20 40.00
20 45.00
Chapter V : Strategic Action Plan for Irrigation in District Dahod Under PMKSY
Name of the state : Gujarat
Name of the District : Dahod
Name of the block : Sanjeli
S Name Concerned Compon Activity Total Com Exist 2016-17 2017-18 2018-19 2019-20 2020-21
166
r. No.
of the Blocks/Sub Distri
cts
Ministry/Department
ent Number/
Capacity(CUM)
mand Area Irrigation Potential (Ha)
ing Irrigation Area (Ha)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund (lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
Additional irrigation area (ha)
Fund
(lacs)
2 Sanjeli
MoWR AIBP Major Irrigation
0 0 0 0 0.00 0 0.00 0 0.00 0 0.00
0 0.00
6 Sanjeli
MoWR Har khetko
pani
RRR of Water bodies
0 0 0 0 0.00 0 0.00 0 0.00 0 0.00
0 0.00
21 State Planned Scheme for Irrigation
21.1
Sanjeli
Checkdams
2 0 0 0 0.00 83 80.00
0 0.00 0 0.00
0 0.00
2 0 0 0 0.00
83 80.00
0 0.00
0 0.00
0 0.00
Annexure-3 – Strategic Action Plan of GWRDC
GWRDC
Taluka Concerned Ministry/
Department Component Activity
Total Number/ Capacity(cum )
Command Area/ lrrigation Potential
(Ha)
Estimated cost (in Lakhs)
No. of years
Dahod MoWR AIBP Lift Irrigation
Scheme 3.2 168 240.24 4
Devgadh baria
MoWR AIBP
Lift Irrigation Scheme
16.8 740 1058.2 4
Har Khet ko Pani
Exploratory Tubewell
2.4 4.8 18 4
167
Dhanera MoWR AIBP Lift Irrigation
Scheme 13.6 656 938.08 4
Fatepura MoWR AIBP
Lift Irrigation Scheme
4.8 180 257.4 4
Har Khet ko Pani
Exploratory Tubewell
3.2 6.4 24 4
Garbada MoWR AIBP
Lift Irrigation Scheme
1.6 80 114.4 4
Har Khet ko Pani
Exploratory Tubewell
2.4 4.8 18 4
Limkheda MoWR AIBP
Lift Irrigation Scheme
0.8 32 45.76 4
Har Khet ko Pani
Exploratory Tubewell
2.4 4.8 18 4
Zalod MoWR Har Khet ko
Pani Exploratory
Tubewell 3.2 6.4 24 4
Total
54.4 1883.2 2756.08
Annexure-4 Strategic Action Plan of GLDC
Name of the blocks/ sub
districts
Concerned Ministry/
Department Component Activity
Total Number/ Capacity (cum)
Command area/ Irrigation
potential (Ha.)
Estimated cost (in Rs.
lakh)
Garbada
Agriculture & Co-operation
Har Khet ko Pani Farm pond 80 115.2 89.6
Sim pond 16 67.2 80
WHS 28 168 31.36
Zalod
Agriculture & Co- operation
Har Khet ko Pani Farm pond 80 115.2 89.6
Sim pond 16 67.2 80
WHS 28 168 31.36
Devgadh baria
Agriculture & Co- operation
Har Khet ko Pani Farm pond 80 115.2 89.6
168
Sim pond 16 67.2 80
WHS 28 168 31.36
Dhanpur
Agriculture & Co- operation
Har Khet ko Pani Farm pond 80 115.2 89.6
Sim pond 16 67.2 80
WHS 28 168 31.36
Fatepura
Agriculture & Co- operation
Har Khet ko Pani Farm pond 80 115.2 89.6
Sim pond 16 67.2 80
WHS 28 168 31.36
Limkheda
Agriculture & Co- operation
Har Khet ko Pani Farm pond 80 115.2 89.6
Sim pond 16 67.2 80
WHS 28 168 31.36
Dahod
Agriculture & Co- operation
Har Khet ko Pani Farm pond 80 115.2 89.6
Sim pond 16 67.2 80
WHS 28 168 31.36
TOTAL
Farm pond 560 806.4 627.2
Sim pond 112 470.4 560
WHS 196 1176 219.52
169
Annexure-5 Strategic Action Plan of GSWMA
GSWMA PMKSY watershed MGNREGA
Cost Area Cost Area
Dahod 2887.8 2254.0 608.5 0
Devgadh baria
0.0 0.0
0
Dhanpur 1229.5 0.0 273.7 0
Fatepura 0.0 0.0
0
Garbada 907.8 5681.1 182.4 0
Limkheda 1169.8 1784.0 269.4 0
Zalod 1701.1 1272.5 282.7 0
Total 7896 10991.6 1616.8 0
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Physical Target for FY (2016-17)
EPA
1 Animal camp No. 30 4.06803 0 0 0 23 2.86 Animal Health
170
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Depa.
2 Animal water trough (Havada)
No. 0 0 0 0 0 0 0 0
3 Causeway on connecting roads
No. 1 1.40878 0 0 0 0 0 0
4 Check / Protection wall No. 0 0.87999 0 0 0 0 0 0
5 Demonstration for Agricultural / Animal Husbandry Productivity Enhancement
No. 0 0 0 0 0 0 0 0
6 Drainage line correction (To prevent flooding of Gamtal)
rmt 0 0 0 0 0 0 0 0
7 Drinking water facility No. 1 0.95 0 0 0 0 0 0
8 Fencing for protection from wild animals
rmt. 0 0 0 0 0 0 0 0
9 Grassland/Gauchar Development
Ha. 0 0 0 0 0 0 0 0
171
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
10 Improvised and energy efficient smashan gruh (Cemetery )
No. 0 0 0 0 0 0 0 0
11 Panchayat Well Repair & Pump Room
No. 0 0 0 0 0 0 0 0
12 Rain water harvesting system
No. 0 0.00051 0 0 0 0 0 0
13 Recharge / Repair of open wells
No. 0 0.2527 0 0 0 0 0 0
14 Repair / development of artificial water bodies
No. 12 24.22835
0 0 0 0 0 0
15 Revival of natural water bodies with recharge activities
No. 0 0 0 0 0 0 0 0
16 Sanitation facilities/Sewerage line
rmt 0 0 0 0 0 0 0 0
17 Use solar power for productive activities
No. 0 0 0 0 0 0 0 0
172
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
18 Wind energy development
No. 0 0 0 0 0 0 0 0
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
19 Cause Way Repairing 0 0 0 0 0 0 0 0
20 Pond Waist Wair 0 0.11302 0 0 5 0 0 0
21 Community Sitting Stand
0 0 0 0 0 0 0 0
22 Pond Repairing 0 0.4105 0 0 10 0 0 0
23 Washing Ghat 1 1.04 0 0 0 0 0 0
24 Checkwall Repairing 0 0 0 0 0 0 0 0
25 Culvert/Culvert Repairing
0 0 0 0 0 0 0 0
26 Community hall repair 0 0 0 0 0 0 0 0
27 Others 5 7.6 0 0 0 0 0 0
28 Books for School Library
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Land Development 0 0 0 0 0 0 0 0
173
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
1 Farm Bunding rmt. 146648
96.570705
3099.36 0 63924 63453 41.343 MGNREGS
2 Afforestation Ha. 58.845909
13.84359
0 0 1853 29804 170.97 Forest Depa.
