customs and border protection report on border walls crossing washes and streams
TRANSCRIPT
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
1/899
SBI-TI
PF 225 and VF 300
Border Fence Projects
Technical IPT
Final Report
California, Arizona,
New Mexico and Texas
Submitted to:
SBI
And
DEPARTMENT OF ARMY
Fort Worth District Corps of Engineers
Fort Worth, Texas
May 2009Project: IPT
Michael Baker Jr.,Phoenix, Arizona
Not for Constructio
Prepared by
001027
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
2/899
i
Executive Summary
On the afternoon of July 12, 2008, a severe monsoon resulted in significant flooding inthe area around Lukeville, Arizona. Shortly after the storm, the Associated Press
published an article titled Border Fence Design Gets a Second Look. That articledescribed the flooding in Lukeville and attributed it to the pedestrian fence (PF) recentlybuilt in the area (specifically the PF 225 segment D-2). On August 8, the National ParkService (NPS) issued a memorandum that also attributed the flooding of July 12 to thepedestrian fence, and, in particular, to poor drainage designs.
The U.S. Army Corps of Engineers (USACE), with the collaboration of Michael BakerCorp (Baker), produced an After Action Review (AAR) report that described the floodevent, why it happened, and recommended solutions (see Appendix A for a copy of theAAR). On October 22, 2008, a drainage summit was held at the Border Patrol station inDouglas, Arizona, to discuss the AAR and develop a plan for addressing the drainageissues as well as the resulting erosion and damage to the fencing. The summit alsodeveloped a preliminary approach to locating and correcting all other areas in which thePF 225 or VF (vehicle fence) 300 fence has the potential of creating similar incidents orhaving a high risk of flooding.
As a result of the drainage summit, an Integrated Project Team (IPT) was created toprepare a plan to identify all the areas subject to flooding because of PF 225 fencing andrecommend solutions for mitigating. (Appendix A also includes a copy of the IPTscharter.). This plan does not, and was never intended to, cover the legacy fences.
The IPT found that one of the factors contributing to the flooding was the collection ofdebris at fence sections built within wash areas. The debris builds-up on the fence
obstructed storm water from flowing freely across the fence, causing the water to rise anddivert from its natural flow pattern. In addition to the flooding, the debris build-up, whichsometimes reached a height of 6 feet, caused a water-fall effect on the other side of thefence resulting in major scour and erosion problems, and increasing the likelihood thatthe fence could be damaged or collapse.
The IPT further found that VF 300 fences resulted in no major drainage concerns becauseof obstructions. However, it expressed concern about the scour, erosion, stability, andlongevity of the vehicle fence, and whether it could withstand high-water pressurewithout being washed out. As a result, the IPT concluded that VF 300 also requiredmitigation (Legacy vehicle fences are not included in the analysis and mitigation)
The IPT collected data on all the washes where the PF 225 or VF 300 fence had beenconstructed (Legacy fences not included), and grouped them into three risk categories(high, medium, and low) using hydrologic and hydraulic criteria, such as flow rates,velocities, channel slopes, and water depth. (Appendices B and C present the list of the
001028
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
3/899
washes and their relative data; while Appendix D shows the locations of the PF 225 andVF 300 washes) The risk categories are defined as follows:
Category 1, Low Risk: There is little or no risk of debris collecting at the fence, orcausing any flooding, scour or erosion problems, or danger to the fence stability.
No action by IPT is anticipated.
Category 2, Medium Risk: There may be a risk of fence failing because offlooding hazards or debris collecting at the fence and causing floods, or scour orerosion problems. Further analysis is required to decide whether a retrofit to thefence is needed or if regular maintenance will suffice.
Category 3, High Risk: There is a high risk of failure because of water pressure,flooding, and scour or erosion problems. Removing or retrofitting the fence andinstalling scour protection are required. This category also includes all of the VF300 crossings located in a FEMA Zone A floodplain.
The IPT team validated the data, visited all the Category 2 and 3 washes (Appendix Eshows photos and site visit forms), and identified the VF washes that needed to bepermanently anchored to the ground, the PF washes that required fence retrofits, thewashes that only required scour protection, and the washes in which regular debrisremoval would suffice. These washes are as follows:
PF 225 crossings needing retrofit:
Segment A2K Washes J1&2 (47+09), J5 (70+50) Segment A2L Washes J6 (23+48), J9 (59+24) Segment D2 Washes E16, W13, E8, W17 Segment D5A Wash 2 (Mariposa) Segment D5B Washes 10 (Las Cuevitas), 44 Segment E2A Wash 5 (Montezuma) Segment E2B Washes M5 (BC Wash), M8 (Gringo wash), M14 (wash
33), M16 (first horseshoe), M21 (second horseshoe) Segment E3 Wash M1 (Christiansen) Wash east of Nogales Port of Entry (POE)
PF 225 crossings needing low water crossings (LWCs) and Rip Rap:
Segment A2A Wash 2 Segment A2D Wash 52+13, 60+57 Segment A2F Wash 5+44 Segment A2J Wash 51+75 Segment A2N Wash 3 Segment D2 Washes E19, E20, E31, E33, W1 Segment D5A Washes 1, 4 Segment D5B Washes 1, 28, 8, 9 (Barranca Honda), 26, 27
001029
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
4/899
Segment E2A Washes 7, 3, 6 Segment E3 Washes M3, M4, US2, US4, US5 Segment I1A Washes 3, 4 Segment L1 Washes 1, 4, 6
VF 300 crossings needing permanent anchoring system and scour protection(length of vehicle fence to be permanently anchored shown in brackets):
Segment CV2A Wash Y6 (180) Segment DV4B Washes 14 (150), A (240), 6 (270), 8 (70) Segment EV1A Washes 6 (100), 42 (200), 52 (50), 53 (100), 55
(50), 61 (70) Segment EV1B Wash F02 (200) Segment EV2B Wash 102 (240) Segment FV1B Washes C13 (Black draw - 450+200), C14 (hay
Hollow - 40+50+100), C6 (Silver Creek - 300+200). Segment HV3 Wash DA6 (50)
VF 300 crossings needing LWC and Rip Rap:
Segment BV1 Wash 100 (Pinto) Segment CV2 Washes 7, 16 Segment DV1 Washes 6, 12, 14, 17, 18, 19, 21, 22, 23 Segment DV3A Washes 1(San Simon Wash), 4 (Chukut Kuk) Segment DV4A Washes 1, 11 (LWC only), 17, 20, 35 (LWC only), 37,
41, 42 (LWC only), 43, 44, 45, 46 (LWC only), 5, 6 (LWC only), 9 (LWConly)
Segment DV4B Washes 17, 21, 9, 12 Segment DV4C Wash 52
Segment DV7 Washes 17, 35 Segment EV1A Washes 35, 38, 40, 45, 56, 58, 59, 60, 63, 66 Segment EV1B Wash F01 Segment FV1B Washes C17 (Cantina), C24, C4 (LWC only), C45
(LWC only), C50, C52 (LWC only), C10, C21, C5. Segment HV2 Washes 4, 8 Segment HV3 Washes DA1, DA4 Segment IV4 Wash 1 Segment JV3 Wash 1
All other crossings requiring future more frequent debris removal:
Segment A2C Washes 1+37, 16+03, 25+22, 6+95 Segment A2D Washes 36+35, 38+28, 39+02, 48+63 Segment A2F Wash 100 Segment A2g Washes 2, 8, 9 Segment A2I Washes 1+56, 16+29, 41+93, 44+41, 52+67, 7+67
001030
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
5/899
Segment A2J Washes E29, E30, E6, W2, W22, 3, 29, 31, 32, 40, 43,
43.5, 46, 55, 57, 58, 59, 20a, 25c, 471, 47b, 48a Segment D6 Washes 1, 3, 4 Segment E2A Washes 1, 2, 4
Segment E3 Wash M2B Segment DV1 Washes 7, 15 Segment DV2 Wash F06 Segment DV3A Washes 9, 12 Segment DV4A Washes 14, 15, 19, 29, 32, 33, 49 Segment FV1B Washes C20, C28 Segment HV2 Washes 6, 7, 9, 22 Segment HV4 Washes 3, 9 Segment IV2 Washes F02, F03, F04, F06 Segment JV2 Wash F01 Segment JV1A Wash 1
Segment JV1B Washes 10, 13, 16, 18.
The IPT also developed conceptual designs for pedestrian fence retrofits. These conceptsare provided in Figures F-1, F-2, and F-8 in Appendix F, with Figure F-8 showing therecommended retrofit. Appendix F also includes concepts for anchoring vehicle fences asalternative solutions to removing the fence (see Figures F-5, F-6, and F-7, with Figure F-7 showing the recommended solution).
