CUMBEY & FAIR, INC
O’Brien Street Roadway Improvements
Cypress Street to Spruce Street
![Page 2: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/2.jpg)
iAGENDA
![Page 3: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/3.jpg)
AGENDA
PROJECT UNDERSTANDING
ROADWAY DESIGN
DRAINAGE & PERMITTING
MANAGEMENT PLAN
![Page 4: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/4.jpg)
PROJECTUNDERSTANDING
![Page 5: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/5.jpg)
Project Understanding
CURRENT TRAFFIC OVERVIEW
• Queues from the dual northbound left‐turn lanes frequently extended back to the south end of O’Brien St.
Afternoon Peak
Dual Northbound left-turn
lanes fail
Morning Traffic from Veterans
Expressway and Courtney
Campbell Causeway utilizes
Spruce Street Exit
![Page 6: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/6.jpg)
Project Understanding
FUTURE TRAFFIC OVERVIEW
• SR 60 @ I-275 Ultimate configuration with express lanes
• The conceptual graphic was created for planning and discussion proposes as of 12/19/13
• The improvements will not significantly improve the traffic on O ‘Brien St.
Afternoon Peak
Reo St. to Kennedy
Blvd. to SR 60
![Page 7: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/7.jpg)
PUBLIC INVOLVEMENT
O’ B
RIE
N S
T
SPRUCE ST
Hillsborough County Aviation
Authority (HCAA)
South Terminal Roadway
Design/Build
![Page 8: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/8.jpg)
Project Understanding
Pedestrian & Bike Accommodations
• Multi-Use Path Terminal
• Connection to Rail Station Area at I-275 along Cypress Street
City of Tampa
Future Bike Lanes &
Sidewalks Project
Westshore Alliance
Future Sidewalks
Project
HCAA Airport
Sidewalks & Multi-
Use Path Project
FDOT
Sidewalks & Multi-
Use Path Project
RAIL STATION
![Page 9: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/9.jpg)
ROADWAYDESIGN
![Page 10: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/10.jpg)
ROADWAY DESIGNPROJECT LOCATION MAP & EXISTING TYPICAL SECTION
O’ B
RIE
N S
T
SPRUCE ST
LAUREL ST
CYPRESS ST
PHASE ONE
PHASE TWO
![Page 11: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/11.jpg)
ROADWAY DESIGN
Existing Typical Sections
• Phase One Laurel St. to Spruce St.
– 3-lane rural roadway
– two-way left-turn center lane
– Right-of-way width varies (85 ft min)
– Existing sidewalk on west
• Phase Two Cypress St. to Laurel St.
– 2-lane rural roadway
– Right-of-way width varies (70 ft min)
– No sidewalk
![Page 12: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/12.jpg)
ROADWAY DESIGN
Typical Sections
• Phase One Laurel St. to Spruce St.
– 4-lane urban roadway
– two-way left-turn center lane
– 6 ft. sidewalk on west
• Phase Two Cypress St. to Laurel St.
– 4-lane urban roadway
– two-way left-turn center lane
– 6 ft. sidewalk both sides
![Page 13: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/13.jpg)
DRAINAGE &PERMITTING
![Page 14: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/14.jpg)
Stormwater Management Plan
• Eliminate South Basin Pond– Maintain existing discharge rate to Lemon St. Canal
– Add new outfall to Spruce Street Canal
– Hydraulic modeling works!
– No regrading of existing pond
• No rework of pond liner
• No regrading of existing 10 ft wide maintenance berm
– $600K Pond Construction & ROW Savings!!!
– Added value for the City
• Excess treatment capacity
• Eliminate 8 Parcel Takes
• Minimize Reconstruction, Maximize Resurfacing in South Basin– Lower existing pond control to match adjacent pond
– Discharge low areas to Outfall Ditch untreated
– Minimize gravity walls
– Reduced storm drain construction
![Page 15: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/15.jpg)
Permitting
• Southwest Florida Water Management District (SWFWMD)
– Met with Richard Alt, Jeff Glass & Estella Gray on July 1st
– Agreeable to Spruce Street Canal Outfall
– Agreeable to discharging low inlets directly to outfall ditch
– Attenuation required for existing outfall to Lemon Street Canal
• FDOT Drainage/Driveway Connections
– Met with Daniel Lauricello, District Drainage Engineer, on July 1st
– Agreeable to Spruce Street Canal Outfall
• Army Corp of Engineers Section 404 Permit
• Hillsborough County EPC Permit
• FAA Regulations for Pond Design
• City of Tampa Stormwater Technical Standards Manual for Public Development
![Page 16: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/16.jpg)
MANAGEMENT PLAN
![Page 17: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/17.jpg)
Management Plan
Project Objectives
• Keep projects independent (flexibility for construction funding)
– Phase One Laurel Street to Spruce Street
– Phase Two Cypress Street to Laurel Street
• Minimize Right-of-Way Impacts
• Simplify drainage/permitting
• Coordinate with adjacent developers, FDOT, utility companies,HCAA, Westshore Alliance & other stakeholders
![Page 18: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/18.jpg)
Management Plan
Notice to Proceed
Phase II (Plans & ROW Maps) Submittals
268 Date (Documents to Right-of-Way)
North Segment (Plans & Maps) Submittals
South Segment (Plans & Maps) Submittals
15% Line and Grade Submittal
Design Survey
Obtain SWFWMD/USACOE Permit Approval
Submit SWFWMD/USACOE Permit Application
SWFWMD/USACOE Joint Pre-App Meeting
45% Drainage Submittal
Permitting
Plan Preparation
20162015 2017
Project Schedule
![Page 19: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/19.jpg)
Management Plan
• Public Involvement (Coordinate with all of the project’s stakeholders)
Public Workshop April 2016
City of Tampa Commission Meeting May 2016
Working with HCAA EOR on the reconstruction of the Airport Service Road
Working with FDOT on the SR 60 @ I-275 Interchange
• Drainage/Permitting (Min. ROW Impacts & Meet Permitting Requirements)
Submit Permit Application for SWFWMD/USACOE Permit March 2016
Eliminate “New Pond” reconfigure existing pond
Lower Tail water elevation with new outfall
• Roadway (Min. ROW & Utility Impacts)
ROW requirements For City Review April 2016
Eliminate reconstruction & walls utilize overbuild and widening
Livable Communities (Westshore Alliance & HCAA #1 Concern Peds & Bikes)
![Page 20: Cypress Street to Spruce Street - Westshore Alliance Street... · Cypress Street to Spruce Street ... –Add new outfall to Spruce Street Canal ... 2015 2016 2017 Project Schedule](https://reader034.vdocuments.us/reader034/viewer/2022042402/5f132da38de9e63eee15de74/html5/thumbnails/20.jpg)
Questions?Cumbey & Fair, Inc. is certified as both a Small Disadvantaged Business (SBE) and a Small Business Administration 8(a) Business by the Federal