3 Agriculture Demo No. 12 1.04 0 0 0 0 0 0
4 Agro Forestry Ha. 0 0 0 0 0 0 0 0
5 Horticulture Ha. 0 0 0 0 0 0 0 0
6 Land leveling Ha. 860.87
94.6957 0 0 10256 194.23 21.364 GLDC
7 Pasture development Ha. 0 0 0 0 0 0 0 0
8 OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Soil & Moisture Conservation
0 0 0 0 0 0 0 0
1
Check wall No. 219 1021.15065
67851 328 7917700 108 486 MGNREGS
2
Earthen bund No. 4 13 0 0 0 0 0
Protection Wall No. 78 182.616 0 0 842 41 124.65 MGNREG
174
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
3
S
4
Waste weir No. 1 1.50231 0 0 0 0 0 0
5
Bench Terracing cumec
0 0 0 0 0 0 0 0
6
Bori bandh No. 0 0 0 0 0 0 0 0
7
Brushwood Checks No. 0 0 0 0 0 0 0 0
8
Countour Bunding rmt. 0 0 0 0 0 0 0 0
9
Countour Trenches rmt. 7500 3.3035 0 0 2263 6300 1.26 0
10
Earthern Dam No. 0 0 0 0 0 0 0 0
11
Field Outlet No. 1287 107.55633
4022 0 267963 8 0.6 MGNREGS
12
Gabion structure No. 27 21.06 0 0 0 0 0 0
13
Graded Bunding rmt. 0 0 0 0 0 0 0 0
175
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
14
Gully plug No. 872.6 66.03794
4330 169.5 550893 0 0 0
15
Loose boulder Checks No. 2620 4.975 0 0 0 0 0 0
16
Nala Plug No. 1750 154.17199
6388.5 343.5 246976 58 45.646 MGNREGS
17
Stone bunding rmt. 21243.365
240.17632
45 551 22481 182.36 2.5478 MGNREGS
18
Straggred Contour trenching(Terrace Talavadi)
0 0 0 0 0 18270 3.654 MGNREGS
19
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
20
Pond 4 8 0 0 1123 2 5 MGNREGS
21
Cement Nala Plug (Small Check Wall)
70 50.61762
1580 25 1669 0 0 0
176
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
22 Grassland/Gauchar Development
0 0 0 0 0 0 0 0
23 Others 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
S.No
Water Harvesting Structure
0 0 0 0 0 0 0 0
1 Cause way cum Chek dam
No. 8 18.77 15 15 1746 0 0 0
2 Check dam No. 191 859.37235
126221 686 34364 102 459 MGNREGS
3 Village/Community Pond
No. 2 18 16304 4.5 12000 0 0 0
4 Farm Pond No. 4 6.069 8100 8 1517 0 0 0
5 Percolation Tank No. 0 0 0 0 0 0 0 0
6 Pond Inlet No. 0 0 0 0 0 0 0 0
7 Pond Outlet No. 0 0 0 0 0 0 0 0
8
OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
177
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
9
Cement Nala Plug (Small Check Wall)
29 22.794 0 0 0 0 0 0
12
0 0 0 0 0 0 0 0
S.No
Existing/Old Water Harvesting Structure Maintance (Renovation & Repair)
0 0 0 0 0 0 0 0
1 Deepening/Desiltation Of Pond
No. 25 53.0445 1260869 75.67 19097 0 0 0
2 Deepening Of Percolation Tank
No. 0 0 0 0 0 0 0 0
3 De-siltation of Checkdam
No. 10 2.02 5000 24 983 8 4.06 MGNREGS
4 Repairing of Checkdam No. 14 10.896 3600 50 933 0 0 0
5 OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
178
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Renovation of Checkdam
7 21 0 0 0 0 0 0
De-siltation of Checkwall
0 0 0 0 0 0 0 0
Repairing of Checkwall 0 0 0 0 0 0 0 0
Renovation of Checkwall
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
S.No
Ground Water Recharging Structures
0 0 0 0 0 0 0 0
1
Dugwell Recharge structure
No. 0 0 0 0 0 0 0 0
2 Farm Recharge Filter No. 0 0 0 0 0 0 0 0
3
Holiya in farm/Field No. 0 0 0 0 0 0 0 0
Pond Recharge structure
No. 0 0 0 0 0 0 0 0
179
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
4
5
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
6
Well Recharge 58 41.46 4076 0 667 7 14 0
0 0 0 0 0 0 0 0
LH & ME & Production System
0 0 0 0 0 0 0 0
1 AGRICULTURE ACTIVITIES
0 0 0 0 0 0 0 0
Agro Center 30 59.75 0 0 0 0 0 0
Agricultural Implements
13 5.1 0 0 0 0 0 0
Agro- Forestry 0 0 0 0 0 0 0 0
Crop Demonstration Plot
198 33.332 150 0 403 30 5.0115 Agriculture
Department
180
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Fishery Development 76 17.54999
5250 0 511 0 0 0
Floriculture Development
201 33.7275 490 0 609 0 0 0
Fodder Bank Development
0 0 0 0 0 0 0 0
Green House 0 0 0 0 0 0 0 0
Horticulture Plantation 321.4 67.1625 910 0 750 3 0.4 Agriculture Dept.