Each of the recommended concepts needs to be further developed before it can be appliedto specific wash sites. For planning purposes, the IPT proposed the following rough orderof magnitude cost estimates for construction of the recommended solutions:
1. Retrofitting PF 225 fences: $9.5 million to $12.1 million2. Anchoring VF 300 fences: $1.8 million to 2.6 million
3. Building LWC and Riprap for PF 225: $1.2 million to $2.2 million
4. Building LWC and Riprap for VF 300: $2.2 million to $4.3 million.
001031
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
6/899
PageA
TABLE OF CONTENTS
Executive Summary ................................................................................................................... iSection 1. Introduction ..............................................................................................................1Section 2. Categorizing Washes ................................................................................................1Section 3. Site Visits ...................................................................................................................3Section 4. Considerations ..........................................................................................................5
PF 225 Proposed Solutions ......................................................................................................... 6Installation of Gates at Wash Crossings that can be Opened During Monsoon Season orPrior to Major Storms ............................................................................................................. 6Retrofit Existing Fence at Wash Crossings with Removable Bollards................................... 6
VF 300 Solutions ........................................................................................................................ 7Remove Existing Fence and Replace with Concrete Boulders or Tetra Pods ........................ 7Anchor Normandy Fences to Ground ..................................................................................... 7Remove Existing Fence and Replace with Widely Spaced Bollards ...................................... 8Remove Existing Fence Before Major Flood Events ............................................................. 8Rebuild Post and Rail Fences with Deeper Foundations ........................................................ 8
Section 5. Recommendations.....................................................................................................8PF 225 Recommendations for High-Risk Washes...................................................................... 8VF 300 Recommendations for High-Risk Washes ..................................................................... 9Recommendations for PF 225 Medium-Risk Wash Crossings ................................................. 10Recommendations for Other VF 300 Medium-Risk Wash Crossings ...................................... 11Prioritizing Criteria ................................................................................................................... 13
Section 6. ROM Cost Estimates ..............................................................................................14Retrofitting PF 225 Fences ....................................................................................................... 14Anchoring VF 300 Fences ........................................................................................................ 15Building Scour Protection for 32 PF 225 Crossings ................................................................. 15Building Scour Protection for Approximately 62 VF 300 Crossings ....................................... 15
Appendix A IPT Charter and After Action Review
Appendix B Wash Ranking Tables for PF 225
Appendix C Wash Ranking Tables for VF 300
Appendix D Summary
Appendix E Site Photos and Forms
Appendix F Concepts
Appendix G Rough Order of Magnitude Calculations
Appendix H Hec-Ras Models for Boulders in a Wash
001032
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
7/899
1
IPT Report
Project PF 225 AND VF 300Department of the Army
Fort Worth, Corps of Engineers
Forth Worth, Texas
MAY 2009
Section 1. Introduction
Pedestrian fence (PF) 225 D-2 near Lukeville, Arizona, was one of the first fencesegments constructed as part of the PF 225 Program. It was constructed using the design-build approach. Shortly after its completion, a large monsoon storm hit the area on July12, 2008, resulting in major flooding and damages along the border. This incident wasreported in an Associated Press article that indicated the barrier acted like a dam duringflash flood. In addition, the National Park Service (NPS), which manages the Organ
Pipe Memorial Park that is located adjacent to the D-2 segment, raised concerns to theU.S. Army Corps of Engineers (USACE) and U.S. Customs and Border Protection (CBP)that the fence caused the flooding. At CBPs request, USACE conducted a study todetermine whether the fence caused or contributed to the flooding. The results of thatstudy, including recommended solutions, were presented in an After Action Review(AAR) report produced by the USACE. (Appendix A presents a copy of this report.)
Shortly after the AAR was completed, a drainage summit was held at the Border Patrolstation in Douglas, Arizona on October 22, 2008. That summit discussed the AAR anddeveloped a plan for addressing the drainage issues as well as the resulting erosion anddamage to the fencing. It also created a preliminary approach to locate and correct anyother washes in which PF 225 or vehicle fence (VF) 300 was built with a likelihood ofpotentially creating similar issues.
The drainage summit further established an Integrated Project Team (IPT) to develop aplan for identifying all of the washes most likely be subject to flooding and severeerosion because of PF 225 and VF 300 fencing, and recommend solutions for mitigatingthose situations (Appendix A also shows the IPTs charter). This plan does not, and wasnever intended to, cover the situations caused by the legacy fences.
This report describes the steps and methods that the IPT used to identify and categorizethe drainage crossings, identifies potential solutions, and proposes rough order ofmagnitude (ROM) cost estimates to implement the solutions.
Section 2. Categorizing WashesThe first step in identifying the washes most susceptible to flooding and erosion was tocollect and analyze the hydrologic and hydraulic information for the washes in which PF225 and VF 300 fence segments crossed, and group them into the following threecategories:
001033
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
8/899
2
Category 1, Low Risk: There is little or no risk of debris collecting at the fence, orcausing any flooding, scour or erosion problems, or danger to the fence stability.No action is anticipated.
Category 2, Medium Risk: There may be a risk of the fence failing because of
flooding hazards, or because of debris collecting at the fence and causing floodsand scour or erosion problems. Further analysis is required to decide whether aretrofit to the fence is needed or if regular maintenance will suffice.
Category 3, High Risk: There is a high risk of failure because of water pressure,flooding, or scour and erosion problems. Removing or retrofitting the fence andinstalling scour protection are required. This category also includes all of the VF300 crossings located in a Federal Emergency Management Agency (FEMA)Zone A floodplain.
When available, the drainage designs and studies prepared for the PF 225 and VF 300projects were thoroughly reviewed for key data pertaining to the hydrology and
hydraulics of the washes. This review covered a 100-year storm event and focused on thefollowing factors:
Flow rate
Flow velocity
Water surface elevation
Flow direction
Channel slopes
Fence type (only for VF-300)
FEMA rating (or zone).
When this information was not available, the IPT conducted a separate hydraulic andhydrologic (H&H) analysis for the 100-year storm event.
In order to assign the drainage crossings to one of the three categories, the IPT used apreliminary set of desk-top criteria. The criteria were selected after analyzing multiplescenarios and consisted of the following factors:
Flow rate: Directly proportional to the risk of flooding (because water will backup) and its capacity to contain sediments and debris. Four thresholds wereselected: 100 cfs, 500 cfs, 1000 cfs, and 3000 cfs.
001034
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
9/899
3
Velocity: Directly proportional to scour and erosion and to the size of sedimentsand debris the flow may contain. Three thresholds were selected: 3 fps, 5 fps, and10 fps.
Flow depth: Directly proportional to the amount of debris and sediments the flow
can contain and to the damages that can be caused when flooding. Threethresholds were selected: 1 ft, 3 ft, and 5 ft.
Channel slope: Directly proportional to the turbulence the flow can have, whichleads to more erosion, scour, debris, and sediment transport. Three thresholdswere selected: 0.2 percent, 0.5 percent, and 1 percent.
The closer the factors for each wash were to the higher thresholds, the higher the categoryof the wash. Tables B-2 and C-6 (in Table 1) show how these factors are linked to thecategorization of the wash. All analysis used the 100-year storm event.
The desk-top analysis resulted in a preliminary grouping of the washes into one of thethree categories. Table 1 summarizes the various tables generated as a result of the desk-top analysis.
Table 1. Results of Desk-Top Analysis
Table Title Location
B-1 PF 225 Washes and Data Appendix B
B-2 Criteria Table Used to Categorize Washes Appendix B
B-3 PF 225: List of Category 2 Washes Appendix B
B-4 PF 225: List of Category 3 Washes Appendix B
C-5 VF 300 Washes and Data Appendix C
C-6 Criteria Table Used to Categorize Washes Appendix CC-7 VF 300: List of Category 2 Washes Appendix C
C-8 VF 300: List of Category 3 Washes Appendix C
D-9 Summary of Total Washes per Category andLocation
Appendix D
D-10 Longitude and Latitude of Washes Appendix D
Because the desk-top analysis and subsequent categorization were based primarily onhydraulic considerations, the IPT conducted site visits to confirm that the washes wereproperly categorized and determine if the recommended retrofits and upgrades werewarranted.
Section 3. Site Visits
The desk-top analysis yielded 106 Category 2 PF 225 fence/wash crossings and 21Category 3 PF 225 fence/wash crossings with more than 66 percent located in Arizona.
001035
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
10/899
4
(Appendixes B and C summarize the PF 225 and VF 300 Category 2 and 3 washcrossings.)
All Category 2 and 3 fence/wash crossings were validated through on-site visits for thefollowing purposes:
Obtain a better idea of the watershed makeup upstream of the wash crossing
Collect basic data concerning the as-built conditions of the fence and grates
Collect bed load data
Determine the likely long-term maintenance requirements following a majorstorm event and or at the end of the monsoon season
Asses the validity of the proposed concept recommendations.
The IPT did not visit the following washes:
All those in Category 1
All crossings associated with segment A-1 because this segment was still underdesign
All Category 2 PF 225 crossings with flow rates below 100 cfs or velocity below2 fps; these crossing were assumed to have no major flooding anticipated.
The site visits were conducted in the following order:1. The washes in New Mexico and Texas (specifically PF 225 Segments I-1A and L-
1) were visited in the early stages of the fence design phase and prior toconstruction; no additional site visits were warranted.
2. Naco to Douglas, Arizona, corridor (PF 225 E and F segments); these visitswere conducted on January 23, 2009; all the crossings within that corridor wereobserved.
3. Lukeville to Nogales, Arizona, corridor (PF 225 D segments); these visits wereconducted on January 30, 2009; all crossings within that corridor were observed.
4. San Diego, California, A-2 segments; these segments were observed on February12, 2009; all crossings of concern were visited and evaluated.
5. All vehicle fences that the IPT initially recommended be removed due toregulatory concerns were visited in 2008 and re-visited recently, as needed.
001036
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
11/899
5
To facilitate the field observations, a standard data collection form was prepared for eachcrossing and pre-populated with existing information, and then supplemented in the fieldwith additional information obtained during the site visit (such as specific grate designs
and fence type). The IPT also took photographs of each crossing visited. (Appendix Eprovides copies of the data collection forms and photographs.)
Section 4. Considerations
PF 225 fencing obstructs drainage flow every time a wash is crossed. With additionaldebris build-up, the International Boundary Water Commissions (IBWCs) criteria forrise in water surface elevations (set at 6 in rural areas and 3 in urban areas) can quicklybe exceeded. Proposed solutions for PF 225 fence projects focus on reducing thedestructive effects of debris at fence drainage crossings. The proposed solutions wouldenable drainage flow to cross the fence while minimizing the risk of flooding, scouring,
and structural failure. Those solutions also need to meet IBWC criteria. In California,Arizona, and New Mexico, PF 225 were built outside FEMAs floodplains, so FEMAcriteria did not apply. Some PF 225 segments in Texas, however, were planned to beconstructed in the tributary crossings of the Rio Grande and will be in FEMA floodplains.The collection of debris in those wash crossings and their impacts on the Rio GrandeFEMA floodplains are addressed in other drainage documents and beyond the scope ofthis report.
