James Wright, PE Résumé 1 EDUCATION BS, Electrical Engineering, New Mexico State University, 1980 REGISTRATIONS / CERTIFICATIONS Registered Professional Engineer: TX, 62404 PROFESSIONAL AFFILIATIONS Institute of Electrical and Electronic Engineers (IEEE), member since 1979 Instrumentation, Systems and Automation Society (ISA), member since 1981 National Fire Protection Association (NFPA), member since 2008 Western Energy Institute, Operations Conference Program Development Team Chairman 2005, 2006; Member 2003, 2004 LANGUAGES English (fluent) YEARS OF EXPERIENCE 35 EXPERIENCE SUMMARY Mr. Wright is an experienced engineering professional with over 30 years’ of professional engineering experience executing projects and providing design, construction and operational support of oil, natural gas and electrical transmission facilities. Mr. Wright has functioned in numerous engineering positions from entry-level electrical engineer to senior project manager and engineering team leader. Mr. Wright has extensive expertise in the design and operation of natural gas transmission pipelines and large horsepower natural gas compression facilities, low and medium voltage electrical systems, pipeline SCADA systems, process controls, PLC control systems and HMI application software development. Additionally, Mr. Wright has developed grounding systems to minimize impacts on cathodic protection systems while significantly improving lightning protection. He has also lead the implementation of pipeline integrity management programs, electrical safety and maintenance programs and conducted numerous process hazard and root cause analyses. While functioning as the responsible project manager, Mr. Wright has successfully completed capital expansion and maintenance projects as large as $42 M. Functioning as a design lead, he has developed projects from concept to completion for projects as large as $65 M. Recently Mr. Wright has contributed to the improvement of the natural gas transmission infrastructure in the Republic of Georgia by assisting the Georgian Oil and Gas Corporation through a $152 M USAID assistance program, by providing pipeline construction project management and contract oversight. During his 30-year tenure with El Paso Corporation, Mr. Wright participated in the design, installation and commissioning of over 450,000-hp of new compressors on the Colorado Interstate Gas and El Paso Natural Gas pipeline systems, and in the development of operations and maintenance plans for over 1.2 million miles of pipeline, compressor stations and processing plants to ensure safe and reliable natural gas transmission across the western United States. A seasoned manager, Mr. Wright has excellent oral and written communication skills and works closely with all project stakeholders to achieve their goals and objectives while maximizing reliability, safety and cost effectiveness. His international experience includes projects in Mexico, Peru and the Republic of Georgia. Mr. Wright is familiar with the following relevant safety, design and operational codes and standards: OSHA, DOT Part 192, IEEE, NEC, NFPA 70E, relevant API and ISA standards, ASME B31.3, B31.8, as well as PHMSA pipeline integrity and control room management requirements.

Upload: james-wright

Post on 07-Jan-2017

255 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CV - Wright, James R

   

James Wright, PE

Résumé 1

EDUCATION

BS, Electrical Engineering, New Mexico State University, 1980

REGISTRATIONS / CERTIFICATIONS

Registered Professional Engineer: TX, 62404

PROFESSIONAL AFFILIATIONS

Institute of Electrical and Electronic Engineers (IEEE), member since 1979

Instrumentation, Systems and Automation Society (ISA), member since 1981

National Fire Protection Association (NFPA), member since 2008

Western Energy Institute, Operations Conference Program Development Team Chairman 2005, 2006; Member 2003, 2004

LANGUAGES

English (fluent)

YEARS OF EXPERIENCE

35

EXPERIENCE SUMMARY

Mr. Wright is an experienced engineering professional with over 30 years’ of professional engineering experience executing projects and providing design, construction and operational support of oil, natural gas and electrical transmission facilities. Mr. Wright has functioned in numerous engineering positions from entry-level electrical engineer to senior project manager and engineering team leader. Mr. Wright has extensive expertise in the design and operation of natural gas transmission pipelines and large horsepower natural gas compression facilities, low and medium voltage electrical systems, pipeline SCADA systems, process controls, PLC control systems and HMI application software development. Additionally, Mr. Wright has developed grounding systems to minimize impacts on cathodic protection systems while significantly improving lightning protection. He has also lead the implementation of pipeline integrity management programs, electrical safety and maintenance programs and conducted numerous process hazard and root cause analyses.