Kitchen Garden 1557 253.27155
830 0 2225 0 0 0
Nursery raising 62 46.5 90 0 450 3 2.25 MGNREGA
OTHERS 0 0 0 0 0 0 0 0
INPUT SUPPORT 0 0 0 0 0 0 0 0
Promoting Micro-Irrigation Systems like drip and Sprinkler Irrigation
495 168.71 0 0 213 276 291.04 TASP & GGRC
Sprinkler Demo. 0 0 0 0 0 0 0 0
181
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Vegetable Nursery Raising with drip irrigation
35 35 0 0 0 35 26.25 GGRC
Vermi compost 864 154.2017
0 0 2450 132 23.4 MGNREGS
2 AGRO PROCESSING ACTIVITIES
0 0 0 0 0 0 0 0
Dal Making Unit 0 0 0 0 0 0 0 0
Flour & Dal/Rice Processing unit
37 27.5444 0 0 0 0 0 0
Garam Masala 0 0 0 0 0 0 0 0
Grading and packaging of agricultural produces,
0 0 0 0 0 0 0 0
Jam-jelly making 0 0 0 0 0 0 0 0
Microenterprises based on Minor Forest Produce (MFP)
0 0 0 0 0 0 0 0
Oil extraction mill 0 0 0 0 0 0 0 0
OTHERS 7 5.7496 0 0 0 0 0 0
182
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Package Food Products 0 0 0 0 0 0 0 0
Pulp making 0 0 0 0 0 0 0 0
Rice mill 0 0 0 0 0 0 0 0
Value added products from milk
0 0 0 0 0 0 0 0
3 Animal Husbandry 0 0 0 0 0 0 0 0
Cattle Feed and Nutrition Store
5 6.1 0 0 0 0 0 0
Animal Health camps 143 16.94662
0 0 0 0 0 0
Animal Travis (Pinjaru) 0 0 0 0 0 0 0 0
Apiculture (Bee keeping)
0 0 0 0 0 0 0 0
Artificial insemination 0 0 0 0 0 0 0 0
Back-yard poultry 0 0 0 0 0 0 0 0
Dairy cooperative promotion,
3 2.682 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
183
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Pasture development 0 0 0 0 0 0 0 0
Poultry Farming to individuals
417 155.07 0 0 1637 0 0 0
Sericulture 0 0 0 0 0 0 0 0
Small ruminants 0 0 0 0 0 0 0 0
Veterinary Aid for livestock
0 0 0 0 0 0 0 0
Cattle Shed 0 0 0 0 0 0 0 0
4 Establishing linkages 0 0 0 0 0 0 0 0
Credit linkages 0 0 0 0 0 0 0 0
Linkages with Future Markets,
0 0 0 0 0 0 0 0
Market linkages, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Raw material supply channel,
0 0 0 0 0 0 0 0
5 Local traditional handicraft
0 0 0 0 0 0 0 0
Bamboo based products,
23 6.3 0 0 133 0 0 0
184
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Kutchi Bandhini, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Pottery 15 3.75 0 0 370 0 0 0
6 Minor Activities 0 0 0 0 0 0 0 0
Embroidery Unit 0 0 0 0 0 0 0 0
Handicraft Unit 0 0 0 0 0 0 0 0
OTHERS 77 87.9098 0 0 370 3 15 SHG/BANK
Provision Store 10 16.025 0 0 0 0 0 0
stiching machine 166 23.381 0 0 222 0 0 0
Up Gradation of centering materials
5 9.75 0 0 0 0 0 0
Vegetable shop 0 0 0 0 0 0 0 0
7 Non-conventional Energy Sources
0 0 0 0 0 0 0 0
Bio gas plant, 87 5.3 0 0 0 5 0.75 0
Bio-fuel plantation, 0 0 0 0 0 0 0 0
energy conservation measures,
0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
185
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Solar energy promotion, 0 0 0 0 0 0 0 0
Wind energy production,
0 0 0 0 0 0 0 0
Total 4415.51 2280.17 9169608 119048 1747.1 0
CB, Monitoring and Evaluation
55.00
Admin
190.25
Consolidation
120.01
Total
365.26
Grand Total 4780.77 2280.17
Physical Target for FY (2017-18)
EPA
1 Animal camp No. 0 0 0 0 0 0 0 0
186
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
2 Animal water trough (Havada)
No. 0 0 0 0 0 0 0 0
3 Causeway on connecting roads
No. 0 0 0 0 0 0 0 0
4 Check / Protection wall No. 0 0 0 0 0 0 0 0
5 Demonstration for Agricultural / Animal Husbandry Productivity Enhancement
No. 0 0 0 0 0 0 0 0
6 Drainage line correction (To prevent flooding of Gamtal)
rmt 0 0 0 0 0 0 0 0
7 Drinking water facility No. 0 0 0 0 0 0 0 0
8 Fencing for protection from wild animals
rmt. 0 0 0 0 0 0 0 0
9 Grassland/Gauchar Development
Ha. 0 0 0 0 0 0 0 0
187
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
10 Improvised and energy efficient smashan gruh (Cemetery )
No. 0 0 0 0 0 0 0 0
11 Panchayat Well Repair & Pump Room
No. 0 0 0 0 0 0 0 0
12 Rain water harvesting system
No. 0 0 0 0 0 0 0 0
13 Recharge / Repair of open wells
No. 0 0 0 0 0 0 0 0
14 Repair / development of artificial water bodies
No. 0 0 0 0 0 0 0 0
15 Revival of natural water bodies with recharge activities
No. 0 0 0 0 0 0 0 0
16 Sanitation facilities/Sewerage line
rmt 0 0 0 0 0 0 0 0
17 Use solar power for productive activities
No. 0 0 0 0 0 0 0 0
188
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
18 Wind energy development
No. 0 0 0 0 0 0 0 0
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
19 Cause Way Repairing 0 0 0 0 0 0 0 0
20 Pond Waist Wair 0 0 0 0 0 0 0 0
21 Community Sitting Stand
0 0 0 0 0 0 0 0
22 Pond Repairing 0 0 0 0 0 0 0 0
23 Washing Ghat 0 0 0 0 0 0 0 0
24 Checkwall Repairing 0 0 0 0 0 0 0 0
25 Culvert/Culvert Repairing
0 0 0 0 0 0 0 0
26 Community hall repair 0 0 0 0 0 0 0 0
27 Others 0 0 0 0 0 0 0 0
28 Books for School Library
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Land Development 0 0 0 0 0 0 0 0
189
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
1 Farm Bunding rmt. 24755 31.29075
0 0 0 9173 6.00445 MGNREGS
2 Afforestation Ha. 36.1818
6.56 0 0 0 306.36 17.5167 Forest Depa.
3 Agriculture Demo No. 12 1.04 0 0 0 0 0 0
4 Agro Forestry Ha. 0 0 0 0 0 0 0 0
5 Horticulture Ha. 0 0 0 0 0 0 0 0
6 Land leveling Ha. 516.75
56.8425 0 0 0 100 11 GLDC
7 Pasture development Ha. 0 0 0 0 0 0 0 0
8 OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Soil & Moisture Conservation
0 0 0 0 0 0 0 0
1
Check wall No. 13 58.5 0 0 0 13 52.5 MGNREGS
2
Earthen bund No. 96 29.96 0 0 0 0 0
Protection Wall No. 35 110.716 0 0 0 38 100.92 MGNREG
190
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
3
S
4
Waste weir No. 2 3 0 0 0 0 0 0
5
Bench Terracing cumec
0 0 0 0 0 0 0 0
6
Bori bandh No. 0 0 0 0 0 0 0 0
7
Brushwood Checks No. 0 0 0 0 0 0 0 0
8
Countour Bunding rmt. 0 0 0 0 0 0 0 0
9
Countour Trenches rmt. 1500 0.3 0 0 0 3700 0.74 MGNREGS
10
Earthern Dam No. 10 30 0 0 0 0 0 0
11
Field Outlet No. 475 35.605 2715 0 445 0 0 0
12
Gabion structure No. 0 0 0 0 0 0 0 0
13
Graded Bunding rmt. 0 0 0 0 0 0 0 0
191
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
14
Gully plug No. 208 10.694 103 0 0 0 0 0
15
Loose boulder Checks No. 2620 4.975 0 0 0 0 0 0
16
Nala Plug No. 573 99.13 67050 618 0 0 0 0
17
Stone bunding rmt. 15242 212.25234
12381 0 1512 0 0 0
18
Straggred Contour trenching(Terrace Talavadi)
0 0 0 0 0 0 0 0
19
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
20
Pond 1 5 2717 25 0 0 0 0
21
Cement Nala Plug (Small Check Wall)
5 3.93 0 0 0 0 0 0
192
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
22 Grassland/Gauchar Development
0 0 0 0 0 0 0 0
23 Others 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
S.No
Water Harvesting Structure
0 0 0 0 0 0 0 0
1 Cause way cum Chek dam
No. 5 15 13587 125 2223 0 0 0
2 Check dam No. 104 469.98 113658.5 828 4669 36 128.25 MGNREGS
3 Village/Community Pond
No. 0 0 0 0 0 0 0 0