Given that the rise in water surface elevation (WSE) after the placement of VF 300fencing typically meets IBWCs criteria (described above), VF 300 fencing was allowedto be constructed in FEMA floodplains. During high-flood events (monsoon season),
however, the VF 300 fence in FEMA floodplains were to be removed and relocated to anoff-site staging area. Given the low rise in WSE, VF-300 fences were allowed to remainin place at all wash crossings permanently without violating IBWC criteria. That policyof leaving the VF 300 fence in floodplains was not considered during the original designphase of the fence project because of the time required to comply with FEMAsrequirements. The IPT was further tasked to assess the flood risks associated with leavingthe VF 300 fence in FEMA floodplains during flood events. Most of the VF 300 fenceplaced in drainage crossings was Normandy style fencing (VF-2), which is set on theground without a foundation. Few VF 300 segments with rail on post fencing (VF-1),with 6-foot deep post foundations were constructed in the floodplains. Both style fencestypically present minimal impacts and pose a very low flood risk. Giving the lack of
schedule constraints, FEMA compliance may be achieved while keeping the VF 300fence in the floodplains and will be addressed under a separate cover. The primaryconcern with the VF 300 drainage crossings is the stability and longevity of the VF-2fence and its ability to withstand flooding. Proposed solutions for VF-2 fencing willaddress maintaining the current fencing against high pressures from the water flowing at
001037
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
12/899
6
high velocities. For the remaining VF 300 fencing with foundations, the IPT consideredsolutions similar to those for the PF 225.
During weekly meetings, the IPT discussed multiple potential solutions to mitigate debris
build-up along PF 225 and VF 300 fence projects. The goal of those solutions was toalleviate debris build-up at the fence and the potential for scour and erosion during majorstorm events. The solutions are briefly discussed in the following subsections.
PF 225 Proposed Solutions
Installation of Gates at Wash Crossings that can be Opened DuringMonsoon Season or Prior to Major Storms
Multiple gate options were considered including swing, sluice, slide, and
retractable. The IPT compared the various types of gates using the followingfactors: drainage efficiency, ease of gate operation, visual deterrence, long-termmaintenance requirements, construction and life-cycle costs, and location (seeTable F-11 in Appendix F). It concluded that retrofitting the existing fence atwash crossings with a sluice gate (sliding vertically) was the best solution. Thisconcept would require the removal of existing grating or fencing, and retrofittingwith one or more vertical gates similar to the concept design depicted in Figure F-8 in Appendix F.
The required height of the gate openings was estimated to be 4 to 9 feet, andwould be a function of the flood water elevation and wash geometry of the
applicable wash. The required width and number of gates would also be afunction of each crossings characteristics. When the required number of gateopenings was known, a customized vertical gate system would be fabricated andinstalled at each crossing. The gates would be opened prior to monsoon or stormevents, thus providing a clear opening for the storm water and debris to flowthrough the fence with minimal obstruction. Following the monsoon or stormevents, the gates would be closed. For low-to-moderate storm events, the gatescould remain in the closed position.
Retrofit Existing Fence at Wash Crossings with Removable Bollards
This concept would require retrofitting the existing fence to allow only a portionof the fence bollards to be removable. By minimizing the height of the bollards tobe removable, operation and maintenance costs would be reduced and heavyequipment would not be required during installation. The required height of theremovable bollards (estimated at 4 to 9 feet) would be a function of the floodwater elevation and wash geometry. Prior to installing the removable bollards, all
001038
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
13/899
7
existing grates would be removed. If the fence has no grate, then another retrofitwould be required to replace the bollard fence with a frame similar to a fence withgrates so that there would be clear openings behind the removable bollards. Thebollards would be removed before monsoon or storm events, thus providing a
clear opening for the storm water and debris to flow through the fence withminimal obstruction. Following the monsoon or storm event, the bollards wouldbe reinstalled. For low-to-moderate storm events, the removable bollards wouldremain in the closed position. The bollards would not need to be removed forevery storm event, only those with the potential for major precipitation. Theconcept design is presented in Figures F-1 and F-2 in Appendix F. This optionwas not as promising as the previous gate option because of the need to find aplace to store after removal and to haul the bollards.
VF 300 Solutions
Remove Existing Fence and Replace with Concrete Boulders or TetraPods
These structures would be large concrete blocks strategically placed in the bed ofthe main wash to stop vehicles from crossing. The IPT performed preliminarycalculations to estimate the size of a concrete cubes required to resist hydrostaticsliding forces. Those calculations showed that each of these structures would needto be between 8 to 12 feet, depending on the velocity of the flow. (Appendix Fshows typical images of similar structures and the IPTs calculations.)
To determine the order of magnitude impact that the concrete blocks or boulderswould have on a water surface elevation, the IPT created a Hec-Ras Model fortwo typical washes: the Cantina Wash (Segment FV-1B Wash C17) and HayHollow Wash (Segment FV-1B wash C14). An analysis showed that installingsuch an obstruction would cause the water surface elevation to rise to a levelhigher than the limit set by IBWC (see Appendix H). In addition, the obstructionswould need to meet FEMAs requirements and regulations for building in afloodplain. For the above reason, the IPT does not recommend this solution.
Anchor Normandy Fences to Ground
This solution calls for installing deep concrete drilled shafts or deep embeddedmetal columns connected to the existing Normandy fence. This approach wouldanchor the fence in place even when it is subjected to the high pressures of stormflows. Details of the Normandy fence and the anchoring system are shown inFigures F-6 and F-7 in Appendix F. The IPT recommends this solution.
001039
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
14/899
8
Remove Existing Fence and Replace with Widely Spaced Bollards
The bollards would need to be clearly separated from each other, but not morethan 4 feet in order to stop vehicles from crossing. The bollards would also need
to be embedded into the ground to sustain the forces of the flow and the scourdepth. The footings for these bollards would likely be concrete drilled shafts toestimated depths of 25 to 30 feet. Figure F-5 in Appendix F shows the details ofsuch a fence. For hydraulic and scour reasons this solution is not recommendedfor high-flow Category 3 washes, but may be considered for lower Category 3washes. This option is not operationally desirable because of the open spacebetween bollards.
Remove Existing Fence Before Major Flood Events
In this solution, the Normandy fence would be modified to facilitate easy and
quick removal with heavy machinery. The VF would be removed from the mainchannel of the wash prior to the monsoon season or a major storm event. Thisoption is not operationally desirable because of the need to find a place to storethe fence after removal and the need to haul the fence, both actions are labor andcost prohibitive.
Rebuild Post and Rail Fences with Deeper Foundations
This solution is less tamper proof then the recommended option, so it is notoperationally desirable.
Section 5. Recommendations
PF 225 Recommendations for High-Risk Washes
The IPT recommends that the existing drainage grates be removed and retrofittedwith vertical slides gate, concrete apron, and rip rap similar to the concept designdepicted in Figure F-8 in Appendix F. Table 2 summarizes the recommendedactions by order of priority.
Table 2. Recommendations: PF 225 High-Risk Washes
Fence ID Wash IDs Category Fence typeFlow
direction
001040
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
15/899
9
Fence ID Wash IDs Category Fence typeFlow
direction
NogalesPOE
Approx 500 feetEast of Nogales
POE 3 Bollards N
D-2
E-16 3 Mesh with grates S
W13 3 Mesh with grates S
E8 2 Mesh with grates S
W17 2 Mesh with grates S
E3 M1 (Christiansen) 3 Bollards with grates N
D-5B10 (Las Cuevita) 3 Bollards N
44 3 Bollards N
D-5A 2 (Mariposa) 3 Bollards N
E2A 5 (Montezuma) 3 Bollards with grates S
E2B
M5 (BC Wash) 2 Staggered bollards N
M8 (gringo Wash) 3 Staggered bollards S
M14 (Wash 33) 2 Staggered bollards N
M16 (1st
Horseshoe) 3 Staggered bollards N
M21 (2nd
horseshoe) 2 Staggered bollards N
A2L J6 3 Bollards with grates N
J9 3 Bollards with grates N
A2K J-1&2 (47+09) 3 Bollards with grates S
J-5 (70+50) 3 Bollards with grates N
VF 300 Recommendations for High-Risk Washes
For the very few washes with rail-on-post fence that are in high risk washes, theIPT recommends removing the existing post foundation, post, and rail and replacethem with deep concrete shaft foundations, new posts with removable rails,concrete aprons, and rip rap.
For the washes with Normandy fence, the IPT further recommends that the fencebe anchored as shown in Figure F-7 in Appendix F, adding concrete aprons andRipRap. Table 3 lists the washes to be retrofitted in order of priority.
Table 3. Recommendations: VF 300 High-Risk Washes
Segment Crossing CategoryApproximate
fence length to beanchored (ft)
FEMAcrossing
FV-1B C6 Silver Creek 3 300+200 Zone A
001041
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
16/899
10
Segment Crossing CategoryApproximate
fence length to beanchored (ft)
FEMAcrossing
C13 Black Draw 3 450+200 Zone A
C14 Hay Hollow 3 40+50+100 Zone A
EV2B 102 3 240 Zone A
EV1A
6 3 100 Zone D
42 3 200 Zone D
52 2 50 Zone D
53 3 100 Zone D
55 2 50 Zone D
61 3 70 Zone D
DV4B
14 3 150 Zone D
A 3 240 Zone D
6 3 270 Zone D
8 2 70 Zone D
EV1B F023 200
Zone BHV-3 DA6 2 50 Zone X
CV2A Y6 2 180 Zone DNote: Short definitions of FEMA zones: Zone A = area with 1 percent annual
chance floodplain; Zone C = areas outside the 1 percent annual chance floodplain; Zone D = areaswhere flood hazards are possible, but undetermined; Zone X = areas outside the 1 percent annualchance floodplain.