While functioning as the responsible project manager, Mr. Wright has successfully completed capital expansion and maintenance projects as large as $42 M. Functioning as a design lead, he has developed projects from concept to completion for projects as large as $65 M.

Recently Mr. Wright has contributed to the improvement of the natural gas transmission infrastructure in the Republic of Georgia by assisting the Georgian Oil and Gas Corporation through a $152 M USAID assistance program, by providing pipeline construction project management and contract oversight.

During his 30-year tenure with El Paso Corporation, Mr. Wright participated in the design, installation and commissioning of over 450,000-hp of new compressors on the Colorado Interstate Gas and El Paso Natural Gas pipeline systems, and in the development of operations and maintenance plans for over 1.2 million miles of pipeline, compressor stations and processing plants to ensure safe and reliable natural gas transmission across the western United States.

A seasoned manager, Mr. Wright has excellent oral and written communication skills and works closely with all project stakeholders to achieve their goals and objectives while maximizing reliability, safety and cost effectiveness. His international experience includes projects in Mexico, Peru and the Republic of Georgia.

Mr. Wright is familiar with the following relevant safety, design and operational codes and standards: OSHA, DOT Part 192, IEEE, NEC, NFPA 70E, relevant API and ISA standards, ASME B31.3, B31.8, as well as PHMSA pipeline integrity and control room management requirements.

Page 2: CV - Wright, James R

Résumé James Wright, PE

2

RELEVANT EXPERIENCE

Tetra Tech, Georgia Power and Gas Infrastructure Oversight Program (PGIOP), Georgia, 2013 to 2015 – Senior Project Manager; Mr. Wright supported the USAID funded $152 M reconditioning and expansion of the Republic of Georgia’s east – west pipeline system. Mr. Wright’s functions included management of a team of local engineers and expat support staff, design and construction oversight as well as providing extensive technical advisory services to support the development of the internal resources of the Georgian Oil and Gas Corporation (GOGC). Several areas in which Mr. Wright directly supported GOGC’s capacity development were in improving construction practices and specifications, implementing pipeline maintenance techniques involving coatings, cathodic protection, valve maintenance, in-line inspections and equipment procurement to improve GOGC’s operations and maintenance program. Additionally he developed and implemented a pipeline integrity program utilized nationally by GOGC and began development of improved gas loss metering methodology.

Mjollnir Holdings, LLC, Colorado Springs, CO, 2010 to 2013 – Principal; Mr. Wright provided consulting engineering services in the following areas: compressor station design, electrical design, automation system design, SCADA system design and security implementation, program management and process safety.

Notable assignments include:

• Engineering support for 100 km natural gas pipeline uprate project that included a new 4 km lateral and interface with a 250 MW power plant for an international client in Mexico. The project included BOP electrical interface design, fuel gas metering, process simulation and final design review of IFC design package. Provided a review and evaluation of the client’s new pipeline integrity program, including a review of inline inspection reports and providing pipeline reconditioning recommendations;

• Electrical safety design review for upstream oil and gas processing facilities. Included a complete review of existing electrical designs for facilities. This included a comprehensive review and recommendations to optimize electrical grounding systems, as well as review of power distribution systems, automation systems and SCADA interfaces for well head gas lift and processing facilities;

• Engineering review of intellectual property and documentation for a client merger and acquisition project. El Paso Corporation, Colorado Springs, CO, 2001 to 2010 – Consultant Engineer; Mr. Wright functioned as technical supervision of up to seven automation and electrical engineers. Mr. Wright also supported the maintenance and capital budgets for assets in the western US, while also providing operational technical support to Operations, Gas Control, Measurement, Reliability and SCADA departments. This position required individual project assignments as well as providing leadership for other team members and the overall coordination of all automation and electrical engineering activities.