4 Farm Pond No. 15 6.8476 18395 287 1517 0 0 0
5 Percolation Tank No. 0 0 0 0 0 0 0 0
6 Pond Inlet No. 0 0 0 0 0 0 0 0
7 Pond Outlet No. 0 0 0 0 0 0 0 0
8
OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
193
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
9
Cement Nala Plug (Small Check Wall)
0 0 0 0 0 0 0 0
12
0 0 0 0 0 0 0 0
S.No
Existing/Old Water Harvesting Structure Maintance (Renovation & Repair)
0 0 0 0 0 0 0 0
1 Deepening/Desiltation Of Pond
No. 0 0 0 0 0 13 48 MGNREGS
2 Deepening Of Percolation Tank
No. 0 0 0 0 0 0 0 0
3 De-siltation of Checkdam
No. 3 1.6 0 0 0 1 0.4 MGNREGS
4 Repairing of Checkdam No. 5 3.54 0 0 0 0 0 0
5 OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
194
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Renovation of Checkdam
11 26 4529 42 743 4 3 MGNREGS
De-siltation of Checkwall
10 36.25 0 0 0 0 0 0
Repairing of Checkwall 0 0 0 0 0 0 0 0
Renovation of Checkwall
3 4.32 0 0 0 0 0 0
0 0 0 0 0 0 0 0
S.No
Ground Water Recharging Structures
0 0 0 0 0 0 0 0
1
Dugwell Recharge structure
No. 0 0 0 0 0 0 0 0
2 Farm Recharge Filter No. 0 0 0 0 0 0 0 0
3
Holiya in farm/Field No. 0 0 0 0 0 0 0 0
Pond Recharge structure
No. 0 0 0 0 0 0 0 0
195
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
4
5
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
6
Well Recharge 64 72.77 58577 0 9592 15 26 0
0 0 0 0 0 0 0 0
LH & ME & Production System
0 0 0 0 0 0 0 0
1 AGRICULTURE ACTIVITIES
0 0 0 0 0 0 0 0
Agro Center 8 14.73 0 0 0 0 0 0
Agricultural Implements
0 0 0 0 0 0 0 0
Agro- Forestry 0 0 0 0 0 0 0 0
Crop Demonstration Plot
49 10.12 0 0 0 0 0 0
196
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Fishery Development 1 0.75 0 0 0 0 0 0
Floriculture Development
45 3.9525 0 0 0 0 0 0
Fodder Bank Development
0 0 0 0 0 0 0 0
Green House 0 0 0 0 0 0 0 0
Horticulture Plantation 50 10 0 0 0 0 0 0
Kitchen Garden 483 92.62755
0 0 0 0 0 0
Nursery raising 12 9 0 0 0 0 0 0
OTHERS 40 7.2 0 0 0 0 0 0
INPUT SUPPORT 0 0 0 0 0 0 0 0
Promoting Micro-Irrigation Systems like drip and Sprinkler Irrigation
108 108 0 0 0 144 120.5 TASP & GGRC
Sprinkler Demo. 72 17.28 0 0 0 72 47.52 GGRC
197
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Vegetable Nursery Raising with drip irrigation
0 0 0 0 0 0 0 0
Vermi compost 131 21.91 0 0 0 126 22.61 MGNREGS
2 AGRO PROCESSING ACTIVITIES
0 0 0 0 0 0 0 0
Dal Making Unit 0 0 0 0 0 0 0 0
Flour & Dal/Rice Processing unit
18 9.49 0 0 0 16 8 SHG/BANK
Garam Masala 0 0 0 0 0 0 0 0
Grading and packaging of agricultural produces,
0 0 0 0 0 0 0 0
Jam-jelly making 0 0 0 0 0 0 0 0
Microenterprises based on Minor Forest Produce (MFP)
0 0 0 0 0 0 0 0
Oil extraction mill 0 0 0 0 0 0 0 0
OTHERS 1 0.75 0 0 0 0 0 0
198
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Package Food Products 0 0 0 0 0 0 0 0
Pulp making 0 0 0 0 0 0 0 0
Rice mill 0 0 0 0 0 0 0 0
Value added products from milk
0 0 0 0 0 0 0 0
3 Animal Husbandry 0 0 0 0 0 0 0 0
Cattle Feed and Nutrition Store
5 7.25 0 0 0 0 0 0
Animal Health camps 127 22.88025
4.8535 0 0 73 17.48 Animal Husband
ry
Animal Travis (Pinjaru) 0 0 0 0 0 0 0 0
Apiculture (Bee keeping)
0 0 0 0 0 0 0 0
Artificial insemination 0 0 0 0 0 0 0 0
Back-yard poultry 0 0 0 0 0 0 0 0
Dairy cooperative promotion,
4 4.58 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
199
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Pasture development 0 0 0 0 0 0 0 0
Poultry Farming to individuals
221 57.84 0 0 0 199 13.93 Animal Husband
ry Sericulture 0 0 0 0 0 0 0 0
Small ruminants 0 0 0 0 0 0 0 0
Veterinary Aid for livestock
0 0 0 0 0 0 0 0
Cattle Shed 40 9.6 0 0 0 40 0.4 Farmers Contributi
on
4 Establishing linkages 0 0 0 0 0 0 0 0
Credit linkages 0 0 0 0 0 0 0 0
Linkages with Future Markets,
0 0 0 0 0 0 0 0
Market linkages, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Raw material supply channel,
0 0 0 0 0 0 0 0
5 Local traditional handicraft
0 0 0 0 0 0 0 0
200
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Bamboo based products,
12 2.05 0 0 0 0 0 0
Kutchi Bandhini, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Pottery 0 0 0 0 0 0 0 0
6 Minor Activities 0 0 0 0 0 0 0 0
Embroidery Unit 0 0 0 0 0 0 0 0
Handicraft Unit 0 0 0 0 0 0 0 0
OTHERS 95 69.15 0 0 0 44 34.66 SHG/BANK
Provision Store 12 19.04 0 0 0 0 0 0
stiching machine 10 1.5 0 0 0 0 0 0
Up Gradation of centering materials
2 3.8 0 0 0 0 0 0
Vegetable shop 0 0 0 0 0 0 0 0
7 Non-conventional Energy Sources
0 0 0 0 0 0 0 0
Bio gas plant, 5 0.25 0 0 0 5 0.75 0
Bio-fuel plantation, 0 0 0 0 0 0 0 0
201
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
energy conservation measures,
0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0 Solar energy
promotion,
0 0 0 0 0 0 0 0
Wind energy production,
0 0 0 0 0 0 0 0
Total
47870.9 1839.8535
1925 20701 14118 660.181
CB, Monitoring and Evaluation
50.00
Admin 152.50
Consolidation 205.69
Total 408.19
Grand Total 2248.05 1925.00
202
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Physical Target for FY (2018-19) EPA
1 Animal camp No. 0 0 0 0 0 0 0 0
2 Animal water trough (Havada)
No. 0 0 0 0 0 0 0 0
3 Causeway on connecting roads
No. 0 0 0 0 0 0 0 0
4 Check / Protection wall No. 0 0 0 0 0 0 0 0
5 Demonstration for Agricultural / Animal Husbandry Productivity Enhancement
No. 0 0 0 0 0 0 0 0
6 Drainage line correction (To prevent flooding of Gamtal)
rmt 0 0 0 0 0 0 0 0
7 Drinking water facility No. 0 0 0 0 0 0 0 0
203
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
8 Fencing for protection from wild animals
rmt. 0 0 0 0 0 0 0 0
9 Grassland/Gauchar Development
Ha. 0 0 0 0 0 0 0 0
10 Improvised and energy efficient smashan gruh (Cemetery )
No. 0 0 0 0 0 0 0 0
11 Panchayat Well Repair & Pump Room
No. 0 0 0 0 0 0 0 0
12 Rain water harvesting system
No. 0 0 0 0 0 0 0 0
13 Recharge / Repair of open wells
No. 0 0 0 0 0 0 0 0
14 Repair / development of artificial water bodies
No. 0 0 0 0 0 0 0 0
15 Revival of natural water bodies with recharge activities
No. 0 0 0 0 0 0 0 0
204
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
16 Sanitation facilities/Sewerage line
rmt 0 0 0 0 0 0 0 0
17 Use solar power for productive activities
No. 0 0 0 0 0 0 0 0
18 Wind energy development
No. 0 0 0 0 0 0 0 0
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
19 Cause Way Repairing 0 0 0 0 0 0 0 0
20 Pond Waist Wair 0 0 0 0 0 0 0 0
21 Community Sitting Stand
0 0 0 0 0 0 0 0
22 Pond Repairing 0 0 0 0 0 0 0 0
23 Washing Ghat 0 0 0 0 0 0 0 0
24 Checkwall Repairing 0 0 0 0 0 0 0 0
25 Culvert/Culvert Repairing
0 0 0 0 0 0 0 0
26 Community hall repair 0 0 0 0 0 0 0 0
27 Others 0 0 0 0 0 0 0 0
205
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
28 Books for School Library
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Land Development 0 0 0 0 0 0 0 0