Recommendations for PF 225 Medium-Risk Wash Crossings
For PF 225 fence wash crossings that do not warrant retrofitting with the sluicebollard gate concept design but are subjected to scour and erosion problems, the
IPT recommends the installation of Low Water Crossings (LWC) and rip rap.Figure F-3 and F-4 in Appendix F provide details of the LWC and Rip Rap foreach flow direction.
The PF 225 fence segments and their associated wash crossings that should haveLWC and rip rap installed are summarized by order of priority in Table 4.
Table 4. Recommendations: PF 225 Medium-Risk Washes
Fence ID Wash IDs Fence typeFlow
direction
A2A 2 Bollards SA2D 52+13 Bollards with grates S
E2A 3 Bollards with grates SA2J 51+75 Bollards with grates N
A2E 5+44 Bollards with grates SA2D 60+57 Bollards with grates SD5B 27 Bollards N
001042
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
17/899
11
Fence ID Wash IDs Fence typeFlow
direction
D5A 4 Bollards ND5B 28 Bollards with grates S
D2 E31 Mesh with grates S
E2A 7 Bollards with grates SD2 W1 Mesh with grates S
D5B 9 (Barranca Honda) Bollards ND5A 1 Bollards N
A2N 3 Bollards with grates ND2 E33 Mesh with grates S
E3 US4 Bollards with grates SE3 US2 Bollards S
E3 M4 Bollards with grates ND5B 8 Bollards with grates NE3 US5 Bollards S
E2A 6 Bollards with grates SL1 4 Bollards S
D2 E20 Mesh with grates SL1 1 Bollards S
D5B 1 Bollards ND5B 26 Bollards N
L1 6 Bollards SE3 M3 Bollards with grates ND2 E19 Mesh with grates S
I1A Subbasin 3 Bollards SI1A Subbasin 4 Bollards S
Recommendations for Other VF 300 Medium-Risk Wash Crossings
The remaining vehicle fence segments and their associated wash crossings thatshould have LWC and rip rap installed are summarized in Table 5 by order ofpriority.
Table 5. Recommendations: VF 300 Medium-Risk Washes
Segment CrossingRequired
installationFence type
Flowdirection
FEMAcrossing
BV-1 100 (Pinto) LWC & RipRap Normandy N Zone A
JV3 1 LWC & RipRap Normandy S Zone X
DV-3A 1 (San Simon) LWC & RipRap Rail on post S Zone D
DV-3A 4 (Chukut kuk) LWC & RipRap Rail on post S Zone D
HV-2 8 LWC & RipRap Normandy N Zone X
001043
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
18/899
12
Segment CrossingRequired
installationFence type
Flowdirection
FEMAcrossing
DV-7 35 LWC & RipRap Rail and post S Zone DFV-1B C5 LWC & RipRap Rail and post S Zone X
EV-1A 63 LWC & RipRap Normandy S Zone D
DV-4B 12 LWC & RipRap Rail and post S Zone D
DV-7 17 LWC & RipRap Rail and post S Zone DDV-4A Basin 11 LWC Only Normandy S Zone D
FV-1B C21 LWC & RipRap Rail and post S Zone X
HV-3 DA1 LWC & RipRap Normandy N Zone X
FV-1B C17 (Cantina) LWC & RipRap Normandy S Zone X
DV-4A Basin 42 LWC Only Normandy S Zone D
EV-1A 66 LWC & RipRap Normandy S Zone D
DV-4B 17 LWC & RipRap Rail and post S Zone D
FV-1B C50 LWC & RipRap Normandy S Zone XHV-2 4 LWC & RipRap Normandy N Zone X
DV-4B 9 LWC & RipRap Rail and post S Zone D
FV-1B C4 LWC Only Normandy N Zone D
EV-1A 60 LWC & RipRap Normandy S Zone D
EV-1B EV-1B_F-01 LWC & RipRap Normandy S Zone D
DV-4A Basin 1 LWC & RipRap Normandy S Zone D
FV-1B C24 LWC & RipRap Normandy N Zone X
DV-4A Basin 9 LWC Only Normandy S Zone D
DV-1 18 LWC & RipRap Normandy S Zone D
DV-4A Basin 35 LWC Only Normandy S Zone D
DV-4A Basin 20 LWC & RipRap Normandy S Zone D
DV-4A Basin 46 LWC Only Normandy S Zone DDV-4A Basin 17 LWC & RipRap Normandy S Zone D
DV-1 12 LWC & RipRap Normandy S Zone D
HV-3 DA4 LWC & RipRap Normandy S Zone X
DV-1 14 LWC & RipRap Normandy S Zone D
EV-1A 59 LWC & RipRap Normandy S Zone D
DV-4A Basin 44 LWC & RipRap Normandy S Zone D
DV-1 21 LWC & RipRap Normandy S Zone D
DV-4A Basin 5 LWC & RipRap Normandy S Zone D
DV-4A Basin 6 LWC Only Normandy S Zone D
FV-1B C52 LWC Only Normandy S Zone X
CV-2 16 LWC & RipRap Normandy S Zone DDV-4B 21 LWC & RipRap Rail and post S Zone D
EV-1A 56 LWC & RipRap Normandy S Zone D
CV-2 7 LWC & RipRap Rail on post S Zone D
DV-4A Basin 45 LWC & RipRap Normandy S Zone D
DV-4A Basin 41 LWC & RipRap Normandy S Zone D
001044
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
19/899
13
Segment CrossingRequired
installationFence type
Flowdirection
FEMAcrossing
EV-1A 58 LWC & RipRap Normandy S Zone D
FV-1B C45 LWC Only Normandy S Zone X
DV-4C Basin 52 LWC & RipRap Normandy S Zone D
DV-1 19 LWC & RipRap Normandy S Zone D
DV-1 17 LWC & RipRap Normandy S Zone D
EV-1A 38 LWC & RipRap Normandy S Zone D
EV-1A 40 LWC & RipRap Normandy S Zone D
DV-4A Basin 43 LWC & RipRap Normandy S Zone D
DV-1 22 LWC & RipRap Normandy S Zone D
EV-1A 45 LWC & RipRap Normandy S Zone D
DV-1 23 LWC & RipRap Normandy S Zone D
EV-1A 35 LWC & RipRap Normandy S Zone D
FV-1B C10 LWC & RipRap Normandy S Zone XDV-1 6 LWC & RipRap Normandy S Zone D
DV-4A Basin 37 LWC & RipRap Normandy S Zone D
IV4 1 LWC & RipRap Rail on post S Zone X
Note: Zones A, C, D, and Z are as defined in Table 3.
Prioritizing Criteria
The risks facing the PF 225 and VF 300 fences have the following order ofpriority:
1. Obstruction to the flow
2. Risking the structural integrity of VFs
3. Scour and erosion.
To mitigate these risks, the IPT recommends implementing the following fourprojects listed in their order of priorities:
1. Retrofit PF with a sluice bollard gate and add scour protection
2. Anchor the VF and add scour protection
3. Add low-water crossings to washes with PFs
4. Add low-water crossings to washes with VFs.
001045
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
20/899
14
Each of these projects has several segments, which are listed below in priorityorder:
Highest priority: Washes falling in FEMA Zone A
Higher priority: Washes with high velocity and high-flow depth
High priority: Washes with lower velocity.
Section 6. ROM Cost Estimates
The IPT calculated unit costs to install a sluice Bollard gate, anchor a vehiclefence, and scour protection. Appendix G shows the details of the costs presentedin this section.
Retrofitting PF 225 Fences
Retrofitting approximately 160 gates into a fence with no grates:
Min:Max:
Retrofitting approximately 359 gates into a fence with grates:
Min:Max:
Scour protection for approximately 3,800 to 4,000 feet:
Min:Max:
Mobilization/demobilization and contingency:
Min: 3% + 15% = 18%Max: 5% + 20% = 25%
Total approximate PF 225 retrofit cost:
Min:Max
001046
(b) (5)
(b) (5)
(b) (5)
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
21/899
15
Anchoring VF 300 Fences
Anchoring approximately 3,310 feet of Normandy fence:
Number of anchors = 3310/16 = 207Min:Max:
Scour protection for approximately 5,500 to 6,000 feet:
Min:Max:
Mobilization/demobilization and contingency:
Min: 3% + 15% = 18%Max: 5% + 20% = 25%
Total approximate VF 300 retrofit cost:
Min:Max:
Building Scour Protection for 32 PF 225 Crossings
Low-water crossings length:
Min length: 32 x 150 = 4,800Max length: 32 x 250 = 8,000
Mobilization/demobilization and contingency:
Min: 3% + 15% = 18%Max: 5% + 20% = 25%
Total approximate PF 225 crossings scour protection cost:
Min:Max:
Building Scour Protection for Approximately 62 VF 300 Crossings
Low -water crossings length:
001047
(b) (5)
(b) (5)
(b) (5)
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
22/899
16
Min length: 62 x 150 = 9,300Max length: 62 x 250 = 15,500
Mobilization/demobilization and contingency:
Min: 3% + 15% = 18%Max: 5% + 20% = 25%
Total approximate VF 300 crossings scour protection cost:
Min:Max:
Table 6 summarizes the costs for these recommendations.
Table 6. Summary of Costs
Min MaxRetrofitPF225fenceAnchorVF300fenceScourprotectionforPF225crossingsScourprotectionforVF300crossingsTotal
001048
(b) (5)
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
23/899
IPT Report
APPENDIX A
IPT Charter & After Action Review
001049
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
24/899
Project Name
SBI-TIPF-225 and VF-300 Border Fence projectsTechnical IPT
Understanding of the Need
The major factor impacting the drainage across the fence is the debris. At wash crossings, the debris starts tobuild up, clogging the fence openings and changing the hydraulics of the flow. This has a direct impact tohigher scour and erosion problems, as well as increase in water surface elevation due to the backwater effect.Controlling the Debris during and after the storm event is needed in order to keep the flooding under control.