Notable assignments and achievements include:

• Field to Central SCADA interface design and support; • SCADA Alarm Management Team - Field Operations SME; • Automation Optimization Team Member and GE Frame Turbine Control Software Development Team

Lead; • Large Electric Driven Compressor Electrical Maintenance Program Development Lead and SME; • Arc Flash Safety Program SME; • Automation and electrical design for 14 new compressor stations and 2 fuel stabilization projects ranging

up to $42 M in cost and 45 k HP; • Project manager for pipeline wide remote SCADA system conversion and upgrade; • Gatekeeper for cyber security standards for regional SCADA and compressor station control systems; • Automation and electrical designer for three new compressor stations constructed in northern Mexico.

Page 3: CV - Wright, James R

Résumé James Wright, PE

3

El Paso Corporation, El Paso, TX, 1988 to 2001 – Consultant Engineer (1983 to 2001); Mr. Wright supported the value added capital budget of the El Paso Natural Gas pipeline while providing technical support to pipeline operations for maintenance and reliability issues related to electrical and automation systems. His position also required individual project assignments as well as leadership and guidance of three A&E professionals.

Notable assignments include:

• Automation and Electrical Design Group Lead; • Manual of Engineering Standards Electrical Committee Member and Chair; • EPNG Y2K Program Manager; • Automation and Electrical Design Lead for 12 new compressor stations projects; • Automation and Electrical Design Lead for 50 mmcfd LNG production plant costing $12 m; • Automation and Electrical Design Lead for two design and build compressor station projects for client in

northern Mexico costing $ 28 m with 22 k HP; • Owners Engineering/Inspection/Commissioning Representative for 173 MW Power Plant, Gas Processing

Plant, pipeline and high voltage transmission line in Eastern Peru for Maple Gas. Principal Engineer (1988 to 1993); Mr. Wright functioned as automation and electrical design engineer for critical expansion projects for El Paso Natural Gas pipeline. Mr. Wright also served as a project manager for numerous capital budget projects. Project management functions included: Capex budget development, scope development, detailed design, equipment and software specification, software design and programming, construction support and commissioning.

Notable assignments include:

• Automation and Electrical Design Lead for four compressor station horsepower replacement projects and six new compressor stations;

• Controls and Electrical Design Lead for a 600 MMCFD Cryogenic Gas Processing Plant, costing $42 m; • Manual of Engineering Standards Electrical Committee Member.

Senior Engineer, (1984 to 1988); Mr. Wright functioned as a project engineer/manager for all assigned capital budget projects for El Paso Natural Gas Pipeline. Duties included: Capex budget development, project scope development, design development, equipment specification, construction coordination and project commissioning.

Notable assignments include:

• Manual of Engineering Standards Electrical Committee Member; • Compressor Station Automation Program Project Manager for 23 compressors stations, total program

expenditures of $ 48 m over four years. Engineer, (1980 to 1984); Mr. Wright functioned as a project engineer/manager for all assigned capital budget projects for the Southern Division of El Paso Natural Gas. His project management functions included: Capex budget estimation, scope development, design development, equipment procurement, construction coordination and project commissioning.

Notable assignments include:

• Conceptual design of Compressor Station Automation Systems; • Implementation of Compressor Station Automation Pilot Projects; • Development of Compressor Station Automation Program; • Completion of approximately 15 to 25 medium sized Capital Expansion projects / year.

Page 4: CV - Wright, James R

Résumé James Wright, PE

4

Department of The Army, Facilities Engineering, White Sands Missile Range, NM, 1980 – Energy Engineer responsible for development and implementation of various energy models to predict and improve energy utilization for White Sands Missile Range facilities.