1 Farm Bunding rmt. 38983 25.3369 0 0 0 6150 3.9975 0
2 Afforestation Ha. 0 0 0 0 0 268 13.58625 Forest Depa.
3 Agriculture Demo No. 0 0 0 0 0 0 0 0
4 Agro Forestry Ha. 0 0 0 0 0 0 0 0
5 Horticulture Ha. 0 0 0 0 0 0 0 0
6 Land leveling Ha. 275.13
30.26463
1495 14 245 147 16.17 GLDC
7 Pasture development Ha. 0 0 0 0 0 0 0 0
8 OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Soil & Moisture Conservation
0 0 0 0 0 0 0 0
Check wall No. 0 0 0 0 0 0 0
206
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
1
2
Earthen bund No. 0 0 0 0 0 120 28.8 MGNREGS
3
Protection Wall No. 6 7 0 0 0 62 98 MGNREGS
4
Waste weir No. 12 18 0 0 0 0 0 0
5
Bench Terracing cumec
0 0 0 0 0 0 0 0
6
Bori bandh No. 0 0 0 0 0 0 0 0
7
Brushwood Checks No. 0 0 0 0 0 0 0 0
8
Countour Bunding rmt. 0 0 0 0 0 0 0 0
9
Countour Trenches rmt. 0 0 0 0 0 0 0 0
10
Earthern Dam No. 9 27 0 0 0 0 0 0
11
Field Outlet No. 10 87 788 7 129 0 0 0
207
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
12
Gabion structure No. 0 0 0 0 0 0 0 0
13
Graded Bunding rmt. 0 0 0 0 0 0 0 0
14
Gully plug No. 0 0 0 0 0 0 0 0
15
Loose boulder Checks No. 0 0 0 0 0 0 0 0
16
Nala Plug No. 0 0 0 0 0 0 0 0
17
Stone bunding rmt. 0 0 0 0 0 0 0 0
18
Straggred Contour trenching(Terrace Talavadi)
0 0 0 0 0 0 0 0
19
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
20
Pond 1 5 2717 25 0 0 0 0
208
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
21
Cement Nala Plug (Small Check Wall)
0 0 0 0 0 0 0 0
22 Grassland/Gauchar Development
0 0 0 0 0 0 0 0
23 Others 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
S.No
Water Harvesting Structure
0 0 0 0 0 0 0 0
1 Cause way cum Chek dam
No. 0 0 0 0 0 0 0 0
2 Check dam No. 21 81.01 63797 530 6670 34 108 MGNREGS
3 Village/Community Pond
No. 0 0 0 0 0 0 0 0
4 Farm Pond No. 48 11.52 5720 476 0 0 0 0
5 Percolation Tank No. 0 0 0 0 0 0 0 0
6 Pond Inlet No. 7 12 0 0 0 1 1.5 MGNREGS
7 Pond Outlet No. 0 0 0 0 0 0 0 0
209
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
8
OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
9
Cement Nala Plug (Small Check Wall)
0 0 0 0 0 0 0 0
12
0 0 0 0 0 0 0 0
S.No
Existing/Old Water Harvesting Structure Maintance (Renovation & Repair)
0 0 0 0 0 0 0 0
1 Deepening/Desiltation Of Pond
No. 0 0 0 0 0 0 0 0
2 Deepening Of Percolation Tank
No. 0 0 0 0 0 0 0 0
3 De-siltation of Checkdam
No. 0 0 0 0 0 0 0 0
210
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
4 Repairing of Checkdam No. 0 0 0 0 0 0 0 0
5 OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
Renovation of Checkdam
0 0 0 0 0 0 0 0
De-siltation of Checkwall
6 21.75 0 0 0 0 0 0
Repairing of Checkwall 0 0 0 0 0 0 0 0
Renovation of Checkwall
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
S.No
Ground Water Recharging Structures
0 0 0 0 0 0 0 0
1
Dugwell Recharge structure
No. 0 0 0 0 0 0 0 0
2 Farm Recharge Filter No. 0 0 0 0 0 0 0 0
211
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
3
Holiya in farm/Field No. 0 0 0 0 0 0 0 0
4
Pond Recharge structure
No. 0 0 0 0 0 0 0 0
5
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
6
Well Recharge 44 140.65 43044 396 7044 19 27.5 0
0 0 0 0 0 0 0 0
LH & ME & Production System
0 0 0 0 0 0 0 0
1 AGRICULTURE ACTIVITIES
0 0 0 0 0 0 0 0
Agro Center 1 2 0 0 0 0 0 0
Agricultural Implements
0 0 0 0 0 0 0 0
Agro- Forestry 0 0 0 0 0 0 0 0
212
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Crop Demonstration Plot
18 4.66 0 0 0 0 0 0
Fishery Development 6 4.5 0 0 0 0 0 0
Floriculture Development
3 0.33 0 0 0 0 0 0
Fodder Bank Development
0 0 0 0 0 0 0 0
Green House 0 0 0 0 0 0 0 0
Horticulture Plantation 7 1.4 0 0 0 0 0 0
Kitchen Garden 228 53.3075 0 0 0 0 0 0
Nursery raising 2 1.5 0 0 0 0 0 0
OTHERS 28 0.28 0 0 0 0 0 0
INPUT SUPPORT 0 0 0 0 0 0 0 0
Promoting Micro-Irrigation Systems like drip and Sprinkler Irrigation
10 10 0 0 0 0 0 0
Sprinkler Demo. 27 0 0 0 0 0 0 0
213
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Vegetable Nursery Raising with drip irrigation
31 8.25 0 0 0 0 0 0
Vermi compost 18 3.24 0 0 0 4 7.2 MGNREGS
2 AGRO PROCESSING ACTIVITIES
0 0 0 0 0 0 0 0
Dal Making Unit 0 0 0 0 0 0 0 0
Flour & Dal/Rice Processing unit
0 0 0 0 0 0 0 0