Another factor include the high pressure of the flow carrying heavy debris (i.e. waterbed rocks) and causingthe removal of the bollards from the ground and transported with the flow downstream, causing high safetyissues. The bollard fence need to have a special structural and foundation design or it must be removed fromthe wash during monsoon seasons.
Deliverables/Objectives
To address the long term and short term solutions that will mitigate the drainage issues described above,and coming up with a maintenance program to sustain the fence and the different alternatives.
Deliverables include design details of the different solutions, locations where these solutions need to beimplemented and when, requirements for a maintenance program.
Preliminary Statement of Work
The following steps describe the method used to reach a solution. Additional steps may be added pendingmeeting outcomes.Step 1: Collect all the crossings and group them into three flooding risk categories: Low, Intermediate andHigh. This step include coming up with criteria and thresholds that will be used to group these crossings.Step 2: Divide the intermediate risk crossings into two categories: High priority (currently under construction)and Low priority (Constructed or Soon to be under construction). This step Assumes that the Low riskcrossings dont require any action, and at high risk crossings will use a temporary fence that will be removedduring the monsoon seasonStep 3: Provide a short term solution for the high priority crossings. Find a strategy or a way to implement thissolution, with its impact on the budget and construction schedule.Step 4: Provide a long term solution for the high and low priority crossing. Find a strategy or a way toimplement this solution, with its impact on the budget and schedule of the incoming construction.Step 5: Provide maintenance requirements for all three flooding risk categories
In Scope
- Review of hydrologic and hydraulic analysis produced for each report
-Produce criteria (non scientific) and have it approved by the IPT team. These criteria will set thethresholds.
- Produce a typical detail for each solution.- Include the pros and cons for each detail- Preliminary cost estimate- Produce meeting minutes
Known Risks- Fences soon to be constructed may not include the proposed solutions in order to meet the deadlines- The proposed solutions may have to be implemented after the fence is constructed (alteration to the
fence already installed)
001050
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
25/899
After Action Review (AAR)
The Monsoon Flooding Event on 12 July 2008 in
Lukeville, Arizona
AndThe Effects of the International Boundary Fence
23 September 2008
US Army Corps of Engineers
001051
(b) (6)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
26/899
After Action Review (AAR)The Monsoon Flooding Event on 12 July 2008 in Lukeville, Arizona
And
The Effects of the International Boundary Fence23 September 2008
PurposeThe purpose of this After Action Review is to determine the cause of the flooding inLukeville, Arizona on July 12, 2008 and to determine the implications of the D-2
Lukeville border fence on drainage and environmental conditions.
Introduction
On the afternoon of July 12, 2008, a severe monsoon event created flooding in the
Lukeville, Arizona area. During this event, the Organ Pipe Cactus National Monument
(OPCNM) recorded 1.99 inches of rainfall over a ninety (90) minute period. This eventwas the first significant rainfall of the summer. Of the area along the fence involved in
the flooding, three noted locations of concern are the Lukeville Port of Entry (POE), the
Gringo Pass Store and the Sonoyta, Sonora, Mexican Port of Entry.
List of Documentation and References1. Request For Proposal, D-2:AJO 3.1 Miles East to 2.1 Miles West of Lukeville, AZ
POE2. Letter: Gringo Pass, Inc. July 14, 2008 to Lee Baiza, Superintendent: Organ Pipe
Cactus National Monument
3. U.S. Border Patrol:Monsoon Storm Flooding in Lukeville, Arizona Area4. National Park Service, Effects if the International Boundary Pedestrian Fence in the
Vicinity of Lukeville, Arizona, on Drainage Systems and Infrastructure, Organ Pipe
Cactus National MonumentAugust 20085. Kiewit/HNTB. Project D-2 AJO 3.1 Miles East to 2.1 Miles West of Lukeville, AZ
Poe Design Complete package: Drainage Report February 2008.6. U.S. Border Patrol, Tucson Sector. Final Environmental Assessment for the proposed
installation, operation, and maintenance of primary pedestrian fence near Lukeville,
Arizona February 20087. National Weather Service Advanced Hydrologic Prediction Service Precipitation
Analysis
Review of Documentation
The following sections are summaries of the documentation reviewed for this report.
The Request for Proposal (RFP) for D-2, Section 1.9.4. Drainage Report and itsaccompanying technical appendix (Ref. 1) detailed the requirements for the contractor,
Kiewit Western Co., under Contract W912BV-07-D-2022, CQ02. The RFP had a
preliminary drainage report and a list of minimum requirements for the contractor toperform which included 1) review of existing drainage and field verify existing wash
locations, 2) provide delineation maps, 3) determine local drainage runoff and sheet flow
conditions as they cross the fence location, 4) provide final hydraulics calculations by
001052
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
27/899
Figure 1: Watershed Delineation by Contractor (Ref. 5)
001053
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
28/899
Figure 2: Watershed Delineation by Contractor (Ref. 5)
001054
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
29/899
Figure 3: Watershed Delineation by Contractor (Ref. 5)
001055
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
30/899
determining velocities associated with select fence type and rise in water surface
elevation, 5) provide final calculations on scour and/or long term degradation, 6) provide
details for fence wash crossing which satisfies rise in water surface elevation, 7) providedetails for protection against scour and long-term degradation, 8) show that cut fill
operation do not adversely affect the natural drainage patterns, 9) provide hydraulicdesign and details for any other site drainage improvements, 10) provide final drainagereport and 11) coordinate with all applicable reviewing agencies. The included
preliminary report by Michael Baker Inc. shows a preliminary hydrologic analysis but no
analysis regarding hydraulics or scour.
A letter supplied by of Gringo Pass Inc to Lee Baiza, Superintendent of the
Organ Pipe Cactus National Monument (Ref. 2) stated that the July 12 storm flooded the
entire Gringo Pass Store. A flood occurred last year which flooded the back of the store.It was stated that Border Patrol vehicles were getting stuck in mud and debris.
A report by the Office of Border Patrol (OBP) on Monsoon Storm Flooding in Lukeville,Az. (Ref. 3) details three flooding issues: 1) the Lukeville POE, 2) the Gringo Pass store
and 3) the Mexican POE. The Lukeville POE contains an atrium in the center of the
building with a dry well system that drains into a 2.5 inch dry well that takes water out of
the building proper. Contributing factors of flooding stated in the report are the buildingfoundation at equal grade as the atrium and the end of the drain having been covered with
earth. It was stated that the Gringo Pass store flooding was due to a combination of
construction on low elevation, obstruction of flow from vegetation on the fence gate,concrete rubble south of the fence in the wash, the amount of rain and its intensity, and
the vegetative ground cover spread (mulch) within the drainage location. The mulchmaterial was removed vegetation from the placement of the border fence that was given
to the OPCNM to grind into mulch and place in the watershed. Flooding at the Mexican
Port of Entry is attributed to the structure, which is 1 ft below the existing grade, beingbuilt in the flood plain. The contractor, the Corps of Engineers (USACE) and OBP
personnel met on site to discuss possible causes. Elevation surveys of the areas were
performed to determine the Gringo Pass store and the Mexican POE were in thefloodplain. Also, it was reasoned that the first flood of the season would produce most of
the debris. The recommendations made were 1) placement of a pressure release system
in the fence on the west side of the wash, 2) insure that the washes are channeled properly
and that debris does not build up against the fence and 3) retrofit sections of the existingfence with a hybrid 4 bollard design to facilitate maximum water flow.
A report from the Organ Pipe Cactus National Monument (OPCNM) of the Nation ParkService (NPS) (Ref. 4) documents the July 12 th event and the performance of the fence
during a flash food and the effects on the floodplains and channel morphology. The July
12 event recorded 1.99 inches of within 90 minutes based on a climate station for theNational Atmospheric Deposition Program operated by the Nation Park Service. The
location of this measurement was at the OPCNM headquarters. Another rain gage
located 1.5 miles west-northwest of the Lukeville measured 1.25 inches in 105 minutes.The radar rainfall estimate for that day from the National Oceanic and Atmospheric
001056
(b) (6)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
31/899
Administration (NOAA) shows the thunderstorm centered north of Lukeville, in thevicinity of the OPCNM headquarters, with a very small region receiving rain in excess of
2.5 inches. The NPS states that the July 12 th storm occurs regularly within OPCNM,
placing the reoccurrence between once every 3-5 years. NPS states that the drainageareas delineated by the Contractor are for W13 or Victoria Wash and E31 or Estes
wash are undersized because OPCNM delineations are more accurate. United StatesGeographic Survey (USGS) equations used were not applicable in areas under 1730 ft inelevation. Mainstream flood flows were contained in flow reaching the fence however
a combination of debris flow blockage and subsurface sediment flow impeded by the
foundation of the fence contributed to the flooding. Documentation of water levels was
up to 7 ft above the foundation wall at W13. Blockages caused lateral flows at the fencewill a) cause scour and b) cause flow to enter different washes. The blockages at
Headquarters Wash (W1) were the cause of the Gringo Store and Lukeville POE
flooding. Ponding of water was not noticed at the fence for the July 12th
storm, howeverit was noticed upstream of the fence where patrol road elevations are above natural
surface elevations; in turn, vegetation change is expected in locations where water pools.
The conclusion that a) the accelerated scour will comprise the integrity of the fence b)lateral flows will erode the patrol road and the pedestrian fence. c) Vegetation will
change which will change rainfall retention, d) riparian vegetation will change due to the
increase of sedimentation, and e) channel morphology will change over time where
channelized water will gully.