Garam Masala 0 0 0 0 0 0 0 0
Grading and packaging of agricultural produces,
0 0 0 0 0 0 0 0
Jam-jelly making 0 0 0 0 0 0 0 0
Microenterprises based on Minor Forest Produce (MFP)
0 0 0 0 0 0 0 0
Oil extraction mill 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
214
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Package Food Products 0 0 0 0 0 0 0 0
Pulp making 0 0 0 0 0 0 0 0
Rice mill 0 0 0 0 0 0 0 0
Value added products from milk
0 0 0 0 0 0 0 0
3 Animal Husbandry 0 0 0 0 0 0 0 0
Cattle Feed and Nutrition Store
0 0 0 0 0 0 0 0
Animal Health camps 8 3.6 0 0 0 8 3.6 Animal Husband
ry
Animal Travis (Pinjaru) 0 0 0 0 0 0 0 0
Apiculture (Bee keeping)
0 0 0 0 0 0 0 0
Artificial insemination 0 0 0 0 0 0 0 0
Back-yard poultry 0 0 0 0 0 0 0 0
Dairy cooperative promotion,
0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
215
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Pasture development 0 0 0 0 0 0 0 0
Poultry Farming to individuals
41 9.84 0 0 0 0 0 0
Sericulture 0 0 0 0 0 0 0 0
Small ruminants 0 0 0 0 0 0 0 0
Veterinary Aid for livestock
0 0 0 0 0 0 0 0
Cattle Shed 0 0 0 0 0 0 0 0
4 Establishing linkages 0 0 0 0 0 0 0 0
Credit linkages 0 0 0 0 0 0 0 0
Linkages with Future Markets,
0 0 0 0 0 0 0 0
Market linkages, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Raw material supply channel,
0 0 0 0 0 0 0 0
5 Local traditional handicraft
0 0 0 0 0 0 0 0
Bamboo based products,
0 0 0 0 0 0 0 0
216
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Kutchi Bandhini, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Pottery 0 0 0 0 0 0 0 0
6 Minor Activities 0 0 0 0 0 0 0 0
Embroidery Unit 0 0 0 0 0 0 0 0
Handicraft Unit 0 0 0 0 0 0 0 0
OTHERS 144 24.93 0 0 0 6 3.6 SHG/BANK
Provision Store 0 0 0 0 0 0 0 0
stiching machine 10 1.5 0 0 0 0 0 0
Up Gradation of centering materials
0 0 0 0 0 0 0 0
Vegetable shop 0 0 0 0 0 0 0 0
7 Non-conventional Energy Sources
0 0 0 0 0 0 0 0
Bio gas plant, 0 0 0 0 0 0 0 0
Bio-fuel plantation, 0 0 0 0 0 0 0 0
energy conservation measures,
0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
217
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Solar energy promotion,
0 0 0 0 0 0 0 0
Wind energy production,
0 0 0 0 0 0 0 0
Total 40004
595.87 1448 14088 6819 311.9538 0
CB, Monitoring and Evaluation
40.00
Admin 61.15
Consolidation 39.76
Total 140.91
Grand Total 736.78 1448.00
Physical Target for FY (2019-20)
EPA
1 Animal camp No. 0 0 0 0 0 0 0 0
2 Animal water trough (Havada)
No. 0 0 0 0 0 0 0 0
218
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
3 Causeway on connecting roads
No. 0 0 0 0 0 0 0 0
4 Check / Protection wall No. 0 0 0 0 0 0 0 0
5 Demonstration for Agricultural / Animal Husbandry Productivity Enhancement
No. 0 0 0 0 0 0 0 0
6 Drainage line correction (To prevent flooding of Gamtal)
rmt 0 0 0 0 0 0 0 0
7 Drinking water facility No. 0 0 0 0 0 0 0 0
8 Fencing for protection from wild animals
rmt. 0 0 0 0 0 0 0 0
9 Grassland/Gauchar Development
Ha. 0 0 0 0 0 0 0 0
219
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
10 Improvised and energy efficient smashan gruh (Cemetery )
No. 0 0 0 0 0 0 0 0
11 Panchayat Well Repair & Pump Room
No. 0 0 0 0 0 0 0 0
12 Rain water harvesting system
No. 0 0 0 0 0 0 0 0
13 Recharge / Repair of open wells
No. 0 0 0 0 0 0 0 0
14 Repair / development of artificial water bodies
No. 0 0 0 0 0 0 0 0
15 Revival of natural water bodies with recharge activities
No. 0 0 0 0 0 0 0 0
16 Sanitation facilities/Sewerage line
rmt 0 0 0 0 0 0 0 0
17 Use solar power for productive activities
No. 0 0 0 0 0 0 0 0
220
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
18 Wind energy development
No. 0 0 0 0 0 0 0 0
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
19 Cause Way Repairing 0 0 0 0 0 0 0 0
20 Pond Waist Wair 0 0 0 0 0 0 0 0
21 Community Sitting Stand
0 0 0 0 0 0 0 0
22 Pond Repairing 0 0 0 0 0 0 0 0
23 Washing Ghat 0 0 0 0 0 0 0 0
24 Checkwall Repairing 0 0 0 0 0 0 0 0
25 Culvert/Culvert Repairing
0 0 0 0 0 0 0 0
26 Community hall repair 0 0 0 0 0 0 0 0
27 Others 0 0 0 0 0 0 0 0
28 Books for School Library
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Land Development 0 0 0 0 0 0 0 0
221
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
1 Farm Bunding rmt. 0 0 0 0 0 0 0 0
2 Afforestation Ha. 0 0 0 0 0 20 8.8 Forest Depa.
3 Agriculture Demo No. 0 0 0 0 0 0 0 0
4 Agro Forestry Ha. 0 0 0 0 0 0 0 0
5 Horticulture Ha. 0 0 0 0 0 0 0 0
6 Land leveling Ha. 0 0 0 0 0 0 0 0
7 Pasture development Ha. 0 0 0 0 0 0 0 0
8 OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Soil & Moisture Conservation
0 0 0 0 0 0 0 0
1
Check wall No. 0 0 0 0 0 0 0 0
2
Earthen bund No. 0 0 0 0 0 0 0 0
3
Protection Wall No. 0 0 0 0 0 0 0 0
222
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
4
Waste weir No. 0 0 0 0 0 0 0 0
5
Bench Terracing cumec
0 0 0 0 0 0 0 0
6
Bori bandh No. 0 0 0 0 0 0 0 0
7
Brushwood Checks No. 0 0 0 0 0 0 0 0
8
Countour Bunding rmt. 0 0 0 0 0 0 0 0
9
Countour Trenches rmt. 0 0 0 0 0 0 0 0
10
Earthern Dam No. 0 0 0 0 0 0 0 0
11
Field Outlet No. 0 0 0 0 0 0 0 0
12
Gabion structure No. 0 0 0 0 0 0 0 0
13
Graded Bunding rmt. 0 0 0 0 0 0 0 0
14
Gully plug No. 0 0 0 0 0 0 0 0
223
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
15
Loose boulder Checks No. 0 0 0 0 0 0 0 0
16
Nala Plug No. 0 0 0 0 0 0 0 0
17
Stone bunding rmt. 0 0 0 0 0 0 0 0
18
Straggred Contour trenching(Terrace Talavadi)
0 0 0 0 0 0 0 0
19
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
20
Pond 5 25 0 0 0 0 0 0
21
Cement Nala Plug (Small Check Wall)
0 0 0 0 0 0 0 0
22 Grassland/Gauchar Development
0 0 0 0 0 0 0 0
23 Others 0 0 0 0 0 0 0 0
224
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
0 0 0 0 0 0 0 0
S.No
Water Harvesting Structure
0 0 0 0 0 0 0 0
1 Cause way cum Chek dam
No. 0 0 0 0 0 0 0 0
2 Check dam No. 0 0 0 0 0 0 0 0
3 Village/Community Pond
No. 0 0 0 0 0 0 0 0
4 Farm Pond No. 0 0 0 0 0 40 9.6 MGNREGS
5 Percolation Tank No. 0 0 0 0 0 0 0 0
6 Pond Inlet No. 0 0 0 0 0 0 0 0
7 Pond Outlet No. 0 0 0 0 0 0 0 0
8
OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
9
Cement Nala Plug (Small Check Wall)
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
225
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
12
S.No
Existing/Old Water Harvesting Structure Maintance (Renovation & Repair)
0 0 0 0 0 0 0 0
1 Deepening/Desiltation Of Pond
No. 0 0 0 0 0 0 0 0
2 Deepening Of Percolation Tank
No. 0 0 0 0 0 0 0 0
3 De-siltation of Checkdam
No. 0 0 0 0 0 0 0 0
4 Repairing of Checkdam No. 0 0 0 0 0 0 0 0
5 OTHERS (Specifiy activities )
No. 0 0 0 0 0 0 0 0
Renovation of Checkdam
0 0 0 0 0 0 0 0
De-siltation of Checkwall
0 0 0 0 0 0 0 0
226
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Repairing of Checkwall 0 0 0 0 0 0 0 0
Renovation of Checkwall
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
S.No
Ground Water Recharging Structures
0 0 0 0 0 0 0 0
1
Dugwell Recharge structure
No. 0 0 0 0 0 0 0 0
2 Farm Recharge Filter No. 0 0 0 0 0 0 0 0
3
Holiya in farm/Field No. 0 0 0 0 0 0 0 0
4
Pond Recharge structure
No. 0 0 0 0 0 0 0 0
5
OTHERS (Specifiy activities )
0 0 0 0 0 0 0 0
227
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
6
Well Recharge 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
LH & ME & Production System
0 0 0 0 0 0 0 0
1 AGRICULTURE ACTIVITIES
0 0 0 0 0 0 0 0
Agro Center 0 0 0 0 0 0 0 0
Agricultural Implements
0 0 0 0 0 0 0 0
Agro- Forestry 0 0 0 0 0 0 0 0
Crop Demonstration Plot
5 1.05 0 0 0 0 0 0
Fishery Development 0 0 0 0 0 0 0 0
Floriculture Development
0 0 0 0 0 0 0 0
Fodder Bank Development
0 0 0 0 0 0 0 0
228
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Green House 0 0 0 0 0 0 0 0
Horticulture Plantation 0 0 0 0 0 0 0 0
Kitchen Garden 15 4.1625 0 0 0 0 0 0
Nursery raising 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
INPUT SUPPORT 0 0 0 0 0 0 0 0
Promoting Micro-Irrigation Systems like drip and Sprinkler Irrigation
0 0 0 0 0 0 0 0
Sprinkler Demo. 20 0 0 0 0 0 0 0
Vegetable Nursery Raising with drip irrigation
0 0 0 0 0 0 0 0
Vermi compost 0 0 0 0 0 0 0 0
2 AGRO PROCESSING ACTIVITIES
0 0 0 0 0 0 0 0
Dal Making Unit 0 0 0 0 0 0 0 0
229
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Flour & Dal/Rice Processing unit
0 0 0 0 0 0 0 0
Garam Masala 0 0 0 0 0 0 0 0
Grading and packaging of agricultural produces,
0 0 0 0 0 0 0 0
Jam-jelly making 0 0 0 0 0 0 0 0
Microenterprises based on Minor Forest Produce (MFP)
0 0 0 0 0 0 0 0
Oil extraction mill 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Package Food Products 0 0 0 0 0 0 0 0
Pulp making 0 0 0 0 0 0 0 0
Rice mill 0 0 0 0 0 0 0 0
Value added products from milk
0 0 0 0 0 0 0 0
3 Animal Husbandry 0 0 0 0 0 0 0 0
230
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Cattle Feed and Nutrition Store
0 0 0 0 0 0 0 0
Animal Health camps 0 0 0 0 0 0 0 0
Animal Travis (Pinjaru) 0 0 0 0 0 0 0 0
Apiculture (Bee keeping)
0 0 0 0 0 0 0 0
Artificial insemination 0 0 0 0 0 0 0 0
Back-yard poultry 0 0 0 0 0 0 0 0
Dairy cooperative promotion,
0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Pasture development 0 0 0 0 0 0 0 0
Poultry Farming to individuals
0 0 0 0 0 0 0 0
Sericulture 0 0 0 0 0 0 0 0
Small ruminants 0 0 0 0 0 0 0 0
Veterinary Aid for livestock
0 0 0 0 0 0 0 0
231
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Cattle Shed 0 0 0 0 0 0 0 0
4 Establishing linkages 0 0 0 0 0 0 0 0
Credit linkages 0 0 0 0 0 0 0 0
Linkages with Future Markets,
0 0 0 0 0 0 0 0
Market linkages, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Raw material supply channel,
0 0 0 0 0 0 0 0
5 Local traditional handicraft
0 0 0 0 0 0 0 0
Bamboo based products,
0 0 0 0 0 0 0 0
Kutchi Bandhini, 0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0
Pottery 0 0 0 0 0 0 0 0
6 Minor Activities 0 0 0 0 0 0 0 0
Embroidery Unit 0 0 0 0 0 0 0 0
Handicraft Unit 0 0 0 0 0 0 0 0
232
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
OTHERS 0 0 0 0 0 0 0 0
Provision Store 0 0 0 0 0 0 0 0
stiching machine 0 0 0 0 0 0 0 0
Up Gradation of centering materials
0 0 0 0 0 0 0 0
Vegetable shop 0 0 0 0 0 0 0 0
7 Non-conventional Energy Sources
0 0 0 0 0 0 0 0
Bio gas plant, 0 0 0 0 0 0 0 0
Bio-fuel plantation, 0 0 0 0 0 0 0 0
energy conservation measures,
0 0 0 0 0 0 0 0
OTHERS 0 0 0 0 0 0 0 0 Solar energy
promotion,
0 0 0 0 0 0 0 0
Wind energy production,
0 0 0 0 0 0 0 0
Total 45 30.2125 0 60 18.4
CB, Monitoring and 30.00
233
Sr.No
Activity Unit Physical Target
Unit Cost (In Lakhs) IWMP
Storage Volumes
(Cubic Meter)
Command Area/
Irrigation Potential
(Ha.)