The design of the pedestrian fence was accomplishment by Kiewit with the drainage
report by HNTB (Ref. 5). The report requirements were as detailed in the RFP. Also,design criteria included the United States International Boundary and Water Commission
(USIBWC) limit of the water surface elevation rise due to the fence for a 100-yearfrequency event to 6 inches in rural areas. Security criteria includes a maximum 6 gap
between vertical members used if there are no horizontal members are used and a
maximum clear opening that would prevent someone from being able to create a 2 by 2gap in the fence within a 15- minute timeframe if both vertical and horizontal members
are used for the fence. The contractors precipitation calculations were based on NOAA
Atlas 14 Point Precipitation Frequency Estimates at the approximate location of theLukeville POE. Wash crossings were determined from available topography, mapping,
and detailed site visits. Drainage area calculations were based on USGS topology,
although it was not specific on what topology was used. The 100-year peak discharge for
the washes were determined in 2 ways: 1) for sub area greater than 10 square miles,USGS Regression equations for Arizona Region 13 were used, 2) for regions under 10
square miles, the National Resources Conservation Service NRCS method was used. The
hydraulics were performed in two parts, 1) HEC-RAS and Bentleys FlowMasterprogram was used to determine the water surface elevation of the wash prior to the gate
and 2) The head loss equation used was the USACE equation for vertical racks to
determine the increase in the water surface elevation when the flow reaches the gate. Thewater surface elevation results were added to the head loss to achieve a final water
surface elevation. Light Detection and Ranging (LIDAR) contour mapping, aerial
photography and field surveys were used to determine wash characteristics and to modelthe wash crossings. The two boundary conditions used were the 100-year peak flow rate
001057
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
32/899
determined in the hydrology analysis and normal depth. It was assumed that the gateswould be cleared prior to a flood event and no debris would be capture on the fence
which would create blockage. High Performance Turf Reinforce Mats (HPTRM) was
set downstream of the border fence to prevent scour on locations where the modeledvelocity was greater than 4 fps. The HPTRM is expected to hold up to velocities of 10
fps.
The Final Environmental Assessment (EA) for the proposed installation, operation, and
maintenance of primary pedestrian fence near Lukeville, Arizona February 2008 (Ref. 6)
states that Furthermore, in most washes or arroyos, the primary pedestrian fence would
be designed and constructed to ensure proper conveyance of floodwaters and to eliminatethe potential to cause backwater flooding on either side of the U.S.-Mexico border. CBP
(U.S. Customs and Border Protection) will remove debris from the fence within
washes/arroyos immediately after rain events to ensure that no backwater floodingoccurs.
Site VisitA site visit of the D-2 border fence occurred on September 3, 2008. The site visit
reviewed the fence 1 mile West and 3.1 miles East from the Lukeville Port of Entry.
There had been a storm on August 26th, and the fence had not been maintained since the
storm. It was reported that there was no flooding in the Lukeville POE or Gringo PassStore during the August 26th storms. Three days of radar satellite imagery from NOAA
are shown in Figures 4-6. The W1 border fence location showed large debris captured at
the grate (Fig. 7), sedimentation on the approach to the fence (Fig. 8) and the HPTRMdownstream of the fence was wrapped around the post-and-rail (Fig. 9). Sedimentation
was shown just upstream of the fence (Fig. 10). Standing water was seen justdownstream on the Mexican side of the wash. Large obstructions exist just downstream
on the Mexican side (Fig. 11) W4 had a small amount of debris build up (Fig.12). The
W5 fence crossing had a pool of water at the fence (Fig 13). The fence crossings at W7,W9 and W10 were free of debris. The fence crossing at W11 had a standing pool of
water (Fig 14). The fence crossing at W13 had debris, sedimentation and erosion
downstream of the fence with HPTRM wrapped around the downstream post-and-rail(Fig 15-17).
Due to the reported flooded at the Lukeville POE, the AAR team investigated the
buildings office atrium. The atrium drains the roof and all of the water captured withinthe atrium into three floor drains located within the atrium (Fig 18). The water drains to a
location near fence crossing E1. The end of the drain was reportedly covered at the time
of the July 12th
flood but was daylighted before the site visit. The E1 fence crossing wasclean of debris during the site visit. Crossings E2-E7 were either clean of debris or had a
relatively small amount of debris. The E8 crossing, which has a tributary drainage area of
14.7 sq. mi., collected significant debris and sediment at the crossing (Fig. 19-21). Thesoil was eroded around the downstream post-and-rail foundation (Fig. 22). Erosion was
seen east of the E8 fence crossing, along the upstream toe of the fence (Fig. 23). Debris
was shown at the fence crossing at E9 (Fig 24, 25). The fence crossing at E13, which has
001058
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
33/899
Figure 4. NOAA Radar Satellite for Aug 26
Figure 5. NOAA Radar Satellite for Aug 27
001059
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
34/899
Figure 6. NOAA Radar Satellite for Aug 28
Figure 7. W1 crossing.
001060
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
35/899
Figure 8. Sedimentation in the approach wash for W1
Figure 9. HPTRM wrapped around the downstream post and rail
001061
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
36/899
Figure 10: W1. Sedimentation just upstream of the fence.
Figure 11. Site W1: Pool downstream of the fence
001062
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
37/899
Figure 12. Debris at W4
Figure 13. Ponding at the W5 crossing
001063
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
38/899
Figure 14. W11 fence crossing, upstream side
Figure 15. W13 crossing, upstream side
001064
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
39/899
Figure 16. W13 crossing
Figure 17 HPTRM rapped around the fence post-and-rail downstream of fence W13
001065
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
40/899
Figure 18. Center drain at Lukeville POE building atrium
Figure 19. Debris build up at E8
001066
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
41/899
Figure 20. A closer look at the debris build up at E8
Figure 21. Sedimentation at E8
001067
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
42/899
Figure 22. Erosion at downstream side of the E8 fence crossing
Figure 23. Erosion at upstream side of the of E8/E9 crossing
001068
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
43/899
Figure 24.Sediment at E9
Figure 25. Debris at E9
001069
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
44/899
a tributary drainage area of 0.6 sq. mi., did not have any debris build up (Fig 26). E16,which has a tributary drainage of 14.7 sq. mi., had significant debris and scour
downstream of the fence (Fig. 27-29). Gabbions and K-Rail, presumably used to support
the post and rail, were exposed by the 3-4 foot downstream scour hole. Sedimentationwas evident on the patrol road. Wash crossing E29, which has a drainage of 0.6 sq mi,
had debris build up of tree branches, vegetative material and sedimentation (Fig. 30). Thefence crossing the E30 wash shows significant erosion on its west side on the upstreamside of the fence likely due to lateral flow along the fence (Fig. 31). Debris clogging is
also evident. E31 captured debris at the wash crossing and west along the wire mesh of
the fence (Fig. 32,33)
Analysis
As stated, the July 12th storm accumulated 1.99 in of rain within 90 minutes. This
amount of rain for that short of duration according to NOAA 14 point precipitationfrequency estimates for the Organ Pipe National Monument classifies it between 10-year
and a 25-year storm. The highest volume of recent rainfall for a day is approximately the
2.5 inches which occurred from 0500 26 August to 0500 27 August, Mountain StandardTime (MST). This amount can be substantiated by the gage recording at the Organ Pipe
Cactus Nation Monument rain gage, which preliminary records show 2.62 inches 24 hour
period ending 27 August 2008. NOAA 1- Day Precipitation for 12 July 2008 0500 MST
to 13 July 2008 500 MST are shown in Figure 34. The design for the pedestrian fence isbased on a 100-year, 24-hour frequency storm. The contractor used an adequate data
source to determine 100-year 24-hour storm.
Under the conditions of these two storms, the border fence is shown ineffective to allow
large debris material to pass. Even after the clearing of first flush debris of thewatershed on July 12th, there was still significant amount of debris found on the wash
crossings with large tributary drainage areas from the storm on August 26th. With the
large debris in the fence, sediments and vegetation are less likely to pass through, and inturn, can accumulate with large debris and clog the lower portion of the fence (see figure
19). The obstruction can cause backwater effects, lateral flows along the fence,
flows flowing over the crest of the debris which may cause significant vortex forces atthe downstream footing of fence, which would lead to scour, endangering the structural
integrity of the fence. The backwater can cause sediment and vegetation to settle out of
the flow before the fence. Lateral flows can cause scour along the upstream side of the
fence, and allow flow to pass the fence at another wash location.
The contractor, in the design of the fence, considers the obstruction of the fence in the
wash contributing to head loss of a 100-year storm, however, does not include debriscollected during the storm in their calculation of the rise of the water surface elevation
due to the fence. The design addresses this on page 10 of the Design Complete package
Drainage Report: Kiewit HNTB:
The fence design permits the passage of flows with minimal effects upstream of the
International Boundary resulting from flows backing up behind the fence. This is true
with the assumption that and debris caught on the fence during a storm event will be
001070
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
45/899
Figure 26. E13 Wash Crossing
Figure 27. Downstream scour at E16 crossing.
001071
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
46/899
Figure 28. Debris captured at E16
Figure 29. Debris captured at E16
001072
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
47/899
Figure 30. Debris at Wash E29 Crossing
Figure 31. Erosion east of E30 wash crossing
001073
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
48/899
Figure 32. Debris at E31
Figure 33. Debris remaining west of E31 crossing
001074
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
49/899
Figure 34. NOAA observed precipitation on July 12th
rainstorm
cleared by the Border Portal or designated maintenance personnel within a reasonable
timeframe. Debris left in place causing significant blockage of flow area could cause an
eventual backwater rise beyond those calculated in this report. The RFP drainage
report does not explicitly state that debris calculations will be performed or considered
when determining the rise in elevation due to the placement of the fence.