Person days/Man
days Planned
Convergence
Unit Amount (In Lakhs)
Name of Schemes
Evaluation Admin 29.70
Consolidation 40.40
Total 100.10
Grand Total 130.31 0.00
234
Annexure-6 Strategic Action Plan of GGRC Blocks Total Drip Irrigation System (DIS) Sprinkler Irrigation System (SIS)
Total Number (Farmers)
Area (Ha.)
Estimated Total Cost (Rs. in lakh)
Estimated Assistance (Rs. in lakh)
Total Number (Farmers)
Area (Ha.)
Estimated Total Cost (Rs. in lakh)
Estimated Assistance (Rs. in lakh)
Total Number (Farmers)
Area (Ha.)
Estimated Total Cost (Rs. in lakh)
Estimated Assistance (Rs. in lakh)
2016-17
Dahod 859.6 1375.4 1100.3 616.2 515.8 825.2 990.3 554.6 343.9 550.2 110.0 61.6
D. baria 209.9 335.8 268.6 150.4 125.9 201.5 241.8 135.4 83.9 134.3 26.9 15.0
Dhanpur 387.1 619.4 495.6 277.5 232.3 371.7 446.0 249.8 154.9 247.8 49.6 27.8
Fatepura 582.1 931.3 745.0 417.2 349.2 558.8 670.5 375.5 232.8 372.5 74.5 41.7
Garbada 592.5 947.9 758.3 424.7 355.5 568.8 682.5 382.2 237.0 379.2 75.8 42.5
Limkheda 676.1 1081.7 865.4 484.6 405.7 649.0 778.9 436.2 270.4 432.7 86.5 48.5
Sanjeli 49.5 79.1 63.3 35.5 29.7 47.5 57.0 31.9 19.8 31.7 6.3 3.5
Zalod 1172.2 1875.5 1500.4 840.2 703.3 1125.3 1350.4 756.2 468.9 750.2 150.0 84.0
Total (2016-17)
4528.9 7246.3 5797.0 3246.3 2717.4 4347.8 5217.3 2921.7 1811.6 2898.5 579.7 324.6
2017-18
Dahod 644.7 1031.6 825.2 462.1 386.8 618.9 742.7 415.9 257.9 412.6 82.5 46.2
D.baria 157.4 251.8 201.5 112.8 94.4 151.1 181.3 101.5 63.0 100.7 20.1 11.3
Dhanpur 290.4 464.6 371.7 208.1 174.2 278.7 334.5 187.3 116.1 185.8 37.2 20.8
Fatepura 436.5 698.5 558.8 312.9 261.9 419.1 502.9 281.6 174.6 279.4 55.9 31.3
Garbada 444.3 710.9 568.8 318.5 266.6 426.6 511.9 286.7 177.7 284.4 56.9 31.9
Limkheda 507.1 811.3 649.0 363.5 304.2 486.8 584.1 327.1 202.8 324.5 64.9 36.3
Sanjeli 37.1 59.4 47.5 26.6 22.3 35.6 42.7 23.9 14.8 23.7 4.7 2.7
Zalod 879.2 1406.7 1125.3 630.2 527.5 844.0 1012.8 567.2 351.7 562.7 112.5 63.0
Total (2017-18)
3396.7 5434.7 4347.8 2434.7 2038.0 3260.8 3913.0 2191.3 1358.7 2173.9 434.8 243.5
2018-19
235
Dahod 644.7 1031.6 825.2 462.1 386.8 618.9 742.7 415.9 257.9 412.6 82.5 46.2
D. baria 157.4 251.8 201.5 112.8 94.4 151.1 181.3 101.5 63.0 100.7 20.1 11.3
Dhanpur 290.4 464.6 371.7 208.1 174.2 278.7 334.5 187.3 116.1 185.8 37.2 20.8
Fatepura 436.5 698.5 558.8 312.9 261.9 419.1 502.9 281.6 174.6 279.4 55.9 31.3
Garbada 444.3 710.9 568.8 318.5 266.6 426.6 511.9 286.7 177.7 284.4 56.9 31.9
Limkheda 507.1 811.3 649.0 363.5 304.2 486.8 584.1 327.1 202.8 324.5 64.9 36.3
Sanjeli 37.1 59.4 47.5 26.6 22.3 35.6 42.7 23.9 14.8 23.7 4.7 2.7
Zalod 879.2 1406.7 1125.3 630.2 527.5 844.0 1012.8 567.2 351.7 562.7 112.5 63.0
Total (2018-19)
3396.7 5434.7 4347.8 2434.7 2038.0 3260.8 3913.0 2191.3 1358.7 2173.9 434.8 243.5
2019-20
Dahod 644.7 1031.6 825.2 462.1 386.8 618.9 742.7 415.9 257.9 412.6 82.5 46.2
D. baria 157.4 251.8 201.5 112.8 94.4 151.1 181.3 101.5 63.0 100.7 20.1 11.3
Dhanpur 290.4 464.6 371.7 208.1 174.2 278.7 334.5 187.3 116.1 185.8 37.2 20.8
Fatepura 436.5 698.5 558.8 312.9 261.9 419.1 502.9 281.6 174.6 279.4 55.9 31.3
Garbada 444.3 710.9 568.8 318.5 266.6 426.6 511.9 286.7 177.7 284.4 56.9 31.9
Limkheda 507.1 811.3 649.0 363.5 304.2 486.8 584.1 327.1 202.8 324.5 64.9 36.3
Sanjeli 37.1 59.4 47.5 26.6 22.3 35.6 42.7 23.9 14.8 23.7 4.7 2.7
Zalod 879.2 1406.7 1125.3 630.2 527.5 844.0 1012.8 567.2 351.7 562.7 112.5 63.0
Total(2019-20)
3396.7 5434.7 4347.8 2434.7 2038.0 3260.8 3913.0 2191.3 1358.7 2173.9 434.8 243.5
236
GGRC
Per drop more crop
Drip Irrigation System (DIS) Sprinkler Irrigation System (SIS)
Total Number (Farmers)
Area (Ha.) Estimated Assistance (Rs. in
lakh)
Total Number (Farmers)
Area (Ha.) Estimated Assistance (Rs. in
lakh)
Dahod 1676.3 2682.0 1802.3 1117.5 1788.0 200.3
Devgadh baria
409.2 654.8 440.0 272.8 436.5 48.9
Dhanpur 754.9 1207.9 811.7 503.3 805.3 90.2
Fatepura 1135.0 1816.0 1220.4 756.7 1210.7 135.6
Garbada 1155.3 1848.5 1242.2 770.2 1232.3 138.0
Limkheda 1318.4 2109.4 1417.5 878.9 1406.3 157.5
Zalod 2285.8 3657.3 2457.7 1523.9 2438.2 273.1
Sanjeli 96.5 154.3 103.7 64.3 102.9 11.5
Total 8831.398326 14130.23732 9495.51948 5887.598884 9420.158214 1055.05772
GRAM
MAIZE