It does not appear that the vegetative material collected at the fence was mulch. There is
no confirmation on the report by the Office of Border Patrol stating the vegetative
material from the construction of the border fence was turned into mulch and depositedwithin the watershed.
The HPTRM showed to be ineffective at the fence crossing W1 and W13. Both are large
washes where respective tributary drainage areas are greater than 1 sq. mi. The HPTRM
was caught in the downstream post-and-rail fence and likely add to the obstruction offlow and backwater effects. It is unknown whether the failure was due to poor installation
or unanticipated flow conditions. There is scour on the downstream side of W13, E8, and
E16.
Scour at the footing on the upstream side of the fence can be seen through inspection at
E8 and E30. Scour at those sites likely incurred due to significant lateral flows. Lateralflows traveled beyond the grate design area and into areas which only contained meshwire, as shown at fence crossing E30 and E31, which indicates the design did not account
for flows within that area (Fig 30, 32).
The OPCNM Report has stated that the flows on July 12 th at fence crossing at W13
reached up to 7 feet from the toe of the fence. According to Contractors report, the 100-
year storm at W13 will reach 4.59 feet above the toe.
001075
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
50/899
There were some instances of pooling of water in some site west of Lukeville (W1, W5,
W11). The pooling of water can be attributed to a difference in grade between the
downstream Mexican and border fence. It is unknown where this difference existed inthe past and pooling was common in these areas. Requirements by the RFP state that the
contractor will provide details for preventing ponding of water at the fence.
The memo prepared by for Gringo Pass Inc. stated that this years flooding in
the store was worst than last year. It is presumed that the post-and-rail fence was the only
erected obstruction last year. No information is available on the volume and duration of
last years storm. The Gringo Store is close to the fence crossing wash W1, and thepedestrian fence was likely responsible for capturing more debris at the crossing than in
years past. The comparable storm on August 26th did not cause the same flooding in the
in the region. One important change was 120 feet of the east side W1 berm was raised 3feet to protect the store from flooding. The store did not incur flooding on August 26 th. It
is unknown if a 25-year storm alone would have flooded the area in the same manner; the
Gringo Pass Store does lie in the 100-year flood plain, but it is unknown if it lies in a 25-year or 10-year floodplain.
The Lukeville POE flooding on July 12th could have been caused in part by the W1
backwater effects. The blockage of the atrium drain was responsible for the buildingsinternal flooding. The subsequent storm on August 26th did not cause flooding in the
area. It is assumed that the berm as well as the clearance of the drain prevented flooding.
The language in the Final EA states Furthermore, in most washes or arroyos, the
primary pedestrian fence would be designed ad constructed to ensure proper conveyanceof floodwaters and to eliminate the potential to cause backwater flooding on either side of
the U.S.-Mexico border. CBP will remove debris from the fence within washes/arroyos
immediately after rain events to ensure that no backwater flooding occurs. Most of themajor washes here, according to the contractors HEC-RAS simulation, are subcritical
flows, therefore, an increase in height at the fence is propagated upstream. Under the
USIBWC, the fence can increase the water surface elevation at the fence at 3 inches inurban area and 6 inches for rural areas. Conceivably, these 3 and 6 inch criteria may not
cause backwater effects if it does not cause the flow to enter the floodplain. If the flow is
out of the floodplain, then the 3 and 6 inches increase at the fence may increase the
flooding. Therefore, under certain conditions, the 3-6 inch allowable criteria are contraryto the EA criterion of no backwater flooding.
Conclusion
It is unknown whether the fence was a major factor impacting the flooding at the Gringo
Pass Store and the Lukeville POE. Under the conditions of the August 26th
storm theGringo Pass Store did not flood. The three foot rise of the berm on the east side of W1
likely helped prevent the flooding from occurring. The Lukeville POE, with the berm
being raised and the end of the atrium drain being cleared helped the building from beingflooded.
001076
(b) (6)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
51/899
The larger washes, where the tributary drainage area at the fence crossing is greater than
1 sq. mi., showed many instances of debris, sediment and vegetation being captured in
the border fence. The debris at W13 is likely causing an increase in the water surfaceelevation at the fence which is greater than the 100-year elevation. Therefore, the rise in
the water surface elevation is possibly greater than the 6 inches permitted by theUSIBWC design criteria. Another possibility of the unexpected rise of the water surfaceelevation at the fence could be in the discrepancy in the tributary drainage area between
the results from the Contractor and the NPS report. The Contractor estimate of 2,839
acres is 774 acres less than NPS estimate of 3,613 acres. There is not enough data at the
other sites which experienced significant debris blockage to determine if those sites didnot meet the USIBWC criteria.
The contractor did not consider blockage of the debris in calculations of the rise in watersurface elevation from existing to proposed conditions, which, depending on the severity,
can increase the water surface elevation at the location of the fence. Instead the contractor
assumed that any debris would be cleared before the next storm and no debris wouldbuild during the storm. There was no explicit guidance or requirement in the RFP to
consider debris, however, the contractor should have assumed that debris would have
built up against the fence and blocked the small openings available for flow to pass.
The blockage of the fence due to debris is likely adding to downstream scour due to water
flowing over the crest of the blockage and causing significant vortices at the downstream
footing of the fence, dislodging HPTRM and creating scour at the downstream side of thefence. There are instances on the upstream portion of the fence where lateral flows are
causing scour. Erosion is seen in locations where the pedestrian fence does not have thegrate portion, but simply the wire mesh, hence the floodplain cast by the storm is greater
than the expected design 100-year floodplain. The requirements of the RFP states that the
contractor will provide details for protection of scour and/or long term degradation alongwith preventing ponding of water at the fence location, however, the scour and ponding
still occurred, therefore, the contractor seemingly did not meet the design and RFP
requirements.
Given the criteria for both the USIBWC and RFP requirements, it would appear the fence
is not performing as originally intended. Debris will accumulate on the fence given the
tolerances required to keep people out. In addition, continuous maintenance after everyflood event is required to clear debris from the openings.
Recommendations
001077
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
52/899
001078
(b) (5)
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
53/899
IPT Report
APPENDIX B
Wash Ranking Tables for PF 225
001079
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
54/899
Project: SBI - TI , Technical IPT
Title: Table B-1: PF 225 washes and data
Date: 4/23/09
Segment CrossingQ
(cfs)
V
(ft/s)
Normal
Depth
(ft)
Flow
Direction (N
/ S)
Bed
Load
Slope
(%)Notes
FEMA
Crossing
Estimated
Construction
Start Date
RANK
A-1 1 7554 34.530 6.61 18.000
Final dranage report not received.
Preliminary Analysis done for two major
wash Zone D 2009 3
A-1 2 7028 35.800 7.86 16.000
Final dranage report not received.
Preliminary Analysis done for two major
wash Zone D 2009 3
A-2A 2 2124 2.870 11.49 S 5.300 Proposed Conditon HEC-RAS Data Zone X 8-Nov-08 2
A-2B 100 0.000 Crossing was not identified Zone X 15-Nov-08 1
A-2C 1+37 13 7.880 0.38 S 13.000 Flow Master Data Zone X 1-Dec-08 2
A-2C 6+95 33 7.870 0.50 S 10.000 Flow Master Data Zone X 1-Dec-08 2
A-2C 16+03 3 5.640 0.30 S 17.000 Flow Master Data Zone X 1-Dec-08 2
A-2C 25+22 36 6.140 0.70 S 4.000 Flow Master Data Zone X 1-Dec-08 2
A-2D 36+35 9 6.770 0.28 S 16.000 Flow Master Data Zone X 16-Dec-08 2
A-2D 38+28 88 11.660 0.82 S 12.000 Flow Master Data Zone X 16-Dec-08 2
A-2D 39+02 3 5.230 0.32 S 13.000 Flow Master Data Zone X 16-Dec-08 2
A-2D 48+63 14 6.190 0.50 S 6.000 Flow Master Data Zone X 16-Dec-08 2
A-2D 52+13 788 17.910 3.05 S 6.000 Flow Master Data Zone X 16-Dec-08 3
A-2D 60+57 70 16.070 0.80 S 24.000 Flow Master Data Zone X 16-Dec-08 2
A-2E 5+87 7 4.380 0.38 S 4.000 Flow Master Data Zone X 18-Dec-08 1
A-2E 5+44 95 20.440 0.84 S 37.000 Flow Master Data Zone X 18-Dec-08 2
A-2F 100 7 8.730 1.38 S 50.000 Culvert Data Zone X 8-Nov-08 2A-2G 8 206 1.930 5.41 S 5.000 Proposed Conditon HEC-RAS Data Zone X 10-Dec-08 2
A-2G 2 8 7.850 1.49 N 50.000 Culvert Data Zone X 10-Dec-08 2
A-2G 9 5.40 6.900 1.19 N 50.000 Culvert Data Zone X 10-Dec-08 2
A-2I 0+79 0.78 4.240 0.49 S 9.300 Flow Master Data Zone D 2-Nov-08 1
A-2J 52+67 15.53 8.16 0.58 S 8.040 Flow Master Data Zone D 2-Nov-08 2
A-2J 51+75 174.00 13.17 3.67 N 5.124 Flow Master Data Zone D 2-Nov-08 2
A-2I 44+41 3.54 6.470 0.85 S 10.650 Flow Master Data Zone D 2-Nov-08 2
A-2I 40+00 1.52 6.000 0.60 N 15.700 Flow Master Data Zone D 2-Nov-08 2
A-2I 36+08 0.25 4.780 0.25 S 27.180 Flow Master Data Zone D 2-Nov-08 1
A-2I 21+89 3.05 4.920 0.12 N 17.580 Flow Master Data Zone D 2-Nov-08 1
A-2I 16+29 4.65 6.200 0.61 N 8.810 Flow Master Data Zone D 2-Nov-08 2
A-2I 7+67 2.80 7.780 0.69 N 20.390 Flow Master Data Zone D 2-Nov-08 2
A-2I 2+67 0.37 2.710 0.07 S 11.760 Flow Master Data Zone D 2-Nov-08 1
A-2I 1+56 2.68 5.660 0.90 S 9.450 Flow Master Data Zone D 2-Nov-08 2
A-2K J-1 (48+50) 1 1.000 1.00 S 0.700 Drainage Report Zone D 17-Dec-08 1
A-2K J-1&J-2 (47+09) 6300 7.000 6.00 S 1.100 Drainage Report Zone D 17-Dec-08 3
A-2K J-3 (50+13) 131 3.000 0.40 S 1.400 Drainage Report Zone D 17-Dec-08 1
A-2K J-4 (54+56) 15 1.730 0.10 S 1.200 Drainage Report Zone D 17-Dec-08 1
A-2K J-5 (70+50) 6400 8.00 5.50 N 2.600 Drainage Report Zone D 17-Dec-08 3
A-2L J-6 (23+48) 17234 4.000 6.00 N 2.500 Drainage Report Zone D 17-Dec-08 3A-2L J-7 (55+12) 19 1.750 0.10 N 1.200 Drainage Report Zone D 17-Dec-08 1
A-2L J-8 (59+24) 71 1.600 0.20 N 1.700 Drainage Report Zone D 17-Dec-08 1
A-2L J-9 (66+39) 1164 5.270 1.58 N 1.200 Drainage Report Zone D 17-Dec-08 2
A-2N 3 334 7.650 1.35 N 5.100 HEC-RAS Data Zone D 1-Nov-08 2
A-2N 4 96 2.610 0.67 N 10.000 HEC-RAS Data Zone D 1-Nov-08 1
B2 1 50 0.000 Final Drainage Report not Available Zone X not awarded 1
B2 2 10 0.000 Final Drainage Report not Available Zone X not awarded 1
B2 3 90 0.000 Final Drainage Report not Available Zone X not awarded 1
B2 4 100 0.000 Final Drainage Report not Available Zone X not awarded 1
B2 5 80 0.000 Final Drainage Report not Available Zone X not awarded 1
B2 6 470 0.000 Final Drainage Report not Available Zone X not awarded 1
B2 7 840 0.000 Final Drainage Report not Available Zone X not awarded 1
B4 1 0 0.000
H&H was not done in the fi nal drainage
report Zone X 1
B4 2 0 0.000
H&H was not done in the fi nal drainage
report Zone X 1
B4 3 0 0.000
H&H was not done in the fi nal drainage
report Zone X 1
B4 4 1515 0.000
H&H was not done in the fi nal drainage
report Zone A 1
B4 6 270 0.000
H&H was not done in the fi nal drainage
report Zone X 1
B4 5 212 0.000
H&H was not done in the fi nal drainage
report Zone X 1
B4 7 0 0.000
H&H was not done in the fi nal drainage
report Zone X 1
V:\PROJECTS\DHS\112319_PF225 Phase 2\IPT meetings- debris\IPT r eport revised May 2009\Appendix B\Table 1- PF225 washes and data.xls
001080
-
7/23/2019 Customs and Border Protection report on border walls crossing washes and streams
55/899
Project: SBI - TI , Technical IPT
Title: Table B-1: PF 225 washes and data
Date: 4/23/09
Segment CrossingQ
(cfs)
V
(ft/s)
Normal
Depth
(ft)
Flow
Direction (N
/ S)
Bed
Load
Slope
(%)Notes
FEMA
Crossing
Estimated
Construction
Start Date
RANK
B4 8 0 0.000
H&H was not done in the final drainage
report Zone X 1
B4 9 0 0.000
H&H was not done in the final drainage
report Zone X 1
B5A 1 220 0.000 Drainage Report Missing Zone D 1
B5B 1 11 0.000
H&H was not done in the final drainage
report (San Dune Area) Zone D 1
B5B 2 5 0.000
H&H was not done in the final drainage
report (San Dune Area) Zone D 1
B5B 3 1 0.000
H&H was not done in the final drainage
report (San Dune Area) Zone D 1
C-1 22 21 1.990 0.49 0.500 HEC-RAS Data, All other wash are small Zone X 1
D2 W22 18 9.300 0.83 S 22.000 Flow Master Data Zone X Completed 2
D2 W21 17 4.010 0.74 S 5.000 Flow Master Data Zone X Completed 1
D2 W20 3 2.310 0.33 S 4.100 Flow Master Data Zone X Completed 1
D2 W19 2 2.540 0.34 S 5.000 Flow Master Data Zone X Completed 1
D2 W18 2 2.010 0.31 S 3.500 Flow Master Data Zone X Completed 1
D2 W17 13 5.250 2.72 S 3.500 Flow Master Data Zone X Completed 2
D2 W16 14 5.250 2.72 S 3.500 Flow Master Data Zone X Completed 2
D2 W15 3 5.250 2.72 S 3.500 Flow Master Data Zone X Completed 2
D2 W14 810 5.250 2.72 S 1.100 HEC-RAS Data Zone X Completed 2D2 W13 2605 8.650 4.00 S 1.660 HEC-RAS Data Zone X Completed 3
D2 W12 2 1.020 0.19 S 1.100 Flow Master Data Zone X Completed 1
D2 W11 16 2.250 0.23 S 2.000 Flow Master Data Zone X Completed 1
D2 W10 46 2.460 0.63 S 1.700 Flow Master Data Zone X Completed 1
D2 W9 5 1.450 0.32 S 1.000 Flow Master Data Zone X Completed 1
D2 W8 52 2.280 0.66 S 1.300 Flow Master Data Zone X Completed 1
D2 W7 34 1.690 0.74 S 1.100 Flow Master Data Zone X Completed 1
D2 W6 4 1.580 0.34 S 2.500 Flow Master Data Zone X Completed 1
D2 W5 47 1.180 0.59 S 0.900 Flow Master Data Zone X Completed 1
D2 W4 164 1.380 1.51 S 0.890 HEC-RAS Data Zone X Completed 1
D2 W3 6 1.380 0.27 S 2.000 Flow Master Data Zone X Completed 1
D2 W2 4 6.000 0.36 S 15.000 Flow Master Data Zone X Completed 2
D2 W1 2796 4.960 5.94 S 0.980 HEC-RAS Data Zone A Completed 2
D2 E1 55 2.330 0.78 S 1.000 HEC-RAS Data Zone X Completed 1
D2 E2 12 1.640 0.46 S 2.670 Flow Master Data Zone X Completed 1
D2 E3 7 0.960 0.29 S 1.250 Flow Master Data Zone X Completed 1
D2 E4 110 1.240 1.16 S 0.720 HEC-RAS Data Zone X Completed 1
D2 E5 1 0.010 1.86 S 1.500 HEC-RAS Data Zone X Completed 1
D2 E6 195 1.250 4.04 S 0.780 HEC-RAS Data Zone X Completed 2
D2 E7 6 1.160 0.15 S 0.420 Flow Master Data Zone X Completed 1D2 E8 5875 2.650 6.56 S 0.900 HEC-RAS Data Zone X Completed 2
D2 E9 94 2.650 6.56 S 0.900 HEC-RAS Data Zone X Completed 2
D2 E10 3 1.370 0.21 S 2.000 Flow Master Data Zone X Completed 1
D2 E11 133 2.450 0.58 S 0.950 HEC-RAS Data Zone X Completed 1
D2 E12 9 1.600 0.26 S 0.830 Flow Master Data Zone X Completed 1
D2 E13 346 1.190 1.44 S 0.870 HEC-RAS Data Zone X Completed 1
D2 E14 8 1.390 0.28 S 1.300 Flow Master Data Zone X Completed 1
D2 E15 30 1.050 0.35 S 1.200 Flow Master Data Zone X Completed 1
D2 E16 5843 4.520 8.43 S 1.320 HEC-RAS Data Zone X Completed 3
D2 E17 33 4.520 8.43 S 1.320 HEC-RAS Data Zone X Completed 2
D2 E18 6 1.050 0.26 S 1.000 Flow Master Data Zone X Completed 1
D2 E19 45 2.530 3.01 S 1.010 HEC-RAS Zone X Completed 2
D2 E20 2335 2.530 3.01 S 1.010 HEC-RAS Zone X Completed 2
D2 E21 97 0.930 0.95 S 0.810 HEC-RAS Data Zone X Completed 1
D2 E22 39 0.930 0.95 S 0.810 HEC-RAS Data Zone X Completed 1
D2 E23 3 1.370 0.15 S 2.000 Flow Master Data Zone X Completed 1
D2 E24 10 0.870 0.50 S 0.200 Flow Master Data Zone X Completed 1
D2 E25 37 2.130 0.56 S 1.300 Flow Master Data Zone X Completed 1
D2 E26 7 1.340 0.25 S 1.000 Flow Master Data Zone X Completed 1
D2 E27 2 1.520 0.14 S 3.000 Flow Master Data Zone X Completed 1D2 E28 36 1.730 0.54 S 0.700 Flow Master Data Zone X Completed 1
D2 E29 371 1.350 3.86 S 0.850 HEC-RAS Data Zone X Completed 2
D2 E30 89 1.350 3.86 S 0.850 HEC-RAS Data Zone X Completed 1
D2 E31 1591 7.120 2.46 S 2.520 HEC-RAS Data Zone X Completed 2
D2 E32 3 7.120 2.46 S 2.520 HEC-RAS Data Zone X Completed 2
D2 E33 16 7.120 2.46 S 2.520 HEC-RAS Data Zone X Completed 2
D2 E34 74 1.660 0.49 S 0.560 HEC-RAS Data Zone X Completed 1
D2 E35 30 1.750 0.34 S 1.000 HEC-RAS Data Zone X Completed 1
V:\PROJEC